SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? SHIP/SHORE LNG TRANSFER˚: HOW TO CUT COST˚? by Bernard DUPONT EURODIM Sa, Michael OFFREDI ITP Interpipe, Emmanuel FLESCH GAZ DE FRANCE Chris THOMAS and Bertrand LANQUETIN TOTALFINAELF Abstract : THIS PAPER WILL FIRST REVIEW THE EXISTING LNG TRANSFER SHIP/SHORE SYSTEMS AND THE TYPICAL COST OF THESE FACILITIES. SIGNIFICANT NOVEL IDEAS TO REDUCE THE COST OF THE TRANSFER FACILITIES WILL BE REVIEWED. A NEW DESIGN OF MARINE TERMINAL, CURRENTLY UNDERTAKEN BY A GROUP OF FRENCH COMPANIES SET UP BY GAZ DE FRANCE AND TOTALFINAELF, WILL BE UNVEILED : - THE TRANSFER LINES ON A COSTLY TRESTLE ARE REPLACED BY NEW CRYOGENIC SUBSEA PIPES DEVELOPED BY ITP INTERPIPE APPLYING PATENTED TECHNOLOGY FROM HP/HT SEA LINE - A NEW CONCEPT OF LOADING PLATFORM AND TRANSFER SYSTEM, LINKING SUBMERGED LINE TO LNG CARRIER IS DEVELOPED BY EURODIM, TAKING ADVANTAGE, INTER ALIA, OF THE EMERGENCE ON THE MARKET OF RELIABLE CRYOGENIC FLEXIBLE LINES AS AN ALTERNATIVE TO CONVENTIONAL LOADING ARMS. OPERATIONAL AND SAFETY ASPECTS OF THE NEW SYSTEMS WILL BE DEVELOPED AND TYPICAL COST ELEMENTS ESTABLISHED. FINALLY, THE PROPOSED PLANS FOR FULL VALIDATION OF THE NOVEL LNG TRANSFER FACILITIES WILL BE PRESENTED. PAGE 1 SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? TABLE OF CONTENTS 1 - SUMMARY 2 - EXISTING LNG TRANSFER FACILITIES 2-1 RECEIVING TERMINAL 2-2 LOADING FACILITIES 2-3 TYPICAL COST ELEMENTS 3 - REVIEW OF UNCONVENTIONAL SCHEMES 3-1 SUBSEA CRYOGENIC PIPE 3-2 TRANSFER SYSTEMS 4- NEW LNG TRANSFER CONCEPTS 4-1 DOUBLE WALL PIPE OBJECTIVES OF THE SUBSEA CRYOGENIC PIPELINE CONCEPT DEFINITION COMPONENTS OF CRYOGENIC PIPE DESIGN PHILOSOPHY FABRICATION & INSTALLATION PRECOMMISSIONING SAFETY REPAIR COST ELEMENTS ON GOING QUALIFICATION PROGRAMME 4-2 TRANSFER SYSTEM ARCHITECTURE CONCEPT DEFINITION DESCRIPTION OF THE COMPONENTS DESIGN CRITERIA AND RESULTS CONNECTING MODULE SAFETY AND OPERATION COST ELEMENTS FUTURE DEVELOPMENT PAGE 2 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 5- CHALLENGES 5-1 CONSERVATISM OF LNG BUSINESS 5-2 TARGET FOR COST REDUCTION 5-3 REGULATORY ASPECT 6- WAY FORWARD 6-1 OVERALL SAFETY ASPECT 6-2 PIPE IN PIPE SPOOL AND CRYOGENIC TEST 6-3 CONNECTING MODULE PAGE 3 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 1 -SUMMARY The existing LNG transfer facilities are robust and safe; over the years the safety level of loading arms have improved but the weight and the associated cost of the jetty head facilities have increased as well. New receiving terminals in emerging countries have to face challenging marine conditions with monsoon season and no natural harbour. Revamping of existing facilities is often difficult because of poor access to new larger ships. Existing LNG transfer facilities were designed for a high gas commodity price; emerging market will offer lower price for gas hence the whole LNG chain cost must be reduced including the transfer facilities. The architecture developed by EURODIM offers a more compliant transfer system based on cryogenic flexible available today; present development focuses on the load filtering and the connection of the flexible to the ship manifold. EURODIM is also working on an open sea transfer system with significant wave height up to 3.5 m. Replacing costly trestle system by sub-sea pipe will globally reduce the cost of the LNG transfer facilities. The cryogenic insulated Pipe developed by ITP Interpipe is based on proven weldability of Invar pipe, Izoflex unique heat insulating characteristics as well as the proven double wall pipe technology developed for TOTAL by ITP Interpipe (Dunbar , 1992) and then extended to further projects such as HP/HT SHELL ETAP or ELF TCHIBELI. Feasibility studies have confirmed that there are neither mechanical nor thermal limitations to the concept and a series of cryogenic tests on a representative spool of Double Wall Pipe will be launched shortly at Gaz de France testing facilities. Full validation of both concepts will require more development work to be carried out within a project framework Irrespective of the unmatched quality of these two novel technologies, the project team will have to convince the LNG community that both concepts are safe and attractive. This may take longer than expected and this paper is the first step toward this goal. PAGE 4 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 2 - EXISTING LNG TRANSFER FACILITIES LNG transfer facilities are as old as the LNG business with currently some 15 LNG Plants and circa 38 receiving terminals in operation; around 70 LNG transfer facilities are in service world-wide and this number is expected to grow yearly by a couple of units. Except for two receiving terminals (COVE POINT in the US and the new OGISHIMA terminal in JAPAN) the transfer arms are linked to the shore by a trestle or a causeway. The storage tanks and the transfer facilities for Cove Point and new OGISHIMA are connected via an underground tunnel. We will give a brief description of the conventional transfer systems, which comprises two distinct sub-systems: - The transfer arms and ship berthing and mooring facilities - The connection between the tank farm and the jetty head The following captures the main functionality of the two sub-systems. 2.1 RECEIVING TERMINAL The transfer facilities usually feature : - A jetty head with berthing and mooring dolphins associated to a platform equipped with gangway and loading arms; several process items are also located on this platform (filters, manifolds, drain drum ). Fire protection equipment (foam, dry powder and firewater) provides adequate safety coverage. A control booth overlooks the transfer platform. Additionally utilities can be provided to the Ship. - Dolphins : 4 berthing dolphins and 6 mooring dolphins are usually required; all the mooring arrangement is designed in accordance with the acceptable drift of the Loading Arms (usually 3.5 m fore/aft). - Loading arms (2 to 4 liquids and 1 vapour) are required to unload the gas carrier at a rate between 3000 to 12000 m3/h. The size of the loading arms are typically 12/16 inch. Most of the loading arms are fitted with an Emergency Disconnection system. It should be noted that over time the sophistication of the transfer arms has increased and the safety level has steadily improved with only a few serious incidents to report. - The unloading facilities are equipped with filters to avoid contamination of the storage tanks by undesirable material. All transfer equipment can be drained into a vessel where LNG is either vented or pumped back to the unloading lines. - Fire fighting systems include high expansion foam monitors over a spill basin which recovers LNG spillage; dry powder fire extinguishers and fire water monitors complement the fire protection hardware. - Monitoring of the ship berthing and operation of gangway and loading arms is done from a PAGE 5 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? technical room. All ship/shore interface electronic equipment is located in this building. - Nitrogen or inert gas is required for commissioning and decommissioning of the loading arms. Additional utilities can be provided by the shore to the ship such as bunker, diesel oil, fresh water, liquid nitrogen - A connecting trestle (or causeway) supports all necessary pipes (process and utilities) along with electric and instrument cables. The trestle supports also a maintenance road. The average length between the storage area and the transfer facilities for the receiving terminals is around 500 meters but can be much longer when no natural harbour is available. - Process pipes The size of unloading pipes is around 24/30 inches to match the LNG carrier cargo pump head ,the elevation of the Storage Tanks and the design flowrate set by the duration of the unloading operation. Usually two pipes of the same size are used in parallel during unloading operation and in series to keep the pipe cold in holding mode. The Vapour displaced in the shore tanks can be returned to the ship by a dedicated line. - Utilities Pipes Firewater, nitrogen, compressed air complemented by bunker, diesel oil, and fresh water as required. - Maintenance Road This maintenance road is designed to carry fire truck and maintenance crane necessary to service the loading arms and other equipment. PAGE 6 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 2.2 LNG PLANT LOADING FACILITIES The description of the LNG loading facilities is very much the same as the unloading facilities described above. The platform accommodates larger drain drum designed for the surge protection of equipment at the Jetty Head. The longest connection between the tank farm and the jetty head is around 6 km for the LNG Plant. Because the relative cost of marine facilities is lower for the LNG Plant than for a LNG receiving terminal, the siteing of LNG plant doesn t always minimise the cost of the transfer facilities. Unlike the receiving terminals the vapour displaced during loading operation is often flared due to jetty length and poor economic incentive to recover marginal flared gas. Figure 2.2 pictures an artistic view of BONTANG 3rd dock. Figure 2.2 BONTANG 3rd LNG/LPG DOCK PAGE 7 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 2.3 TYPICAL COST ELEMENTS Although there are differences from one project to another in terms of sizing and cost of LNG transfer facilities, our project has retained the following estimation for reference: Berthing and mooring Jetty head Trestle Pipes/ cables ESTIMATE ($/99) 15 M$ 20 M$ 15 M$/1000 meter 13 M$/1000 meter The above in-house estimates for overall project are based on typical productivity and manpower rates for emerging countries. 3 - REVIEW OF UNCONVENTIONAL SCHEMES 3.1 SUB SEA CRYOGENIC PIPE Sub-sea cryogenic pipe is not in itself a novel idea; but the current project applies un-common new design features. Since the very early days of the LNG industry, cryogenic pipelines have been one of the subject of choice in world wide conference [1][2][3][4][5]. Subsea cryogenic pipelines have been also described in some details [6],[7],[10]. The main problems associated with submarine cryogenic pipes are : - material of construction should be resistant to low temperature; - shrinkage of the pipe should be accommodated; - insulation system highly effective thermally, water tight and strong to permit handling; - fail-safe system i.e. the line should remain operational in case of local damage. Several solutions have been proposed, out of which the most significant are: - retrained / pre-strained double pipe system [6] recommending the fabrication of pre-strained section of pipe with the limit of non-uniform prestrain along the length of the pipe. SHELL tested at cryogenic temperature sections of pre-strained pipe. - Modular sections [7] wherein multiple LNG pipe sections utilising expansion joints to compensate for contraction are connected together by braces to form an integral frame, including pressure vessels enclosing the expansion joints to permit access for inspection and maintenance . Patent drawing is shown below (figure 3.1) : - Concentrical LNG pipe-in pipe with a main transfer conduit and a return conduit both positioned within an outer jacket [10]. PAGE 8 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? Figure 3.1 US PATENT 4,826,354 general principle None of these systems have been applied in projects. Among current development effort, a company proposing a Poly Urethane Light Foam System have been working for some time on a cryogenic pipeline that could well be used offshore. Fullscale cycle test at cryogenic temperature have been successfully conducted by this company. The patented novel cryogenic sub-marine pipe as developed by ITP InTerPipe differs from the above systems by the following features: - Double Wall Pipe technology currently used on sub-sea HP/HT projects. Internal pipe in INVAR with no loops or expansion joints. Best insulating material IZOFLEX thus reducing the size of the external pipe. Continuous annular. External pipe to handle massive external aggression. PAGE 9 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 3.2 LNG TRANSFER SYSTEMS A number of R&D programs have been launched to develop un-conventional LNG transfer system. In the past, TOTAL has been associated in the CHAGAL program [8]. This project was based on the development of a cryogenic Single Point Mooring, which required sub-sea flow lines and PLEM, flexible hoses and a cryogenic swivel to be designed and tested. 8 cryogenic flexible was designed and tested by COFLEXIP. Patents for the cryogenic 16-inch swivel initiated by EMH were taken over by SBM. As yet, no LNG transfer project has been based on this concept. More recently however, COFLEXIP STENA OFFSHORE has promoted a JIP for the development of a 16 NPS cryogenic flexible to be used for offshore LNG transfer. Offshore LNG transfer has prompted also extensive R&D programs by FMC (Boom To Tanker), SBM (single offloading arm) and STATOIL(Offshore Cryogenic Loading System). While offshore development of LNG Plant on barge or FPSO remains still prospective, several LNG terminals in emerging countries are at various design stages and are expected to come to fruition in the near future, probably sooner than LNG offshore transfer from FPSO to LNG carrier. Hence the approach of our group to appraise if technology developed for the far future (in our case large cryogenic flexible) could be used to reduce the cost of our current projects. The architecture as developed by EURODIM is based on existing cryogenic flexibles already tested or being tested by the industry. PAGE 10 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 4- NEW LNG TRANSFER CONCEPTS Although the novel systems presented in this paper could apply to both export terminals and receiving terminals, our effort has focused more on receiving terminal because there are currently more receiving terminals at project phases within the portfolios of the sponsors of this research program. Our work has been based on a receiving terminal without vapor return for sake of simplicity. It should be noted that a vapor return line could be added using the same concepts ;moreover unloading an LNG carrier without vapor return has been safely achieved in the past and would require only minor modification to existing LNG carriers re-gasification facilities. 4.1 DOUBLE WALL PIPE 4.1.1 OBJECTIVES OF THE SUBSEA CRYOGENIC PIPELINE The sub-sea cryogenic pipeline provides the LNG connection between the offloading platform and the onshore storage facility. The main criteria that led to the final design for this sub-sea system are the following : - cost reduction. Operators shall consider the new architecture of interest only if significant cost savings are associated with it by comparison with the conventional scheme. - Simple and robust design. With respect to operators requirements, the selected design must avoid as much as possible complex devices or high technology components which increase the OPEX (maintenance costs) and the risk of failure of the system. Concepts such as underwater tunnels or sub-sea expansion loops/ expansion joints were not considered. - High thermal performances. Due to the length of line targeted by the project (more than 1 mile; typically 3 miles), the heat transfers between the transport pipe and sea environment have to be reduced as much as possible. The thermal performances of ITP insulated systems with IZOFLEX material were recently confirmed by full scale thermal tests carried out in Houston by a JIP led by TEXACO associated with BPAmoco, ExxonMobil and TotalFinaElf. - Reliability and safety of the system, during installation and in operation. 4-1-2 CONCEPT DEFINITION To meet the various requirements listed above, the project team selected a design based on the Double Wall Pipe technology developed by ITP InTerPipe and already in operation for the transportation of hot effluent. ITP double wall pipeline technology consists of two coaxial pipes: an inner pipe is inserted within an outer pipe and both pipes are linked at their ends. The sealed annular space between the pipes allows to implement high performance insulation material that reduce significantly the heat transfer between inner pipe, containing LNG and outer pipe in contact with the seawater. PAGE 11 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? The ITP system provides the following main benefits to the project: - Capex and Opex reduction; Safe and simple design for a reduced failure risk; Environmental friendliness (sub-sea installation); High insulation capacity to reduce heat ingress. 4-1-3 COMPONENTS OF CRYOGENIC PIPE The double wall pipe developed by ITP includes: - Inner pipe The inner pipe is made of a Nickel alloy with 36% of Ni, commercially named INVAR or Pernifer 36. Because of its very low expansion coefficient, the thermal stresses and strains resulting from the temperature difference are maintained low (approx. 10 times smaller than stainless steel material). Combined with its high mechanical strength, high tenacity and good welding properties, the INVAR material simplifies the design and fabrication of the system. Indeed, there is no need of artificial expansion device due to the thermal or mechanical length variation. - Insulation material : IZOFLEX The selected insulation is the Izoflex, a material developed, patented by ITP and already implemented to insulate several hot effluent pipeline including pipe with significant temperature difference between transported multiphase product and outside environment. TYPICAL CRYOGENIC DOUBLE WALL PIPELINE CONCRETE LAYER TM IZOFLEX INSULATION 100 MM OUTER PIPE : CARBON STEEL 48 /20.6 mm INNER PIPE : INVAR 36 / 6 MM PAGE 12 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? The high thermal insulation properties of the IZOFLEX enables to design a high thermal performance double wall pipeline within a reduced annular. The thickness of IZOFLEX to be used is four times smaller than the one that would have been necessary with Poly Isocyanate Resin (PIR) insulation for equivalent thermal performances. The resulting compact system contributes to costs savings. Mechanical testing in cryogenic environment carried out during the design phase of the project confirmed the suitability of the material for LNG transport application. The good mechanical behaviour at any temperature combined with a limited shrinkage effect at low temperatures and a good annular filling ensures the concentricity of the inner and outer pipes. No annular spacers are required. Due to the fabrication procedure and insulation material installation process, thermal-bridging effect along the overall pipeline is reduced to a minimum and overall thermal performance is optimised. - Outer pipe The outer pipe is made of regular carbon steel. This material is designed to protect the internal pipe & the insulation system. The high weight increases the sub-sea stability of the line. The low cost of the material contributes to the Capex reduction. - Concrete A concrete layer is added for additional protection and pipe stability. PAGE 13 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 4-1-4 DESIGN PHILOSOPHY The pipe system has been designed to withstand: - the loads induced by the installation process (string weight and associated tension, hydrostatic pressure, temperature variations ); the loads in operation (thermal loads, internal and external pressures and differential pressures, seabed stability, fatigue ) during the life of the pipe. These various criteria have been reviewed in accordance with the main codes and standards for refrigeration and sub-sea pipelines. Basically, the inner pipe and the insulation material reduce the impact of the temperature variations and the outer pipe ensures the integrity of the system. The continuous annulus all the way through the line allows the placement of additional control devices. Pressure and temperature control gauges and secondary annular protection increase the safety of the system and allow the operator to control the system at any time. 4-1-5 FABRICATION & INSTALLATION A specific fabrication process has been developed for the cryogenic double wall pipeline. This sequence is driven by the installation procedure based on the towing method. The fabrication sequence is divided into several fabrication steps. A first step is the pre-assembly of insulated units (6 or 12 meters long). These pieces are welded together to produce 250 m long strings or longer. Once the strings are ready, they are welded onshore before being pulled by suitably adapted means up to the appropriate location. A double wall insulated riser provides the connection between the sub-sea pipe and the offloading platform at one end. At the other end, an onshore connecting pipe will be tied up to the manifold of the storage tanks. Up to 5000-m long double wall pipeline lay boats or heavy lift crane barge (bottom towing method) might pull system from the shore to its final position on the seabed. 4-1-6 PRECOMMISSIONING In order to control the mechanical integrity of the Double Wall Pipe strings, pneumatic testing is carried out on welded strings before starting the installation. PAGE 14 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 4-1-7 SAFETY Safety issues, as for every new LNG technology, have been particularly addressed. The major safety issues for the sub-sea cryogenic double wall pipeline are related to a failure of the containment systems. - Water ingress (failure of external pipe): The risk of occurrence of such an event is reduced to an acceptable level, thanks to proper design of the pipe external protection (trenching, concrete protection). Water ingress is monitored by continuous analysis of the annular space normally operating under reduced pressure; in case of external pipe failure, a large water ingress can be prevented by pressurisation of the annular space with air. - LNG egress (failure of the internal pipe): Similarly LNG leaks will be detectable by continuous monitoring of the temperature in the annular space and minor leaks can be reduced by back pressurisation of the annular space by fuel gas while the system is safely decommissioned for repair. 4-1-8 REPAIR Various scenarii are considered for repair in case of accidental pipe failure: - Sub-sea repair, in dry atmosphere in shallow water depth - Surface repair after pipe recovery by a lifting barge when a section of the pipe needs replacement. Repair procedure takes into account the corrosive behaviour of sea water on Invar piping. 4-1-9 COST ELEMENTS For a 2 x 36 inch, our internal evaluation is around 13 000 $/m as direct cost and around 8500 $/m for a 2 x 30 inch configuration. 4-1-10 ON GOING QUALIFICATION PROGRAMME The next step of our development program is the fabrication and testing of a full-scale double wall pipeline sample. The scope of work includes notably the review of the fabrication process, analysis of component behaviour during LNG circulation, confirmation of the thermal performances of the system. Testing will be done at Gaz de France cryogenic premises at NANTES. PAGE 15 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 4-2 TRANSFER SYSTEM ARCHITECTURE 4-2-1 CONCEPT DEFINITION The architecture and system proposed by EURODIM is based on an equipment that has been successfully tested or are currently being tested such as cryogenic flexibles lines from M/S COFLEXIP or M/S COMPOFLEX. The flexibles lines with their supporting infrastructure are significantly lighter as compared to traditional articulated arms. Additionally maintenance of the flexibles and other process items doesn t require a large crane. Both aspects reduce the overall dimensions and the cost of the transfer facilities. 4-2-2 DESCRIPTION OF THE COMPONENTS The transfer facilities main components are: - - - A two level platform with a technical room, a drain drum, compressed air and nitrogen reserves and a boat landing with utilities connections at the cellar deck; On the main deck, manifolds, filters and pipes connecting the cryogenic sealines to the flexibles. A structure supporting in stand-by mode all the flexibles lines and the associated connecting modules stored separately; a light lifting crane is designed to handle efficiently all connectors and flexible lines. Gangway and fire water monitors are located on the same structures Typical berthing and mooring dolphins as required for the traditional transfer facilities Firewater connections are located on the closest mooring dolphins. Figure 4.2.1 pictures a simplified view of the new transfer system for a Receiving Terminal. PAGE 16 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? FIG. 4.2.1 NOVEL TRANSFER SYSTEM ARTISTIC VIEW 4-2-3 DESIGN CRITERIA AND RESULTS For the LNG transfer system and architecture, our group has focused on a Receiving Terminal for standard LNG carriers ranging from 70 000 m3 to 135 000 m3. The LNG unloading rate considered is 10 000 m3/hour. As for the present terminals, the berthing site is considered as relatively sheltered (in the first phase of development) and loading/mooring environment corresponds to significant wave heights of 1.5 to 2 meters. In these conditions, the safe operating envelope of movements of the ship manifold axis during loading is typically 11 meters fore/aft, 6 meters transversally and 8 meters vertically. In order to achieve our objective to reduce cost while maintaining or even improving the safety level of the new transfer system, we have taken a very conservative stand for the working conditions of the flexible lines. The newly developed large size cryogenic flexible hoses coming to the market are somewhat ’overdone’ for the present application — since they are designed and built to permit offshore LNG transfer (from FPSO to LNG carrier) in sea states of some 5 meters significant wave. Notably we have based the conceptual design and architecture on a minimal bending radius of 10 PAGE 17 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? meters for the catenary suspended cryogenic lines. The catenary suspension of the cryogenic hose has been chosen because it is ideal in order to keep excellent internal working conditions in the flexible even in the case of large 3-D motions of the offshore transfer. The flow rate of 10 000 m3/hour requires 3 x 16" diameter lines for a length of 45 meters each. We have developed a system able to cope with 3 to 4 x 16" diameter lines (possibility to include one spare flexible) or even with 20" diameter flexible lines, should it be interesting economically. With regards to safety, the transfer system design also integrates the mandatory requirement of a safe and reliable emergency disconnection system for the LNG lines. The reliability and simplicity of the system for normal operations such as connection/disconnection and storage are also participating to the safety of the concept, for which user friendliness has been a governing design factor. This, combined with the very limited acceptable load on the flanges of the ship manifold, has led to a design based on a flexible line attached at one end to the fixed platform and on the other end on a Multi-function Cryogenic Connection Module (MCCM) , interfacing the ship manifold flange and flexible line mobile extremity, which serves all the complex functions of the transfer system. 4-2-4 CONNECTING MODULE Thus, for each flexible, the Multi-function Cryogenic Connection Module (patent pending) has the following functions: - - Normal connection (flexible hot); Filtering of the stresses induced by the physical motions and the loads induced by the flexible line at cryogenic temperature in order to cope with the limited stress permissible at the ship manifold flanges; Normal disconnection (flexible cold); Emergency closure of the valves; Emergency disconnection of the flexible assembly from the ship manifold. This conceptual approach concentrating all the complex mechanical functionalities of the transfer system in a modular unit which can be loaded, with the system integrated crane, onto a supply vessel for possible inspection/maintenance, is an additional attractive point serving reliability and consequently system availability and safety. The flexible line, is nicely suspended in catenary configuration out of reach of any ’aggression’ in all conditions, i.e. storage or fluid transfer and is not very sensitive to wind loads. Our analyses confirm that the new transfer system developed is technically feasible and economical. Notably loads and cyclic movements imposed to the flexible lines are acceptable for the various existing technologies of cryogenic flexible hoses (one manufacturer has confirmed in depth our analyses) and the loads induced by the flexible lines movements and loads are acceptable for standard Emergency Release Couplers and/or Quick Connect Disconnect Couplers. Further, it should be noted that thanks to the flexible lines configuration, sophisticated and costly LNG swivel joints can be saved and the system is ideally pure and simple. PAGE 18 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 4-2-5 SAFETY AND OPERATION The main safety requirements of the new system are comparable to the safety requirement of the traditional articulated arm as in fact in both cases the major risk occurrence is located in the area of ship manifold at the level of the connectors. In addition, one should note the extreme ’comfort’ in which the flexible hoses are working thanks to : a) Benign environment. b) There is a great margin in the utilization ratio of the flexible lines as the maximum movement envelope considered is based on acceptable cyclic loading criteria. An accidental excursion out of the working envelope will not lead to an alteration of the flexible hose (such as for instance the yield stress of the stainless steel liner). Only minor leakage can be expected in case of major incident. Naturally available cascade margins of multiple layers flexible pipe with regard to acceptable ship movement are an interesting feature of the solution. Further, all transfer flexible lines can be disconnected at once in case of emergency (in case of ship movements risking to overstretch flexible lines). Commissioning and decommissioning of the flexibles will follow the standard practices outlined by the SIGTTO for the articulated arm; in particular, the flexibles shall be self-drainable and shall be inerted. Cool-down procedures relevant for cryogenic flexible lines shall be developed. Between two consecutive cargo transfer, all operations to achieve the optimum readiness for the next loading (basic maintenance and supply of utilities) will be done with a support vessel berthed at the main transfer platform. During LNG transfer operation, the supply vessel will be moored at a mooring dolphin for fire water supply and readiness to evacuate personnel in case of emergency. Major maintenance activities such as replacement of flexible will be done by simple winching and only a basic working barge or supply vessel is required for these operations. In terms of operation, the proposed facilities have the same functionality that the base case; in our estimation of the OPEX, we have included an additional supply boat, a contract for diving services on subsea lines and regular replacement for re-certification of the transfer flexibles. As for the Safety aspect, all the criteria of traditional transfer facilities are met or exceeded. 4-2-6 COST ELEMENTS Cost reduction for the transfer facilities have been estimated at some 5 M$ in terms of direct cost. The lower cost of the flexibles versus articulated arms and the simpler transfer platform both participate equally to this cost reduction. Further studies on the simplification of the berthing and mooring pattern to fully use all the potential of the flexibles in terms of drifting should further reduce the cost of the transfer facility. PAGE 19 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 4-2-7 FUTURE DEVELOPMENT The current efforts to develop this novel transfer system focus on: - - finalisation of the MCCM and industrialisation with manufacturers of cryogenic equipment; modification of the berthing pattern in order to fully utilise the potential of the flexibles with a direct objective to reduce the cost associated with the dolphin arrangement in a traditional terminal; research and screening of more compliant transfer systems to match near shore open sea conditions up to Hs = 3,5 m (see fig 4.2.7). Fig 4.2.7 COMPLIANT LNG LOADING SYSTEM PAGE 20 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 5- CHALLENGES 5.1 CONSERVATISM OF LNG BUSINESS Traditionally, the LNG business has been very conservative but, by the end of the last decade, novel designs have been applied to cope with the necessary cost reduction to increase LNG market share. Introduction of large single shaft gas turbine driving refrigeration compressor can be regarded in many respects as more challenging than a sub-marine cryogenic pipe and/or a transfer system based on cryogenic flexibles. Constant pressure for cost reduction pushes all operators to select innovative design. 5.2 TARGET FOR COST REDUCTION and IMPACT ON THE LNG PRICE Clearly for a grass roots LNG Plant, the target of cost reduction when applying both concepts would be at best a couple of percent of the overall project cost. Cryogenic sub sea pipe offers a large choice for the location of additional LNG berths in the case of expansion projects. For a receiving facility, the cost reduction can be in the range 10-15% of the project cost when a breakwater and/or major dredging is mandatory. Altogether, the cost reduction in terms of saleable LNG in the range of 3/5 cents/Mmbtu is modest but more cost reduction can be expected if the siteing of the LNG receiving facilities is optimised with regards to the location of large existing consumers (reduced interconnecting cost to bring the gas to the market). 5.3 REGULATORY ASPECT For the Double Wall Pipe, governmental agencies will challenge the safety aspect of the sub-sea LNG pipe and the effect of a plausible loss of containment. Specific programs to address this issue are currently under development. For the transfer facilities, the use of flexible is not forbidden but their use is currently limited to very specific applications such as emergency transfer of cryogenic cargo. Hoses have been traditionally compared to articulated arms and papers presented at SIGTTO panel [9] have advocated that hose operations are less risky than hard-arms or at least not more risky. Indeed, the use of large bore hoses is limited because of the uneasy operation of the flexible compared to balanced hard arms. In our project, a specific architecture with manipulating crane will be used for all the operation related to connection / disconnection. Thus, the issues raised in the codes and procedures can be successfully addressed by our proposed system but full recognition of both novel concepts by regulatory/government agencies is expected to require some time. 6- WAY FORWARD In order to get wider acceptance, additional work is required. 6-1 OVERALL SAFETY ASPECT Both concepts must be carefully designed and detailed Quantitative Risk Assessment study is prerequisite prior to the full endorsement of the concepts by operators. PAGE 21 PROGRAM MENU SHIP/SHORE LNG TRANSFER : HOW TO CUT COST ? 6-2 DOUBLE WALL PIPE SPOOL AND CRYOGENIC TEST A spool of Double Wall Pipe will be fabricated by ITP Interpipe and tested at GAZ de FRANCE cryogenic test premises; detailed procedures for fabrication and installation will also be developed to better assess the cost of installed pipe. 6-3 CONNECTING MODULE A detailed design of the connecting module based on full scale simulation and typical lay-out of LNG carriers manifolds will be carried out shortly. This will confirm the feasibility of the connecting module for all operating scenarios. The partners with a specialised manufacturer will develop a detailed mechanical design for the module and confirm cost estimation. ACKNOWLEDGMENT : this project is partly funded by the French Ministry of Industry. REFERENCES: [1] [2] [3] [4] [5] [6] [7] [8] [9] [10] LNG PIPELINES by P Herv Air Liquide LNG 1 1968 Paper 29b LIQUEFIED NATURAL GAS MAINS by O Ivan TZOV LN2 1970 Paper 3.7 TECHNICAL FEASIBILITY AND COST OF LNG PIPES by TE Hoover LNG 2 1970 Paper 3.8 PIPELINE AND GAS JOURNAL , June 1975 LES PIPELINES CRYOGENIQUES by Mr Mialon PETROLE & TECHNIQUES May 1984 A SUBMARINE OFFSHORE LOADING LINE FOR LNG by CWN Veeling (SHELL) LNG 3 paper II-8 1972 US PATENT 4,826,354 dated May 2sd 1989 UNDERWATER CRYOGENIC PIPELINE SYSTEM Inventor A Adorjan EXXON. OFFSHORE LOADING SYSTEMS FOR LIQUEFIED GAS by P Branchereau EMH LNG 8 Paper IV-7 1986. HARD ARMS versus HOSES SIGTTO PANEL 29/07/93; US PATENT 6,012,292 dated Jan,11,2000 by Alan SILVERMAN (MOBIL). CONTACTS For more details on the project, please contact : - double pipe wall for ITP.Interpipe@wanadoo.fr - transfer system : Eurodim_SA@wanadoo.fr PAGE 22 PROGRAM MENU
© Copyright 2024