Connection Process: For Negotiated High Voltage Retail Customer Connections Embedded Generators >30kW

Connection Process:
For Negotiated High Voltage Retail Customer
Connections
and
Embedded Generators >30kW
October 2014
October 2014
ISSUE 8
UNCLASSIFIED
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
ENQUIRIES:
P L E A S E C O N T A C T N E T W O R K C O N N E C T I O N S O N 13 23 91
OR
EMAIL: NETWORKCONNECTIONS@ESSENTIALENERGY.COM.AU
DOCUMENT NUMBER:
C EO P8 079 - I S S U E 8
This plan is copyright. No part may be reproduced by any process without written permission, except as
permitted under the copyright act.
DISCLAIMER
1
Essential Energy may change the information in this document without notice. All changes take effect
on the date made by Essential Energy. A print version is always an uncontrolled copy. Before using
this document, please ensure that it is still current.
2
This document may contain confidential information. Restrictions on the use and disclosure of
confidential information by employees are set out in your contract of employment. Restrictions on the
use and disclosure of confidential information by contractors are set out in your contract of engagement
with Essential Energy. Sub-contractors are bound by the confidentiality provisions set out in their
contract with the contractor engaged by Essential Energy.
2014 Essential Energ y
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 2 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Contents
1.
2.
3.
4.
5.
INTRODUCTION ........................................................................................................................ 6
WHY THESE INSTRUCTIONS ARE IMPORTANT ..................................................................... 6
CONNECTION ENQUIRY – PROCESS FLOW CHART ............................................................. 7
DEEMED CONNECTION – PROCESS FLOW CHART .............................................................. 9
CONNECTION PROCESS - CH5 NER – EMBEDDED GENERATION 5MW AND ABOVE ...... 10
5.1
5.2
Exploratory Connection Enquiry .................................................................................................. 10
Preliminary Connection Enquiry .................................................................................................. 10
5.2.1
5.2.2
5.3
Detailed Connection Enquiry ....................................................................................................... 12
5.3.1
5.3.2
6.
Exploratory Connection Enquiry .................................................................................................. 13
Preliminary Connection Enquiry .................................................................................................. 14
6.2.1
6.2.2
9.
10.
General ........................................................................................................................................ 16
Information to be provided with Connection Application .............................................................. 17
Australian Energy Market Operator (AEMO) ............................................................................... 18
Essential Energy .......................................................................................................................... 18
The Application Fee ..................................................................................................................... 19
The Offer to Connect ................................................................................................................... 19
Acceptance of Offer to Connect ................................................................................................... 20
CONNECTION AGREEMENT .................................................................................................. 20
CONTESTABILITY OF SERVICES........................................................................................... 21
12.1
12.2
12.3
13.
Preliminary Connection Enquiry – Connection Applicant obligations.................................... 14
Preliminary Connection Enquiry – Essential Energy Response ........................................... 14
CONNECTION ENQUIRY QUEUING ....................................................................................... 15
CONNECTION INVESTIGATION SERVICES AGREEMENT (CISA) AND LAND ACCESS
INVESTIGATION AGREEMENT (LAIA) .................................................................................... 15
MODIFICATION TO EXISTING CONNECTION........................................................................ 16
CONNECTION APPLICATION ................................................................................................. 16
10.1
10.2
10.3
10.4
10.5
10.6
10.7
11.
12.
Detailed Connection Enquiry – Connection Applicant obligations ........................................ 12
Detailed Connection Enquiry Response ............................................................................... 12
CONNECTION PROCESS - CH5A NER – EMBEDDED GENERATION LESS THAN 5MW
AND RETAIL CUSTOMER CONNECTIONS (HV LOAD CUSTOMERS) .................................. 13
6.1
6.2
7.
8.
Preliminary Connection Enquiry – Connection Applicant obligations.................................... 10
Preliminary Connection Enquiry - Essential Energy Response ............................................ 11
General ........................................................................................................................................ 21
Accredited Services Providers ..................................................................................................... 22
Guarantee of Revenue (GoR) (Security Fee) .............................................................................. 22
HV ASSETS GENERAL REQUIREMENTS .............................................................................. 22
13.1
13.2
13.3
13.4
13.5
13.6
Initial Requirements ..................................................................................................................... 22
Network Connection Configuration .............................................................................................. 23
Structural Adequacy ..................................................................................................................... 23
Subtransmission and Distribution Network .................................................................................. 23
TransGrid Requirements (if required) .......................................................................................... 24
HV Metering ................................................................................................................................. 24
13.6.1
13.6.2
13.7
General ................................................................................................................................. 24
Metering Voltage .................................................................................................................. 24
Construction Works ...................................................................................................................... 24
13.7.1
13.7.2
13.7.3
General ................................................................................................................................. 24
Environmental Impact ........................................................................................................... 25
Environmental Impact Assessment ...................................................................................... 25
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 3 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
13.7.4
13.7.5
13.7.6
13.7.7
13.7.8
13.7.9
13.7.10
13.8
Testing and Commissioning......................................................................................................... 27
13.8.1
13.8.2
13.8.3
13.9
13.10
13.11
14.
Records ........................................................................................................................................ 28
Training ........................................................................................................................................ 28
Authority for Placing Major Electrical/Plant Equipment into Service ............................................ 29
General ........................................................................................................................................ 29
Design, Equipment and Materials ................................................................................................ 29
Design References ...................................................................................................................... 29
14.3.1
14.3.2
14.3.3
14.3.4
14.3.5
14.3.6
14.3.7
14.3.8
14.4
14.5
Transmission, Zone, Generating and Switching Stations ..................................................... 29
Transmission Powerlines ...................................................................................................... 30
HV Cables ............................................................................................................................ 30
Protection ............................................................................................................................. 30
Supervisory Control and Data Acquisition (SCADA) and Distribution System Automation ... 30
Load Control ......................................................................................................................... 30
Communications ................................................................................................................... 30
Earthing ................................................................................................................................ 31
Testing and Commissioning......................................................................................................... 31
14.4.1
14.4.2
14.4.3
14.4.4
14.4.5
General ................................................................................................................................. 31
Notice and Acceptance Testing ............................................................................................ 31
Standards ............................................................................................................................. 31
Commissioning Tests ........................................................................................................... 32
Acceptance Testing by Essential Energy ............................................................................. 33
Handover and Defects Liability Period ......................................................................................... 33
HV ASSETS TO BE OWNED AND OPERATED BY OTHERS ................................................. 33
15.1
15.2
Design, Equipment and Materials ................................................................................................ 33
Design References ...................................................................................................................... 34
15.2.1
15.2.2
15.2.3
15.2.4
15.2.5
15.2.6
15.2.7
15.3
Transmission, Zone and Switching Stations ......................................................................... 34
Transmission Powerlines ...................................................................................................... 34
HV Cables ............................................................................................................................ 34
Protection ............................................................................................................................. 34
HV Metering.......................................................................................................................... 34
Load Control ......................................................................................................................... 34
Earthing ................................................................................................................................ 34
Testing and Commissioning......................................................................................................... 34
15.3.1
16.
General ................................................................................................................................. 27
Commissioning Program ...................................................................................................... 27
Commissioning Tests ........................................................................................................... 28
HV ASSETS TO BE OWNED BY ESSENTIAL ENERGY ON COMPLETION ........................... 29
14.1
14.2
14.3
15.
Construction Environmental Management Plan (CEMP) ...................................................... 25
Clearing of Vegetation .......................................................................................................... 25
Construction Standards ........................................................................................................ 25
Program ................................................................................................................................ 26
Ownership of Electricity Works ............................................................................................. 26
Constructions Works – Easements and Land Acquisition .................................................... 27
Provision of Registrable Instruments .................................................................................... 27
General ................................................................................................................................. 34
HV OPERATING PROTOCOL .................................................................................................. 35
16.1
16.2
16.3
General ........................................................................................................................................ 35
Operating Protocol ....................................................................................................................... 35
HV Customer Switching and Operational Protocol ...................................................................... 35
16.3.1
16.3.2
16.3.3
Ownership and maintenance ................................................................................................ 35
Maintenance of Switchgear and Protection Equipment ........................................................ 36
Protection Coordination ........................................................................................................ 36
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 4 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
16.3.4
16.3.5
16.3.6
16.3.7
16.3.8
16.3.9
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
Auditing ................................................................................................................................ 36
HV Operations under Normal Conditions ............................................................................. 36
HV Regulatory Requirements ............................................................................................... 37
Operating Procedures .......................................................................................................... 38
Authorised Staff and Access Permits ................................................................................... 38
Network Operations .............................................................................................................. 38
DISPUTE RESOLUTION .......................................................................................................... 39
KEY TERMS AND DEFINITIONS ............................................................................................. 39
ATTACHMENT A – PRELIMINARY CONNECTION ENQUIRY FORM ..................................... 41
ATTACHMENT B – EXAMPLE PROJECT TIMELINE............................................................... 43
ATTACHMENT C - OPERATING PROTOCOL TEMPLATE ..................................................... 44
ATTACHMENT D - SCHEDULE 5.5.3 – NETWORK & PLANT TECHNICAL DATA OF
EQUIPMENT AT OR NEAR CONNECTION POINT ................................................................. 54
ATTACHMENT E - SCHEDULE 5.5.4 - NETWORK PLANT AND APPARATUS SETTING
DATA ........................................................................................................................................ 57
ATTACHMENT F - SCHEDULE 5.5.5 – LOAD CHARACTERISTICS AT CONNECTION POINT59
ATTACHMENT G - APPLICATION FEE MATRIX .................................................................... 60
ATTACHMENT H - CONNECTION SEQUENCE ..................................................................... 61
ATTACHMENT I - CONNECTION SCOPE OF WORKS .......................................................... 62
REFERENCES ......................................................................................................................... 63
REVISIONS .............................................................................................................................. 65
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 5 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
1.
INTRODUCTION
This Operational Procedure is designed to cover the requirements that need to be satisfied
by a Retail Customer taking supply at high voltage and/or an Embedded Generator as a
Connection Applicant to ensure that Essential Energy’s minimum standards for major
customer connections are met.
This Operational Procedure applies to:
a) all negotiated retail customer connection applicants and will follow the connection
process as outlined in CH5A of the NER; and
2.
b)
all Embedded Generator connection applicants and will follow the connection
process as outlined in:
i.
CH5A of the NER for systems greater than 30kW and less than 5MW; or
ii.
CH5 of the NER for systems greater than or equal to 5MW
c)
generators VAr ratios - generation sites greater than 30kW that absorb system
reactive power (measured in VAr’s) at a ratio greater than 4.84kVAr absorbed to
10kW exported must be referred to Essential Energy for further evaluation (refer
Essential Energy Connection Policy – Connection Charges for electricity retail customers CEOP2513.06)
WHY THESE INSTRUCTIONS ARE IMPORTANT
Firstly to ensure a safe and consistent standard is met when undertaking High Voltage
connections and Embedded Generators to the Essential Energy Distribution Network (the
Grid).
Secondly and more importantly, to ensure that connection applicants are informed and
understand the connection process – refer Attachment H - Connection Sequence.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 6 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
3.
CONNECTION ENQUIRY – PROCESS FLOW CHART
3.1
Chapter 5 NER Process
Applicable for all generator connection applications for new systems or modifications to
existing systems greater than or equal to 5MW as defined under CH5 of the NER.
Connection Applicant
Preliminary
Connection
Enquiry
Submitted
Prospecting 3 Months
Initiate
Connection
Discussions
with EE
Essential Energy
Received
Yes – within 5 days
Acknowledge
Enquiry &
Request
additional
details
No – within 5 days
Advise if
Adequate
Continue
Optional
at
Connection Applicant
request
Open for 15 days
Written Advise
to EE
Yes
No
Provide
Preliminary
Response
to Enquiry
Yes – within 15 days
Provide Invoice
Connection
Enquiry Fee
Receipted
Provide
Detailed
Response
to Enquiry
Yes – within 30 days
Potential Delay
Lodge
Connection
Enquiry
Fee
Terminate
Project
Invoice
Receipted
No
Continue
Open for 3 months
Written Advise
to EE
Feasibility 24 Months
Yes
Proponent to undertake
(and not limited to)
technical network performance
analysis
voltage regulation
fault level & sensitivity
stability & harmonics
protection analysis
earthing analysis
operating parameters
No
Investigate
Connection
Requirements
EXECUTE
Land Access
Investigation
Agreement - LAIA
EXECUTE
Connection
Investigation
Services
Agreement CISA
Quality Assurance
(Constestable
Works Linkage)
Upfront
Connection
Investigation
Fee Receipted
EE privide network data and
assess analysis provided
No
Yes
Construction 18 months
Request
additional
details
No
Continue
Proponent to undertake
(and not limited to)
route options analysis
environmental (REF)
Easements/freehold title
connection arrangement
design submission
design dpproval
load control
connection construction
communication
SCADA
commissioning
defects liability
No
Yes
No
Development 24 months
Submit
Connection
Application
Received
Yes – within 5 days
Acknowledge
&
Request
additional
details
No – within 10 days
Advise if
Adequate
Yes – within 4 months
provide
offer to connect
Yes
Open for 20 days
Written Advise
to EE
Received
No
CISA Fees
Invoiced
&
Paid to EE
No
Recoverable
Costs Invoiced
&
Paid to EE
Finalise
connection
agreement &
operating
protocol
Negotiate
(T’s & C’s)
Yes
Yes – time line dependent on negotiations
Operational 25 Years +
Yes
No
offer to
connect
accepted
Finalise Development 12 months
Contestable
Works
Complete
&
Commissioned
Yes
Complete
Execute
connection
agreement &
operating
protocol
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 7 of 66
FOR PUBLIC RELEASE
Yes
Connection
Agreement
EXECUTED
Yes
Proceed
To energise
(with yes x2)
No
Connect Applicants Project to Essential Energy’s Distribution Network
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
3.2
Chapter 5A NER Process
Applicable for all negotiated retail applications (HV load) and embedded generator
connection applications for systems or modifications to existing systems greater than 30kW
and less than 5MW as defined under CH5A of the NER.
Connection Applicant
Prospecting 3 Months
Initiate
Connection
Discussions
with EE
Essential Energy
Preliminary
Connection
Enquiry
Submitted
Received
Yes – within 5 days
Acknowledge
Enquiry &
Request
additional
details
No – within 5 days
Advise if
Adequate
Continue
Open for 3 months
Terminate
Project
Feasibility 24 Months
No
Investigate
Connection
Requirements
Written Advise
to EE
Yes
No
Continue
Yes
EXECUTE
Connection
Investigation
Services
Agreement CISA
Written Advise
to EE
Yes
EXECUTE
Land Access
Investigation
Agreement - LAIA
Proponent to undertake
(and not limited to)
technical network performance
analysis
voltage regulation
fault level & sensitivity
stability & harmonics
protection analysis
earthing analysis
operating parameters
No
Provide
Preliminary
Response
to Enquiry
Yes – within 20 days
Quality Assurance
(Constestable
Works Linkage)
Upfront
Connection
Investigation
Fee Receipted
EE privide network data and
assess analysis provided
No
Yes
Construction 18 months
Request
additional
details
No
Continue
Proponent to undertake
(and not limited to)
route options analysis
environmental (REF)
Easements/freehold title
connection arrangement
design submission
design dpproval
load control
connection construction
communication
SCADA
commissioning
defects liability
No
Yes
No
Development 24 months
Submit
Connection
Application
Received
Yes – within 5 days
Acknowledge
&
Request
additional
details
No – within 10 days
Advise if
Adequate
Yes – within 65 days
provide
offer to connect
Yes
Open for 20 days
Written Advise
to EE
Received
No
CISA Fees
Invoiced
&
Paid to EE
No
Recoverable
Costs Invoiced
&
Paid to EE
Finalise
connection
agreement &
operating
protocol
Negotiate
(T’s & C’s)
Yes
Yes – time line dependent on negotiations
Operational 25 Years +
Yes
No
offer to
connect
accepted
Finalise Development 12 months
Contestable
Works
Complete
&
Commissioned
Yes
Complete
Execute
connection
agreement &
operating
protocol
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 8 of 66
FOR PUBLIC RELEASE
Yes
Connection
Agreement
EXECUTED
Yes
Proceed
To energise
(with yes x2)
No
Connect Applicants Project to Essential Energy’s Distribution Network
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
4.
DEEMED CONNECTION – PROCESS FLOW CHART
Customer
Essential Energy
Initiate Connection Discussions with Customer
Customer to provide technical data,
premise information pertaining to the “Schedules”
of the Connection Agreement, (HV Deemed
Connection Contract (HV-DCCC); and
the requirements of the Operating Protocol.
Initiate preliminary Connection Agreement and
Operating Protocol
discussions and the requirements under Section 7
of the NSW Service & Installation Rules (SIR).
Minimum
HV Single Line Diagram
Protection Report including next line of protection
(refer attachment B of the SIR)
Section 7 SIR
Requirements
Customer has
authorised
switching staff?
Yes
Yes
Customer has
Safety Management Plan,
Electrical Safety Rules
and
HV Maintenance Plan.
Yes
No
Additional
Information
required
No
Customer to contract
ASP and provide copy
of Letter of
Authorisation.
Yes
Adequate
and/or
Additional
information
required
No
No
Yes
Provided
and
Compliant
Yes
Proposed
amendments to
Connection Agreement
And/or
Operating Protocol
Draft Connection Agreement
and
Operating protocol prepared
(includes commercial, legal and
technical terms and conditions)
No
Accept
Prepare final
Connection Agreement
and
Operating protocol
for execution
Yes
Documents executed by Customer and Essential Energy
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 9 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
5.
CONNECTION PROCESS - CH5 NER – EMBEDDED GENERATION
5MW AND ABOVE
5.1
Exploratory Connection Enquiry
This stage of the Essential Energy connection process is informal and not prescribed under
the National Electricity Rules (NER). This phase generally consists of exploratory discussions
between the Connection Applicant and Essential Energy’s Planning and/or Network
Connections business branches.
The purpose of these exploratory discussions is to ensure that the Connection Applicant
understands the Essential Energy connection process, timeframes, potential connection
options and connection requirements.
To make this stage effective, considerable investigation work by the Connection Applicant is
usually required regarding possible connection options prior to formal Connection Enquiry
process. Consultation with Essential Energy’s network planning specialists can assist with
this analysis.
The exploratory discussions with the Connection Applicant often cover in general terms:
NER connection process and timeframes;
Indicative delivery timeframes; and
Information required from the Connection Applicant pursuant to an Adequate
Connection Enquiry or application to connect.
The formal Connection Enquiry process is a two staged process as per CH5 of the NER
5.2
Preliminary Connection Enquiry
This stage of the connection process is a formal requirement under the NER. A Connection
Applicant must make an adequate connection enquiry in accordance with clause 5.3.1A CH5
of the NER before submitting an application to connect.
This requirement also applies to an existing embedded generator planning to modify an
existing connection.
All embedded generator connection enquiries; (5MW and greater) should be directed to
Essential Energy’s nominated project representative - the Customer Connections Manager
by email: networkconnections@essentialenergy.com.au.
Essential Energy will only respond to enquiries from the Connection Applicant or their
authorised representative. Any enquiries by unauthorised third parties will be directed to
the Connection Applicant.
The key objective of this stage is to assist the Connection Applicant to determine a single
preferred connection option before advancing to the Detailed Enquiry Stage of the
Connection Process.
5.2.1
Preliminary Connection Enquiry – Connection Applicant obligations
The Preliminary Connection Enquiry must include all the information as specified on the
Preliminary Connection Enquiry Form (refer to Attachment A – Preliminary Connection
Enquiry Form) to be considered an “adequate connection enquiry”:
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 10 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Expected type of load/ generation;
Preliminary system planning data as listed in Schedule 5.4 of the NER;
Required connection timeframes;
Reliability requirements (eg N, N-1);
Preferred connection location;
Alternative connection locations;
Proposed route of any easements and location of land on which the Electricity
Works are to be constructed or installed;
Project status; and
Company information.
A connection applicant may choose to skip the preliminary response stage by completing
the preliminary connection enquiry and requesting Essential Energy to proceed directly to a
detailed response. In this case the connection applicant will need to submit the preliminary
enquiry together with all the required information for a detailed response and pay the
detailed enquiry fee, refer to clause 5.3.
5.2.2
Preliminary Connection Enquiry - Essential Energy Response
Essential Energy must respond to the Connection Applicant in accordance with clause 5.3A.7
of the NER on receiving an adequate connection enquiry and must:
Within 5 business days acknowledge receipt the Connection Applicant’s Preliminary
Connection Enquiry; and
Also within 5 business days advise the Connection Applicant if any further
information is required to process the connection enquiry; and
Within 15 business days unless otherwise agreed, provide a Preliminary Connection
Enquiry Response.
The response will include the following information
relevant technical information about the DNSP’s network, including guidance on
how the Connection Applicant may meet those requirements;
written details of applicable minimum, automatic and plant standards and normal
voltage level;
identity of other parties to be involved in connection;
those services that are contestable;
worked examples of connection charges;
information regarding the DNSP and its network, system limitations and other
relevant constraints;
whether augmentation may be required;
links to the information pack;
contact details;
DNSP response to objectives of connection sought;
an overview of any available options for connection;
description of the detailed enquiry process;
further information requirements from the connection applicant;
estimate of the enquiry fee and component payable;
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 11 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
estimate of the application fee;
other relevant information 5.3A; and
all information required in S5.4A
5.3
Detailed Connection Enquiry
This stage of the connection process is a formal requirement under the NER. A Connection
Applicant must make a Detailed Connection Enquiry in accordance with the NER before it
can make an application to connect.
This requirement also applies to an existing embedded generator planning to modify an
existing connection.
The purpose of this stage of the Connection Process is to provide Connection Applicants with
the network information needed to prepare a sound business case for their development;
especially for those who are not familiar with the technical and security impacts of proposed
connections on distribution networks.
5.3.1
Detailed Connection Enquiry – Connection Applicant obligations
Following the preliminary enquiry response, a connection applicant may request a detailed
enquiry response by submitting the information requested in the preliminary enquiry
response and paying the required detailed enquiry fee.
The Detailed Connection Enquiry must include all and any additional information or
requirements specified in the preliminary Connection Enquiry Response.
5.3.2
Detailed Connection Enquiry Response
The purpose of this stage is to provide generators with the information they need to prepare
a sound business case for their development; especially for those who are not familiar with
the technical and security impacts of proposed connections on distribution networks.
Essential Energy must respond to the Connection Applicant in accordance with clause 5.3A.8
of the NER on receiving a Detailed Connection Enquiry and the nominated Connection
Enquiry fee. Essential Energy must:
Within 5 business days acknowledge receipt the Connection Applicant’s Detailed
Connection Enquiry and receipt the nominated Connection Enquiry fee;
Within 10 business days advise the Connection Applicant if any further information
is required to process the Detailed connection enquiry; and
Once all the information has been received, Essential Energy will unless otherwise
agreed provide a Detailed Connection Enquiry Response within 30 business days.
The response will include the following information
contact details of the DNSP;
written details of applicable minimum, automatic and plant standards and normal
voltage level;
details of the connection requirements;
details of the level and standard of service of power transfer capability;
negotiated access standards requiring AEMO involvement;
list of technical data as set out in schedule 5.5;
commercial information to satisfy any prudential requirements;
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 12 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
itemised estimate of connection costs;
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
risks and obligations in respect of proposed connection associated with planning
and environmental laws;
draft connection agreement;
description of the process for lodging the application to connect;
application fee;
whether the DNSP agrees to a validity period;
any other relevant information 5.3A;
TransGrid and Australian Energy Market Operator (AEMO) costs for processing a
Connection Enquiry and application to connect;
Whether another Transmission Network Service Provider (TNSP) or Distribution
Network Service Provider (DNSP) should be involved in the connection process;
Definition of the various connection services under the NER and potential
negotiated, contestable or prescribed make-up; and
Essential Energy may elect to, at this initial stage, advise AEMO (Power System
Planning and Development) of the Preliminary Connection Enquiry depending on its
nature.
Essential Energy’s detailed connection enquiry response will only be valid for the network
configuration which exists at the date of the response.
6.
CONNECTION PROCESS - CH5A NER – EMBEDDED GENERATION
LESS THAN 5MW AND RETAIL CUSTOMER CONNECTIONS (HV LOAD
CUSTOMERS)
6.1
Exploratory Connection Enquiry
This stage of the connection process is informal and not prescribed under the National
Energy Rules (NER). This phase generally consists of exploratory discussions between the
Connection Applicant and Essential Energy’s Planning and/or Network Connections Business
Units.
The purpose of these exploratory discussions is to ensure that the Connection Applicant
understands the connection process, timeframes and potential connection options.
To make this stage effective, considerable investigation work by the Connection Applicant is
usually required regarding possible connection options. Consultation with Essential Energy’s
network planning specialists can assist with this analysis.
Essential Energy may be able to offer some services on a ‘fee for service’ basis to review
these investigations, or through entry into a Connection Investigation Services Agreement
(CISA) and/or Land Acquisition Investigation Agreement (LAIA).
The exploratory discussions with the Connection Applicant often cover in general terms:
NER connection process and timeframes;
TransGrid and Australian Energy Market Operator (AEMO) costs for processing a
Connection Enquiry and application to connect;
Whether another Transmission Network Service Provider (TNSP) or Distribution
Network Service Provider (DNSP) should be involved in the connection process;
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 13 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Definition of the various connection services under the NER and potential
negotiated, contestable or prescribed make-up;
Indicative delivery timeframes; and
Information required from the Connection Applicant pursuant to an Adequate
Connection Enquiry or application to connect.
Essential Energy may elect to, at this initial stage, advise AEMO (Power System Planning
and Development) of the Preliminary Connection Enquiry depending on its nature.
6.2
Preliminary Connection Enquiry
This stage of the connection process is a formal requirement under the NER. A Connection
Applicant must make an adequate connection enquiry in accordance with clause 5A.C.1 of
the NER before it can make an application to connect.
All HV load and embedded generator connection enquiries (not connecting as Basic or
Standard Connections) should be directed to Essential Energy’s nominated project
representative
the
Connection
Contracts
Manager
by
email:
networkconnections@essentialenergy.com.au.
Essential Energy will only respond to enquiries from the Connection Applicant.
enquiries by third parties will be directed to the Connection Applicant.
Any
This requirement also applies to an existing HV customer or an embedded generator
planning to modify an existing connection.
6.2.1
Preliminary Connection Enquiry – Connection Applicant obligations
The connection enquiry must include the following information (refer to Attachment A –
Summary NER Schedule 5.4 Connection Enquiry) to be adequate:
Expected type of load/ generation;
Preliminary system planning data as listed in Schedule 5.4 of the NER;
Required connection timeframes;
Reliability requirements (eg N, N-1);
Preferred connection location;
Alternative connection locations;
Proposed route of any easements and location of land on which the Electricity
Works are to be constructed or installed;
Project status; and
Company information.
The key objective of this stage is to assist the Connection Applicant to determine a single
preferred connection option before advancing to a formal Connection Application. It also
clarifies the information required to achieve an NER compliant Connection Application.
6.2.2
Preliminary Connection Enquiry – Essential Energy Response
Essential Energy must respond to the Connection Applicant in accordance with clause
5A.D.2 of the NER on receiving an adequate connection enquiry and must:
Within 5 business days acknowledge the Connection Applicants connection Enquiry
and advise the Connection Applicant if any further information is required to
process the connection enquiry
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 14 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Within 20 business days advise the Connection Applicant:
o
if another TNSP or DNSP is to be involved;
o
if any of the connection works are contestable;
o
of a preliminary programme indicating milestones;
o
the technical requirements;
o
the access standards (automatic);
o
the applicable plant standards;
o
the nominal voltage level;
o
if AEMO is to be involved in any of the above;
o
the connection application requirements;
o
specifications of the facility to be connected;
o
power transfer capability;
o
the fee applicable for Essential Energy to process an application to connect;
and
o
any other information required pursuant to an application to connect.
Essential Energy may also be able to assist the Connection Applicant in reviewing their
analysis of the various connection options to determine the required information necessary
for a valid connection application. This service is outside the NER framework and the
Connection Applicant may be required to enter into a CISA and/or LAIA at this time.
Essential Energy’s preliminary connection enquiry response will only be valid for the
network configuration which exists at the date of the response.
7.
CONNECTION ENQUIRY QUEUING
Essential Energy is cognisant that a Connection Applicant may attempt to “lock up” network
capacity by making a connection enquiry which does not result in a connection application
within a reasonable timeframe, thereby making it difficult for Essential Energy to make this
capacity available to any other party. Essential Energy will adopt the following policy with
regard to the treatment of connection enquiries and Connection Applications (to the extent
that it has the power to do so):
IF a connection enquiry is received which is NER compliant and a resulting connection
enquiry response has been provided by Essential Energy,
AND Essential Energy is of the opinion that insufficient progress is being made towards a
Connection Application by the Connection Applicant, such application being expected within
3 months of the date of Essential Energy’s final response to the Connection Enquiry,
THEN the Connection Applicant will be asked to show cause why the network capacity
applied for should not be offered to any other Connection Applicants who have made a
connection enquiry for this capacity. Until and unless Essential Energy issues a show cause
notice, Essential Energy will allocate available network capacity in amounts requested by
applicants based on the date Essential Energy receives each Connection Enquiry.
8.
CONNECTION INVESTIGATION SERVICES AGREEMENT (CISA) AND
LAND ACCESS INVESTIGATION AGREEMENT (LAIA)
Where the proposed connection is typical and/or investigation/assessment is required,
Essential Energy will seek to enter into a CISA with the Connection Applicant. Where
Electricity Works are to be constructed or installed, Essential Energy will seek to enter into
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 15 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
an LAIA with the Connection Applicant. This may be done at any time following the receipt
of a connection enquiry or during the connection application process.
An example project timeline to be provided by the Connection Applicant is included in
Attachment B.
Add hyperlink to these documents <CISA> <LAIA>
9.
MODIFICATION TO EXISTING CONNECTION
An existing customer proposing to modify their HV connection will be required to lodge a
connection application in accordance with this guideline and the NER.
Where a Connection Applicant has an executed connection agreement it will be necessary to
either enter in to a deed of amendment to document the modifications to the original
agreement or execute a new connection agreement.
In accordance with the NER, Deemed HV customers modifying their connections
(Connection Applicant) will be required to enter in to a connection agreement with Essential
Energy.
10.
CONNECTION APPLICATION
10.1
General
This stage of the connection process is a formal requirement under CH5 of the NER.
A Connection Applicant intending to connect to Essential Energy’s network must make a
Connection Application in accordance with clause 5.3.4 of the NER.
Where the Connection Applicant has made a conforming Connection Application, Essential
Energy must make an offer to connect in accordance with clause 5.3.5 of the NER.
The key objective of this stage is to finalise the technical and commercial arrangements
applicable to the connection, including, if necessary, the negotiation of performance
standards pursuant to clause 5.3.4A of the NER.
Essential Energy will review the connection application and if incomplete, will within 10
business days advise the connection applicant of the outstanding requirements.
Once a conforming Connection Application has been accepted, Essential Energy will issuing
the connection applicant an offer to connect. An offer to connect will be issued within 4
months of receipt of the conforming Connection Application unless an extension has been
agreed by the connection applicant. The offer to connect will include connection services
costs.
The connection applicant will then have 20 business days, or another period as agreed with
Essential Energy, to review and accept the offer to connect and enter into a Connection
Agreement. A sample Connection Agreement can be found on the Essential Energy Website.
This stage is finalised when the Connection Applicant accepts Essential Energy’s offer to
connect.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 16 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
10.2
Information to be provided with Connection Application
In general, confirmation of the location, proposed capacities, type of generator/load and
connection arrangements need to be provided by the Connection Applicant for consideration
against a specific project application before an offer to connect can be made.
The Connection Applicant must include the following information in a connection application:
Maximum transfer capability (real power) requirements;
Contribution to fault levels;
Size and rating of all relevant power transformers (and test certificates prior to
connection);
Protection analysis - Report ( to include a protection SLD);
Communication systems;
Voltage control;
Reactive power capability;
Agreed target voltage range at the Connection Point;
Proposed negotiated performance standards pursuant to clause 5.3.4A of the NER;
Technical network performance analysis (including stability and harmonics) –
Report;
Voltage regulation analysis – Report;
Fault level and sensitive analysis – Report;
Earthing analysis – Report;
Operational parameters;
Detailed system planning data as detailed in Schedule 5.5.3, Schedule 5.5.4 and
Schedule 5.5.5 of the NER;
Connection date (commissioning date of the Connection Point);
Reliability requirements (N, N-1);
Connection Point location and connection configuration arrangement (Single Line
Diagram – showing the agreed Connection Point (CP) and Point of Common
Coupling (PoCC);
Project status;
Commissioning date of Connection Point;
Ownership of connection assets;
Technology of embedded generation units if applicable;
Single Line Diagram of facility to be connected (showing metering location);
General arrangement - facility substation/switching station (showing connection
point);
Company information;
Schedule of connection equipment;
The application fee where applicable;
Table S5.5.3 – Network & Plant Technical Data of Equipment at or near Connection
Point Attachment D;
Table S5.5.4 – Network Plant and Apparatus Setting Data Attachment E;
Table S5.5.5 – Load characteristics at Connection Point Attachment F; and
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 17 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Details of the land tenure for the electricity works including land owner agreements,
the consultation processes and easement requirements or land acquisitions that
remain outstanding - Please note, easements must be registered and any decision
to connect without them is at the absolute discretion of Essential Energy.
Other relevant information that may be required by Essential Energy includes but is not
limited to:
A detailed construction program;
Details of assets to be transferred to Essential Energy;
Full copy of all approvals required by environmental laws for the construction and
operation of the assets and all documents that supported the application for such
approvals and compliance with them;
The requirements for route corridor, centreline, access (particularly permanent
access) to the electricity works, and/or details of land required for infrastructure,
survey and design options analysis;
If requested, draft route/ corridor, centreline, access and land requirements are
best initially obtained by GPS survey but after investigation must be fixed by formal
registered survey to enable the prompt registration of appropriate plans for the
acquisition of land or grant of easements;
Land owner agreements, consultation processes and easement requirements or
land acquisitions by agreement;
All relevant Essential Energy design specifications; and
Approved materials list, approved equipment may if available be purchased from
Essential Energy or by negotiation with the manufacturer.
In addition to the requirements under the NER, the Connection Applicant must comply with
the requirements of Section 7 of the Service and Installation Rules of NSW for loads and
additionally, Section 8 for embedded generators.
Particular attention should be paid to clause 13.10 of this document. Reasonable lead time
must be left to train employees to operate the installation in accordance with Section 7 of
the Service and Installation Rules of NSW.
10.3
Australian Energy Market Operator (AEMO)
Essential Energy must notify AEMO of the Connection Application and supply AEMO with the
Connection Applicant’s proposed negotiated performance standards.
AEMO must within 20 business days of receiving proposed negotiated performance
standards from Essential Energy:
Respond in writing in respect of any negotiated performance standards that are
defined by the NER as “AEMO advisory matters”; and
Advise Essential Energy and the Connection Applicant whether the proposed
metering installation is acceptable.
Essential Energy must accept AEMO’s advice with respect to AEMO advisory matters.
10.4
Essential Energy
Essential Energy must maintain power transfer capability, power quality and system stability
as specified in the National Electricity Rules to all network users. Therefore when assessing
a connection application, the impact of the connection on the network along with any
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 18 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
operational issues, protection, earthing and safety issues will be considered in each stage of
the application process.
Within 30 business days of receiving proposed negotiated performance standards, Essential
Energy must:
Accept the proposed negotiated performance standards; or
Reject and nominate revised, negotiated performance standards.
Essential Energy must scope and estimate works required to provide the negotiated
connection services, and determine the negotiated service charges to apply (if applicable).
For contestable electricity works, the Connection Applicant and Essential Energy will discuss
the requirements.
Essential Energy may also advise charges applicable to the contestable works if it is willing
to provide those services.
10.5
The Application Fee
The Connection Applicant must submit a connection application, including fees, in
accordance with Essential Energy’s normal invoicing practices. The connection application
will only be deemed to be received from the date the connection application fee is received
by Essential Energy and all relevant materials are provided under clause 10.2.
If the Connection Applicant does not enter into a CISA with Essential Energy, a nonrefundable connection application fee based on Essential Energy’s connection fee matrix will
be payable (refer Appendix G Application Fee). The connection application fee covers the
reasonable costs of work anticipated to arise from reviewing the connection application and
preparing the associated offer to connect, including, but not limited to, provision of relevant
network data, review designs, planning assessment and legal fees. It also covers reasonable
costs of AEMO and other Network Service Providers to assess the connection application.
If the Connection Applicant enters into a CISA with Essential Energy, the connection
application fee may be in addition to the amounts payable by the Connection Applicant for
services rendered under the CISA. The decision as to whether a CISA will be required will be
at Essential Energy’s discretion.
Connection Applicants will be required to meet other reasonable costs incurred by Essential
Energy, typically being; review of updated documents previously submitted and found
inadequate, to AEMO, other Network Service Providers (for example, TransGrid) and in
obtaining legal advice in negotiating the connection agreement. Essential Energy will
invoice these fees on a cost pass through basis as they are incurred.
10.6
The Offer to Connect
Essential Energy must respond to a connection application with an offer to connect in
accordance with the NER.
The offer to connect will:
Highlight any planning and environmental laws not covered by the NER which may
be relevant to the construction and operation of the assets;
Advise if TransGrid and/or AMEO will be involved and their costs;
Outline the technical requirements of equipment to be connected;
Outline the automatic access standards;
Outline the negotiated access standards;
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 19 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Outline the extent and cost of any augmentations works to the network;
Outline any network service charges;
Outline effects on other network users (transfer capacity);
Advise of cost for remote control and monitoring equipment required by AEMO if
applicable; and
Contain commercial terms and conditions.
The offer to connect will also include the Connection Agreement containing the proposed
terms and conditions for connection to the network in accordance with Clause 5.3.6 of the
NER. The Connection Applicant and Essential Energy will then negotiate the commercial and
technical, terms and conditions with respect to the proposed connection.
10.7
Acceptance of Offer to Connect
If the Connection Applicant wishes to accept an offer to connect, the Connection Applicant
agrees to be bound by relevant provisions of the NER; and agree to negotiate connection
agreement with Essential Energy.
11.
CONNECTION AGREEMENT
Essential Energy’s connection agreement will deal with:
Location of connection project;
The agreed point of connection (shown on a Single Line Diagram - SLD);
The Connection Agreement term, commencement and termination dates;
The maximum Voltage fluctuation;
Connection assets to be transferred to Essential Energy;
Easements and other Registrable Instruments;
Land title deeds;
Route or land plans – initial survey and final form of survey;
The agreed technical standards of equipment to be connected;
The agreed access standards (automatic or negotiated);
The agreed performance standards (for generators);
Any augmentation work to the network;
Any ancillary services provided by the Connection Applicant;
Any network service charges;
The agreed network transfer capacity;
The remote control and monitoring equipment required by AEMO if applicable;
Proposed metering installation;
Arrangements for meter provision;
The commercial terms and conditions;
Maximum voltage fluctuation;
Authorised staff; and
Land tenure, if required and not addressed in any LAIA.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 20 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Note that the connection of the connecting assets may be conditional on gaining
environmental and planning approvals for any necessary augmentation or extension works
to Essential Energy’s network and finalisation of other schedules to the connection
agreement post execution.
The agreement may also address the delivery of assets required to give physical effect to
the connection service.
The minimum requirements to be followed during negotiations between Essential Energy
and a Connection Applicant wishing to negotiate a connection contract under Chapter 5A of
the Rules are set out CEOP2513.08 Essential Energy’s Negotiation Framework.
If a deemed connection is required to be documented under the NER, the connected person
will be taken to be a Connection Applicant for the purposes of the connection agreement.
Template connection agreements are available by contacting the Customer Connections
Manager by email: networkconnections@essentialenergy.com.au
Failure to establish a Connection Agreement prior to connection will cause a delay to
connection.
12.
CONTESTABILITY OF SERVICES
12.1
General
Essential Energy advises that in the NSW jurisdiction, the following services are contestable:
Design, planning and protection studies;
Design of network connection assets (including telecommunications, control and
protection systems);
Procurement and construction of network connection assets; and
Metering design, installation and provision of data services for type 1 to 4 meters.
Connection Applicants need to engage an appropriate service provider(s) to carry out the
required contestable services. Connection Applicants will also be required to complete and
submit full studies of the network performance regarding voltage regulation, fault level and
sensitivity, stability and harmonics, protection and operating parameters for the proposed
connection as part of the assessment and approval process. Essential Energy will assist
with the provision of network information relating to these connection assessments as
requested.
Please note that in addition to the planning and design approvals above,
Connection Applicants will be fully responsible for all works and costs associated
with providing the required connection assets including the acquisition of line
easements and substation/switching station sites, environmental and planning
approvals, materials procurement, construction and commissioning.
For the avoidance of doubt, the Connection Applicant may also be required to fund EE asset
extensions and/or augmentation in addition to the charges that may apply for connection
services described within other sections of this document.
Essential Energy will cooperate in the provision of any required connection information.
Refer to Attachment I - Connection Scope of Works - for a summary of likely works required
to be undertaken by the Connection Applicant.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 21 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
12.2
Accredited Services Providers
Under the Electricity Supply Act 1995, customers are required to fund certain works which
are required to enable new or expanded connection to the electricity network. Essential
Energy will advise whether the work is contestable in accordance with CEOP8019 – Capital
Contributions and the parts of the work required to be funded by the Connection Applicant.
If the work is contestable, the Connection Applicant will need to seek quotes from
appropriately qualified Accredited Service Providers (ASPs) to carry out these works.
The ASP must be accredited as an ASP to undertake the type of work proposed. That
accreditation, along with a system of inspecting and auditing of completed works, seeks to
ensure that any work is designed, constructed or installed to provide for the efficient,
reliable and safe operation of the completed works.
The accreditation of ASP’s is administered by the NSW Trade and Investment. Information
about the scheme, levels of accreditation and currently accredited ASPs is available from the
website:
http://www.resourcesandenergy.nsw.gov.au/energy-supply-industry/pipelines-electricitygas-networks/network-connections/contestable-works
In the event that Essential Energy is required to invest in infrastructure and the costs of
that investment are not transferable to the customer, clause 12.3 will apply.
12.3
Guarantee of Revenue (GoR) (Security Fee)
In accordance with Chapters 5A and 6 of the NER and the Retail Connection Charge
Guideline, Essential Energy will require a Connection Applicant to provide a financial
guarantee or Guarantee of Revenue (GoR), where their connection requires substantial
Essential Energy funded network augmentation which is initially only for the Connection
Applicant’s benefit; and in relation to which Essential Energy is of the view that there is a
high risk that Essential Energy will not earn the estimated incremental revenue.
The GoR is a financially binding legal agreement between Essential Energy and the
Connection Applicant where the Connection Applicant guarantees the payment to Essential
Energy of a minimum level of network revenue each year for the duration of the GoR, to
make up any shortfall in their actual ‘Network use of system’ charges over the period,
usually between 5 and 10 years depending upon the circumstances.
The GoR will be established at the same time as the Connection Offer is accepted and/or the
design information package is issued and prior to the network augmentation being initiated.
This will allow the network augmentation to proceed in parallel with the associated
Contestable works.
The GoR is secured by a bank guarantee provided by the Connection Applicant for no more
than the value of the incremental costs Essential Energy will incur in undertaking the
network augmentation, or other suitable financial instrument as agreed by Essential Energy.
As a last resort, Essential Energy is entitled to withdraw from the bank guarantee any
shortfall in actual Network use of system payment, in accordance with the terms of the GoR
and the bank guarantee.
13.
HV ASSETS GENERAL REQUIREMENTS
13.1
Initial Requirements
The design of the electricity works will constitute contestable work and must be carried out
by a Level 3 ASP (accredited to design transmission and distribution works).
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 22 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Details of the Level 3 ASP selected by the Connection Applicant shall be submitted to
Essential Energy for approval.
Plant and equipment should be designed in accordance with Essential Energy’s requirements
in accordance with Clauses 7, 8 and 9 of this document as applicable and with the relevant
access standards set out in the following Schedules in the NER:
Schedule 5.2 for connection of generators;
Schedule 5.3 for connection of customers (loads); and
Schedule 5.3a for connection of a market network service.
The proposed design shall be submitted to Essential Energy for approval prior to
commencement of the connection works.
If any part of the proposed electricity works is situated on a mining lease, the area of land
the site encompasses and suitable access for vehicles and plant must be excised from the
mining lease (including access and buffer zone).
Essential Energy will require the
Connection Applicant to commit to this process as part of the connection agreement.
Significant delays in achieving this may impact on commissioning programs.
The Work Health and Safety Regulation 2011 requires all designers, manufacturers, and
suppliers of plant and equipment to provide all available information about the plant and
equipment that is necessary to enable other persons to fulfil their responsibilities, in
accordance with CECM1000 – Health, Safety and Environmental Manual: Index, to:
Identify hazards;
Assess risks arising from those hazards;
Eliminate or control those risks; and
Provide information.
13.2
Network Connection Configuration
The configuration arrangements for overhead and underground connections are detailed in
Essential Energy documents CEOM7114.01, CEOM7114.02 and CEOM7114.03 which are
available from our website.
13.3
Structural Adequacy
A suitably authorised professional must certify that all aspects of the plant and equipment
design have been assessed for structural adequacy.
13.4
Subtransmission and Distribution Network
Subtransmission and distribution network design and equipment requirements will be
advised by Essential Energy through the issue of a Design Information Pack (DIP).
Standard equipment may vary depending on the location of the proposed installation.
Essential Energy’s design and construction manuals can be obtained from:
External Sales Officer
Telephone: 13 23 91
Copies of these documents are also available on Essential Energy’s website:
http://www.essentialenergy.com.au/DocumentLibrary/registration
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 23 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
13.5
TransGrid Requirements (if required)
TransGrid will require sufficient notice to install upstream metering and protection
equipment required by the NER.
The costs of TransGrid upgrades will be payable by the Connection Applicant.
13.6
HV Metering
13.6.1
General
Any metering installation unit to be connected to the national grid and operate under
market conditions must have Voltage Transformer (VT) and Current Transformer (CT)
National Association of Testing Authorities (NATA) traceable test certificates provided by the
installing contractor or manufacturer. All metering must comply with the AEMO national
metrology procedure (documents are available from AEMO’s website). The following link to
the AEMO Metrology Procedure provides information on the application of metering
installations to connection points and sets out provisions for metering installations and
metering data services.
http://www.aemo.com.au/Electricity/Policies-and-Procedures/Metrology-Procedures-andUnmetered-Loads/NEM-Metrology-Procedure
For further details also refer to Chapter 7 of the NER.
13.6.2
Metering Voltage
Chapter 7 of the NER stipulates that the metering point be located as close as practicable to
the connection point. All new connection points must be metered in the customer’s
installation at the connection point supply voltage. Metering on the secondary side of
transformers owned or leased by the customer is not permitted for new installations.
Also to comply with the NER, in the event of any electrical alterations, existing installations
metered on the secondary side of a customer’s transformer must be modified so that they
are metered at the connection point voltage.
13.7
Construction Works
13.7.1
General
The construction of contestable works must be carried out by a Level 1 or Level 2 ASP.
Level 1 accreditation allows for the construction and installation of transmission and
distribution works including substations
Level 2 accreditation allows for the construction of service lines between the
distribution system and the point of connection to the premises and for the
installation and energising of metering services.
In addition to accreditation from NSW Trade and Investment, Level 1 and Level 2 ASPs
working on or near the electricity network must have written authorisation and conditions
granted by Essential Energy.
The Connection Applicant must ensure that there is a safe system of work for all involved in
the project in compliance with all applicable standards and statutory requirements.
The Connection Applicant must ensure that all construction activities meet the requirements
of the environmental impact assessment as well as all applicable statutory environmental
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 24 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
approvals
and
requirements
(CECM1000.70
Environmental Impact Assessment).
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Environmental
Operations
Manual:
Work that does not satisfy the requirements of certified plans, design information,
regulatory requirements and quality of materials will cause delay of connection.
13.7.2
Environmental Impact
Early provision of land and easement requirements for the project including preliminary
survey details of any route, corridor and centreline of the corridor for transmission
requirements and access to the corridor should be provided by the Connection Applicant.
Essential Energy must be consulted about its requirements for such corridor and access at
an early stage of any proposed electricity works.
13.7.3
Environmental Impact Assessment
The environmental impact assessment of the proposed electricity works, including clearing
of vegetation, must be provided by the Connection Applicant to Essential Energy and include
a list of mitigation measures that will be implemented to limit the extent of environmental
impacts. Refer to REF Guidelines
13.7.4
Construction Environmental Management Plan (CEMP)
The Connection Applicant must develop a CEMP to be used for the practical construction of
the Electricity Works, especially a transmission line.
The CEMP must address and comply with:
All approvals which apply to the construction and operation of the assets;
Mitigation measures identified in the environmental impact assessment; and
All other environmental requirements issued by Essential Energy or any relevant
statutory authority to the Connection Applicant from time to time.
13.7.5
Clearing of Vegetation
Where required all vegetation clearing along the route of the power line shall be the
responsibility of the Connection Applicant. This work must be done in accordance with all
environmental laws, approvals and Essential Energy’s requirements and standards.
(CECM1000.77 – Environmental Operations Manual: Flora and Fauna.)
Vegetation clearing must not commence until the Connection Applicant has obtained all
relevant Approvals, the consent of all affected landowners.
13.7.6
Construction Standards
All construction must be in accordance with the approved design drawings. Assets that are
to be transferred to Essential Energy will be subject to audit by Essential Energy during
construction. Essential Energy will appoint an auditor to ensure compliance to design and
the quality of the assets. Inspection will be undertaken at key stages of the construction
process, with the minimum number of inspections determined prior to commencement of
construction on receipt of the approved schedule/construction program.
The design process may introduce risk to Essential Energy unless the process is controlled
and due consideration given to Occupational Health and Safety (OHS) issues during the
design phase. Design control seeks to eliminate risks emanating from the design process
through the implementation of procedures that identify and account for risk in design
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 25 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
activities such as the construction and use of plant, equipment, facilities and processes
(CECM1000 – Safety, Security, Health and Environmental Management – 4.4.6).
13.7.7
Program
A detailed construction program (including project milestones and test points) must be
submitted to Essential Energy for approval prior to commencement of works.
The program must identify any work involving outages of other Essential Energy assets,
especially if it means an interruption to customer supply. All efforts must be made by the
Connection Applicant to ensure safe working methods are used and to avoid or minimise the
number of customer outages. If customer outages are unavoidable, the Connection
Applicant will be responsible for the provision of local generation to affected customers; the
costs of which are to be borne by the Connection Applicant. This includes all costs
associated with advertising and notifying customers of the proposed supply interruptions.
If a supply interruption is required, it will take place at a time and date determined by
Essential Energy, minimising any inconvenience to existing customers.
Essential Energy may request a variation to the program to allow for augmentation of the
existing network and other requirements of Essential Energy.
13.7.8
Ownership of Electricity Works
Once the construction of the assets has been completed, the Connection Applicant may
either retain ownership of completed assets, or negotiate to gift them either in full or in
part, to Essential Energy to own and operate.
The point of connection to Essential Energy’s network infrastructure is dependent on the
Connection Applicant’s choice:
If ownership is retained then the point of connection will be where the Connection
Applicant’s connection assets join Essential Energy’s shared network; and
If ownership is gifted to Essential Energy then the Point of Connection will be on the
network side of the Connection Applicant’s isolating equipment.
Generally, the conditions on which Essential Energy will accept ownership of the connection
assets are:
The connection assets are designed and constructed in accordance with all
environmental laws, approvals and Essential Energy’s standards and guidelines.
Essential Energy may require that certain types of equipment be supplied by certain
suppliers before it will take ownership. This will permit Essential Energy to
maintain common spare parts and standardise product training for its employees so
that the duration of outages caused by any failure of the electricity works can be
minimised; and
Essential Energy will charge the Connection Applicant to recover the costs of
maintenance and operation of the electricity works and any system augmentation
works caused by the connection.
Further considerations in relation to ownership of electricity works are set out in Clause 13.
Once Essential Energy assumes ownership of any electricity works, they become part of
Essential Energy’s distribution system and are available for access by other parties in
accordance with the National Electricity Law. These other parties may be required to
contribute a fair and reasonable proportion of the capital cost of establishing, operating and
maintaining the system. Appropriate capital reimbursement may be made to the Connection
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 26 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Applicant based on IPART’s determination on capital contributions and any other applicable
law.
13.7.9
Constructions Works – Easements and Land Acquisition
Any new electricity works constructed or installed on non-public land or Crown land or
Crown roads must normally be contained within an easement or land to be transferred or
vested in Essential Energy.
The general details of the easement requirements are outlined in Essential Energy’s
document CEOP8046 Easement Requirements which contains details of the form and terms
of the easement required.
Where land is to be transferred or vested in Essential Energy or easements for the
electricity works are necessary, the proposed land or easement corridor and centreline of
any electricity transmission line will need to be prepared by a registered surveyor as soon
as possible. This may be effected initially by GPS, and following negotiations with
landholders, by full formal registered survey after due investigation in accordance with all
approvals.
13.7.10 Provision of Registrable Instruments
By the end date for construction and prior to connection, relevant registrable instruments in
a form satisfactory to Essential Energy together with all necessary deeds, consents and
documents of title necessary to register the easements the subject of the registrable
instruments without recourse to any third party, will need to be provided to Essential
Energy. Failure to provide instruments prior to connection will result in a delay of that
connection.
13.8
Testing and Commissioning
13.8.1
General
Essential Energy needs to ensure that appropriate tests have been completed on all high
voltage equipment before it can be safely energised. This will require close cooperation
between the ASP and Essential Energy.
13.8.2
Commissioning Program
Prior to energising or commissioning any HV equipment, a detailed step by step
commissioning procedure must be submitted to Essential Energy for approval
(Commissioning program).
The commissioning program must detail the sequence to be undertaken to energise each
piece of high voltage equipment and must include:
Single line diagrams of all HV equipment as installed;
A proposed timetable for the commissioning works, nominated supervisor and
employees involved including contact details;
A summary of pre-commissioning checks completed and results to date; and
Confirmation that all work undertaken by the Connection Applicant for the project
meets the relevant Australian Standards including AS3000, AS3007 (where
applicable), Service and Installation Rules of NSW (any requirements specific to
NSW, Victoria or QLD as applicable) as well as tests required by the manufacturer
of specific items of plant and equipment.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 27 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
On receipt of the commissioning program, Essential Energy will assess its adequacy.
Essential Energy may require additional testing to be performed if it considers that the
proposed commissioning program is not in accordance with Essential Energy’s
commissioning policies and procedures.
13.8.3
Commissioning Tests
Essential Energy and the Connection Applicant shall meet to determine a mutually
acceptable time for commissioning tests to be carried out.
Before any commissioning test is performed, Essential Energy and the Connection Applicant
must agree on the procedures to be used for relevant commissioning tests and any
modification to or deletion from the procedures that are relevant to the commissioning
tests.
Commissioning tests must be carried out in the presence of representatives nominated by
the Connection Applicant and Essential Energy. The Connection Applicant must provide the
results of the commissioning tests to Essential Energy.
Commissioning tests must be carried out in accordance with good industry practice. The
Connection Applicant and Essential Energy must use their best endeavours to cooperate
with each other and coordinate the testing and commissioning of all HV assets.
If commissioning tests confirm further corrective work is required on the Connection
Applicant’s HV assets, the Connection Applicant must then:
Undertake, at its own cost, all rehabilitation, modification or remediation work
required to the reasonable satisfaction of Essential Energy; and
Report back to Essential Energy in writing when all corrective work has been
completed and renegotiate a suitable program to recommence commissioning tests.
Refer to the commissioning documents:
<Commissioning & test procedure subtransmission cable>
<Commissioning & test procedure subtransmission overhead lines>
13.9
Records
During the commissioning phase, records of OHS inspection, testing and monitoring must
be maintained and readily accessible on request.
13.10
Training
The Connection Applicant must comply with the requirements of the Service and Installation
Rules of NSW – Section 7. Particular attention is drawn to Clause 7.5.9 of the Service and
Installation Rules of NSW with respect to operating a HV installation. Reasonable lead time
must be left to train employees to operate the installation. The Connection Applicant must
provide evidence to Essential Energy that these requirements have been satisfied.
If Essential Energy is to be retained as the HV operator for the site, the same restrictions to
commissioning procedures will apply until the same proficiency in operating the equipment
on site has been satisfactorily attained – refer to the Essential Energy brochure
ESS304_SafeWorkTrainingFlyer_HR which is available from our web site.
Essential Energy can also arrange for training of the Connection Applicant’s nominated
employees given sufficient notice well in advance of the commissioning date (subject to
trainers being available). Details of training requirements are outlined in Essential Energy
document CEOP2238 High Voltage: Customer Operational Training Requirements.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 28 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
13.11
Authority for Placing Major Electrical/Plant Equipment into Service
Authority for placing major electrical/plant Equipment into service (CEOP2047) applies to all
new major electrical plant/equipment.
The purpose of procedure CEOP2047 is to ensure that Essential Energy’s Network
Operations department receives written notification that all construction and precommissioning checks on major electrical plant/equipment are complete and ready for
service.
Prior to final commissioning and energising of the high voltage equipment, direct lines of
communication must be established between:
The Connection Applicant’s nominated person for site commissioning and ongoing
operations; and
The designated Essential Energy System Operations Centre.
14.
HV ASSETS TO BE OWNED BY ESSENTIAL ENERGY ON
COMPLETION
14.1
General
In addition to the requirements listed under Section 13, of these Guidelines, the
requirements of this section 14 must be complied with for all assets to be owned by
Essential Energy on completion of the electricity works.
14.2
Design, Equipment and Materials
All design details including equipment/materials must be endorsed by a Level 3 ASP and
submitted to Essential Energy for approval in principle prior to the Connection Applicant or
its representative ordering equipment or commencing works on site.
All associated design manuals and test certificates must be provided to Essential Energy.
Essential Energy will detail the specific equipment that will need to be installed in
accordance with the design requirements of this section.
Essential Energy will provide a copy of CEOM7004 - Materials Inventory, Contestability
(Approved) –for reference.
All equipment must generally be approved by Essential Energy.
If the Connection Applicant intends using non-Essential Energy approved equipment, then a
verification process must be undertaken. If Essential Energy accepts the equipment, then
sufficient spare parts and appropriate training for operational and maintenance
requirements must also be provided by the Connection Applicant.
14.3
Design References
14.3.1
Transmission, Zone, Generating and Switching Stations
Transmission, zone, generating and switching station design must comply with the
requirements of CEOP8032 Transmission and Zone Substations Design Guidelines.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 29 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
14.3.2
Transmission Powerlines
Transmission powerlines must comply with the requirements of:
AS/NZS 7000:2010 “Overhead line design – Detailed procedures”;
CEOM7097 Overhead Design Manual; and
CEOM7099 Overhead Construction Manual.
14.3.3
HV Cables
HV cables must comply with the requirements of:
CEOM7097 Overhead Design Manual;
CEOM7098 Underground Design Manual;
CEOM7099 Overhead Construction Manual; and
CEOM7199 Underground Construction Manual.
14.3.4
Protection
The Connection Applicant/ASP must liaise and negotiate with Essential Energy’s Protection
Design team as to the type and electrical characteristics of HV and associated secondary
equipment to be installed. This will allow Essential Energy to install and set appropriate
protection schemes upstream and at the connection point and manage the system. If
Essential Energy needs to install new and/or replace existing protection schemes as a result
of this process the Connection Applicant must pay those costs.
Essential Energy will require two months’ notice prior to any commissioning of HV and
associated secondary equipment.
Protection design must comply with the requirements of the following Essential Energy
documents:
CEOP8002 High Voltage Protection Guidelines; and (if applicable)
CEOP8012 Cogeneration Protection Guidelines.
14.3.5
Supervisory Control and Data Acquisition (SCADA) and Distribution System Automation
SCADA and distribution system automation design shall comply with the requirements of
CEOP8084 Design Guidelines for SCADA and Distribution System Automation.
14.3.6
Load Control
Load control design shall comply with the requirements of CEOP8085 Design Guidelines for
Load Control.
14.3.7
Communications
Communications design shall comply with the requirements of CEOP8032 Design Guidelines
for Transmission and Zone Substations.
Note that the Connection Applicant will be responsible for the design, supply and installation
of all SCADA link equipment. Essential Energy, upon request, and for an appropriate fee,
will provide a radio link design and equipment specification.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 30 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
14.3.8
Earthing
Earthing design must comply with the requirements of the following Essential Energy
documents:
CEOM7109 Distribution System Earthing; and
CEOP8012 Radio Sites: Earthing Telecommunication
Protection and Earth Termination Interface.
14.4
Testing and Commissioning
14.4.1
General
Installations
Lightning
Essential Energy will not proceed to connect or energise any HV equipment until it is
satisfied that the Connection Applicant has met the requirements of section 13.8, 13.9,
11.9, 11.10 and 14.4.
Essential Energy has a vested interest in assets that are to be transferred. As such
Essential Energy has a policy to acceptance test or witness all appropriate tests to ensure all
HV equipment, control and protection equipment, auxiliary supplies and earthing
requirements are in compliance with specific manufacturer’s requirements and/or its own
internal operational and maintenance requirements.
14.4.2
Notice and Acceptance Testing
In addition to requiring notice in writing of the ASP that the Connection Applicant intends to
use for commissioning and testing, Essential Energy will also require:
10 business days’ notice to program employees for witness/acceptance testing in
accordance with 11.7.2;
The Connection Applicant have employees available during Essential Energy’s
acceptance tests to confirm operation of any equipment that is not being tested by
Essential Energy;
All wiring diagrams and drawings made on site that reflect that actual construction
undertaken, including electronic vector versions, be available prior to Essential
Energy commencing acceptance tests on site; and
Copies of all pre-commissioning checks carried out by the Connection Applicant to
be provided to Essential Energy prior to Essential Energy commencing acceptance
testing.
14.4.3
Standards
All tests must be carried out in accordance with the relevant standards, guides, codes, and
regulations for the relevant plant and equipment.
All tests required by the manufacturer of specific items of plant and equipment before
commissioning must be performed.
All tests must be recorded in a report that details:
The plant and equipment tested (including the type of plant or equipment,
manufacturer’s name, type and serial numbers, ratings for voltage, current and
other relevant nameplate details);
Test equipment used (including type of equipment, manufacturers’ name, type and
serial numbers and the date of last accuracy test);
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 31 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Where relevant, temperature and humidity details; and
The results achieved from the test.
Each test report must be:
Signed and dated by the testing officer(s) and the witnessing officer; and
Provided to Essential Energy.
14.4.4
Commissioning Tests
The Connection Applicant will produce a test plan to cover the commissioning requirements
of all High Voltage assets and secondary equipment. This plan must identify testing
responsibilities and actions for all parties and must be submitted for Essential Energy’s
agreement and approval. Essential energy must approve the commissioning program, final
design and equipment requirements, prior to it being finalised by the Connection Applicant’s
ASP or its nominated representative.
Commissioning tests will vary depending upon the type and make of equipment to be
installed, the manufacturer’s recommendations and Essential Energy’s policies covering
commissioning tests for zone substation equipment, secondary systems, HV transmission
lines and cables.
Final commissioning may also require phase identification, temporary protection schemes,
service voltage testing, phasing out checks, protection directional checks and in-service
balances and in-service metering checks.
Essential Energy needs to ensure that all appropriate tests have been completed so that all
HV equipment can be energised. This will require close cooperation between the ASP and
Essential Energy employees. Essential Energy will also expect the Connection Applicant to
rectify all defects found as a result of testing and checks by Essential Energy or others
employed by the Connection Applicant. Any delay in defect rectification may impact on final
commissioning which may, in turn, delay commissioning of other infrastructure owned by
the Connection Applicant.
Commissioning tests and checks to ensure compliance may include but not be limited to:
Substations;
General compliance including civil and building works, secondary containment
systems, fencing, public safety, security, fire protection systems, general layout of
equipment;
Identification of equipment in accordance with Essential Energy’s requirements;
Earth grid and earthing of equipment;
Conductivity and insulation testing;
HV disconnect and earthing switches;
HV circuit breakers;
HV current transformers;
HV voltage transformers;
Power transformers (including high voltage testing and On Load Tap Changer
(OLTC);
Protection schemes and associated secondary equipment;
Substation control systems;
Metering;
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 32 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
SCADA systems;
Communication systems;
Substation batteries and battery chargers;
Building / substation low voltage services;
Generator performance;
HV cables; and
HV transmission lines.
14.4.5
Acceptance Testing by Essential Energy
Once the Connection Applicant has successfully completed the commissioning tests,
Essential Energy may elect to do an alternative test to satisfy its own requirements. Any
discrepancies will need to be rectified by the Connection Applicant. Only after Essential
Energy’s acceptance tests have been completed will the asset be allowed to be energised.
14.5
Handover and Defects Liability Period
"Handover" of the electricity works from the Connection Applicant to Essential Energy will
occur on practical completion which will be evidenced by Essential Energy issuing a
Certificate of Acceptance (defined in the relevant connection agreement as the
commissioning date of the Connection Point). The defects liability period will commence on
the date of acceptance and will end on the expiration of the period specified in the contract
after the date of acceptance (or if there a several such periods, for example where there are
separable portions, the last to expire).
During the defects liability period, Essential Energy may direct the Connection Applicant to
rectify any defects in the electricity works. The contract may allow Essential Energy to direct
the time within which the Connection Applicant must commence and complete the
rectification of defect. Essential Energy may also set a further defects liability period in
respect of work rectified - that period being effective from the date of rectification for a
period specified by Essential Energy.
While security held by Essential Energy is usually reduced upon practical completion, the
remainder of the security should be held until the later of the issue of the final certificate
under the contract (which occurs after the expiry of the defects liability period) and date on
which all defects identified during the defects liability period have been rectified in
accordance with the Code of Practice Contestable Works and Essential Energy’s operational
procedure document CEOP2015 General Terms And Conditions For The Supply Of Electricity
To New Subdivisions And Site Developments.
15.
HV ASSETS TO BE OWNED AND OPERATED BY OTHERS
In addition to the requirements listed under Section 11 of these Guidelines the following
requirements must be complied with for all assets to be owned and operated by others.
15.1
Design, Equipment and Materials
All design details must be endorsed by a Level 3 ASP to meet the requirements of AS/NZS
3000 Australia/New Zealand Wiring Rules, the Service and Installation Rules of NSW and
AS/NZS 7000:2010 Overhead line design – Detailed procedures.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 33 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
15.2
Design References
15.2.1
Transmission, Zone and Switching Stations
HV assets must meet the requirements of AS/NZS 3000 Australian/New Zealand Wiring
Rules, and the Service and Installation Rules of NSW.
15.2.2
Transmission Powerlines
Electricity works may only be owned and operated by the Connection Applicant if the asset
does not supply any other customer and the Connection Applicant accepts full responsibility
to comply with all laws, rules, regulations and environmental planning and approval
requirements with respect to the electricity works. The Connection Applicant should also
incorporate the requirements of AS/NZS 7000:2010 Overhead line design – Detailed
procedures.
15.2.3
HV Cables
For the safe installation of HV cables the Connection Applicant should incorporate the
guidelines of the cable manufacturer and any applicable standard.
15.2.4
Protection
The Connection Applicant / ASP must liaise and negotiate with Essential Energy’s Protection
Design team as to the type and electrical characteristics of high voltage and associated
secondary equipment to be installed. This will permit Essential Energy to install and set
appropriate protection schemes upstream and at the connection point. If Essential Energy
needs to install new and/or replace existing protection schemes as a result of this process
the Connection Applicant must pay those costs.
Essential Energy will require 2 months’ notice prior to any commissioning of HV and
associated secondary protection equipment.
Protection design must comply with the requirements of:
CEOP8002 High Voltage Protection Guidelines; and (If Applicable)
CEOP8012 Cogeneration Protection Guidelines.
15.2.5
HV Metering
HV metering design and installation should comply with the requirements of AEMO’s
Metrology Procedures and the Connection Applicants nominated meter provider.
15.2.6
Load Control
HV equipment must meet the requirements of the Service and Installation Rules of NSW.
15.2.7
Earthing
Earthing design must comply with the requirements of the appropriate Australian Standard.
15.3
Testing and Commissioning
15.3.1
General
Essential Energy will not proceed to connect or energise any HV equipment until it is
satisfied that the Connection Applicant has met the requirements of section 13.8, 13.9, and
14.4.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 34 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Where commissioning of HV equipment is on land covered by a mining lease, Essential
Energy also requires confirmation that the installation meets the specified safety criteria and
requirements covered by the terms of the applicable mining law.
16.
HV OPERATING PROTOCOL
16.1
General
All Connection Applicants are required to have an operating protocol in place that
outlines the procedures to be followed for the safe and efficient operation of the
system arrangements. The protocol must be executed prior to the connection of the
Electricity Works. The operating protocol template will be provided by Essential
Energy and a copy is shown at Attachment C.
Where the Connection Applicant does not have authorised personnel on staff then
an operating agreement between the Connection Applicant and a suitable qualified
provider must be entered in to and a copy made available for inclusion in the
operating protocol.
Failure to establish an operating protocol prior to connection will cause delay of that
connection.
16.2
Operating Protocol
An operating protocol should cover:
Supply Configuration;
Operational Responsibilities;
o
Connection Point
o
Asset Ownership
o
System Constraints and limitations
o
Network Configuration
Communications;
Training and HV Operator Authorisation;
o
Training and Authorisation of Staff
o
Essential Energy
o
The Customer
Authorised Network Operators;
Site access;
Planned Switching;
Emergency and Unplanned Switching;
Faults and Incidents;
Operating Agreement; and
Duration of Protocol.
16.3
HV Customer Switching and Operational Protocol
16.3.1
Ownership and maintenance
The Connection Applicant must prepare a high voltage Operating Diagram.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 35 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Essential Energy’s asset ownership and responsibility in respect of maintenance of
high voltage equipment terminates at a point selected by Essential Energy and
indicated on the Connection Applicant’s high voltage operating diagram
(“connection point”).
Ownership and maintenance of all high voltage equipment beyond the connection
point, including all metering transformers, is the Connection Applicant’s
responsibility.
16.3.2
Maintenance of Switchgear and Protection Equipment
The Connection Applicant must have a maintenance program in place as outlined in
AS 2467-2008 Maintenance of Electrical Switchgear, AS/NZS 3000 Australian/New
Zealand Wiring Rules and the relevant equipment manufacturer's instructions.
The maintenance program
qualifications to do so.
16.3.3
must
be
prepared
by
persons
with
acceptable
Protection Coordination
Essential Energy requires full grading with the Connection Applicant’s first line of
protection to guarantee correct fault discrimination.
The Connection Applicant, in liaison with Essential Energy’s protection group, will
negotiate settings to the generator’s protection equipment. These settings may not
be modified without Essential Energy’s prior agreement.
16.3.4
Auditing
Essential Energy may need to audit maintenance records at any time upon
negotiation with the Connection Applicant.
Essential Energy may request that maintenance be carried out within a nominated
time period and relevant records forwarded to Essential Energy.
16.3.5
HV Operations under Normal Conditions
16.3.5.1 Planned Switching Not Involving Essential Energy
The operation of all high voltage equipment at the Connection Applicant’s site
beyond and inclusive of the connection point is the Connection Applicant’s
responsibility and will normally be carried out by the Connection Applicant’s
authorised Operating Staff or authorised service provider.
The Connection Applicant must notify Essential Energy’s Network Operations before
any major new item of high voltage equipment is commissioned.
16.3.5.2 Planned Switching Involving Essential Energy
Other than for emergency conditions Essential Energy requires the following notification
periods for the planned isolation or switching of equipment:
Fifteen (15) working days when there will be no interruption to other Essential
Energy customers.
Twenty One (21) working days when the planned work will result in the
interruption of supply to other Essential Energy customers.
All notifications regarding planned switching are to be referred to Essential Energy
- System Control as referenced in Appendix C.
When Essential Energy requires isolation of the Customers equipment for routine work on
Essential Energy’s equipment, ten (10) working days prior notice will be provided to the
Customer. Where possible, Essential Energy will provide earlier notification.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 36 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
The party requesting the switching shall indicate:
the date and time;
the expected duration of the work; and
any requirements expected from the other party.
Where work requires switching operations to be carried out, each party shall pay their own
network operator costs, irrespective of who initiated the switching request.
Restoration of the network to normal will not commence until a completed or cancelled
Operating Agreement has been returned to Essential Energy, and confirmation has been
received by the Essential Energy Network Operator and the Customer or their nominated
ASP/electrical contractor, that restoration has been approved.
16.3.6
HV Regulatory Requirements
16.3.6.1 Connection Applicant’s Obligations
The Connection Applicant as a high voltage customer must comply with this
Operational Procedure CEOP8079.
The Connection Applicant’s installation must be operated, isolated and made safe
for work in accordance with the requirements of Electricity Supply (Safety and
Network Management) Regulation 2008, which imposes obligations on network
operators.
The Connection Applicant must comply with the Essential Energy Network
Management Plan.
The Connection Applicant (or their accredited service provider) must have a set of
Electrical Safety Rules, complying with the Network Management Plan, Codes of
Practice and AS 2467-2008 Maintenance of Electrical Switchgear and Appendix A
Example of Electrical Safety Rules, covering the operation of the electrical
installation.
All employees engaged in work on the Connection Applicant’s high voltage electrical
apparatus must be trained, assessed for competence and audited by the Connection
Applicant as being competent to work in accordance with the Connection Applicant’s
Electrical Safety Rules.
Up to date HV system diagrams must be prominently and permanently displayed in
each substation.
Suitable operating equipment must be provided for the electrical apparatus
installed.
Suitable earthing equipment must be provided for the electrical apparatus as
installed.
Live-line testing equipment, with self-testing facilities, must be provided for proving
de-energised the electrical apparatus installed.
Suitable tape barriers (and stands if necessary) must be provided to identify safe
working areas on isolated HV electrical apparatus.
Safety posters, showing resuscitation methods and instructions for release of
persons from live low voltage conductors, must be displayed in each substation.
Work of testing on HV electrical apparatus must be carried out in accordance with
AS 2467-2008 Maintenance of Electrical Switchgear.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 37 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
16.3.7
Operating Procedures
Where the Connection Applicant requires isolation of Essential Energy’s high voltage supply,
or Essential Energy requires isolation of the Connection Applicant’s supply, an operating
agreement will be exchanged between the Connection Applicant’s authorised operator and
Essential Energy’s Operating Staff to guarantee that the apparatus will remain isolated until
work is complete.
Essential Energy Network Operations will prepare the operating
agreement.
16.3.8
Authorised Staff and Access Permits
16.3.8.1 Connection Applicant’s Authorised Staff
Only staff who have been authorised in writing by the Connection Applicant to operate the
customer’s high voltage equipment and nominated to Essential Energy in the Operating
Protocol are permitted to carry out high voltage switching.
Authorised Staff must comply with the following conditions:
Are either the Connection Applicant’s staff or staff of the Connection Applicant’s
ASP/electrical contractor;
Have been trained in the Connection Applicant’s installation;
Have successfully completed a Safe Working Practices - Access Permit Issuers and
recipients training course – full details are available on Essential Energy’s website:
http://www.essentialenergy.com.au/DocumentLibrary/registration
Are able to negotiate with Network Operations on matters relating to the supply of
electricity
Are able to coordinate safety and operating procedures with Network Operations
when necessary
Refresher courses should be attended to maintain operating skills and keep abreast
of relevant rules and regulation changes
When a change occurs in the Connection Applicant’s authorised staff, the Connection
Applicant must ensure that Essential Energy is notified so that the competency of the new
authorised person can be assessed. The Connection Applicant must also provide the new
authorised person’s details to Essential Energy immediately.
16.3.8.2 Access Permits
Access permits may only be issued by persons who have been trained and assessed
as competent in the Safe Working Practices - Access Permit Issuers training course.
Access Permits may only be issued to persons who have been trained and assessed
as competent in the Access Permit Recipients training course or equivalent.
The training referred to in Subclause (b) must be carried out by Essential Energy
(at a fee) or another registered training organisation accredited by the Vocational
Education and Training Accreditation Board.
Refresher courses must be attended by high voltage operating personnel to
maintain operating skills and to keep up to date with changes to relevant rules and
regulations.
16.3.9
Network Operations
Essential Energy’s Network Operations is manned 24 hours a day and can be contacted at
any time on matters relating to the operation of Essential Energy’s high voltage system
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 38 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
and/or the supply of electricity through Essential Energy’s Customer Service or Supply
Interruption contact centres.
17.
DISPUTE RESOLUTION
The Connection Applicant may request Essential Energy to review its decisions and
processes in relation to the Connection.
Connection applicants may seek assistance in resolving disputes on technical and other
matters arising during the connection process through the Dispute Resolution Advisor
appointed by the AER and in accordance with Chapter 8 of the National Electricity Rules.
18.
KEY TERMS AND DEFINITIONS
In this Operational Procedure, definitions are as given in the National Electricity Rules (NER)
unless otherwise stated below.
Accredited Service Provider (ASP): A person accredited under a scheme approved by
the NSW Department of Trade and Investment.
Adequate Connection Enquiry: A connection enquiry which includes the information
required by Schedule 5.4 of the NER.
AEMC: Australian Energy Market Commission.
AEMO: Australian Energy Market Operator.
AER: Australian Energy Regulator, established to enforce the NER.
Approval: Any approval, consent, licence, permission or certificate issued by or required to
authorise the construction, operation, maintenance and operation of the Electricity Works by
the relevant Statutory Authority.
Authorisation (of Accredited Service Provider): Authorisation means permission in
writing, generally to an ASP, given by Essential Energy to undertake works on or near the
Essential Energy transmission and/or distribution network.
Connection Enquiry: Initial Enquiry made by a Connection Applicant in accordance with
Clause 5.2 and 5.3 of the NER for connection to a network and/or the provision of network
services or modification of a connection to a network and/or the provision of network
services.
Connection Agreement: An agreement between Essential Energy and a Connection
Applicant by which are connected to the Essential Energy distribution network and/or
receives transmission services or distribution services.
Connection Applicant:
A Participant wanting to establish or modify connection to
Essential Energy’s transmission network or distribution network and/or who wishes to
receive network services in accordance with Chapter 5 of the NER.
Connection Application: Application made by a Connection Applicant in accordance with
Clause 8.1-8.7 of these Guidelines for connection to a network and/or the provision of
network services or modification of a connection to a network and/or the provision of
network services.
Connection Investigation Services Agreement (CISA): A connection investigation
agreement pursuant to which Essential Energy will review, assess and/or investigate the
proposed connection in order to provide connection and network services to the Connection
Applicant under the Rules.
Contestable Works: Those works for which a Connection Applicant may choose the
provider of the services in accordance with the Electricity Supply Act 1995.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 39 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
CT: Current Transformer.
Deemed Connection: A connection to the network prior to 13 December 1998.
EMF: Electric and Magnetic Fields.
ENA: Energy Networks Association.
Electricity Works: Any high voltage electricity transmission line and all associated
equipment and includes all poles, stays, stay poles, wires, cables, foundations, pipes,
conduits, switches, switchgear, pillar boxes, transformers, fuses, Major Electrical
Plant/Equipment and any other above or underground ancillary works.
Environmental Law: Any Law, whether statute or common law, concerning environmental
matters, and includes but is not limited to Laws concerning land use, development,
pollution, contamination, waste disposal, toxic and hazardous substances, climate change,
greenhouse gases, energy use or efficiency, water use or access and conservation of natural
or cultural resources.
Generator: Connection Applicant developing embedded generation greater than 30kW
without the use of an inverter.
HV or High Voltage: Voltage nominally 1000 volts and above.
NSW Trade and Investment: The accrediting agency responsible for the accreditation of
service providers to undertake contestable work in New South Wales and any successor
charged with the same or similar responsibilities.
Land Access Investigation Agreement (LAIA): An agreement between the parties for
assessing, investigating and obtaining relevant approvals in relation to environmental and
planning and applicable Registrable Instruments associated with the construction of the
Electricity Works required in order to provide Connection Services and Distribution Services
to the Connection Applicant.
Land Tenure: Such rights or interest in land required by Essential Energy to protect the
Electricity Works located on such land and includes the Registrable Instruments,
Law: Includes any requirement of any statute, rule, regulation, statutory instrument,
proclamation, order, ordinance or by-law whether Commonwealth, state, territorial or local.
Major Electrical Plant/Equipment: means any electrical equipment (including overhead
lines and underground cables) associated with the supply of electricity at high voltage, the
conductors of which are live or can be made live. Examples of major plant include Power
Transformer Circuits and Regulators associated with Transmission, Subtransmission, Zone
Substations, Switching Stations and Generation Substations.
NATA: National Association of Testing Authorities.
OLTC: On Line Tap Changer.
Registrable Instruments: Land dealings in registrable form for the creation of easements
in favour of, or the transfer of land to, Essential Energy.
NER: National Electricity Rules. The NER are available for download from the AEMC
website at: http://www.aemc.gov.au/rules.php/.
Service and Installation Rules of NSW: Service and Installation Rules of New South
Wales.
VT: Voltage Transformer.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 40 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
19.
ATTACHMENT A – PRELIMINARY CONNECTION ENQUIRY FORM
(also available for download from Essentials Energy’s website)
---------------------------------------------------------------------------------------------------------------HV Customer and Embedded Generator Connection Enquiry Form
(it is intended that the Connection Applicant will write to Essential Energy and include all of the following information in the
Preliminary Connection Enquiry)
Enquiry Date: <dd/mm/yyyy>
Name of Enquirer:
Company Name:
Company ABN:
Postal Address:
Contact Details (for single point of Contact)
Name:
Office Phone:
Mobile Phone:
Email address:
Postal Address:
Please provide a detailed qualitative description of the objectives of the project proposal which is
intended later to become an application to connect.
Schedule 5.4 NER Information to the Provided with Preliminary Enquiry
The following items of information are required to be submitted with a preliminary enquiry for
connection or modification of an existing connection: Refer NER for details
Item
Information Description
Details Required
(a)
Type of plant (eg. gas turbine generating unit;
rolling mill, etc.).
(b)
Preferred site location –
(Lot and DP – of entire facility)
(listing any alternatives in order of preference as
well).
(c)
(d)
(e)
Maximum power generation or demand of
whole plant – (maximum MW and/or MVA,
or average over 15 minutes or similar).
Expected energy
production (MWh per month).
Plant type and configuration - (eg. number
and type of generating units or number of separate
production lines).
(f)
Nature of any disturbing load (size of
disturbing component MW/MVAr, duty cycle, nature
of power electronic plant which may produce
harmonic distortion).
(g)
Technology of proposed generating unit
(e.g. synchronous generator, induction generator,
photo-voltaic array, etc).
(h)
When plant is to be in service - (eg.
estimated date for each generating unit).
(i)
(j)
Name and address of enquirer, and, if
relevant, of the party for whom the
enquirer is acting.
Other information may be requested by
the Network Service Provider, such as
amount and timing of power required
during construction or any auxiliary power
requirements.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 41 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Other supporting information required with preliminary connection enquiry.
1. Provision of detailed qualitative description of the objectives of the project proposal which is
intended later to become an application to connect;
2. Approximate Location of facility substation (pin on google map – with Lot and DP nominated
for the entire facility site;
3. Facility site Address;
4. Any information plans drawings and presentations helpful in providing a detailed response to
the preliminary connection enquiry; and
5. A list of the information required from Essential Energy in relation to the Connection
Applicants, application to connect and supporting reasons for the request.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 42 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High Voltage Retail Customer Connection and Embedded Generators
>30kW
20.
ATTACHMENT B – EXAMPLE PROJECT TIMELINE
To be provided by the Connection Applicant.
October 2014 - Issue 8
Approved By: Customer Connections Manager
Page 43 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
21.
ATTACHMENT C - OPERATING PROTOCOL TEMPLATE
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 44 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 45 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 46 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 47 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 48 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 49 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 50 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 51 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 52 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 53 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
22.
ATTACHMENT D SCHEDULE 5.5.3 – NETWORK & PLANT
TECHNICAL DATA OF EQUIPMENT AT OR NEAR CONNECTION POINT
Data Description
Voltage Rating:
Nominal voltage
Highest voltage
Units
Dat
a
Cat.
Value
kV
kV
S,D
D
value required
value required
kVp
D
value required
kV
D
value required
kA
kA for seconds
S, D
D
value required
value required
text
S,D
text required
Text
kA for seconds
S,D
D
text required
value required
D
value required
Pollution level
mm
Level
815
D
value required
Controls
Remote control and data transmission
arrangements
Text
D
text required
A/A
V/kV
D
D
D
value required
value required
value required
Text
R1
text required
S,D,
R1
Single Line Diagram
to be provided
as an attachment
S,
value required
Insulation Co-ordination:
Rated lightning impulse withstand
voltage
Rated short duration power frequency
withstand voltage
Rated Currents:
Circuit maximum current
Rated Short Time Withstand Current
Ambient conditions under which above
current applies
Earthing:
System Earthing Method
Earth grid rated current seconds
Insulation Pollution Performance:
Minimum total creepage
Metering Provided by Customer:
Measurement transformer ratios:
Current transformers
Voltage transformers
Measurement
Transformer
Test
Certification details
of
IEC
Network Configuration:
Operation Diagrams showing the
electrical circuits of the existing and
proposed main facilities within the
Registered
Participant's
ownership
including
busbar
arrangements,
phasing
arrangements,
earthing
arrangements, switching facilities and
operating voltages.
Single
Diagrams
Network Impedance:
For each item of plant:
% on 100 MVA
Line
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 54 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Data Description
Units
details of the positive, negative and
zero sequence series and shunt
impedance, including mutual coupling
between physically adjacent elements.
Short
Circuit
Infeed
to
the
Network:
Maximum generator 3-phase short
circuit infeed including infeeds from
generating units connected to the
Registered
Participant's
system,
calculated by method of AS 3851
(1991).
The total infeed at the instant of fault
(including contribution of induction
motors).
Minimum zero sequence impedance of
Registered Participant’s network at
connection point.
Minimum
negative
sequence
impedance of Registered Participant's
network at connection
Load Transfer Capability:
Where a load, or group of loads, may
be fed from alternative connection
points:
Load normally taken from connection
point X
Load normally taken from connection
point Y
Arrangements
for
transfer
under
planned or fault outage conditions
Dat
a
Cat.
base
D,
R1
Value
to be provided
as
a
attachment
table
kA
S,
D,
R1
value required
kA
D,R1
value required
% on 100 MVA
base
D,
R1
% on 100 MVA
base
D,
R1
EE to provide once
Connection
Point
mutually established
EE to provide once
Connection
Point
mutually established
MW
D,R1
value required
MW
D,R1
value required
Text
D
text required
D, R
value required
D, R
value required
D, R
value required
D, R
value required
Circuits
Connecting
Embedded
Generating
Units to the Network:
For all generating units, all connecting
lines/cables, transformers etc.
Shunt Susceptance % on 100
% on 100 MVA
base
% on 100 MVA
base
% on 100 MVA
base
Normal
MVA
Series Resistance
Series Reactance
and
short-time
emergency
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 55 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Data Description
Units
Dat
a
Cat.
Value
ratings Technical Details of generating
units and generating systems as per
the Generating System Design Data
Sheet, Generating System Setting
Data Sheet and the Generating System
Model Guidelines where such details
are not confidential information
Transformers at connection points:
Saturation curve
Equipment associated with DC Links
Number of poles
Converters per station
Reactive
Power
consumption
of
converters
Location and Rating of A.C. Filters
Location
and
Rating
of
Shunt
Capacitors
Location and Rating of Smoothing
Reactor
Location and Rating of DC Filter
Diagram
R
diagram required
MVA
Quantity
D,R
D,R
value required
value required
MCAr
MVAr
D,R
D,R
value required
value required
MVAr
D,R
value required
MVAr
MVAr
D,R
D,R
value required
value required
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 56 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
23.
ATTACHMENT E SCHEDULE 5.5.4 - NETWORK PLANT AND
APPARATUS SETTING DATA
Data Description
Protection Data relevant to Connection
Point:
Reach of all protections on transmission
lines, or cables
Number of protections on each item
Total fault clearing times for near and
remote faults
Line reclose sequence details
Tap Change Control Data:
Time delay settings of all transformer tap
changers.
Reactive Compensation:
Location and Rating of individual shunt
reactors
Location and Rating of individual shunt
capacitor banks
Capacitor bank capacitance
Inductance of switching reactor (if fitted)
Resistance of capacitor plus reactor
Details of special controls (e.g. Point-onwave switching)
For each shunt reactor or capacitor
bank:
Method of switching
Details of automatic control logic such that
operating
characteristics can be determined
FACTS Installation
Data sufficient to enable static and dynamic
performance of the installation to be
modelled
Transmission line flow control device
Details of the operation of the control
device under normal operation conditions
(including start up and shutdown of the
line) and during a fault (close up and
remote)
Models for the control device and
transmission line appropriate for load flow,
small signal stability and transient stability
analysis
Capability of the line flow control device
Details of the rate of change of flow
capability of the control device
Details of the capability of the control
Units
Data
Cat.
Value
ohms or % on
100 MVA base
Text
S, D
S, D
value required
text required
ms
Text
S,D,R1
S,D,R1
value required
text required
Seconds
D, R1
value required
MVAr
D,R1
value required
MVAr
microfarads
millihenries
Ohms
D,R1
D
D
D
value
value
value
value
Text
D
text required
Text
S
text required
Text
D,R1
text required
Text,
diagrams,
control settings
Text
S,
R1
D
required
required
required
required
D,
text required
text and/or diagram
required
diagrams
Text,
KA, MVA, MW
D
D
text required
value required
Text D
Text,
D
text required
text required
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 57 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Data Description
device to provide frequency and voltage
control Description of possible failure
modes of control device
Description of possible failure modes of
control device
Details of performance of the control device
under disturbance conditions including
changes in AC frequency, variations in AC
system voltages and Ac system waveform
distortion.
For DC control devices, contribution to the
AC system short circuit level
Type of Load eg controlled rectifiers or
large motor drives
Units
Data
Cat.
Value
Text,
D
text required
Text,
D
text required
value required
KA, MVA D
Text
S
text required
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 58 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
24.
ATTACHMENT F - SCHEDULE 5.5.5 – LOAD CHARACTERISTICS AT
CONNECTION POINT
Data Description
Units
Data
Cat.
Value
For All Types Of Load
Type of Load eg controlled rectifiers or
large motor drives
For Fluctuating Loads
Cyclic variation of active power over
period
Cyclic variation of reactive power over
period
Maximum rate of change of active
power
Maximum rate of change of reactive
power
Shortest
Repetitive
time
interval
between fluctuations in active and
reactive power reviewed annually
Largest Step Change:
In active power
In reactive power
Text
Graph
MW/time
Graph
MVAr/time
S
text required
S
graph required
as an attachment
graph required
as an attachment
MW/s
S
value required
MVAr/s
S
value required
s
S
value required
MW
MVAr
S
S
value required
value required
S
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 59 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
25.
ATTACHMENT G - APPLICATION FEE MATRIX
Connection Application Fee - Matrix
Load
Size
Fee
man hours Rate/hr
<30kW
$0
2
>30kW <1MW
$2060
21
>1MW<5MW
$3050
31
$98.40
>5MW<30MW
$5010*
51
>30MW
$10030*
102
Embedded Generation
Size
Fee
man hours Rate/hr
<30kW
$0
2
>30kW<200kW**
$0
2
>30kW<200kW
$1080
11
>200kW<500kW
$2060
21
$98.40
>500kW<1MW
$3050
31
>1MW<5MW
$5010
51
>5MW<30MW
$10030*
102
>30MW
$15050*
153
Detailed Enquiry Fee
Size
Fee
man hours Rate/hr
Al l
$1080
11
$98.40
Note
Fee structure exc. GST
* or CISA schedule of rates
** no network analysis required
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 60 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
26.
ATTACHMENT H - CONNECTION SEQUENCE
Connection Applicant makes an "adequate" Preliminary Connection Enquiry
EE responds with Preliminary Connection Enquiry Response includes high level connection options
Connection Applicant requests a Detailed Connection Enquiry Response
EE responds with a Detailed Connection Enquiry Response
Connection Applicant elects to proceed with project and formally advises EE
EE may issue ClSA and LAIA for execution if applicable
Connection Applicant returns ClSA and LAIA signed
EE issues Invoice for ClSA and LAIA Up-front fees
Proponent pays Up-front fees (ClSA and LAIA).
EE releases network planning and protection data to Connection Applicant for network modelling (steady state &
dynamic studies)
Connection Applicant undertake REF (for power line connection assets) – submits to EE - determining authority
REF to include Route Options Paper for the connection powerline assets
DA to State Planning for actual PROJECT (not to include connection assets to be gifted to EE)
Connection Applicant to secure registered easements for power line and freehold title for substation/switching station
where assets are to be gifted to EE
Connection Applicant to undertake and provides to EE for review
Network modelling with and without PROJECT- (steady state & dynamic network performance studies)
including voltage regulation, fault level & sensitivity, stability, harmonics
To include supporting details for Access Standards met
For generators GPS & technical schedules for review before proponent lodges with AEMO
Connection arrangement including SLD, general arrangement and site plan
Load control (>10MW) including underfrequency load control
Protection analysis and Report including SLD, telecommunications and SCADA control
Earthing analysis and Report
Operational parameters/requirements (for inclusion in Operating Protocol and Connection Agreement)
Connection Applicant request design information requirements (DIR) for construction standards for connection assets
(contestable works flow chart)
- design must be certified before construction begins.
Connection Applicant undertakes concept and final design of connecting infrastructure
Submit design to EE for approval & certification (must include plans – pdf format schedule of
drawings with details easements/free hold title once approved submit CAD drawings for
certification).
Connection Applicant submits Connection Application & pays Connection Application Fee
Connection Applicant authorised to construct connection infrastructure once
Provision/advise and acceptance by EE of
 Qualification & experience of the ASP’s staff
 Proposed works schedule – construction timeline
 Proposed material list/schedule
 Environmental construction plans
 Construction safety plans
 Proposed commissioning plans (including EE acceptance testing requirements)
 Defects liability period
EE to make an Offer to Connect
Connection Applicant must accept Offer to Connect
Both parties Execute Connection Agreement & Operating Protocol
Physical connection of the PROJECT can occur on
Execution CA and Operating protocol by both parties;
AEMO generator registration complete (for generation);
contestable works completed, commissioned and then accepted by EE (including registered easements, land
title and any securities required by EE and/or other Network Service provider);
Equipment test certificates provided ; and
all outstanding fees/recoverable costs incurred, invoiced and paid to EE .
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 61 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
27.
ATTACHMENT I - CONNECTION SCOPE OF WORKS
Contestable Works
- to be undertaken by the Connection Applicant
Physical Works
Fencing
Civil
transformer
switch gear
buildings (control room)
Earthing System
Land acquisition
telecommunications sytem
Control Systems
SCADA
Protection Systems
Easements acquisition and compensation
Materials selection and procurment
design and construction
earth type (overhead Earth/OPGW/ADSS)
Contractural
Agreements
Contestable
Works
Powerline
Secondary
System
Switching Station/Substation
Primary System
(assets Transferred to EE)
Technical Analysis
to be reviewed by EE
Route Options Report
Environmental Analysis
Connection Arrangement
Connection Point - Isolation switch gear
Network Modelling load flow /harmonics etc.
Voltage Regulation
Load Control/under frequency load shedding (>10MW)
Concept and final Switching Station/Substation system design to be Certified by EE
Concept and final primary system design to be Certified by EE
Concept and final secondary system design to be Certified by EE
Concept and final Line Design to be certified by EE
Protection & fault level Report and settings
Earthing Analysis & Report
IN ADDITION FOR EMBEDDED GENERATORS
AEMO Registration
Construction Schedule/Plan
Materials Schedule
Construction Environmental Management Plan
Construction Safety and enviormrntal Plans
Commissioning Plan
Connection Agreement
Operating Protocol
Registered easements
Freehold title - substation/switchyard
Safety management Plan
Electricity Safety Rules
Maintenance Plan
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 62 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
28.
REFERENCES
CECM1000 – Health, Safety and Environmental Manual: Index
CECM1000.70 –
Assessment, NSW
SSHE
Environmental
Operations
Manual:
Environmental
Impact
CECM1000.77– Environmental Operations Manual: Flora and Fauna
CEOP4005 -
Underground cable Testing
CEOP2513.08 - Essential Energy’s Negotiation Framework.
CEOP8085 – Design Guidelines for Load Control
CEM7097 – Overhead Design Manual
CEM7099 – Overhead Construction Manual
CEOM7199 – Underground Construction Manual
CEOM7004 - Materials Inventory, Contestability (Approved)
CEOM7098 – Underground Design Manual
CEOM7621.01 Technology Guideline
CEOM7114.01 – HV Customer Overhead Connection Arrangement
CEOM7114.02 - HV Customer Underground Connection Arrangement
CEOM7114.03 - HV Customer General Connection Arrangement – non-dedicated feeder
CEOM7621.01 – Technology Guideline
CEOP8012 – Cogeneration Protection Guidelines
CEOP8082 SCADA & DSA Philosophy
CEOP2238 – High Voltage: Customer Operational Training Requirements
CEOP8002 – High Voltage Protection Guidelines
CEOP8008 - Vegetation Management Plan
CEOP8008a - Essential Energy Vegetation Management Plan Purpose Statement
CEOP8019 – Capital Contributions
CEOP8032 – Transmission and Zone Substations: Design Guidelines
CEOP8046 – Easement Requirements
CEOP8082 SCADA & DSA Philosophy
CEOP8084 – Design Guidelines for SCADA and Distribution System Automation
CEOF9097A -
Terms of Easement OH
CEOF9097B -
Terms of Easement UG
CEOF9097C -
Terms of Easement multi purpose
CEPG2047 – Authority for Placing Major Electrical/Plant Equipment into Service
ESS304 - SafeWorkTrainingFlyer_HR
Generic GDI HV Connection Requirements
CEOP2513.06
Essential Energy Connection Policy – Connection Charges for electricity
retail customers
Essential Energy Review of Environmental Factors Guideline
Commissioning & test procedure subtransmission cable
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 63 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
Commissioning & test procedure subtransmission overhead lines
REF Guidelines
AS1824
http://www.saiglobal.com/online/
–
AS2067 http://www.saiglobal.com/online/
AS/NZS 3000 – Australian/New Zealand Wiring Rules
http://www.saiglobal.com/online/
AS 3007 – Electrical Installations
http://www.saiglobal.com/online/
AS/NZS 7000:2010 “Overhead line design – Detailed procedures ”Contestable Works”
http://www.saiglobal.com/online/
Electricity Supply Act 1995
http://www.energy.nsw.gov.au/electricity/network-connections/contestable
National Electricity Rules (site down 5/8/2014)
Service and Installation Rules of NSW
http://www.resourcesandenergy.nsw.gov.au/energy-supply-industry/pipelines-electricitygas-networks/network-connections/rules
Code of Practise of Contestable Works.
http://www.resourcesandenergy.nsw.gov.au/energy-supply-industry/pipelines-electricitygas-networks/network-connections/contestable-works
National Metrology
http://www.aemo.com.au/Electricity/Policies-and-Procedures/Metrology-Procedures-andUnmetered-Loads/NEM-Metrology-Procedure
NMI Allocation Procedure
http://www.aemo.com.au/Search?a=NMI%20allocation
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 64 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
29.
REVISIONS
Issue Number
Section
2
Flowchart
3.2.1
3.2.2
4.1
5.1
6
7.1
3
7.7.1
8.2.8
Attachment A
Attachment D
Attachment I
Attachment J
Attachment K
10
All
All
4
3.2.2
3.2.2
5
All sections
6
All Sections
All Sections
3
11.5.2
11.3
14
7
Details of Changes in this Revision
Definitions updated/added:
Accredited Service Provider (ASP)
Authorisation (of Accredited Service Provider)
Connection Investigation Agreement (CIA)
DWE
ETL
Office of Fair Trading
Registrable Instruments
Processes added to include Provision of CIA and Registrable
Instruments
First paragraph – 2 weeks changed to 10 business days
4 weeks changed to 20 business days
Categories of relevant information added
Reference to standard form CIA added
Additional information required specified
Accreditation agency changed from DEUS to OFT – website
updated
7th paragraph added
Reference to CEPG2016 has been replaced with CEM7022.01
11th paragraph added
Reference to CEPG2010 has been replaced with CEM7022.08
Clause added for Provision of Registrable Instruments
Updated to current version October 2006
Updated to current version
Updated to current version
Added
Added
References adjusted as necessary.
Documents added:
CEM7022.01 – Environmental Operations Manual:
Environmental Impact Assessment
CEM7022.08 – Environmental Operations Manual: Flora
and Fauna
CEOP2238 – High Voltage: Customer Operational Training
Requirements.
Update document to reflect changes to Essential Energy policy
requirements
NEMMCO replaced with AEMO
Manager Network Commercial replaced with Manager Network
Connections
Email address included
Template/logo & references updated in line with Essential
Energy branding.
Complete revision and Re-write of entire document
Connection Proponent replaced with Connection Applicant
Flow Chart Updated and replaced
Clause added
Web link added
Section expanded and added
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 65 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED
OPERATIONAL PROCEDURE CEOP8079
Connection Process for Negotiated High
Voltage Retail Customer Connection and
Embedded Generators >30kW
8
10
11.1
11.5
14
14.3.5.2
All Sections
Reference to NSW Department Trade & Investment updated
Updated Work Health and Safety Regulation
Revised HV Metering comment
Inclusion of an Operating Protocol template – Attachment C
Update planned switching involving Essential Energy
Reviewed and amended to comply CH5 NER Rule change (Oct
2014)
October 2014 - Issue 8
Approved By: Connection Contracts Manager
Page 66 of 66
FOR PUBLIC RELEASE
UNCONTROLLED COPY IF PRINTED