Volume 1 of 1 BID DOCUMENTS: NOVEMBER 19TH, 2013 PROJECT MANUAL Greenwich Public Schools ISD Gym Window Replacement Board of Education Bid Number: 988-13 KSQ Project # 1317908.00 Architect: KSQ Architects, P.C. 235 Main Street, Suite 410 White Plains, NY 10601 T. 914.682-3700 F. 917.591.7013 www.ksqarchitects.com Owner: Greenwich Public Schools 290 Greenwich Avenue Greenwich, CT 06830 Facility Names: Western Middle School 55 Florence Road, Riverside, CT 06878 Construction Manager: School Construction Consultants, Inc. 190 Motor Parkway Suite 201 Hauppauge, NY 11788 Structural Engineer: MEP Engineer: Environmental Engineer: GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0110 - TABLE OF CONTENTS DIVISION 0 - BIDDING DOCUMENTS, CONTRACTS AND CONDITIONS 00 0101 00 0110 00 0300 00 0301 COVER TABLE OF CONTENTS INVITATION TO BIDDERS (LETTER) INSTRUCTIONS TO BIDDERS 00 0400 00 0410 BID FORM CONTRACTOR'S QUALIFICATION STATEMENT 00 0460 00 0461 00 0462 NON-COLLUSIVE AFFIDAVIT PREVAILING WAGE SCHEDULE REFERENCES 00 0472 00 0473 00 0474 FORM OF BID BOND CERTIFICATE AS TO CORPORATE PRINCIPAL PERFORMANCE MAINTENANCE AND PAYMENT BOND 00 0481 00 0482 00 0483A 00 0483B 00 0483C INSURANCE PROCEDURE INSURANCE REQUIREMENTS SAMPLE ENDORSEMENT LETTER A.M. BEST KEY RATING AFFIRMATIVE ACTION COMPLIANCE AFFIDAVIT 00 0484 SAMPLE CONTRACT 00 0485 00 0486 CONSENT OF SURETY AFFIDAVIT FOR FINAL PAYMENT 00 8500 LIST OF DRAWINGS DIVISION 1- GENERAL REQUIREMENTS 01 1000 01 1100 01 2100 01 2300 01 2600 01 2900 01 3119 01 3300 01 3301 01 4000 01 5000 01 6000 01 7329 01 7400 01 7423 01 7700 01 7701 01 7823 SUMMARY OF WORK MILESTONE SCHEDULE ALLOWANCES ALTERNATES MODIFICATION PROCEDURES PAYMENT PROCEDURES PROJECT MEETINGS ELECTRONIC SUBMITTAL PROCEDURES SUBMITTAL COVER PAGE QUALITY REQUIREMENTS TEMPORARY FACILITIES AND CONTROLS PRODUCT REQUIREMENTS CUTTING AND PATCHING WARRANTIES CLEANING UP EXECUTION AND CLOSEOUT REQUIREMENTS CHECKLIST FOR PROJECT CLOSEOUT AND PROCESSING OF FINAL PAYMENT OPERATION AND MAINTENANCE DATA TABLE OF CONTENTS 00 0110 - 1 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 01 7839 NOVEMBER 19TH, 2013 PROJECT RECORD DOCUMENTS DIVISION 2 – SITE WORK 02 4119 SELECTIVE STRUCTURAL DEMOLITION DIVISION 6 - WOOD AND PLASTICS 06 1000 ROUGH CARPENTRY DIVISION 7- THERMAL AND MOISTURE PROTECTION 07 4700 ALUMINUM SOFFIT PANELS 07 8400 FIRESTOPPING 07 9200 JOINT PROTECTION DIVISION 8 – DOORS AND WINDOWS 08 1113 08 1255 08 4523 08 5113 08 7100 08 8000 HOLLOW METAL DOORS AND FRAMES ALUMINUM FRAMES & F.R.P. DOORS INSULATED TRANSLUSCENT FIBERGLASS WALL SYSTEM ALUMINUM WINDOWS FINISH HARDWARE GLAZING DIVISION 9 – FINISHES 09 5113 ACOUSTICAL PANEL CEILINGS 09 9100 PAINTING DIVISION 10 – SPECIALTIES ALL MECHANICAL, ELECTRICAL, & PLUMBING SPECIFICATIONS ARE INDICATED ON THOSE RESPECTIVE DRAWINGS. END OF SECTION 00 0110 TABLE OF CONTENTS 00 0110 - 2 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 GREENWICH PUBLIC SCHOOLS Purchasing Department 290 Greenwich Ave. Greenwich, Connecticut 06830 (203) 625-7400 Fax (203) 625-7677 EUGEGE H. WATTS Senior Buyer November 19th, 2013 Dear Sir / Madam: You are invited to submit a bid for ISD Gym Window Replacement for Greenwich Public Schools at the International School at Dundee. This bid will be a lump sum for your work or material in accordance with the plans and specifications or the work on the following project. The attached bid specifications detail the requirements we are looking for. Bidders are urged to read all documents carefully and fill out all information requested. Bids which are incomplete, obscure, or conditional, and which contain irregularities of any kind, will be subject to rejection for failure to comply strictly with these conditions. Bids must be submitted on the schedule form attached hereto. All unit prices must be filled in. Each bid must be submitted with one (1) original and three (3) copies of the bid. Bidders must submit bids in a clear, concise, and legible manner so as to permit proper evaluation of responsive bids. Faxed bids will not be accepted. The original bid and copies must be in sealed envelope plainly marked: International School at Dundee – Gym Window Replacement - BID NUMBER: 988-13 A. Pre-Bid Conference: 1. Date: November 25th, 2013 2. Time: 12:00 PM 3. Location: International School at Dundee 4. Address: 55 Florence Road, Riverside, CT 06878 5. Prospective bidders are strongly encouraged to attend. B. Bid Due Date: 1. Sealed proposals will be received as indicated below, and at that time and place will be publicly opened and read aloud. 2. Date: December 10th, 2013 3. Time: 12:00 PM local time 4. Location: Havemeyer Building 5. Address: GREENWICH PUBLIC SCHOOLS, 290 Greenwich Ave., Greenwich, Connecticut 06830, (203) 625-7400 6. All bidders and other interested persons are invited to be present at the opening of this bid opening(s). Additional information for bidding is provided in the Instructions to Bidders. Very truly yours, Eugene H. Watts INVITATION LETTER 00 0300 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0301 - INSTRUCTIONS TO BIDDERS PART 1 - GENERAL 1.1 The Greenwich Public Schools, Greenwich, CT, invites bid proposals for the following: A. ISD Gym Window Replacement for the Greenwich Public Schools at the following schools: International School at Dundee – 55 Florence Road, Riverside, CT 06878 1.2 BACKGROUND: A. TOWN / DISTRICT: The Town of Greenwich is approximately 30 miles northeast of New York City and has a population of about 60,000 residents. The Greenwich Public Schools enjoy a national reputation for excellence and have strong support from the community. The fifteen public schools have an enrollment of 9,000 students and consists of eleven elementary schools (K-5), three middle schools (6-8), and one comprehensive high school (9-12). B. ARCHITECT: KSQ Architects, PC, 235 Main Street, White Plains, NY 10601, 914.682.3700. C. CONSTRUCTION MANAGER: School Construction Consultants, 190 Motor Parkway, Suite 201, Hauppauge, NY 11788. 1.3 SCHEDULE: A. B. Bidding Documents Available: 1. Digital Viewing: At 2:00 PM on Tuesday November 19th, 2013. Project Specifications can be viewed at the Greenwich Public Schools website: www.greenwichschools.org 2. At 2:00 PM on November 19th, 2013 copies of said Bidding Documents can be purchased from ARC/TRI-STATE, 87 Taylor Avenue, Norwalk, CT 06854, (tel) 203.866.5600 Attn: Peter Rowland. Documents may be viewed at www.bpirepro.com. Pre-Bid Conference: 1. 2. 3. 4. 5. C. Date: November 25th, 2013 Time: 12:00 PM Location: International School at Dundee Address: 55 Florence Road, Riverside, CT 06878 Prospective bidders are encouraged to attend. Bid Due Date: 1. 2. 3. 4. 5. 6. Sealed proposals will be received as indicated below, and at that time and place will be publicly opened and read aloud. Date: December 10th, 2013 Time: 12:00 AM local time Location: Havemeyer Building Address: GREENWICH PUBLIC SCHOOLS, 290 Greenwich Ave., Greenwich, Connecticut 06830, (203) 625-7400 All bidders and other interested persons are invited to be present at the opening of this bid opening(s). INSTRUCTIONS TO BIDDERS 00 0301 - 1 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 D. QUESTIONS: 1. 2. 3. 4. 5. 1.4 NOVEMBER 19TH, 2013 Questions concerning this bid will be received by email only and directed to: a. bid_department@greenwich.k12.ct.us. In the subject line you must put BID #988-13, ISD Gym Window Replacement. All questions must be submitted no later than noon, December 3rd, 2013. All answers will be provided by written BID ADDENDUM at www.greenwichschools.org at noon on December 5th, 2013. It is the responsibility of all bidders to verify that they current with all. Failure to comply with these conditions will result in the bidder waiving his right to dispute the bid specifications and conditions. BID SUBMISSION / REQUIREMENTS: A. Each bid shall be signed and accompanied by a bid security payable to the Town of Greenwich in the amount of ten (10%) of the bid and shall be in the form of a Bid Bond only as issued in the bid documents. Bid Bonds must use the Greenwich Public Schools Bid Bond Form (included within the bid documents), issued by a surety company listed on the current U.S. Dept of Treasury’s Federal Register and be licensed to underwrite bonds in the State of Connecticut. B. Each bid shall be accompanied by a completed copy of the CONTRACTOR'S QUALIFICATION STATEMENT included in the bid documents. The Greenwich Public Schools reserves the right to request further information and/or supplemental information with respect to the QUALIFICATION STATEMENT of its sole discretion. C. Each bidder shall utilize the specified manufacturers. Should the contractor desire to substitute other articles, materials, apparatus, products or process, other than those specified or approved as equal, the contractor shall apply to the architect, in writing, for approval of such substitution. It should be noted that the bid shall not be based on a substituted article, material, apparatus, product or process. No substitution review shall take place prior to bid. D. Each form of the bid contains a section for alternates and for unit prices. All alternates prices must be completed with a dollar value. Blanks, “Not Applicable” (N/A), “No Effect”, etc in these portions of the BID FORM shall be construed to indicate that the particular alternate shall be performed without increased to the contract price as they relate to the scope of the trade package. E. Unit prices which do not affect the work all the bidder’s trade may be filled in “Not Applicable” or “(N/A)”. “Not Applicable” or Blanks in these Bid Forms shall be construed to indicate that the unit price is not applicable as it relates to the scope of the trade package. F. TAX: No amount shall be added for the Connecticut sales tax or Federal tax. The Greenwich Public School system is exempt from the payment of taxes imposed by the Federal government and/or State of Connecticut. Taxes must not be included in the bid price. G. PERMIT FEES: Greenwich Public Schools will secure the building permit(s) and upon award of the Contract they will be transferred to the awarded contractor / vendor. No cost should be included in the base bid for the building permit. H. WAGES: All work shall be done in accordance with applicable State statutes; conditions of Prevailing Wages shall apply. Prevailing Wage Schedule provided herein is for demonstrable purposes only. It is the responsibility of the bidder / vendor to verify actual rates. INSTRUCTIONS TO BIDDERS 00 0301 - 2 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 I. NOVEMBER 19TH, 2013 COLLUSION AMONG BIDDERS: 1. 2. 3. More than one offer from an individual, firm, partnership, corporation, or association under the same or different name will be rejected. Reasonable grounds for believing that a bidder is interested in more than one bid for the work contemplated will cause rejection of all bids in which the bidder is interested. Any or all bidders will be rejected if there is any reason for believing that collusion exists among the bidders. Participants in such collusion may not be considered in the future offers for the same work. Each bidder, by submitting a bid, certifies that it is not part to any collusive action. Each bid shall be accompanied by a completely filled in and properly executed NonCollusive Affidavit, provided. J. EMPLOYMENT DISCRIMINATION BY CONTRACTOR PROHIBITED: The successful bidder will not discriminate against any employee or applicant for employment because of race, religion, color, sex, or nation origin, except where religion, sex or national original is a bona fide occupational qualification reasonably necessary to the normal operation of the contractor. The successful bidder agrees to post in a conspicuous place, available to employees and applicants for employment, notices setting forth the provision of this nondiscrimination clause. The successful bidder in all solicitations or advertisements for employment, placed by or on behalf of the contractor, will state that such successful bidder in an EQUAL OPPORTUNITY EMPLOYER. K. QUALIFICATIONS: No qualifications to the bid are allowed. If bids are qualified, they may be deemed non-responsive and subsequently rejected. L. No Bidder may withdraw their Bid within 90 days after the actual date of Bid Opening. M. COPIES: Failure to submit a bid with four copies does not constitute a material defect. N. BID EVALUATION: A committee composed of various administrators will evaluate bids. The following criteria guidelines will be used in analyzing and evaluating this bid: 1. Conformance to the requirements of this bid, i.e. conformance to Terms, Conditions and Scope of Work. 2. Proven skills and technical competence. 3. Background of the firm. 4. For Vendor firm, identification of all personnel who will have a principal responsibility. 5. The Board of Education may consider proximity of the vendor’s service as a factor in determining lowest responsible bid. Companies must be located within 60 miles of the School District in order to submit a bid. 6. The Board of Education shall have the right to take such steps as it deems necessary to determine the ability of the bidder to perform the work and the bidder shall furnish the Board of Education with information and data for this purpose as the Board of Education may request. The right is reserved to reject any bid where, on investigation, the evidence or information submitted by such bidders does not satisfy the Board of Education that the bidder is qualified to carry out properly the terms of the Contract. 7. Apparent low bidder agrees to submit the following Supplements to Greenwich Pubic Schools within 48 hours after submission of the Bid for consideration in award of the Contract: a. Subcontractors; Include the names of all Subcontractors and the portions of the Work they will perform. b. Cost Breakdown identifying the Bid Price/Sum segmented into portions as requested, broken down per school building. (Schedule of Values) INSTRUCTIONS TO BIDDERS 00 0301 - 3 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 O. AWARD: The Contract shall be awarded to the lowest responsible and qualified bidder, meaning the bidder whose bid is the lowest of those bidders possessing the skill, ability, and integrity necessary to faithfully perform the work based on objective criteria considering past performance and financial responsibility. In considering past performance, the Greenwich Public Schools shall evaluate the skill, ability, and integrity of bidders in terms of the bidders’ fulfillment of contract obligations and all the bidders’ experienced or lack of experience with projects of similar size and scope. The Greenwich Public Schools reserves the right to consider as unqualified to do the work required by the bid documents any bidder that does not habitually perform with its own forces the major portion of the work involved in the bid documents. No contract will be awarded to any bidder who is at time of award not qualified under applicable regulations issued by the Secretary of Labor, United States of Department of Labor, or any applicable State and local laws and regulations. P. REJECTION: after review of all sectors, terms, and conditions, including price, Greenwich Public Schools reserves the right to reject any and all bids, or any part thereof, or waive defects in same. Q. Any bid may be withdrawn prior to the opening time and date. Any bids received after the specified time and date will not be considered. 1.5 BIDDER QUALIFICATIONS: A. The Contractor shall hold a current “DAS Contractor Prequalification Certificate” (not a predetermination letter) from the Department of Administrative Services of the State of Connecticut according to Connecticut General Statutes Section 4a-100, 4b-101, 4b-91, previously stated as Public Act 03-215 and as amended by Public Act 04-141. B. Bidders shall submit with their bids a “DAS Contractor Prequalification Certificate” as well as a current “Update (bid) Statement”. C. Questions regarding these requirements should be directed to the State of Connecticut, DAS. Contact information can be found at www.das.state.ct.us. D. Companies must be located within 60 miles of the School District in order to submit a bid. E. Companies submitting a bid must be in business under the same corporate name for a minimum of five (5) years. F. Non-Connecticut Contractors: Pursuant to Connecticut General Statutes §12-430(7), as amended by Public Act No. 11-61, Section 66, a non-resident contractor shall comply with the State of Connecticut’s bonding requirements. 1.6 CONTRACT: A. PRIME CONTRACT will be let for: 1. General Construction 2. Bid awards must be approved by the Greenwich Public Schools. All contractors shall be required to execute the Greenwich Public Schools standard form of Contract and accompanying Payment & Performance Bonds without exception. B. LENGTH: This bid is for awarding the contract to cover the period beginning July 1, 2014. Once this Bid is awarded, successful bidder must make arrangements to meet with Greenwich Public Schools as required. INSTRUCTIONS TO BIDDERS 00 0301 - 4 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 C. OPTION TO EXTEND: The Board of Education may, at their option and with the approval of the vendor, extend the period of the Contract for the 2013-2014 and 2014-2015 school years. If the Board of Education intends to extend the contract period, the vendor shall be notified in writing by the purchasing department at least fourteen (14) calendar days prior to the expiration of the original contract. D. AWARD OF CONTRACT: The contract will be awarded by the Board of Education to a qualified firm or person at compensation determined to be fair and reasonable considering budgetary limitations, scope, complexity, and the nature of goods and/or services. 1. If there is a conflict between the Contract Agreement and the General Conditions, the Contract Agreement shall prevail. 2. The successful bidder will produce for the Greenwich Public Schools review a current financial statement, which will remain strictly confidential. E. The contractor shall simultaneously with the signing of the Contract, furnish the Town the executed Performance, Maintenance, and Payment Bond of a surety company authorized to do business the State of Connecticut, and acceptable to the Town, in the sum of all the full amount of the Contract Obligation in the form provided by the Town. The Performance Bond will not be required where the total estimated cost of labor and materials under the contract with respect to which such general bid is submitted is less than one hundred thousand dollars ($100,000). Once a contract exceeds $100,000 the bidder will be responsible for obtaining and paying for all bonds required by Greenwich Public Schools. F. FEE PAYMENTS: The Greenwich Public Schools reserves the right to provide payment in accordance with completion of services based on the Project Schedule. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 PROVISIONS: A. Consumption or use of alcohol and / or drugs is prohibited on school property. Any individual with alcohol or drugs will be removed from said property and will not be allowed to work on the project. Smoking is prohibited in all school buildings and on school grounds. B. Greenwich Public Schools reserves the right to reject any proposed subcontactor for reasonable cause. END OF SECTION 00 0301 INSTRUCTIONS TO BIDDERS 00 0301 - 5 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0400 BID FORM INTERNATIONAL SCHOOL AT DUNDEE-GYM WINDOW REPLACEMENT The undersigned hereby proposes to furnish all labor, materials, devices, appliances, supplies, equipment, services and other facilities necessary to complete all of the work of the above referenced Contract, as required by, and in accordance with, the provisions of the Instructions to Bidders, the Conditions of the Contract, the Drawings and Specifications, all as prepared by KSQ Architects, P.C., and that, if this Proposal is accepted, the Undersigned agrees to enter into an Agreement with the Owner to perform this work for the sum(s) as follows: BID OPENING DATE: DECEMBER 10TH, 2013 12:00 PM SUBMITTED BY: ________________________________ Phone: ________________________ Bidder’s Full Name: _____________________________________________________________ Address: ______________________________________________________________________ _____________________________________________________________________________ City, State, Zip 1.1 BASE BIDS – Part 1 & Part 2 A. BASE BID- Part 1: The Material Base Bid of this Proposal for all work required by the Contract Documents for Gym Window Replacement and Related Work as follows: Furnishing of Materials, including but not limited to: shop drawings including field measurements and provisions of production and delivery of window and door materials to the site prior to June 30th,2014. ____________________________________________________ ($ )DOLLARS B. BASE BID – Part 2: The Labor Base Bid of this Proposal for all work required by the Contract Documents for Gym Window Replacement and Related Work as follows: Provision of Labor, to perform removals, abatement and fully install all the window materials in the material BASE BID-Part I above. ____________________________________________________ ($ 1.2 )DOLLARS ALTERNATES – Phase 1: A. No Alternates. 1.3 ALLOWANCES: A. The undersigned Contractor has included the Allowances as specified in Section 012100 in their Base Bid: $10,000 DOLLARS. 1.4 ACCEPTANCE: A. BID FORM If this bid is accepted by Greenwich Public Schools within the time period stated above, we will: 1. Execute the Agreement within seven days of receipt of Notice of Award. 2. Furnish the required bonds within seven days of receipt of Notice of Award. 00 0400 - 1 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 B. 1.5 If this bid is accepted within the time stated, and we fail to commence the Work or we fail to provide the required Bond(s), the security deposit shall be forfeited as damages to Greenwich Public Schools by reason of our failure, limited in amount to the lesser of the face value of the security deposit or the difference between this bid and the bid upon which a Contract is signed. CONTRACT TIME: A. 1.6 The Undersigned agrees in the Base Bid to complete the work as per the Milestone Schedule provided in the Specifications. ADDENDA: A. The following Addenda have been received. The modifications to the Bid Document noted below have been considered and all cost are included in the Bid Sum. 1. 2. 3. 4. 5. 1.7 NOVEMBER 19TH, 2013 Addendum#______________________ Date__________________. Addendum#______________________ Date__________________. Addendum#______________________ Date__________________. Addendum#______________________ Date__________________. Addendum#______________________ Date__________________. BIDDER’S FURTHER AFFIRMATION AND DECLARATION A. The above name bidder and should this bid be a joint bid each party thereto, further affirm and declares; 1. That said bidder is of lawful age and the only one interested in this bid; and that no other person, firm or corporation, except those herein above names has any interest in this bid or in the contract proposed to be entered into. 2. That said bidder is not in arrears to the Greenwich Public School upon debt or contract, and is not a defaulter, as surety or otherwise upon any obligation to the Greenwich Public Schools. 3. That no member of the Greenwich Public Schools or any officer or employee of the Greenwich Public School or person whose salary is payable in whole or in part from the School District treasury, or the spouse of any foregoing is or shall be or become interested, directly or indirectly, as a contracting party, partner, stockholder, surety or otherwise, in this bid, or in the performance of the Contract, or in the supplies, materials or equipment and work or labor to which it relates, or in any portion of the profits thereof. 4. That he/she has carefully examined the site of the work and that, from his / her own investigations, he/ she has satisfied him/ herself as to the nature and location of the work, and character, quality and quantity of material, and all difficulties likely to be encountered, the kind and extent of equipment and other facilities needed for the performance of the work, the general and local conditions, and all other items which may, in any way, effect the work or its performance. 5. That if a corporation, this bid or proposal containing the Non-Collusive Binding Certification and the foregoing Affirmation and Declaration has been authorized by the Board of Directors of such Corporation, which authorization includes the signing and submission of this bid or proposal and the inclusion therein of the said Certificate of Non-Collusion and Affirmation and Declaration as the Act and Dees of the Corporation. BID FORM 00 0400 - 2 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.8 NOVEMBER 19TH, 2013 BID FORM SIGNATURE(S) ______________________________________________________________________ Signature Corporate Seal Company Name:_________________________________________________________ was hereunto affixed in the presence of: ______________________________________________________________________ Subscribed and sworn before me this ____ day of ____________ 2013 Notary Public:___________________________________________________________ My Commission Expires:__________________________________________________ END OF SECTION 00 0400 BID FORM 00 0400 - 3 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0410 - CONTRACTOR’S QUALIFICATION STATEMENT With the submittal of the Bid Proposal Form (Section 00 0400), the bidder shall attach this Contractor' Qualification Statement and shall answer the Questions herein. Failure to answer these questions in full may be cause for rejection of the bidder’s proposal. If more space is needed, please attach other sheets with reference to subject paragraph. The Board of Education reserves the right to consider, but not limited to, the financial responsibility, experience and reputation in the construction industry, as well as the specific qualifications listed below and elsewhere in this document in considering bids and awarding the contract. The Board of Education reserves the right to waive any informalities if, at its discretion the interest of the Greenwich Public Schools will be better served. The Undersigned certifies under oath that the information provided herein is true and sufficiently complete so as not to be misleading. SUBMITTED TO: Greenwich Public Schools ADDRESS: 290 Greenwich Avenue, Greenwich, CT 06830 SUBMITTED BY: Corporation NAME Partnership ADDRESS: Individual PRINCIPAL OFFICE Other NAME OF PROJECT (if applicable) ISD Gym Window Replacement - 2014 TYPE OF WORK (file separate for each Classification of Work) ____________General Construction ___________HVAC ____________Plumbing ___________Electrical ____________Other 1.1 ORGANIZATION A. How many years has your organization been in business as a Contractor? B. How many years has your organization been in business under its present business name? 1. C. Under what other or former names has your organization operated? What is the firm’s bonding range? 1. Single 2. Aggregate CONTRACTOR’S QUALIFICATION STATEMENT 00 0410 - 1 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 D. E. F. G. If your organization is a corporation, answer the following: 1. Date of Incorporation: 2. State of Incorporation: 3. President’s name: 4. Vice-president’s name(s): 5. Secretary’s name: 6. Treasurer’s name: If your organization is a partnership, answer the following: 1. Date of organization: 2. Type of partnership (if applicable): 3. Name(s) of general partner(s): If your organization is individually owned, answer the following: 1. Date of organization: 2. Name of owner: If the form of your organization is individually owned, answer the following: 1. 1.2 NOVEMBER 19TH, 2013 If the form of your organization is other than those listed above, describe it and name the principals: OWNERSHIP, MANAGEMENT, AFFILIATION A. Identify each person who is or has been within the past five years, an owner of 5.0% or more of the firm’s shares, one of the five largest shareholders, a director, an officer, a partner or the proprietor, or a managerial employee. First Name MI Last Name DOB CONTRACTOR’S QUALIFICATION STATEMENT % Owned Director Y or N Officer Y or N Title Partner Y or N 00 0410 - 2 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 B. Joint Ventures: Provide information for all firms involved. Fill in name, % owned, office held; indicate by Y or N whether director, officer, partner and title. First Name C. NOVEMBER 19TH, 2013 MI Last Name DOB % Owned Director Y or N Officer Y or N Title Partner Y or N Identify any other firms in which now or in the past five years, the firm or any of the individuals listed in questions 1.2.A and 1.2.B above, either owned or owns 5.0% or more of the shares of or was or is one of the five largest shareholders, a director, an officer, a partner or a proprietor of said other firm. ______Yes, list below ________No Federal ID No. % Owned Firm/Company Name: Position Company Address D. Has the firm or any firm listed in response to questions above defaulted or been terminated and its surety called upon to complete, any contract awarded within the past five years ( ) Yes, ( ) No. If yes, give date(s), agency(ies)/owner(s), project(s), contract numbers, and describe including the result: E. List below any projects performed by the bidder in the past five (5) years on which any of the following events occurred: 1. 2. 3. 4. Were any extension of time requested by the contractor, and were such requests granted? Was litigation and/or arbitration commenced by either the Owner or the bidder as a result of the work of the project performed by the bidder? Were any liens filed on the project by subcontractors or material suppliers of the bidder? Did the bidder make any claims for extra work on the project, and did said claim result in a change order? Project Owner F. 1.3 Type of Event Name/Address of Owner Name & Phone # of Contact Person at For ALL contracts within the past five years: (a) List all liens or claims over $25,000 filed against the firm and remaining undischarged or unsatisfied for more than 90 days; and (b) list and describe all liquidated damages assessed. FINANCIAL INFORMATION A. Provide a copy of the firm’s most recent annual financial statement. CONTRACTOR’S QUALIFICATION STATEMENT 00 0410 - 3 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.4 NOVEMBER 19TH, 2013 OTHER INFORMATION A. Within the past five years has the firm, any affiliate, any predecessor company or entity or any person identified in questions number 1.1 through 1.2 above been the subject of any of the following: (Respond to each question and describe in detail the circumstances of each affirmative answer: (Attach additional pages if necessary). 1. A judgment of conviction for any business-related conduct constituting a crime under state or federal law. No_______ Yes_____ 2. A criminal investigation or indictment for any business-related conduct constituting a crime under state or federal law? No_______Yes______ 3. An order of protection filed against an officer or employee prohibiting access to jobsite(s) or prohibiting contact with any staff of any owner? No_______ Yes______ 4. A grant of immunity for any business-related conduct constituting a crime under state and federal law? No______ Yes______ 5. A federal or state suspension or debarment? 6. A rejection of any bid for lack of qualifications, responsibility or because of the submission or an informal, non-responsive or incomplete bid? No_______Yes______ 7. A rejection of any proposed subcontract for lack of qualifications, responsibility or because of the submission or an informal, non-responsive or incomplete bid? No_______ Yes______ 8. A denial or revocation of prequalication? No_______ Yes______ 9. A voluntary exclusion from bidding/contracting agreement? No_______ Yes______ 10. Any administrative proceeding or civil action seeking specific performance or restitution in connection with any public works contract except any disputed work proceeding? No______ Yes______ No_______ Yes______ 11. An OSHA Citation and Notification of Penalty containing a a violation classified as serious? No______ 12. An OSHA Citation or Notification of Penalty containing a a violation classified as willful? No______ Yes______ 13. A prevailing wage or supplement payment violation? No______ Yes______ 14. A State Labor Law violation deemed willful? No______ Yes______ Yes______ 15. Any other federal or state Citations, Notices, violation orders, pending administrative hearings or proceedings or determinations of a violation of any labor law or regulation? No______ Yes______ 16. Any criminal investigation, felony indictment or conviction concerning formation of or any business association with, an allegedly false or fraudulent women’s, minority or disadvantaged business enterprise? No______ Yes______ CONTRACTOR’S QUALIFICATION STATEMENT 00 0410 - 4 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 17. Any denial, decertification, revocation or forfeiture of Women’s Business Enterprise, Minority Business Enterprise or Disadvantaged Business Enterprise status? NOVEMBER 19TH, 2013 No______ Yes_____ 18. Rejection of a low bid on a State contract for failure to meet statutory affirmative action M/WBE requirements? No______ Yes_____ 19. A consent order with the NYS Department of Environmental Conservation or a federal, state or local government enforcement determination involving a violation of federal or state environmental laws? No_____ Yes_____ 20. Any bankruptcy proceeding? 21. Any suspension or revocation of any business or professional license? No______ Yes_____ No______ Yes_____ 22. a. b. c. d. e. f. g. Any citations, notices, violation orders, pending administrative hearings or proceedings or determinations for violation of: No______ Yes_____ Federal, state or local health laws, rules or regulations No______ Yes_____ Federal, state or local environmental laws, rules and regulations. No______ Yes_____ Unemployment insurance or workers compensation coverage or claim requirements No______ Yes_____ ERISA (Employee Retirement Income Security Act) No______ Yes_____ Federal, state or local human rights laws No______ Yes_____ Federal or state security laws No______ Yes_____ Withdrawal or an agreement to withdraw a bid submitted to a public owner or a request by a public owner to withdraw a bid? No______ Yes_____ B. During the five year period preceding the submissions of this bid, has the bidder been named as a part in any lawsuit in an action involving a claim for personal injury or wrongful death arising from performance of work related to any project in which it has been engaged? If the answer to this question is yes, list all such lawsuits, the index number associated with said suit and the status of the lawsuit at the time of the submission of this bid. No______ Yes_____ C. During the five year period preceding the submission of this bid, has the bidder been the subject of proceedings before the Department of Labor for alleged violations of the Labor Law as it relates to the payment of prevailing wages and/or supplemental payment requirements? If the answer to this question is yes, please list each such instance of the commencement of a Department of Labor proceeding, for which project such proceeding was commenced, and the status of the proceeding at the time of the submission of this bid. No______ Yes_____ D. During the five year period preceding the bidder’s submission of this bid, has the bidder been the subject of proceedings involving allegations that it violated the Worker’s Compensation Law including but not limited to the failure to provide proof of worker’s compensation or disability coverage and/or any lapses thereof. If the answer to this question is yes, list such instance of violation and the status of the claimed violation at the time of disposition of this bid. No____ CONTRACTOR’S QUALIFICATION STATEMENT Yes___ 00 0410 - 5 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 E. NOVEMBER 19TH, 2013 Has the bidder, its officers, directors, owner and/or managerial employees been convicted of a crime or been the subject of a criminal indictment during the five years preceding the submission of this bid? If the answer to this question is yes, list the name of the individual convicted or indicted the charge against the individual and the date of disposition of the charge. No______ Yes_____ F. During the five year period preceding the bidder’s submission of this bid, has the bidder been charged with and/or found guilty of any violations of federal, state, or municipal environmental and/or health laws, codes, rules and/or regulations. If the answer to this question is yes, list the nature of the charge against the bidder, the date of the charge, and the status of the charge at the time of the submission of this bid. No______ Yes_____ G. Has the bidder ever defaulted or had its surety called upon to complete any contract awarded within the past five years. If the answer to this question is yes, list the projects, the dates and the nature of the termination (convenience, suspension, for cause). No______ Yes_____ H. Has any officer or partner of the bidder’s organization ever defaulted or had its surety called upon to complete any contract awarded within the past five years or been an office or partner of some other organization that has been terminated from a project by an owner? If yes, state No_____ Yes_____ Name of Individual(s) 1.5 Name of Organization(s) Reason(s) LICENSING A. List jurisdictions and trade categories in which your organization is legally qualified to do business, and indicate registration of license numbers, if applicable. B. List jurisdictions in which your organization’s partnership or trade name is filed: C. Has any director, officer, owner or managerial employee had any professional license suspended or revoked? If the answer is yes, list the name of the individual, the professional license he/she formally had, whether the license was revoked or suspended and the date of the revocation or suspension. No______ Yes_____ 1.6 EXPERIENCE A. List the categories of work that your organization will perform with its own forces: B. Claims and Suits. (If the answer of any of the questions below is yes, please attach details.) 1. Have you or has any director, officer, owner or managerial employee ever failed to complete any work awarded to them? If yes, list the project(s) the date(s) and the reason(s) for the failure to complete. 2. Are there any judgments, claims, arbitration proceedings or suits pending or outstanding CONTRACTOR’S QUALIFICATION STATEMENT 00 0410 - 6 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 against your organization or its officers? 3. Has your organization filed any law suits or requested arbitration with regard to construction contracts within the last five years? C. Within the last five years, has any officer or principal of your organization ever been an officer or principal of another organization when it failed to complete a construction contract? (If the answer is yes, please attach details.) No______ Yes__ D. On a separate sheet, list all similar construction projects your organization has in progress or completed, giving the name of project, owner, architect, contract amount, percent complete and scheduled completion date. 1. E. On a separate sheet, list all projects, not listed above, that your organization has completed or in progress in the past five years, giving the name of the project, owner, architect, contract amount, date of completion and percentage of the cost of the work performed with your own forces. 1. F. 1.7 State total worth of work in progress and under contract: State average annual amount of construction work performed during the past five years: On a separate sheet, list the construction experience and present commitment of the key individuals of your organization. REFERENCES A. Trade reference: B. Bank references: C. Surety: 1. 2. 3. Name of present bonding company: Name and address of agent: Name or previous bonding company: CONTRACTOR’S QUALIFICATION STATEMENT 00 0410 - 7 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.8 NOVEMBER 19TH, 2013 CERTIFICATION A. The undersigned recognizes that this questionnaire is submitted for the purpose of the Greenwich Public Schools (Owner) to award a contract or approve a subcontract; acknowledges that the Owner may in its discretion, by means which it may choose, determine the truth and accuracy of all statements made herein; acknowledge that intentional submission of false or misleading information may constitute a felony, or a misdemeanor, and may also be punishable by a fine or imprisonment; and states that the information submitted in this questionnaire and any attached pages is true, accurate and complete. Dated at this day of ___________ _________________________________________________________________________________ Name of Organization: _________________________________________________________________________________ By: _________________________________________________________________________________ Title: SWORN AND SUBSCRIBED TO BEFORE ME, A NOTARY PUBLIC, IN AND FOR THE COUNTY OF ____________________ AND THE STATE OF __________________________ THIS _______________________ DAY OF _______________________, 2013 ______________________________ NOTARY PUBLIC MY COMMISSION EXPIRES_________ END OF SECTION 00 0410 CONTRACTOR’S QUALIFICATION STATEMENT 00 0410 - 8 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0460 - NON-COLLUSIVE AFFIDAVIT GREENWICH PUBLIC SCHOOLS 290 GREENWICH AVE GREENWICH, CONNECTICUT State of ___________________________: County of _________________________:s.s. I state that I am the_______________________ of __________________________________________ (TITLE) (NAME OF MY FIRM) and that I am authorized to make this affidavit on behalf of my firm, and its owners, directors, and officers. I am the person responsible in my firm for the price(s) and the amount of this bid. I state that: (1) The price(s) and amount of this bid have been arrived at independently and without consultation communication or agreement with any other contractor, bidder/proposer or potential bidder/proposer. (2) Neither the price(s) nor the amount of this BID/RFP, and neither the approximate price(s) nor approximate amount of this BID/RFP, have been disclosed to any other firm or person who is a bidder/proposer or potential bidder/proposer, and they will not be disclosed before BID/RFP opening. (3) No attempt has been made or will be made to induce any firm or person to refrain from bidding/proposing on this contract, or to submit a bid/proposal higher than this BID/RFP, or to submit any intentionally high or noncompetitive BID/RFP or other form of complementary BID/RFP. (4) I fully understand that more than one offer from an individual, firm partnership; corporation or association under the same or different name will be rejected. Reasonable grounds for believing that a bidder/proposer is interested in more than one BID/RFP for the work contemplated may cause rejection of all BID/RFP in which the bidder/proposer is interested. Any or all bidders/proposers will be rejected if there is any reason for believing that collusion exists among the bidders/proposers. Participants in such collusion may not be considered in the future offers for the same work. Each bidder/proposer by submitting a bid/proposal certifies that it is not a part to any collusive action. (5) The BID/RFP of my firm is made in good faith and not pursuant to any agreement or discussion with, or inducement from, any firm or person to submit a complementary or other noncompetitive bid/proposal. (6) ______________________________________its affiliates, subsidiaries, officers, (NAME OF MY FIRM) directors and employees are not currently under investigation by any governmental agency and have not in the last four years been convicted or found liable for any act prohibited by State or Federal law in any jurisdiction, involving conspiracy or collusion with respect to bidding/proposing on any public contract, except as follows: I state that __________________________ understands and acknowledges that (NAME OF MY FIRM) NON-COLLUSIVE AFFIDAVIT 00 0460 - 1 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 the above representations are material and important, and will be relied on by Greenwich Public Schools in awarding the bid/proposal for which this is submitted. I understand and my firm understands that any misstatement in this affidavit is and shall be treated as fraudulent concealment from Greenwich Public Schools of the true facts relating to the submission of bids/proposals for this contract. (7) I agree deliver all services on the date and time agreed on by ____________________________________________________ and the (NAME OF MY FIRM) Greenwich Board of Education. Furthermore, there will not be any cancellations to the Board of Education. If a bidder/proposer submits a bid/proposer on any item he/she will be responsible for delivering that item at the bid/proposal cost, in accordance with the attached above specifications, which were submitted with this bid/proposal and upon which the bid/proposal was made. (8) In submitting this bid/proposal, the undersigned declares that this is made without any connection with any persons making another bid/proposal on the same contract; that the bid/proposal is in all respects fair and without collusion, fraud or mental reservation; and that no official of the Town, or any person in the employ of the Town, is directly or indirectly interested in said bid/proposal or in the supplies or work to which it relates, or in any portion of the profits thereof. (9) In submitting this bid, the undersigned further declares that it has not, and will not, induce or attempt to induce any Town of Greenwich employee or officer to violate the Greenwich Code of Ethics in connection with its offer to provide goods or services under, or otherwise in the performance of such contract. (10) The undersigned further understands that the above declarations are material representations to the Town of Greenwich made as a condition to the acceptance of the bid/proposal. If found to be false, the Town of Greenwich retains the right to reject said bid/proposal and rescind any resultant contract and/or purchase order and notify the undersigned accordingly, thereby declaring as void said bid/proposal and contract or purchase order. (11) The Greenwich Code of Ethics can be found at www.greenwichct.org Code of Ethics stated as follows: (2) DEFINITION. (1) Indirect interest, without limiting its generality, shall mean and include the interest of any subcontractor in any prime contract with the Town and the interest of any person or his immediate family in any corporation, firm or partnership which as a direct or indirect interest in any transaction with the Town. (2) Substantial financial interest shall mean any financial interest, direct or indirect, which is more than nominal and which is not common to the interest of other citizens of the Town. (3) Town Officer shall mean and include any official, commission, committee, legislative body or other agency of the Town. (4) Transaction shall mean and include the offer, sale or furnishing of any real or personal property, material, supplies otherwise, for the use and benefit of the Town for a valuable consideration, excepting the services of any person as a Town Officer. NON-COLLUSIVE AFFIDAVIT 00 0460 - 2 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 (3) GIFTS AND FAVORS. No Town Officer or his immediate family shall accept any valuable gift, things, favor, loan or promise which might tend to influence the performance or nonperformance of his official duties. (4) IMPROPER INFLUENCE. No Town Officer having a substantial financial interest in any transaction with the Town or in any action to be taken by the Town shall use is office to exert his influence or to vote on such transaction or action. By signing this proposal the proposer understands and agrees to the attached terms, conditions, and specifications, including Collusion among Proposers. Employment Discrimination by the Contractor Prohibited. VENDOR INFORMATION: (Please print the following) ___________________________________________________________________________________ Vendor Name ___________________________________________________________________________________ Address ___________________________________________________________________________________ Telephone Fax # ___________________________________________________________________________________ E-MAIL WEB SITE ___________________________________________________________________________________ PRINTED NAME & SIGNATURE TITLE SWORN AND SUBSCRIBED TO BEFORE ME, A NOTARY PUBLIC, IN AND FOR THE COUNTY OF ____________________ AND THE STATE OF __________________________ THIS _______________________ DAY OF _______________________, 2013 ______________________________ NOTARY PUBLIC MY COMMISSION EXPIRES_________ END OF SECTION 00 0460 NON-COLLUSIVE AFFIDAVIT 00 0460 - 3 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0461 – PREVAILING WAGE RATES Building Rates - Greenwich (effective July 1, 2013) Classification Hourly Rate Benefits $35.00 27.41 2) Boilermaker $35.24 25.01 3a) Bricklayer, Cement Mason, Concrete Finisher (including caulking), Stone Masons $32.50 27.24 + a 3b) Tile Setter $32.94 22.42 3c) Terrazzo Mechanics and Marble Setters $31.69 22.35 3d) Tile, Marble & Terrazzo Finishers $26.25 19.20 3e) Plasterer $32.50 26.21 4) Group 1: Laborers (common or general), acetylene burners, carpenter tenders, concrete specialists, wrecking laborers, fire watchers. $26.40 17.15 4a) Group 2: Mortar mixers, plaster tender, power buggy operators, powdermen, fireproofer/mixer/nozzleman, fence erector. $26.65 17.15 4b) Group 3: Jackhammer Operators/Pavement Breaker, mason tender (brick) and mason tender (cement/concrete) $26.90 17.15 1a) Asbestos Worker/Insulator (Includes application of insulating materials, protective coverings, coatings, & finishes to all types of mechanical systems; application of firestopping material for wall openings & penetrations in walls, floors, ceilings 1b) Asbestos/Toxic Waste Removal Laborers: Asbestos removal and encapsulation (except its removal from mechanical systems which are not to be scrapped), toxic waste removers, blasters.**See Laborers Group 7** ------LABORERS------ WAGE DETERMINATION SCHEDULE 00 0461 - 1 of 6 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 4c) **Group 4: Pipelayers (Installation of water, storm drainage or sewage lines outside of the building line with P6, P7 license) (the pipelayer rate shall apply only to one or two employees of the total crew who primary task is to actually perform the m $26.65 17.15 4d) Group 5: Air track operators, Sand blasters $27.15 17.15 4e) Group 6: Nuclear toxic waste removers, blasters $29.40 17.15 4f) Group 7: Asbestos/lead removal and encapsulation (except it's removal from mechanical systems which are not to be scrapped) $27.40 17.15 4g) Group 8: Bottom men on open air caisson, cylindrical work and boring crew $26.90 17.15 4h) Group 9: Top men on open air caisson, cylindrical work and boring crew $26.40 17.15 4i) Group 10: Traffic Control Signalman $16.00 17.15 5) Carpenter, Acoustical Ceiling Installation, Soft Floor/Carpet Laying, Metal Stud Installation, Form Work and Scaffold Building, Drywall Hanging, Modular-Furniture Systems Installers, Lathers, Piledrivers, Resilient Floor Layers. $30.45 21.65 5a) Millwrights $30.78 22.15 6) Electrical Worker (including low voltage wiring) (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2 V-1,2,7,8,9) $48.75 37.73 7a) Elevator Mechanic (Trade License required: R-1,2,5,6) $46.41 25.185+a+b Groundman $24.99 6.5% + 9.75 Linemen/Cable Splicer $45.43 6.5% + 16.20 8) Glazier (Trade License required: FG-1,2) $34.18 17.75 9) Ironworker, Ornamental, Reinforcing, Structural, and Precast Concrete Erection $33.50 28.98 Group 1: Crane handling or erecting structural steel or stone, hoisting engineer 2 drums or over, front end loader (7 cubic yards or over); work boat 26 ft. and over. (Trade License Required) $36.05 21.55 + a Group 2: Cranes (100 ton rate capacity and over); Backhoe/Excavator over 2 cubic yards; Piledriver ($3.00 $35.73 21.55 + a -----LINE CONSTRUCTION---- ----OPERATORS---- WAGE DETERMINATION SCHEDULE 00 0461 - 2 of 6 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 premium when operator controls hammer). (Trade License Required) Group 3: Excavator; Backhoe/Excavator under 2 cubic yards; Cranes (under 100 ton rated capacity), Grader/Blade; Master Mechanic; Hoisting Engineer (all types of equipment where a drum and cable are used to hoist or drag material regardless of motive pow $34.99 21.55 + a Group 4: Trenching Machines; Lighter Derrick; Concrete Finishing Machine; CMI Machine or Similar; Koehring Loader (Skooper). $34.60 21.55 + a Group 5: Specialty Railroad Equipment; Asphalt Paver; Asphalt Reclaiming Machine; Line Grinder; Concrete Pumps; Drills with Self Contained Power Units; Boring Machine; Post Hole Digger; Auger; Pounder; Well Digger; Milling Machine (over 24" Mandrell) $34.01 21.55 + a Group 5 continued: Side Boom; Combination Hoe and Loader; Directional Driller; Pile Testing Machine. $34.01 21.55 + a Group 6: Front End Loader (3 up to 7 cubic yards); Bulldozer (rough grade dozer). $33.70 21.55 + a Group 7: Asphalt roller, concrete saws and cutters (ride on types), vermeer concrete cutter, Stump Grinder; Scraper; Snooper; Skidder; Milling Machine (24" and under Mandrell). $33.36 21.55 + a Group 8: Mechanic, grease truck operator, hydroblaster; barrier mover; power stone spreader; welding; work boat under 26 ft.; transfer machine. $32.96 21.55 + a Group 9: Front end loader (under 3 cubic yards), skid steer loader regardless of attachments, (Bobcat or Similar): forklift, power chipper; landscape equipment (including Hydroseeder). $32.53 21.55 + a Group 10: Vibratory hammer; ice machine; diesel and air, hammer, etc. $30.49 21.55 + a Group 11: Conveyor, earth roller, power pavement breaker (whiphammer), robot demolition equipment. $30.49 21.55 + a Group 12: Wellpoint operator. $30.43 21.55 + a Group 13: Compressor battery operator. $29.85 21.55 + a Group 14: Elevator operator; tow motor operator (solid tire no rough terrain). $28.71 21.55 + a Group 15: Generator Operator; Compressor Operator; Pump Operator; Welding Machine Operator; Heater Operator. $28.30 21.55 + a WAGE DETERMINATION SCHEDULE 00 0461 - 3 of 6 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 Group 16: Maintenance Engineer/Oiler. $27.65 21.55 + a Group 17: Portable asphalt plant operator; portable crusher plant operator; portable concrete plant operator. $31.96 21.55 + a Group 18: Power safety boat; vacuum truck; zim mixer; sweeper; (Minimum for any job requiring a CDL license). $29.54 21.55 + a 10a) Brush and Roller $30.62 17.75 10b) Taping Only/Drywall Finishing $31.37 17.75 10c) Paperhanger and Red Label $31.12 17.75 10e) Blast and Spray $33.62 17.75 11) Plumber (excluding HVAC pipe installation) (Trade License required: P-1,2,6,7,8,9 J-1,2,3,4 SP-1,2) $39.31 26.27 12) Well Digger, Pile Testing Machine $33.01 19.40 + a Roofer: Cole Tar Pitch $37.00 12.75 + a Roofer: Slate, Tile, Composition, Shingles, Singly Ply and Damp/Waterproofing $35.50 12.75 + a 15) Sheetmetal Worker (Trade License required for HVAC and Ductwork: SM-1,SM-2,SM-3,SM-4,SM-5,SM-6) $43.41 31.90 16) Pipefitter (Including HVAC work) (Trade License required: S-1,2,3,4,5,6,7,8 B-1,2,3,4 D-1,2,3,4, G-1, G-2, G-8 & G-9) $39.31 26.27 17a) 2 Axle $27.88 18.27 + a 17b) 3 Axle, 2 Axle Ready Mix $27.98 18.27 + a 17c) 3 Axle Ready Mix $28.03 18.27 + a 17d) 4 Axle, Heavy Duty Trailer up to 40 tons $28.08 18.27 + a 17e) 4 Axle Ready Mix $28.13 18.27 + a 17f) Heavy Duty Trailer (40 Tons and Over) $28.33 18.27 + a 17g) Specialized Earth Moving Equipment (Other Than Conventional Type on-the-Road Trucks and Semi-Trailers, Including Euclids) $28.13 18.27 + a 18) Sprinkler Fitter (Trade License required: F-1,2,3,4) $38.98 19.87 + a 19) Theatrical Stage Journeyman $22.22 6.53 ------PAINTERS (Including Drywall Finishing)------ ------TRUCK DRIVERS------ WAGE DETERMINATION SCHEDULE 00 0461 - 4 of 6 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 Welders: Rate for craft to which welding is incidental. *Note: Hazardous waste removal work receives additional $1.25 per hour for truck drivers. **Note: Hazardous waste premium $3.00 per hour over classified rate. Crane with boom including jib, 150 feet - $1.50 extra. Crane with boom including jib, 200 feet - $2.50 extra. Crane with boom including jib, 250 feet - $5.00 extra. Crane with boom including jib, 300 feet - $7.00 extra. Crane with boom including jib, 400 feet - $10.00 extra. ~ ~ ~ All classifications that indicate a percentage of the fringe benefits must be calculated at the percentage rate times the "base hourly rate". Apprentices duly registered under the Commissioner of Labor's regulations on "Work Training Standards for Apprenticeship and Training Programs" Section 31-51-d-1 to 12, are allowed to be paid the appropriate percentage of the prevailing journeymen hourly base and the full fringe benefit rate, providing the work site ratio shall not be less than one full-time journeyperson instructing and supervising the work of one apprentice in a specific trade. ~~Connecticut General Statute Section 31-55a: Annual Adjustments to wage rates by contractors doing state work ~~ The Prevailing wage rates applicable to this project are subject to annual adjustments each July 1st for the duration of the project. Each contractor shall pay the annual adjusted prevailing wage rate that is in effect each July 1st, as posted by the Department of Labor. It is the contractor's responsiblity to obtain the annual adjusted prevailing wage rate increases directly from the Department of Labor's website. The annual adjustments will be posted on the Department of Labor's Web page: www.ctdol.state.ct.us. The Department of Labor will continue to issue the initial prevailing wage rate schedule to the Contracting Agency for the project. All subsequent annual adjustments will be posted on our Web Site for contractor access. Effective October 1, 2005 - Public Act 05-50: any person performing the work of any mechanic, laborer, or worker shall be paid prevailing wage. All Persons who perform work ON SITE must be paid prevailing wage for the appropriate mechanic, laborer, or worker classification. All certified payrolls must list the hours worked and wages paid to All Persons who perform work ON SITE regardless of their ownership i.e.: (Owners, Corporate Officers, LLC Members, Independent Contractors, et. al) WAGE DETERMINATION SCHEDULE 00 0461 - 5 of 6 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 Reporting and payment of wages is required regardless of any contractual relationship alleged to exist between the contractor and such person. ~~Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clause (29 CFR 5.5 (a) (1) (ii)). Please direct any questions which you may have pertaining to classification of work and payment of prevailing wages to the Wage and Workplace Standards Division, telephone (860)263-6790. END OF SECTION 00 0461 WAGE DETERMINATION SCHEDULE 00 0461 - 6 of 6 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0462 – REFERENCES List at least five (5) references for similar projects in size, scope, and complexity, within Connecticut and / or New York. THIS PAGE MUST BE COMPLETED AND SUBMITTED WITH YOUR BID. 1) Client________________________________________________________________________ Project Address_______________________________________________________________ Approximate $ Value _____________ Date: Started __________ Completed ___________ Contact: Name ____________________________Telephone # ________________________ 2) Client________________________________________________________________________ Project Address_______________________________________________________________ Approximate $ Value _____________ Date: Started __________ Completed ___________ Contact: Name ____________________________Telephone # ________________________ 3) Client________________________________________________________________________ Project Address_______________________________________________________________ Approximate $ Value _____________ Date: Started __________ Completed ___________ Contact: Name ____________________________Telephone # ________________________ 4) Client________________________________________________________________________ Project Address_______________________________________________________________ Approximate $ Value _____________ Date: Started __________ Completed ___________ Contact: Name ____________________________Telephone # ________________________ 5) Client________________________________________________________________________ Project Address_______________________________________________________________ Approximate $ Value _____________ Date: Started __________ Completed ___________ Contact: Name ____________________________Telephone # ________________________ END OF SECTION 00 0462 REFERENCES 00 0462 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0472 – FORM OF BID BOND TOWN OF GREENWICH, CONNECTICUT BID BOND _____________________________________________________________________________ Date Bond Executed ____________________________________________________________________________________________ Principal ____________________________________________________________________________________________ Surety ____________________________________________________________________________________________ Penal Sum of Bond (express in words and figures ) Date of Bid _____________________________________________________________________________ KNOW ALL MEN BY THESE PRESENTS, that we, the principal and surety above named, are held and firmly bound unto the Town of Greenwich, Connecticut, in the penal sum of the amount stated above, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally, firmly by these presents, THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the principal has submitted the accompanying bid, dated as shown above for ______________________________. (name of bid) _____________________________________________________________________________ NOW THEREFORE, if the principal shall not withdraw said bid within the period specified therein after the opening of the same, or if no period be specified, within sixty (60) days after said opening, and shall within the period specified therefor, or if no period specified, within ten (10) days after the prescribed forms are presented to him for signature, execute such further contractual documents, if any, as may be required by the term of the Bid as accepted, and give bonds with good and sufficient surety or sureties as may be required, for the faithful performance and proper fulfillment of the resulting contract, and for the protection of all person supplying labor and material in the prosecution of the work provided for in such contract or in the event of the withdrawal of said bid within the period specified, or the failure to enter into such contract and give such bonds within the time specified, if the principal shall pay the Town of Greenwich, Connecticut, the difference between the amount specified in said bid and the amount for which said Town may procure the required work, supplies, and services, if the latter amount be in excess of the former, then the above obligation shall be void and of no effect, otherwise to remain in full force and virtue. IN WITNESS WHEREOF the above bounden parties have executed this instrument under their several seals on the date indicated above. The name and corporate seal (if applicable) of each corporate party being hereto affixed: FORM OF BID BOND 00 0472 - 1 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 _____________________________________________________________________________ Name of Partnership ______________________________________________________________________________________(SEAL) Business Address ____________________________________________________________________________________________ Partner- (Hereunto Duly Authorized) IN THE PRESENCE OF: WITNESS INDIVIDUAL PRINCIPAL 1.__________________________________AS TO__________________________(SEAL) 2.__________________________________AS TO__________________________(SEAL) 3.__________________________________AS TO__________________________(SEAL) 4.__________________________________AS TO__________________________(SEAL) ************************************************************************ __________________________________________ CORPORATE/ LLC PRINCIPAL WITNESS __________________________________________ BUSINESS ADDRESS AFFIX CORPORATE SEAL _________________________________ ______________________________________ BY- (HEREUNTO DULY AUTHORIZED) ______________________________________ TITLE ************************************************************************ __________________________________________ CORPORATE/ LLC PRINCIPAL WITNESS __________________________________________ BUSINESS ADDRESS AFFIX CORPORATE SEAL _________________________________ _________________________________________ BY- (HEREUNTO DULY AUTHORIZED) _________________________________________ TITLE FORM OF BID BOND 00 0472 - 2 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0473 - CERTIFICATE AS TO CORPORATE PRINCIPAL CERTIFICATE AS TO CORPORATE PRINCIPAL I, ________________________________________________________________, certify that I am the _____________________________________ of the corporation named as principal in the within bond; that ___________________________________, who signed said bond on behalf of the principal, was then ____________________________ of the corporation; that I know his signature, and his signature thereto is genuine; and that said bond was duly signed, sealed and attested for and in behalf of said corporation by authority of its governing body. ___________________________________ (Corporate Seal) END OF SECTION 00 0473 CERTIFICATE AS TO CORPORATE PRINCIPAL 00 0473 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0474 – PERFORMANCE, MAINTENANCE AND PAYMENT BOND BOND NO. _______________________ CONTRACT NO. _______________________________ KNOW ALL MEN BY THESE PRESENTS. That we ___________________________________________ _____________________________________, as Principal, and ________________________________ a corporation organized under the laws of the State of_________________________ and authorized to do business in the State of Connecticut as Surety, for holder and firmly bound jointly and severally unto the Town of Greenwich, Connecticut, herein referred to as the Town, the territorial corporation located in the County of Fairfield, in the penal sum of _________________________________________________________ Dollars ($__________________), to be paid to it or its certain attorney, successors or assigns, to which payment well and truly to be made, we the said Obligors do bind ourselves, and each of us, our heirs, executors, administrators, and successors firmly by these presents. IN WITNESS WHEREOF we have hereunto set for cause to be set our respective hands, names and seals this ___________________________ day of __________________________, 20_____ The condition of this obligation is such, that whereas the above named Principal has entered into a certain written contract with the Town of Greenwich, Connecticut, dated the ___________________________ day of __________________________, 20_____ NOW, THEREFORE, if the said Principal shall well and faithfully perform said contract according to its provisions, and fully indemnify and save harmless the Town from all costs and damages which the Town may suffer by reason of failure so to do, and shall pay for all equipment, appurtenances, materials and labor furnished, used or employed in the execution of said contract, and shall indemnify and save harmless the Town from all suits or claims of any nature or description against the Town by reason of any injuries or damages sustained by any person or persons on account of any act or omission of said Principal, his servants or agents, or his subcontractors in the construction of the work or in guarding the work, or on account of the use of faulty or improper materials, or by reason of claims under the Workmen’s Compensation Laws or other laws by any employee of the Principal or his subcontractors, or by reason of the use of patented material, machinery, device, equipment, process, method of construction or design in any way involved in the work, and shall indemnify the Town against such defective workmanship, material and equipment as may be discovered within one (1) year after completion and final acceptance of the work, and shall make good in such defective workmanship and material as may be discovered within said period of one (1) year, then the obligation shall be void, otherwise to remain in full force and effect. The Surety hereby stipulates and agrees that any modifications, omissions or additions in or to the terms of the aforesaid contract, or in or to the plans or specifications therefor, or any extension of time, shall in no wise affect the obligation of the Surety under this bond, the surety hereby waiving any and all right to any notice of any such modifications, omissions, changes, additions or extensions. Contractor Name:__________________________ By:__________________________________ Surety Name:_____________________________ By:__________________________________ END OF SECTION 00 0474 PERFORMANCE MAINTENANCE AND PAYMENT BOND 00 0474 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0481 - INSURANCE PROCEDURE PLEASE NOTE: THIS PAGE MUST BE RETURNED WITH YOUR BID/PROPOSAL. FAILURE TO DO SO MAY RESULT IN YOUR BID/PROPOSAL BEING REJECTED. Please take the insurance requirements of the Contract to your agent/broker immediately upon receipt of the bid documents to determine your existing coverage and any costs for new or additional coverage required for the work noted in this Request for Bid/Proposal. Any bids/proposals with deficient insurance requirements will be rejected. The firm who is awarded the Bid/Proposal must return the contract, agent/broker and insurance form within two (2) weeks from the date on the award letter. PLEASE CHECK THE APPROPRIATE BOX YES NO 1. General Liability $3,000,000.00 Includes minimum coverages for combined bodily injury and property damage liability of $2,000,000 general aggregate and $1,000,000 per occurrence. 2. Automobile Liability $1,000,000.00 3. Excess Liability $5,000,000.00 4. Worker’s Compensation and Employer’s Liability 5. Ability to Return Contract and Insurance Documents Within Two (2) Weeks 6. Able to Provide the Town with Thirty (30) Days Prior Written Notice of Cancellation STATEMENT OF VENDOR: I have read the insurance requirements for this work and have taken the documentation to my insurance agent/broker. The bid/proposal cost reflects any additional costs relating to insurance requirements for this work. Signature Date Contract END OF SECTION 00 0481 INSURANCE PROCEDURE 00 0481 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0482 – INSURANCE REQUIREMENTS Insurance Requirements: Before starting and until final completion and acceptance of the work called for in the Contract and expiration of the guarantee period provided for in the Contract, the Contractor and its subcontractors, if any, shall procure and maintain insurance of the types and amounts checked in paragraphs A through F below for all Contract operations. A. General Liability, with minimum coverages for combined bodily injury and property damage liability of $2,000,000 general aggregate, $1,000,000 per occurrence including: 1. Commercial General Liability. 2. Town as additional insured. 3. Owners and Contractors Protective Liability (separate policy in the name of the Town). B. Comprehensive Automobile Liability, with minimum coverages of $1,000,000 combined single limit for bodily injury and property damage, including, where applicable, coverage for any vehicle, all owned vehicles, scheduled vehicles, hired vehicles, non-owned vehicles and garage liability. C. Excess Liability, with minimum coverage of $5,000,000 in umbrella form, or such other form as approved by Town Department Head and Risk Management Director. D. Workers' Compensation and Employer's Liability, with minimum coverages as provided by Connecticut State Statutes. E. Professional Liability (for design and other professionals for Errors and Omissions), with minimum coverage of $1,000,000. If the policy is on a claims-made basis, coverage shall be continually renewed or extended for three (3) years after work is completed under the Contract. F. Other (Builder's Risk, etc.): G. CERTIFICATE HOLDER: TOWN OF GREENWICH / GREENWICH PUBLIC SCHOOLS ATTN: BOARD OF EDUCATION (Also fill in on ACORD Certificate of Insurance) . 101 Fieldpoint Road, Greenwich, CT 06830. The Acord certificate of insurance form must be executed by your insurance agent/broker and returned to this office. Company name and address must conform on all documents including insurance documentation. It is required that agent/broker note the individual insurance companies providing coverage, rather than the insurance group, on the Acord form. The Contract number (provided to the awarded Contractor), project name and a brief description must be inserted in the “Description of Operations” field. It must be confirmed on the Acord Form that the Town of Greenwich / Greenwich Public Schools, KSQ Architects, PC, and School Construction Consultants, Inc. is endorsed as an additional insured by having the appropriate box checked off and/or stating such in the “Description of Operations” field. A letter from the awarded vendor’s agent/broker certifying that the Town of Greenwich / Greenwich Public Schools has been endorsed onto the general liability policy as an additional insured is also mandatory. This letter must follow exactly the format provided by the Board of INSURANCE REQUIREMENTS 00 0482 - 1 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 Education and must be signed by the individual authorized representative who signed the Acord form. Contract development will begin upon receipt of complete, correct insurance documentation. The Contractor shall be responsible for maintaining the above insurance coverages in force to secure all of the Contractor's obligations under the Contract with an insurance company or companies with an AM Best Rating of B+:VII or better, licensed to write such insurance in Connecticut and acceptable to the Risk Manager, Town of Greenwich. For excess liability only, non-admitted insurers are acceptable, provided they are permitted to do business through Connecticut excess line brokers per listing on the current list of Licensed Insurance Companies, Approved Reinsurers, Surplus Lines Insurers and Risk Retention Groups issued by the State of Connecticut Insurance Department. END OF SECTION 00 0482 INSURANCE REQUIREMENTS 00 0482 - 2 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0483A – SAMPLE ENDORSEMENT LETTER AGENT/BROKER (LETTERHEAD) (Date) Town of Greenwich Board of Education Attention: Eugene Watts, Senior Buyer 290 Greenwich Avenue Greenwich, CT 06830 Re: (Name of the Insured) Town of Greenwich Contract No. Dear Mr. Watts: The undersigned hereby certifies as follows: (1) I am a duly licensed insurance agent under the laws of the State of [insert state] and an authorized representative of all companies affording coverage under the Acord form submitted herewith; (2) The Town of Greenwich has been endorsed as an additional insured under general liability policy no. [insert policy number], issued by [insert company affording coverage] to [name of insured]; (3)] The general liability policy referenced in paragraph (2) above meets or exceeds the coverage in Commercial General Liability ISO form CG 00 01 10 01, including contractual liability; (4) The policies listed in the Acord form submitted to the Town of Greenwich in connection with the above referenced contract have been issued to the insured in the amounts stated and for the periods indicated in the Acord form; and (5) The Town of Greenwich shall be given thirty (30) days prior written notice of cancellation, lapse or restrictive amendment (except ten days notice of non-payment) of the policies listed in the Acord form. Sincerely, (Signature) Authorized Representative for all companies listed in the Acord form END OF SECTION 00 0483A SAMPLE ENDOREMENT LETTER 00 0483A - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 00 0483B – A.M. BEST KEY RATING GUIDE FORM The following insurance companies are licensed in the State of Connecticut per the 2011 edition of the A.M. Best Key Rating Guide For Property and Casualty, 1. 2. 3. 4. 5. 6. Company Name: __________________________________ a) Page Number: _____________ b) Rating is: _____________ Company Name: __________________________________ a) Page Number: _____________ b) Rating is: _____________ Company Name: __________________________________ a) Page Number: _____________ b) Rating is: _____________ Company Name: __________________________________ a) Page Number: _____________ b) Rating is: _____________ Company Name: __________________________________ a) Page Number: _____________ b) Rating is: _____________ Company Name: __________________________________ a) Page Number: _____________ b) Rating is: _____________ END OF SECTION 00 0483B A.M. BEST KEY RATING GUIDE FORM 00 0483B - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0483C - AFFIRMATIVE ACTION COMPLIANCE AFFIDAVIT COMMISSION ON HUMAN RIGHTS AND OPPORTUNITIES CONTRACT COMPLIANCE REGULATIONS NOTIFICATION TO BIDDERS AFFIRMATIVE ACTION COMPLIANCE AFFIDAVIT The contract to be awarded is subject to contract compliance requirements mandated by Sections 4a-60 and 4a-60a of the Connecticut General Statutes; and, when the awarding agency is the State, Sections 46a-71(d) and 46a-81i(d) of the Connecticut General Statutes. There are Contract Compliance Regulations codified at Section 46a-68j-21 through 43 of the Regulations of Connecticut State Agencies, which establish a procedure for awarding all contracts covered by Sections 4a-60 and 46a-71(d) of the Connecticut General Statutes. According to Section 46a-68j-30(9) of the Contract Compliance Regulations, every agency awarding a contract subject to the contract compliance requirements has an obligation to “aggressively solicit the participation of legitimate minority business enterprises as bidders, contractors, subcontractors and suppliers of materials.” “Minority business enterprise” is defined in Section 4a-60 of the Connecticut General Statutes as a business wherein fifty-one percent or more of the capital stock, or assets belong to a person or persons: “(1) Who are active in daily affairs of the enterprise; (2) who have the power to direct the management and policies of the enterprise; and (3) who are members of a minority, as such term is defined in subsection (a) of Section 32-9n.” “Minority” groups are defined in Section 32-9n of the Connecticut General Statutes as “(1) Black Americans . . .(2) Hispanic Americans . . . (3) persons who have origins in the Iberian Peninsula . . . (4)Women . . . (5) Asian Pacific Americans and Pacific Islanders; (6) American Indians . . .” An individual with a disability is also a minority business enterprise as provided by Section 4a-60g of the Connecticut General Statutes. The above definitions apply to the contract compliance requirements by virtue of Section 46a-68j-21(11) of the Contract Compliance Regulations. The awarding agency will consider the following factors when reviewing the bidder’s qualifications under the contract compliance requirements: (a) the bidder’s success in implementing an affirmative action plan; (b) the bidder’s success in developing an apprenticeship program complying with Sections 46a-68-1 to 46a-68-17 of the Administrative Regulations of Connecticut State Agencies, inclusive; (c) the bidder’s promise to develop and implement a successful affirmative action plan; (d) the bidder’s submission of employment statistics contained in the “Employment Information Form”, indicating that the composition of its workforce is at or near parity when compared to the racial and sexual composition of the workforce in the relevant labor market area; and (e) the bidder’s promise to set aside a portion of the contract for legitimate minority business enterprises. See Section 46a-68j-30(10)(E) of the Contract Compliance Regulations. AFFIRMATIVE ACTION COMPLIANCE AFFIDAVIT 00 0483C - 1 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 *INSTRUCTIONS: NOVEMBER 19TH, 2013 Bidders must sign acknowledgement below and return acknowledgement to Awarding Agency along with bid proposal. The undersigned acknowledges receiving and reading a copy of the “Notification to Bidders” form. ________________________________ Signature ___________________________ Date On behalf of: ___________________________________ ____________________________________ ____________________________________ END OF SECTION 00 0483C AFFIRMATIVE ACTION COMPLIANCE AFFIDAVIT 00 0483C - 2 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0484B – SAMPLE CONTRACT THE FOLLOWING PAGES ARE A SAMPLE COPY OF THE TOWN OF GREENWICH CONTRACT FOR YOUR REVIEW. YOU MUST BE ABLE TO SIGN THIS CONTRACT AND MEET THE NECESSARY INSURANCE AS REQUIRED BY THE TOWN OF GREENWICH IN ORDER FOR YOUR PROPOSAL TO BE CONSIDERED. State of Connecticut SAMPLE CONTRACT 00 0484B - 1 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 Town of Greenwich Contract Town Department: Contract No.: Division: Account Name: Name and Address Of Contractor Account Code: Total Amount: of Contract This Agreement made this ____day of __________, (year) between Town of Greenwich/BOE hereafter called the Town and (Company Name) hereafter called the Contractor Witnessed as follows: 1. The contractor agrees to furnish materials and perform services as shown in specifications and contract documents hereto attached and made a part hereof, and consisting of numbered pages from 1 to (total pages) 2. The Town agrees to pay the price designated for such materials and services upon certification by the proper agent of the Town. 3. This contract shall not be valid until approved by the Town Counsel and countersigned by the Town Comptroller. TOWN OF GREENWICH By_____________________________________________________ Its Managing Director of Operations Benjamin B. Branyan CONTRACTOR By_____________________________________________________ Its President CORPORATE ACKNOWLEDGEMENT (STATE OF CONNECTICUT) (COUNTY OF FAIRFIELD) ss: , 2013 of ___________________________________________ Personally appeared (Name and title of Officer) Signer and sealer of the foregoing instrument, who being duly authorized and appointed by the Board of Directors of said Corporation, acknowledged the foregoing instrument to be his free act and deed and the free act and deed of said _____________________________________, before me (Corporation) ____________________________________________ Notary Public SAMPLE CONTRACT 00 0484B - 2 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 INDIVIDUAL OR PARTNERSHIP ACKNOWLEDGEMENT (delete words in parenthesis if not a partnership) (STATE OF (COUNTY OF ) ) ss: _________________________________________, 2013 , (one of the members of the partnership of) Personally appeared ________________________ , signer and sealer of the foregoing instrument and acknowledged the same to be his free act and deed (and the free act and deed of said partnership), before me _________________________________________ Notary Public (seal) Approved as to legal sufficiency Date________________________________________ __________________________________________ Town Counsel I hereby certify that the estimated amount of this contract does not exceed the unencumbered balances of amounts duly appropriated and against which this contract is chargeable as indicated hereon. Date_________________________________________ SAMPLE CONTRACT _________________________________________ Comptroller 00 0484B - 3 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 AGREEMENT CONTRACT NO. THIS AGREEMENT, executed this day of in the year Two Thousand Thirteen (herein referred to as the "AGREEMENT"), by and between the Town of Greenwich, Connecticut, acting through __________________________________________________ hereunto duly authorized, "OWNER" and ___________________________________________, acting through __________________________________________________ (insert name of individual and title) duly authorized, "CONTRACTOR". WITNESSETH, that the parties to these presents, each in consideration of the under-taking, promises and agreements on the part of the other herein contained, have undertaken, promised and agreed to do hereby undertake, promise and agree, the Owner for itself, its successors and assigns, and the Contractor for himself and his heirs, executors, administrators, successors and assigns, as follows: 1. DEFINITIONS: Wherever the words hereinafter defined or pronouns used in their stead occur in the Contract Documents, they shall have the following meaning: The word "Owner" shall mean the Town of Greenwich and shall include its authorized representative. The word "Contractor" shall mean the person or organization identified as such in this Agreement and shall include his authorized representative. The words "Contracting Officer or Agency" shall mean that official of the Town which awards the contract, executes the Agreement and is the Owner's authorized representative. The Information for Bidders, the Contractor's Bid as accepted by the Owner, the Contract Conditions and Specifications and the General, Technical and Materials Specifications, the Drawings, and all addenda and amendments to any of the foregoing, collectively constitute the Contract Documents, and are sometimes herein referred to as the "Contract". 2. DESCRIPTION OF WORK: 3. PAYMENT: The Contractor shall be paid on a monthly basis after presentation of vouchers, and subject to acceptance and approval by the Town of Greenwich. Such payments will be made by the Town of Greenwich monthly for all services actually rendered, and the acceptance by the Contractor of any such monthly payment shall be a release to the Town of all claims and all liability to the Contractor in connection with the contract, arising during the period for which payment is made. No payment, however, shall operate to release the Contractor or its sureties or insurers from any obligation under the Contract to be entered into or the Performance Bond or any insurance policies issued in connection with said contract. SAMPLE CONTRACT 00 0484B - 4 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 4. NOVEMBER 19TH, 2013 PERFORMANCE MAINTENANCE AND PAYMENT BOND: The Contractor shall, simultaneously with the signing of the Contract, furnish the Town the executed Performance, Maintenance and Payment Bond of a surety company authorized to do business in the State of Connecticut, and acceptable to the Town, in the sum of the full amount of the Contract obligation in the form provided by the Town. THE ABOVE IS ONLY REQUIRED FOR CONTRACTS EXCEEDING $100,000.00. 5. GUARANTEE: The Contractor guarantees that the Work and services to be performed, furnished, used or installed in the construction of the same, shall be free from defects and flaws, and shall be performed and furnished in strict accordance with the Drawings, if any, Specifications, and other Contract Documents, that the strength of all parts of all manufactured equipment shall be adequate and as specified and that the performance test requirements of the Contract shall be fulfilled. This guarantee shall be for a period of one year from and after the date of completion and acceptance of the Work as stated in the final estimate. The Contractor shall repair, correct or replace as required, promptly and without charge, all work, equipment and material, or parts thereof, which fail to meet the above guarantee or which in any way fail to comply with or fail to be in strict accordance with the terms and provisions and requirements of the Contract during such one-year period, and also shall repair, correct, or replace all damage to the Work resulting from such failure. 6. DEFECTIVE WORK: The inspection of the Work shall not relieve the Contractor of any of his obligations to perform and complete the Work as required by the Contract. Defective work shall be corrected and unsuitable materials, equipment apparatus and other items shall be replaced by the Contractor, notwithstanding that such work, materials, equipment, apparatus and other items may have been previously overlooked or accepted or estimated for payment. If the work or any part thereof shall be found defective at any time before the final acceptance of the work, the Contractor shall forthwith make good such defect in a manner satisfactory to the Town; if any material, equipment, apparatus or other items brought upon the site for use or incorporation in the work, or selected for the same, is condemned by the Town as unsuitable or not in conformity with the Specifications or any of the other Contract Documents, the Contractor shall forthwith remove such materials, equipment, apparatus and other items from the site of the Work and shall at his own cost and expense make good and replace the same and any material furnished by the Town which shall be damaged or rendered defective by the handling or improper installation by the Contractor, his agents, servants, employees or subcontractors. 7. COMPLIANCE WITH LAWS: The Contractor shall keep himself fully informed of all existing and future federal, state and local laws, ordinances, rules and regulations affecting those engaged or employed on the work, the materials and equipment used in the work or the conduct of the work, and of all orders, decrees and other requirements of bodies or tribunals having any jurisdiction or authority over the same. If any discrepancy or inconsistency is discovered in the Drawings, if any, Specifications or other Contract Documents in relation to any such law, ordinance, rule, regulation, order, decree or other requirement, the Contractor shall forthwith report the same to the Town in writing. The Contractor shall at all times observe and comply with, and cause all his agents, servants, employees and subcontractors to observe and comply with all such existing and future laws, ordinances, rules, regulations, orders, decrees and other requirements, and he shall protect, indemnify and save harmless the Town, its officers, agents, servants and employees from and against any and all claims, demands, suits proceedings, liabilities, judgments, penalties, losses, damages costs and expenses, including attorneys' fees, arising from or based upon SAMPLE CONTRACT 00 0484B - 5 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 any violation or claimed violation of any such law, ordinance, rule, regulation, order, decree or other requirement, whether committed by the Contractor or any of his agents, servants, employees or subcontractors. 8. INDEMNITY: The Contractor shall indemnify and save harmless the Town and its officers, agents, servants and employees, from and against any and all claims, demands, suits, proceedings, liabilities, judgments, awards, losses, damages, costs and expenses, including attorneys' fees, on account of bodily injury, sickness, disease or death sustained by any person or persons or injury or damage to or destruction of any property, directly or indirectly arising out of, relating to or in connection with the Work, whether or not due or claimed to be due in whole or in part to the active, passive or concurrent negligence or fault of the Contractor, his officers, agents, servants or employees, any of his subcontractors, the Town any of his respective officers, agents, servants or employees and/or any other person or persons, and whether or not such claims, demands, suits or proceedings are just, unjust, groundless, false or fraudulent; and the Contractor shall and does hereby assume and agrees to pay for the defense of all such claims, demands, suits and proceedings; and provided that the Contractor shall not be required to indemnify the Town, its officers, agents, servants or employees against any such damages occasioned solely by acts or omissions of the Town other than supervisory acts or omissions of the Town in connection with the Work. INDEMNITY AGAINST SUBCONTRACTORS' CLAIMS: If any other contractor or any subcontractor of any such other contractor shall suffer or claim to have suffered loss, damage or delay by reason of the acts or omissions of the Contractor or of any of his subcontractors, the Contractor agrees to assume the defense against any such claim and to reimburse such other contractor or subcontractor for such loss or damage. The Contractor agrees to and does hereby indemnify and save harmless the Town from and against any and all claims by such other contractors or subcontractors, alleging such loss, damage or delay and from and against any and all claims, demands, suits, proceedings, liabilities, judgments, awards, losses, damages, costs and expenses including attorneys' fees, arising out of, relating to or resulting from such claims. 9. PATENTS: The Contractor shall indemnify and save harmless the Town and all persons acting for or on behalf of the Town from all claims and liability of any nature or kind, and all damages, costs and expenses, including attorneys' fees, arising from or occasioned by an infringement or alleged infringement of any patents or patent rights on any invention, process, materials, equipment, article, or apparatus, or any part hereof, furnished and installed by the Contractor, or arising from or occasioned by the use or manufacture thereof, including their use by the Town. 10. CHANGES: The Town, through its designated Agent, may make changes in the Work and in the Drawings, if any, and Specifications therefore by making alterations therein, additions, thereto or omissions there from. All work resulting from such changes shall be performed and furnished under and pursuant to the terms and conditions of the Contract. If such changes result in an increase or decrease in the Work to be done hereunder, or increase or decrease the quantities thereof, adjustment in compensation shall be made therefore. For eliminated or decreased work the Contractor shall allow the Town a reasonable credit as determined by the Parties. Except in an emergency endangering life or property, no change shall be made unless in pursuance of a written order from the Town authorizing the change, and no claim for additional compensation shall be valid unless the change is so ordered. The Contractor agrees that he shall neither have nor assert any claim for or be entitled to any additional compensation for damages or for loss of anticipated profits on work that is eliminated. SAMPLE CONTRACT 00 0484B - 6 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 11. NOVEMBER 19TH, 2013 CLAIMS FOR DAMAGES: If the Contractor makes claim for any damages alleged to have been sustained by breach of contract or otherwise, he shall, within ten (10) days after occurrence of the alleged breach or within ten (10) days after such damages are alleged to have been sustained whichever date is the earlier, file with the Contracting Officer a written, itemized statement of the details of the alleged breach and the details and amount of the alleged damages. The Contractor agrees that unless such statement is made and filed as so required, his claim for damages shall be deemed waived, invalid and unenforceable, and that he shall not be entitled to any compensation for any such alleged damages. Within ten (10) days after the timely filing of such statement, the Contracting Officer shall file with the appropriate department of the Town, one copy of the statement, and shall file with the Town and the Contractor his determination thereon. The Contractor shall not be entitled to claim any additional compensation for damages by reason of any direction, instruction, determination or decision of the Town or its agents, nor shall any such claims be considered, unless the Contractor shall have complied in all respects with the provisions of this paragraph. 12. ABANDONMENT OF THE WORK OR OTHER DEFAULT: If the Work shall be abandoned, or any part thereof shall be sublet without previous written consent of the Town, or the Contract or any moneys payable hereunder shall be assigned otherwise than as herein specified, or if at any time the Contracting Officer shall be of the opinion, and shall so certify in writing, that the conditions herein specified as to rate of progress are not being complied with, or that the Work or any part thereof is being unnecessarily or unreasonably delayed, or that the Contractor has violated or is in default under any of the provisions of the Contract, or if the Contractor becomes bankrupt or insolvent or goes or is put into liquidation or dissolution, either voluntarily or involuntarily, or petitions for an arrangement or reorganization under the Bankruptcy Act, or makes a general assignment for the benefit of creditors or otherwise acknowledges insolvency, the happening of any of which shall be and constitute a default under the Contract, the Town may notify the Contractor in writing, with a copy of such notice mailed to the surety, to discontinue all Work or any part thereof; thereupon the Contractor shall discontinue such Work or such part thereof as the Town may designate; and the Town may, upon giving such notice, by Contract or otherwise as it may determine, complete the Work or such part thereof and charge the entire cost and expense of so completing the work. The Town shall be entitled to reimbursement from the Contractor and the Contractor agrees to pay to the Town any losses, damages, costs and expenses, including attorneys' fees, sustained or incurred by the Town by reason of any of the foregoing causes. For the purpose of such completion the Town may for itself or for any Contractors employed by the Town take possession of and use or cause to be used any and all materials, equipment, plant, machinery, appliances, tools, supplies and such other items of every description that may be found or located at the site of the Work. All costs, expenses, losses, damages, attorneys' fees, and any and all other charges incurred by the Town under this subsection shall be charged against the Contractor and deducted and/or paid by the Town out of any moneys due and payable or to become due or payable under the Contract to the Contractor; in computing the amounts chargeable to the Contractor, the Town shall not be held to a basis of the lowest prices for which the completion of the Work or any part thereof might have been accomplished, but all sums actually paid or obligated therefore to effect its prompt completion shall be charged to and against the account of the Contractor. In case the costs, expenses, losses, damages, attorneys' fees and other charges together with all payments theretofore made to or for the account of the Contractor are less than the sum which would have been payable under the Contract if the Work had been properly performed and completed by the Contractor, the Contractor shall be entitled to receive the difference, and, and in case such costs, expenses, losses, damages, attorneys' fees and other charges, together with all payments theretofore made to or for the account of the Contractor, shall exceed the said sum, the Contractor shall pay the amount of the excess to the Town. SAMPLE CONTRACT 00 0484B - 7 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 13. NOVEMBER 19TH, 2013 LIENS: If at any time any notices of lien or other legal process are filed for labor performed or materials or equipment manufactured, furnished, or delivered to or for the Work, the Contractor shall, at its own cost and expense, promptly discharge, remove or otherwise dispose of the same, and until such discharge, removal or disposition, the Town shall have the right to retain from any moneys payable hereunder an amount which, in its sole judgment, it deems necessary to satisfy such liens and pay the costs and expenses, including attorneys' fees, of defending any actions brought to enforce the same, or incurred in connection therewith or by reason thereof. 14. CLAIMS: If at any time there be any evidence of any claims for which the Contractor is or may be liable or responsible hereunder, the Contractor shall promptly settle or otherwise dispose of the same, and until such claims are settled or disposed of, the Town may retain from any moneys which would otherwise be payable hereunder so much thereof as, in its sole judgment, it may deem necessary to settle or otherwise dispose of such claims and to pay the costs and expenses, including attorneys' fees, of defending any actions brought to enforce such claims or incurred in connection therewith or by reason thereof. 15. LIABILITY OF TOWN: No person, firm or corporation, other than the Contractor, who signed this Contract as such, shall have any interest herein or rights hereunder. No claim shall be made or be valid either against the Town or any agent of the Town and neither the Town nor any agent of the Town shall be liable for or be held to pay any money, except as herein provided. The acceptance by the Contractor of the payment as fixed in the final estimate shall operate as and shall be a full and complete release of the Town and of every agent of the Town of and from any and all claims, demands, damages and liabilities of, by or to the Contractor for anything done or furnished for or arising out of or relating to or by reason of the Work or for or on account of any act or neglect of the Town or of any agent of the Town or of any other person, arising out of, relating to or by reason of the Work, except the claim against the Town for the unpaid balance, if any there be, of the amounts retained as herein provided. 16. PROVISIONS REQUIRED BY LAW DEEMED INSERTED: Each and every provision of law and clause required by law to be inserted in the Contract shall be deemed to be inserted herein, and the Contract shall be read and enforced as though they were included herein. If through mistake or otherwise any such provision is not inserted, or is not correctly inserted, then upon the application of either party, the Contract shall forthwith be physically amended to make such insertion. 17. PERMITS: The Contractor shall, at his own expense, take out and maintain all necessary permits from the State, Town, or other public authorities; shall give all notices required by law; and shall post all bonds and pay all fees and charges incident to the due and lawful prosecution of the Work. 18. NOT TO SUBLET OR ASSIGN: The Contractor shall constantly give his personal attention to the faithful prosecution of the Work, shall keep the same under his personal control, shall not assign the Contract or sublet the Work or any part thereof without the previous written consent of the Town, and shall not assign any of the moneys payable under the Contract, or his claim thereto, unless by and with the like written consent of the Town and the surety on the Contract Bonds. Any assignment or subletting in violation hereof shall be void and unenforceable. SAMPLE CONTRACT 00 0484B - 8 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 19. NOVEMBER 19TH, 2013 EMPLOY COMPETENT PEOPLE: The Contractor shall employ only competent people on the Work and shall not employ people or means which may cause strikes, work stoppages and/or disturbances by workmen employed by the Contractor, any subcontractor, the Town, the Contracting Officer or any other contractor. Whenever the Contracting Officer notifies the Contractor in writing that in his opinion any person on the Work is incompetent, unfaithful, disorderly, or otherwise unsatisfactory or not employed in accordance with the provisions of the Contract, such person shall be discharged from the Work and shall not again be employed on it, except with the written consent of the Contracting Officer. 20. EMPLOY SUFFICIENT LABOR AND EQUIPMENT: If in the sole judgment of the Contracting Officer the Contractor is not employing sufficient labor, plant, equipment or other means to complete the Work within the time specified, the Contracting Officer may, after giving written notice, require the Contractor to employ such additional labor, plant, equipment and other means as the Contracting Officer deems necessary to enable the Work to progress properly. 21. INTOXICATING LIQUORS: The Contractor shall not sell and shall neither permit nor suffer the introduction or use of intoxicating liquors upon or about the Work. 22. ACCESS TO WORK: The Town, the Contracting Officer, and their officers, agents, servants and employees may at any and all times and for any and all purposes, enter upon the Work and the site thereof and the premises used by the Contractor, and the Contractor shall at all times provide safe and proper facilities therefore. 23. EXAMINATION OF WORK: The Contracting Officer shall be furnished by the Contractor with every reason able facility for examining and inspecting the Work and for ascertaining that the Work is being performed in accordance with the requirements and intent of the Contract, even to the extent of requiring the uncovering or taking down portions of finished work by the Contractor. 24. EXTRA WORK: The Contractor shall perform any extra work (work in connection with the Contract but not provided for herein) when and as ordered in writing by the Contracting Officer, at the unit prices stipulated in the Contract for such work or, if none are so stipulated, either (a) at the price agreed upon before such work is commenced and named in the written order for such work, or (b) if the Contracting Officer so elects, for the reasonable cost of such work, as determined by the Contractor and approved by the Contracting Officer, plus a percentage of such cost, as may be agreed upon by Contract and Contracting Officer. 25. CHANGES NOT TO AFFECT BONDS: It is distinctly agreed and understood that any changes made in the work or the Drawings or Specifications therefore (whether such changes increase or decrease the amount thereof or the time required for its performance) or any changes in the manner or time of payments made by the Town to the Contractor, or any other modifications of the Contract, shall in no way annul, release, diminish or affect the liability of the surety on the Contract Bonds given by the Contractor, it being the intent hereof that notwithstanding such changes the liability of the surety on said bonds continue and remain in full force SAMPLE CONTRACT 00 0484B - 9 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 and effect. 26. PRICES FOR WORK: The Town shall pay and the Contractor shall receive the prices stipulated in the Bid made a part hereof as full compensation for everything performed and furnished and for all risks and obligations undertaken by the Contractor under and as required by the Contract. 27. MONEYS MAY BE RETAINED: The Town may at any time retain from any moneys which would otherwise be payable hereunder so much thereof as the Town may deem necessary to complete the Work hereunder and to reimburse it for all costs, expenses, losses, damage and damages chargeable to the Contractor hereunder. 28. USE OR PARTIAL PAYMENT NOT ACCEPTANCE: It is agreed that this is an entire contract for one whole and complete Work or result and that neither the Town’s entrance upon or use of the Work or any part thereof nor any partial payments by the Town shall constitute an acceptance of the Work or any part thereof before its entire completion and final acceptance. 29. NON-CONNECTICUT CONTRACTORS: Pursuant to Connecticut General Statutes §12-430(7), as amended by Connecticut Public Act #11-61, Section 66, a nonresident contractor shall comply with the State of Connecticut’s bonding requirements. 30. PAYMENT TO SUBCONTRACTORS: As required by Section 49-41a of the Connecticut General Statutes, within thirty days after payment to the Contractor by the Town for work under this Contract, he shall pay any amounts due any subcontractor, whether for labor performed or materials furnished when such labor or materials has been included in a requisition submitted by such Contractor and paid by the Town. 31. INSURANCE: Insurance coverage required as noted in "Exhibit A" attached. 32. PREVAILING WAGE RATES; CONSTRUCTION SAFETY AND HEALTH COURSE: Except as noted below, the Contractor shall comply with the current provisions of Section 31-53 of the General Statutes of the State of Connecticut, a part of which is quoted as follows: "The wages paid on an hourly basis to any person performing the work of any mechanic, laborer or worker on the work herein contracted to be done and the amount of payment or contribution paid or payable on behalf of each such person to any employee or welfare fund, as defined in subsection (h) of section 31-53 of the General Statutes, shall be at a rate equal to the rate customary or prevailing for the same work in the same trade or occupation in the town in which such public works project is being constructed. Any contractor who is not obligated by agreement to make payment or contribution on behalf of such persons to any such employee welfare fund shall pay to each mechanic, laborer or worker as part of such person’s wages the amount of payment or contribution for such person’s classification on each pay day." SAMPLE CONTRACT 00 0484B - 10 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 All Contractors and subcontractors shall submit certified weekly payrolls, on forms furnished by the Town, for all contracts meeting the aforementioned monetary limits. The certified payrolls shall be submitted with the Contractor's monthly certificate for payment. Section 31-55a of the General Statutes of the State of Connecticut provides that the prevailing wage rates applicable to any awarded contract or subcontract are subject to annual adjustments each July 1st for the duration of the project. Each Contractor that is awarded a contract shall pay the annual adjusted prevailing wage rate that is in effect each July 1st, as posted by the Department of Labor. It is the Contractor’s responsibility to obtain the annual adjusted prevailing wage rate increases directly from the Department of Labor’s web site. The annual adjustments will be posted on the Department’s of Labor web page: www.ctdol.state.ct.us. For those without Internet access, contact the division listed below. The Contractor shall also furnish proof with the weekly certified payroll for the first week each employee begins work that any person performing the work of a mechanic, laborer or worker has completed a course of at least ten (10) hours in duration in construction safety and health approved by the federal Occupational Safety and Health Administration in accordance with Connecticut General Statutes Section 3153b and regulations adopted by the State of Connecticut Labor Commissioner. The provisions of this section (32) shall not apply where the total cost of all work to be performed by all Contractors and subcontractors in connection with new construction of any public works project is less than four hundred thousand dollars ($400,000) or where the total cost of all work to be performed by all contractors and subcontractors in connection with any remodeling, refinishing, refurbishing, rehabilitation, alteration or repair of any public works project is less than one hundred thousand dollars ($100,000). Questions can be directed to the Contract Compliance Unit, Wage and Workplace Standards Division, Connecticut Department of Labor, 200 Folly Brook Blvd., Wethersfield, CT 06109 at 860-2636790. 33. GOVERNING LAW: The laws of the State of Connecticut shall govern this Contract and any and all litigation related to this Contract. In the event of litigation related to this Contract, the exclusive forum shall be the State of Connecticut and the exclusive venue for such litigation shall be the Judicial District for Stamford/Norwalk at Stamford. IN WITNESS, WHEREOF, the parties of the AGREEMENT have hereunto set their hand and seals the day first above written. TOWN OF GREENWICH, CONNECTICUT BY_________________________________ THE CONTRACTOR BY_________________________________ END OF SECTION 00 0484 SAMPLE CONTRACT 00 0484B - 11 of 11 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 DOCUMENT 00 0485 – CONSENT OF SURETY CONSENT OF SURETY The Undersigned surety, being the surety which issued bonds No._________ for the Town of Greenwich Contract No. ___________ hereby consents to release of final payment and all retainages to the contractor- principal. (Name of Surety) By_______________________________________ Its ACKNOWLEDGMENT STATE OF: ss: COUNTY OF: This is to certify the above signatory who executed this instrument was either known to me or satisfactorily proven to me to be the person whom he purports to be. ______________________________________ Notary Public END OF SECTION 00 0485 CONSENT OF SURETY 00 0485 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 0486 AFFIDAVIT FOR FINAL PAYMENT AFFIDAVIT FOR FINAL PAYMENT The undersigned, being duly sworn, deposes and says: 1. That he is the _______________________________(Title) of the contractor in hereinafter referred to and is authorized to execute this affidavit on behalf of the contractor; 2. In connection with Contract #___________ for ________________________ (Project Title) it is represented that all payroll, bills for services, materials, supplies, equipment and other indebtedness have been paid or otherwise satisfied and that there are no outstanding claims against the undersigned by any sub-contractor or material supplier, or no outstanding claims to file a claim against the Town of Greenwich; 3. This affidavit is made at the request of the Town of Greenwich for the purpose of inducing final payment and knowing that it will rely upon the truth of the representation herein made. Subscribed and sworn to before me this____ day of____________, 20___ _______________________________ Notary Public ________________________________ (Type or print name person authorized to sign) END OF SECTION 00 0486 AFFIDAVIT FOR FINAL PAYMENT 00 0486 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 00 8500 – LIST OF DRAWINGS DWG N0. DRAWING NAME A000 A001 COVER SHEET ABBREVIATIONS, SYMBOLS, NOTES ARCHITECTURAL A100 A101 A102 GYMNASIUM PLANS, DOOR TYPES, DETAILS GYMNASIUM BUILDING ELEVATIONS WALL SECTIONS, WINDOW TYPES END OF SECTION 00 0850 LIST OF DRAWINGS 00 8500 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 1000 – SUMMARY OF WORK PART 1 - GENERAL 1.1 PROJECT INFORMATION A. Project: International School at Dundee Gym Window Replacement Project B. Project Location: 1. International School at Dundee 55 Florence Road, Riverside, CT 06878 C. Owner: Greenwich Public Schools. D. Architect: KSQ Architects, PC. 235 Main Street, White Plains, NY 10601 E. Construction Manager: School Construction Consultants, 190 Motor Parkway, Suite 201, Hauppauge, NY 11788 F. The Gymnasium Building work is to include all of the existing windows and frames to be removed and replaced with new system. This is to include the interior vestibule area and exterior egress doors. G. Work by Owner: No separate contracts are anticipated for the completion of this work. H. The Project will be constructed under a single prime-contracting arrangement. 1.2 GENERAL REQUIREMENTS A. DIVISION 0 - BIDDING DOCUMENTS, CONTRACTS AND CONDITIONS B. DIVISION 1 - GENERAL REQUIREMENTS 1.3 GENERAL WORK CONTRACTOR A. Owner’s Contract Documents and Forms B. The work of the General Contract includes but not limited to the following: BASE BID: Part 1 C. 1. All front end documentation, schedules, submittals, field measurements and preparation of shop drawings, followed by ordering windows. 2. Provision of window system, consisting of fixed, operable, insulated and spandrel units. 3. Delivery of windows stored in containers provided by the contractor. The work of the General Contract includes but not limited to the following: BASE BID: Part 2 1. Asbestos Abatement 2. Scoping of work area. 3. Scaffolding or operable lift sequencing. 4. Selective removals of existing façade curtainwall (by abatement contractor). 5. Temporary watertight protection of openings. 6. Provision of structural work, clips, fastener plates etc. 7. Installation of new window system, doors, panels. 8. Providing insulation as required. SUMMARY OF WORK 01 1000 - 1 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 D. 1.4 A. NOVEMBER 19TH, 2013 9. Partial removal of existing ceilings to access work. 10. Partial installation of new ceilings at window heads. 11. Provide caulking as required. 12. Provision of close out documents, including but not limited to as-builts, operations manuals and warranty/ guarantees. 13. Firestopping for work under this contract. Special Notes: Contract #1 - General Work Contractor: 1. Access doors furnished by General Contractor. 2. All existing ceiling removal / replacements necessary to install GC work will be by GC including temporary support for all lighting fixtures, smoke detectors, etc. 3. All new roof curbs, if indicated, are provided by GC. Temporary weather protection by GC. Demo of existing roof curbs by GC. Curbs, pitch pockets, etc. will be flashed / watertight by GC. 4. GC and subcontractors will not be allowed to use existing or new plumbing fixtures to wash out mortar pans, grout, adhesives, etc. 5. GC is specifically reminded that there may be miscellaneous asbestos pipe insulation / fittings above some ceiling areas. Contractor will investigate above the ceiling prior to demolition and carefully perform the removal where necessary to not disturb any insulation / fittings above. 6. GC will paint all existing door frames scheduled for new doors / hardware on door schedule. Frame to be painted on all sides. SUBCONTRACTORS / SUPPLIERS Submittal of Primary Sub-Contractors and Suppliers include but not limited to the following: TO BE INCLUDED IN CONTRACTOR’S PROPOSAL Construction Contractor: 1.5 1. Asbestos Abatement 2. Windows 3. Doors and Frames CONTRACTOR’S USE OF PREMISES A. General: During the construction period the prime Contractors jointly shall have full use of the premises for construction operations, including use of the site. Each prime contractor’s use of the premises is limited only by the Owner’s right to perform work or retain other contractors on portions of the Project. B. Access to each building will be Monday through Friday, 6:00 am thru 9:00 pm. Access to the buildings on weekends will not be permitted without written permission by the Owner. If access is granted on weekends, the District reserves the right to invoice the Contractor for their personnel costs in the form of a change order to the Contract. C. Use of the Site: Limit use of the premises to work in areas indicates. Confine operations to areas within contract limits indicated. Do not disturb portions of the site beyond the areas in which the Work is indicated. 1. Owner Occupancy: Allow for Owner occupancy and use by the public. SUMMARY OF WORK 01 1000 - 2 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. D. 1.6 NOVEMBER 19TH, 2013 Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Owner, the Owner’s employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site. Use of the Existing Building: Maintain the existing building in a weather tight condition throughout the construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building and its occupants during the construction period. OCCUPANCY REQUIREMENTS A. Full Owner Occupancy: The Owner will occupy the site and existing building during the entire construction period. Cooperate with the Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with the Owner’s operations. B. Partial Owner Occupancy: The Owner reserves the right to occupy the place and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work, Such placing of equipment and partial occupancy shall not constitute acceptance of the total Work. 1.7 A. B. 1. The Architect will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner occupancy. 2. Obtain a Certificate of Occupancy from local building officials prior to Owner occupancy. 3. Prior to partial Owner occupancy, mechanical and electrical systems shall be fully operational. Required inspections and tests shall have been successfully completed. Upon occupancy, the Owner will operate and maintain mechanical and electrical systems serving occupied portions of the building. 4. Upon occupancy, the Owner will assume responsibility for maintenance and custodial service for occupied portions of the building. DEFINITIONS Definitions as applied to “Contractors” involved with the work of this Project: 1. “The Contractor” or “Contractor” meaning that Respective Prime Contractor normally responsible for that work referenced; 2. “Respective Prime Contractor” meaning either the - General Trades, Plumbing, HVAC or Electrical Contractors normally responsible for the referenced work; 3. “Trade Contractor” meaning that Respective Prime Contractor as above; and such other terms relating to Contractors to be taken in context with respect to referenced work. 4. Further, wherein said Division 0 and 1 and respective Sections therein, any reference is made to “General Contractor”, same shall be construed to mean “Contractor for the General Construction”. 5. The Architect cannot guarantee the correctness of the existing conditions shown and assumes no responsibility therefore, it shall be the responsibility of the Contractor to visit the site and verify all existing conditions prior to bid. The Owner will purchase certain items required for the overall operation of this facility. 1. The Contractor(s) will cooperate with said vendors as may be necessary to permit the work to be accomplished. SUMMARY OF WORK 01 1000 - 3 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 a. b. NOVEMBER 19TH, 2013 The cooperation may extend to the receiving, unloading and placement of said equipment if directed by the Owner. Terms of payment, if any, shall be in accordance with Article 7 of the General Conditions as amended or modified. C. The Contractor is advised that the Owner may enter into separate contracts as may be in their best interests. D. The Contractor is further advised that there will be a full time on-site Project Representative/ Construction Manager, whose duties will be defined at the pre-construction meeting. E. ADDITIONAL SECURITY PROVISIONS 1.8 1. All Contractors’ employees shall use a single means of access and egress, except in the case of emergency, to be designated by the Construction Manager. 2. Each Contractor and each Subcontractor shall require his employees, while on the job site, to wear, in a conspicuous location, a Photo I.D. button bearing the name of the Contractor. The buttons of each Contractor shall be numbered consecutively. An up-todate list of all I.D. buttons, indicating the name and number for each employee, shall be furnished to the Construction Manager. ASBESTOS AND LEAD PAINT AWARENESS REQUIREMENTS A. Contractor agrees not to use or permit the use of any asbestos containing material in or on any property belonging to the Owner. B. For purposes of this requirement, asbestos free shall mean free from all forms of asbestos, including - actinolite, amosite, anthrophyhllite, chrysotile, cricidolite and tremolite, both in friable and non-friable states and without regard to the purposes for which such material is used. C. Reference Section 028200 of these documents for procedures and protocols to be followed in the event of discovery of asbestos or lead paint contamination. D. Contractors will investigate / verify then carefully demolish existing ceiling items so as not to disturb any asbestos containing fittings and / or insulation which may be located above existing ceilings. 1.9 A. CONSTRUCTION TIME AND PHASING REQUIREMENTS The Contractor is advised the “time is of the essence” of the Contract as defined in Article 8 of the “General Conditions” for the completion of the construction of the facility. 1. It is understood that the work is to be carried through to completion with the utmost speed consistent with good workmanship. 2. Time of Completion shall be as established in the Milestone Schedules (Section 011100). 3. Further, safe and legal ingress and egress shall be maintained at all times to and through the occupied portions of the construction site. B. Work shall proceed in such a manner as to cause the least amount of disruption to the ongoing operations as possible. C. COORDINATE CLOSELY WITH SCHOOL OPERATING PERSONNEL. D. All work and storage areas shall be completely enclosed by a fence or barricade at all times so that no student or the public can approach the area or the equipment. 1. The Contractor shall maintain fences and barricades at all times and shall - 2. Repair/ restore and/ or pay for any temporary fencing damaged by their work. SUMMARY OF WORK 01 1000 - 4 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 E. 1.10 A. 1.11 A. 1.12 A. NOVEMBER 19TH, 2013 3. Maintain at all times, all exits and walkways from the Building. 4. Where the barricade is removed for work, the Contractor performing such work shall provide adequate safety personnel to prevent unauthorized persons from approaching the work area. CONSTRUCTION PHASING 1. The phasing and/ or milestone schedule contained in Section 011100 has been established for the overall construction of the project. 2. The Contractor is advised that areas of the existing buildings which are to be added to and / or altered under this Contract will remain in use during construction, coordinate with Section 015000 for temporary facilities. 3. Electrical and mechanical services to the functioning spaces shall be maintained at all times. 4. Swing-overs to new facilities shall be made so as to cause the least interruption to the facilities’ operations. 5. Limit utility shutdowns to two consecutive non-school work days at no additional cost to the Owner unless prior agreement is made with the operating personnel of the facility. 6. The Contractor shall provide and maintain all required separations between old and new construction to prevent: a. Unauthorized entrance to construction areas by others than Architect, Construction Manager or Owner. b. Heat loss from existing buildings. c. Water (rain or ground water) infiltration into existing building. 7. Exterior alteration and restoration, as requires, may proceed outside of phasing schedule at the Contractor’s option with concurrence from the Architect, Construction Manager and Owner. 8. Site development work shall proceed in such a manner to cause the least amount of disruption to the ongoing operations as possible. PROOF OF ORDERS AND DELIVERY DATES - Coordinate with Sections 01 3300. Within 2 weeks after the approval of shop drawings, samples, product data and the like, the Contractor shall provide copies of purchase orders for all equipment and materials which are not available in local stock. The Contractor shall submit written statements from suppliers confirming the orders and stating promised delivery dates. INTENT OF DOCUMENTS In the event of conflict, ambiguity and/or unclear circumstances between any of the requirements of the Contract Documents, the requirement that is most inclusive and of highest quality, quantity, and/or cost shall govern. The Contractor shall (1) provide the better quality or greater quantity of Work and/or (2) comply with the more stringent requirement; either or both in accordance with the Architect’s interpretation. The Contractor herewith agrees that no extra compensation shall be awarded to him based upon a claim of conflict, ambiguity or unclear circumstances in the Contract Documents. See the General Conditions for greater detail. FIELD MEASUREMENTS Each Respective Contractor shall take all necessary field measurements prior to fabrication and installation of work and shall assume complete responsibility for accuracy of same. SUMMARY OF WORK 01 1000 - 5 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 B. 1.13 A. 1.14 NOVEMBER 19TH, 2013 This project is an ALTERATION / RENOVATION and therefore necessitates additional attention to existing conditions receiving newly fabricated and installed equipment, i.e. note the requirements for field dimensioning of shop fabricated items whether or not so required by each technical section. INITIAL SUBMITTAL REQUIREMENTS As outlines in Sections 01 3300 and 01 5000, each Contractor shall provide items noted including - bonds, insurance, emergency telephone numbers, progress scheduling, schedules of submittals, subcontractor listings and the like prior to the start of any work. SCHEDULES A. The milestone schedule presented in the documents is for bidding and general purposes. Due to the nature of the work, it is the intention of the Construction Manager to negotiate actual work periods for the project among the various Prime Contractors involved with this bidding process, as well as separate contractors involved with other phases of the work solicited under separate proposals. Each Contractor shall, under terms of Article 6 of the General Conditions, mutually cooperate in the rescheduling of work to permit an uninterrupted use of the facilities by the Owner, without additional cost to the Owner. B. General C. 1.15 A. 1. The objective of this project is to complete the overall work in the shortest period of time and to protect the building and occupants from damages caused by weather and construction activity during the progress of the work. 2. To meet these objectives, the Contractor shall plan the work, obtain materials, and execute the construction in the most expeditious manner possible in accordance with the requirements listed below. 3. If the Contractor fails to expedite and pursue any part of the work, the Owner may terminate the Contract. 4. The Contractor shall work in coordination with work of other Contractors and with school activities with special attention to noise, dust, safety and other contract requirements for work in and around the occupied buildings. Milestone Schedule (See Section 01 1100). ADDITIONAL REQUIREMENTS The following are additional general and special requirements which will govern the work of the projects covered by these Documents. 1. If it appears that some of the work cannot be completed by the scheduled date, the Contractor shall increase the work force or increase the hours of work, including evenings and weekends as necessary, at no additional cost to the Owner. 2. If the work is complete but the area is not cleaned and debris or equipment is not removed, the Owner shall have the right to prepare the area for occupancy with his own forces and deduct the costs from the Contract Amount. (If Contractor does not respond within 24 hours’ notice). 3. If the Contractor fails to staff the job adequately to meet the completion date, the Owner reserves the right to assume possession of the material and complete installation with the Owner’s forces or other Contractors or to require the Contractor to work evenings and weekends at no additional cost. SUMMARY OF WORK 01 1000 - 6 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 4. The school can be made available on weekends and evenings to allow the Contractor adequate time to complete the work before final completion date. Any custodial cost resulting in this after hours scheduling will be the Contractor’s responsibility. 5. In addition to the above-stated requirements for phasing of the work, the Contractors shall not do any noisy work in the areas where examinations will be conducted as per the published school calendar. 6. Work in each work period shall progress at least at a pace in proportion to the Contract time available. 7. The Contractor is responsible for temporary protection of all work until acceptance. 8. The Schools will be closed on Saturdays, Sundays, regularly schedules District holidays, and at night after cleaning crews have finished. 9. If any contractor wishes to work at any time when the school is normally closed, that Contractor shall arrange and pay for custodial services for the building at the applicable district pay rates. 10. All existing conditions must be verified in the field. The Owner takes no responsibility for actual conditions found deviating from the drawings. If existing condition interferes with contract work, contractor is responsible to eliminate this condition. 11. Contractor must plan, provide and maintain his own access, ramping, and egress as required into and out of the site, staging of trailer(s), materials, machinery, and equipment in agreement with the Construction Manager’s Superintendent. Maintain free and safe access on the jobsite for other related project personnel. Maintain safe pedestrian or vehicular traffic must be regulated by a flagman. Trucking and delivery operation should be coordinated with Construction Manager’s Superintendent and all other trades. 12. Time is of the essence. Contractors’ proposed schedule must be approved by the Construction Manager. Contractor shall indicate significant events such as submittals, shop drawings, material ordering, fabrication, delivery, coordination precedents, installation, testing and turnover by area or system as agreed with Construction Manager. A revised progress status shall be required on a weekly basis. 13. Decisions required from the Construction Manager, Architect and/or Engineer, shall be anticipated by the Contractor to provide ample time for inspection, investigation or detailed drawings. 14. Contractor shall limit his operations including storage of materials and prefabrication to areas within the Contract Limit Lines unless otherwise permitted by the Construction Manager at the Owner’s option. 15. Contractor shall coordinate the use of premises with the Owner and Construction Manager and shall move at his own expense any stored products under Contractor’s control, including excavated material, which interfere with operations of the Owner or separate contractors. 16. Contractor shall obtain and pay for the use of additional storage of work areas needed for operations. 17. Contractor shall assume full responsibility for the protection and safekeeping of products under this Contract stored on the site and shall cooperate with the Construction Manager to insure security for the Owner’s Property. 18. The intention of the work is to follow a logical sequence; however, the Contractor may be required by Construction Manager to temporarily omit or leave out any section of his work, or perform his work out of sequence. All such out of sequence work and come back time to these areas shall be performed at no additional cost. SUMMARY OF WORK 01 1000 - 7 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 19. Contractor shall submit a two-week look ahead (man-loaded by work activity and area) to Construction Manager each week. Contractor’s representative shall attend a weekly meeting with all contractors, chaired by Construction Manager, for the purpose of job coordination and sequencing. Contractor is responsible to coordinate the job with other trades and Construction Manager, and to cooperate with other trades in pursuit of the overall project’s shop drawings and actively participate in resolving discrepancies, conflicts, interferences, etc. 20. Sufficient manpower shall be provided at all times to maintain progress of the job. A shortage of labor in the industry shall not be accepted as an excuse for not properly manning the job. 21. The contractor shall take special care in verifying that his equipment matches the characteristics of the power being supplied. 22. Insubordination, unsafe practices, horseplay, abusive behavior or language, wanton destruction of property, use of drugs or alcohol, possession of firearms, and solicitation shall not be tolerated. There will be no warnings, and Contractor shall designate a responsible on-site supervisor to handle any situations that may arise, including termination. 23. Contractor is responsible to supply and install all wood blocking/bracing necessary to properly secure their work. This responsibility includes coordinating the installation in concealed areas without delaying other trades. 24. Union business shall not be conducted on site. Any Union representatives that visit the site must declare what Contractor’s personnel they represent, and must be escorted by that Contractor’s Union steward at all times. No visitors, sales representative or nonworking personnel shall be permitted on site without prior consent of the Construction Manager. No photographs shall be taken without the Construction Manager’s prior approval. 25. Organize daily clean ups as well as participating in a weekly joint clean up involving all prime contractors on site. Clean up shall be considered a safety issue. All Contractors that do not participate in clean-up will have the work performed by others and their contract amount adjusted accordingly. 26. Contractor shall provide protection from damage to adjacent and adjoining work and/or structures. Contractor shall clean, repair and/or replace any damage for which this contractor is responsible. 27. Contractor shall submit hourly rate sheets that would apply to time and material work for all pertinent trades upon Award of Contract. 28. Contractor shall examine surfaces and conditions prior to start of work. Report unacceptable conditions to the Construction Manager. Do not proceed until unacceptable conditions are corrected and acceptable. Starting of work implies acceptance. 29. Upon removal of exterior walls and window units, the building security and weather protection is the responsibility of the prime contractor performing the removals. 30. Contractor shall include general housekeeping of light debris. All debris from will be collected daily and disposed of into dumpsters. Contractor shall provide a weekly broom sweep of all areas for the entire duration of the project. The broom sweep shall include debris from all trades working on site. 31. It is the responsibilities of all Prime Contractors to review the entire Summary of Work and remaining documents for additional work items. 32. Each Contractor shall coordinate with the Construction Manager for lay down areas, staging areas, and overall use of project site. SUMMARY OF WORK 01 1000 - 8 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 33. All contractors and their employees, subcontractors and supplier are expressly prohibited from entering the occupied areas of the school buildings during school hours without prior written permission of the Construction Manager and for using any of its facilities (i.e. restrooms, cafeteria, etc.). 34. Janitorial hourly wage rate to be charged to the Contractor for access to the building(s) on off work hours shall be $45.00 per hour. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION (NOT USED) END OF SECTION 011000 SUMMARY OF WORK 01 1000 - 9 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 1100 – MILESTONE SCHEDULE PART 1 - GENERAL 1.1 MILESTONE The following milestone schedule serves as a basis for bidding. A Master Schedule will be developed at a general meeting of the successful bidders within 7 days of Letter of Intent to Award the Contracts. Each prime contractor will coordinate activities, forward submittals, deliver materials and provide necessary manpower to meet the milestones listed below. 1.2 MILESTONE SCHEDULE A. Start Date: Award of Contract a. December 12th , 2013 B. Start of Construction: 1. BASE BID: Part 1 – BUILDING MATERIALS a. b. c. 2. Start Date: Award of Contract Tasks: Schedule of Values, Progress Schedule, Contracts, Bonds and Insurance, Field verification of existing conditions, Submittals, then ordering and delivery of materials to the site. Completion: BASE BID Phase I: June 26th, 2014 BASE BID: Part 2 – BUILDING LABOR a. b. c. Start Date: July 1, 2014 Tasks: Start of construction removals, abatement, and all installation of window system, doors, window treatment systems and other associated work as per the construction documents. Completion: August 19th, 2014. C. Completion: a. ALL WORK must be completed by August 12, 2014 b. All systems must be checked and testing and fully operational, and punch list complete by August 19, 2015. ALL WORK REQUIRED BY ANY OF THE OWNER’S REPRESENTATIVES AND CONSULTANTS, INCLUDING THE CONSTRUCTION MANAGER, ARCHITECT, ARCHITECT’S CONSULTANTS, OWNER’S ATTORNEYS, ETC., TO EXECUTE FINAL CLOSE-OUT OF CONTRACT AFTER 60 DAYS BEYOND MILESTONE DATES IF DETERMINED TO BE CAUSED BY CONTRACTOR, SHALL RESULT IN PAYMENT(S) TO THE OWNER’S REPRESENTATIVES AND CONSULTANTS, INCLUDING THE CONSTRUCTION MANAGER, ARCHITECT, ARCHITECT’S CONSULTANTS, OWNER’S ATTORNEYS, ETC., IN THE FORM OF A CHANGE ORDER DEDUCT TO THE BASE CONTRACT. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION 01 1100 MILESTONE SCHEDULE 01 1100 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 2100 - ALLOWANCES PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes administrative and procedural requirements governing allowances. B. Selected materials and equipment are specified in the Contract Documents by allowances. In some cases, these allowances include installation. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when additional information is available for evaluation. If necessary, additional requirements will be issued by Change Order. C. Types of allowances include the following: D. 1.3 1. Lump-sum allowances. 2. Contingency allowances. Related Sections: The following Sections contain requirements that relate to this Section: 1. Division 1 Section "Modification Procedures" specifies procedures for submitting and handling Change Orders. 2. Division 1 Section "Quality Requirements" specifies procedures governing the use of allowances for inspection and testing. SELECTION AND PURCHASE A. At the earliest practical date after award of the Contract, advise the Architect of the date when the final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work. B. At the Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work. C. Purchase products and systems selected by the Architect from the designated supplier 1.4 SUBMITTALS A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders. B. Submit invoices or delivery slips to show the actual quantities of materials delivered to the site for use in fulfillment of each allowance. 1.5 A. CONTINGENCY ALLOWANCES Use the contingency allowance only as directed for the Owner's purposes and only by Change Orders that indicate amounts to be charged to the allowance. ALLOWANCES 01 2100 - 1 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. The Contractor's overhead and profit, including costs for bonds and insurance, delivery, equipment rental and similar costs, for these allowances shall be included in the values of the general requirements of contract sum and are not chargeable under allowance disbursement. C. At Project closeout, credit unused amounts remaining in the contingency allowance to the Owner by Change Order. 1.6 UNUSED MATERIALS A. Return unused materials to the manufacturer or supplier for credit to the Owner, after installation has been completed and accepted. B. When requested by the Architect, prepare unused material for storage by Owner where it is not economically practical to return the material for credit. When directed by the Architect, deliver unused material to the Owner's storage space. Otherwise, disposal of unused material is the Contractor's responsibility. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 A. 3.2 A. 3.3 A. EXAMINATION Examine products covered by an allowance promptly upon delivery for damage or defects. PREPARATION Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work. SCHEDULE OF ALLOWANCES Allowance: Contractor shall include a contingency allowance of $10,000 for use according to the Owner's instructions for unforeseen conditions where work will be performed. END OF SECTION 01 2100 ALLOWANCES 01 2100 - 2 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 2300 - ALTERNATES PART 1 - GENERAL 1.1 A. 1.2 A. 1.3 A. RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY This Section includes administrative and procedural requirements governing Alternates. DEFINITIONS Alternate: An alternate is an amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid amount if the Owner decides to accept a corresponding change in either the amount of construction to be completed, or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. 1. 1.4 A. The cost or credit for each Alternate is the net addition to or deduction from the Contract Sum to incorporate the Alternate into the Work. No adjustments are made to the Contract Sum. PROCEDURES Coordination: Modify or adjust affected adjacent Work as necessary to completely and fully integrate that Work into the Project. 1. Include as part of each Alternate, miscellaneous devices, accessory objects, similar items incidental to or required for a complete installation, removals and preparation of other work to receive indicated Alternate, whether or not mentioned as part of the Alternate. 2. The cost of related coordination, preparation, modification and/or adjustment shall be included in the cost of the Alternate. B. Notification: Immediately following the award of the Contract, notify each party involved, in writing, of the status of each Alternate. Indicate whether Alternates have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated modifications to Alternates. C. Execute accepted Alternates under the same conditions as other Work of this Contract. D. Schedule: A “Schedule of Alternates” is included at the end of this Section. Specification Sections references in the Schedule contain requirements for materials necessary to achieve the Work described under each Alternate. PART 2 - PRODUCTS (Not Applicable) ALTERNATES 01 2300 - 1 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 PART 3 – EXECUTION 3.1 A. SCHEDULE OF ALTERNATES ALTERNATE 1: 1. The contractor shall state the amount to be ADDED TO the Base Bid to provide, Material and Labor for the ISD Gym Window Replacement project for the Alternate Bid Scope Area of Work and related work as follows: Provide blast resistant glazing film on all exterior doors vision lites. END OF SECTION 01 2300 ALTERNATES 01 2300 - 2 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 2600 – MODIFICATION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section specifies administrative and procedural requirements for handling and processing contract modifications. 1. B. Related Sections: The following Sections contain requirements that relate to this Section: 1. 2. 1.3 Division 1 Section "ELECTRONIC SUBMITTAL PROCEDURES" for requirements for the Contractor's Construction Schedule. Division 1 Section "PAYMENT PROCEDURES" for administrative procedures governing Applications for Payment. MINOR CHANGES IN THE WORK A. 1.4 Multiple Prime Contracts: Provisions of this Section apply to the work of each prime contractor. The Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or Contract Time, on AIA Form G710, Architect's Supplemental Instructions. SUBMITTALS A. Every change or allowance proposal (regardless of who initiated) will be accompanied by the following information: 1. Labor Rate worksheet (attached at the end of this section) must be filled out for each trade and notarized with the required supporting documentation. 2. Full itemized breakdown: All proposals to be broken down by material, labor, man hours, quantities, unit prices, overhead, profit, subcontractor, and supplier quotes attached. 3. If the contractor fails to submit this required information timely, it will be cause for delay and will be addressed as such under the applicable sections of the contract. 1.5 CHANGE ORDER PROPOSAL REQUESTS A. Owner-Initiated Proposal Requests: The Architect will issue a detailed description of proposed changes in the Work that will require adjustment to the Contract Sum or Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications. MODIFICATION PROCEDURES 01 2600 - 1 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. Proposal requests issued by the Architect are for information only. Do not consider them as an instruction either to stop work in progress or to execute the proposed change. 2. Within 5 days of receipt of a proposal request, submit an estimate of cost necessary to execute the change to the Architect for the Owner's review. a. b. c. B. 2. 3. 4. 1.6 Include an itemized list of quantities of products required and unit costs, with the total amount of purchases to be made. Furnish survey data and backup paperwork to substantiate quantities. Separate labor hours by trade and indicate labor rate. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. Include a statement indicating the effect the proposed change in the Work will have on the Contract Time. Contractor-Initiated Proposals: When latent or unforeseen conditions require modifications to the Contract, the Contractor may propose changes by submitting a request for a change to the Architect. 1. C. NOVEMBER 19TH, 2013 Include a statement outlining the reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and Contract Time. Include an itemized list of quantities of products required and unit costs, with the total amount of purchases to be made. Furnish survey data to substantiate quantities. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. Comply with requirements in Section "Product Requirements" if the proposed change requires substitution of one product or system for a product or system specified. Proposal Request Form: Use AIA Document G709 for Change Order Proposal Requests. ALLOWANCES A. Allowance Adjustment: For allowance-cost adjustment, base each Change Order Proposal on the difference between the actual purchase amount and the allowance, multiplied by the final measurement of work-in-place. Where applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins. 1. 2. 3. 4. 5. Include installation costs in the purchase amount only where indicated as part of the allowance. When requested, prepare explanations and documentation to substantiate the margins claimed. Submit substantiation of a change in scope of work claimed in the Change Orders related to unit-cost allowances. The Owner reserves the right to establish the actual quantity of work-in-place by independent quantity survey, measure, or count. Contractor’s overhead and profit, including costs for bonds & insurances, for these allowances shall be included in the values of the general MODIFICATION PROCEDURES 01 2600 - 2 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 requirements of contract sum and are not chargeable under allowance disbursement. B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or the Contractor's handling, labor, installation, overhead, and profit. Submit claims within 15 days of receipt of the Change Order or Construction Change Directive authorizing work to proceed. The Owner will reject claims submitted later than 15 days. 1. 2. 1.7 CONSTRUCTION CHANGE DIRECTIVE A. Construction Change Directive: When the Owner and the Contractor disagree on the terms of a Proposal Request, the Architect may issue a Construction Change Directive on AIA Form G714. The Construction Change Directive instructs the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. 1. B. The Construction Change Directive contains a complete description of the change in the Work. It also designates the method to be followed to determine change in the Contract Sum or Contract Time. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive. 1. 1.8 Do not include the Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in Contract Documents. No change to the Contractor's indirect expense is permitted for selection of higher or lower-priced materials or systems of the same scope and nature as originally indicated. After completion of the change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract. CHANGE ORDER PROCEDURES A. Upon the Owner's approval of a Proposal Request, the Construction Manager will issue a Change Order for signatures of the Owner and the Contractor on AIA Form G701. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION 01 2600 MODIFICATION PROCEDURES 01 2600 - 3 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 2900 - PAYMENT PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section specifies administrative and procedural requirements governing each prime contractor's Applications for Payment. 1. B. Related Sections: The following Sections contain requirements that relate to this Section. 1. 1.3 Coordinate the Schedule of Values and Applications for Payment with the Contractor's Construction Schedule, Submittal Schedule, and List of Subcontracts. Schedules: The Contractor's Construction Schedule and Submittal Schedule are specified in Division 1 Section "Submittals." SCHEDULE OF VALUES A. Form to be used: AIA G702/703 B. Coordination: Each prime Contractor shall coordinate preparation of its Schedule of Values for its part of the Work with preparation of the Contractors' Construction Schedule. 1. Correlate line items in the Schedule of Values with other required administrative schedules and forms, including: a. b. c. d. e. f. 2. C. Contractor's Construction Schedule. Application for Payment forms, including Continuation Sheets. List of subcontractors. Schedule of allowances. Schedule of alternates. Schedule of submittals. Submit the Schedule of Values in duplicate, to the Construction Manager within 10 days of receipt of Letter of Intent. Format and Content: Use the Table of Contents of this Project Manual as a guide to establish the format for the Schedule of Values. Provide at least one line item for each Specification Section. 1. Identification: Include the following Project identification on the Schedule of Values: a. b. c. d. e. Project name and location. Name of the Architect. Project number. Contractor's name and address. Date of submittal. PAYMENT PROCEDURES 01 2900 - 1 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed: a. b. c. d. e. f. g. Related Specification Section or Division. Description of Work. Name of subcontractor. Name of manufacturer or fabricator. Name of supplier. Change Orders (numbers) that affect value. Dollar value. 1) Percentage of Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent. 3. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Break principal subcontract amounts down into several line items. 4. Round amounts to nearest whole dollar; the total shall equal the Contract Sum. 5. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment, purchased or fabricated and stored, but not yet installed. a. Differentiate between items stored on-site and items stored off-site. requirements for insurance and bonded warehousing, if required. Include 6. Provide separate line items on the Schedule of Values for initial cost of the materials, for each subsequent stage of completion, and for total installed value of that part of the Work. 7. Unit-Cost Allowances: Show the line-item value of unit-cost allowances, as a product of the unit cost, multiplied by the measured quantity. Estimate quantities from the best indication in the Contract Documents. 8. Margins of Cost: Show line items for indirect costs and margins on actual costs only when such items are listed individually in Applications for Payment. Each item in the Schedule of Values and Applications for Payment shall be complete. Include the total cost and proportionate share of general overhead and profit margin for each item. a. 9. 1.4 NOVEMBER 19TH, 2013 Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at the Contractor's option. Schedule Updating: Update and resubmit the Schedule of Values prior to the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum. APPLICATIONS FOR PAYMENT A. Each Application for Payment shall be consistent with previous applications and payments as certified by the Architect and paid for by the Owner. 1. The initial Application for Payment, the Application for Payment at time of Substantial Completion, and the final Application for Payment involve additional requirements. PAYMENT PROCEDURES 01 2900 - 2 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Payment-Application Times: Each progress-payment date is indicated in the Agreement. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement. C. Payment-Application Times: The date for each progress payment is the 7th day of each month (or as designated by the Owner). The period covered by each Application for Payment is the previous month. D. Payment-Application Forms: Use AIA Document G702/CMa and Continuation Sheets G703 as the form for Applications for Payment. 1. E. F. Application Preparation: Complete every entry on the form. Include notarization and execution by a person authorized to sign legal documents on behalf of the Contractor. The Construction Manager and Architect will return incomplete applications without action. 1. Entries shall match data on the Schedule of Values and the Contractor's Construction Schedule. Use updated schedules if revisions were made. 2. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the construction period covered by the application. 3. Provide copies of payrolls which are signed and notarized documenting compliance with prevailing wage laws. Transmittal: Submit 3 signed and notarized original copies of each Application for Payment to the Construction Manager by a method ensuring receipt within 24 hours. One copy shall be complete, including waivers of lien and similar attachments, when required. 1. G. Separate Continuation Sheets shall be provided for work which takes place on each building, which will detail that portion of the contract which is attributable to the specific building. The appropriate Greenwich Bid number shall be shown on the top of each continuation form. Transmit each copy with a transmittal form listing attachments and recording appropriate information related to the application, in a manner acceptable to the Construction Manager and Architect. Waivers of Mechanics Lien: With each Application for Payment, submit waivers of mechanics liens from subcontractors, sub-subcontractors and suppliers for the construction period covered by the previous application. 1. Submit partial waivers on each item for the amount requested, prior to deduction for retainage, on each item. 2. When an application shows completion of an item, submit final or full waivers. 3. The Owner reserves the right to designate which entities involved in the Work must submit waivers. a. 4. H. Submit final Applications for Payment with or proceeded by final waivers from every entity involved with performance of the Work covered by the application that is lawfully entitled to a lien. Waiver Forms: Submit waivers of lien on forms, and executed in a manner, acceptable to the Owner. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of the first Application for Payment include the following. The initial payment application will not be processed until all of these actions and submittals have been PAYMENT PROCEDURES 01 2900 - 3 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 received by the Construction Manager. When preliminary submissions are received with the initial application (items 4 and 7), the final submission for these items must be received and approved by the Construction Manager prior to submission of the second application for payment. I. 1. List of subcontractors. 2. List of principal suppliers and fabricators. 3. Schedule of Values. 4. Contractor's Construction Schedule (preliminary if not final). 5. Schedule of principal products. 6. Schedule of unit prices. 7. Submittal Schedule (preliminary if not final). 8. List of Contractor's staff assignments. 9. List of Contractor's principal consultants. 10. Copies of building permits. 11. Copies of authorizations and licenses from governing authorities for performance of the Work. 12. Initial progress report. 13. Report of preconstruction meeting. 14. Certificates of insurance and insurance policies. 15. Performance and payment bonds. 16. Data needed to acquire the Owner's insurance. 17. Initial settlement survey and damage report, if required. Application for Payment at Substantial Completion: Following issuance of the Certificate of Substantial Completion, submit an Application for Payment. 1. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work. 2. Administrative actions and submittals that shall precede or coincide with this application include: a. b. c. d. e. f. g. h. i. j. k. l. Occupancy permits and similar approvals. Warranties (guarantees) and maintenance agreements. Test/adjust/balance records. Maintenance instructions. Meter readings. Startup performance reports. Changeover information related to Owner's occupancy, use, operation, and maintenance. Final cleaning. Application for reduction of retainage and consent of surety. Advice on shifting insurance coverages. Final progress photographs. List of incomplete Work, recognized as exceptions to Architect's Certificate of Substantial Completion. PAYMENT PROCEDURES 01 2900 - 4 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 J. NOVEMBER 19TH, 2013 Final Payment Application: Administrative actions and submittals that must precede or coincide with submittal of the final Application for Payment include the following: 1. Completion of Project closeout requirements. 2. Completion of items specified for completion after Substantial Completion. 3. Ensure that unsettled claims will be settled. 4. Ensure that incomplete Work is not accepted and will be completed without undue delay. 5. Transmittal of required Project construction records to the Owner. 6. Certified property survey. 7. Proof that taxes, fees, and similar obligations were paid. 8. Removal of temporary facilities and services. 9. Removal of surplus materials, rubbish, and similar elements. 10. Change of door locks to Owner's access. PART 2 - PART 1 - PRODUCTS (Not Applicable) PART 3 - PART 2 - EXECUTION (Not Applicable) END OF SECTION 01 2900 PAYMENT PROCEDURES 01 2900 - 5 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 3119 -PROJECT MEETINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This Section specifies administrative and procedural requirements for project meetings, including, but not limited to, the following: 1. 2. 3. 4. B. Related Sections: The following Sections contain requirements that relate to this Section: 1. 1.3 Preconstruction conferences. Preinstallation conferences. Progress meetings. Coordination meetings. Division 1 Section "Electronic Submittal Procedures" for submitting the Contractor's Construction Schedule. PRECONSTRUCTION CONFERENCE A. A preconstruction conference will be scheduled before starting construction, at a time convenient to the Owner and the Architect, but no later than 15 days after execution of the Agreement. The conference will be held at the Project Site or another convenient location. B. Attendees: Authorized representatives of the Owner, Architect, and their consultants; the Contractor and its superintendent; major subcontractors; manufacturers; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work. C. Agenda: Discuss items of significance that could affect progress, including the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Tentative construction schedule. Critical work sequencing. Designation of responsible personnel. Procedures for processing field decisions and Change Orders. Procedures for processing Applications for Payment. Distribution of Contract Documents. Submittal of Shop Drawings, Product Data, and Samples. Preparation of record documents. Use of the premises. Parking availability. Office, work, and storage areas. Equipment deliveries and priorities. Safety procedures. PROJECT MEETINGS 01 3119 - 1 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 14. 15. 16. 17. D. 1.4 NOVEMBER 19TH, 2013 First aid. Security. Housekeeping. Working hours. Reporting: The Contractor shall prepare and issue minutes to attendees and interested parties. PREINSTALLATION CONFERENCES A. Conduct a pre-installation conference at the Project Site before each construction activity that requires coordination with other construction. B. Attendees: The Installer and representatives of the Prime Contractor, manufacturers and fabricators involved in or affected by the installation, and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise the Owner and Architect of scheduled meeting dates. 1. Review the progress of other construction activities and preparations for the particular activity under consideration at each pre-installation conference, including requirements for the following: a. b. c. d. e. f. g. h. i. j. k. l. m. n. o. p. q. r. s. t. u. v. w. 2. 3. 4. Contract Documents. Options. Related Change Orders. Purchases. Deliveries. Shop Drawings, Product Data, and quality-control samples. Review of mockups. Possible conflicts. Compatibility problems. Time schedules. Weather limitations. Manufacturer's recommendations. Warranty requirements. Compatibility of materials. Acceptability of substrates. Temporary facilities. Space and access limitations. Governing regulations. Safety. Inspecting and testing requirements. Required performance results. Recording requirements Protection. Record significant discussions and agreements and disagreements of each conference and the approved schedule. Promptly distribute the record of the meeting to everyone concerned, including the Owner and the Architect. Do not proceed with the installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene the conference at the earliest feasible date. Reporting: Prime Contractor or Installer shall issue minutes to attendees, CM, Owner and Architect. PROJECT MEETINGS 01 3119 - 2 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.5 NOVEMBER 19TH, 2013 PROGRESS MEETINGS A. Progress meetings will be held at the Project Site at regular intervals (typically weekly) as determined by the Architect. B. Attendees: In addition to representatives of the Owner and the Architect, each Prime Contractor shall be represented at these meetings. Attendance is mandatory at each meeting and a penalty sum of $500.00 per missed meeting will be assessed to the Prime Contractor not attending without prior written authorization from the Owner. Subcontractors, suppliers, or other entities will be invited at the discretion of the Owner, Construction Manager, and the Architect. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work. C. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project. 1. 2. Contractor's Construction Schedule: Review progress since the last meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to insure that current and subsequent activities will be completed within the Contract Time. Review the present and future needs of each entity present, including the following: a. b. c. d. e. f. g. h. i. j. k. l. m. n. o. D. 1.6 Interface requirements. Time. Sequences. Status of submittals. Deliveries. Off-site fabrication problems. Access. Site utilization. Temporary facilities and services. Hours of work. Hazards and risks. Housekeeping. Quality and work standards. Change Orders. Documentation of information for payment requests. Reporting: Approximately 5 days after each meeting, the Construction Manager will prepare and distribute minutes of the meeting to each party present and to parties who should have been present. Include a brief summary, in narrative form, of progress since the previous meeting and report. COORDINATION MEETINGS A. Conduct project coordination meetings at regular intervals convenient for all parties involved. Project coordination meetings are in addition to specific meetings held for other purposes, such as regular progress meetings and special pre-installation meetings. B. Request representation at each meeting by every party currently involved in coordination or planning for the construction activities involved. PROJECT MEETINGS 01 3119 - 3 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 C. Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting. D. The Contractors Field Manager will conduct daily meetings with all prime contractors performing work. The purpose of the meeting is to provide the opportunity for each prime contractor to communicate to the Field Manager any items relating to their respective construction activity for that day (request for shutdown, deliveries, etc.) The meetings will commence from 7:00 o’clock am until 7:30 o’clock am. The foreman of each Prime Contractor must attend. These meetings are generally informal. The Contractors Field Manager will keep minutes of these meetings when appropriate and will be available upon request. 1.7 SAFETY MEETINGS A. Each Prime Contractor will be responsible to conduct safety meetings on a regular basis (but not less than three times during any thirty day period.) B. Minutes of the Safety Meeting must be submitted to the Architect within 4 business days. Failure to conduct and submit meeting minutes will be grounds to reject the Prime Contractor’s progress payment. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION 01 3119 PROJECT MEETINGS 01 3119 - 4 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 3300 - ELECTRONIC SUBMITTAL PROCEDURES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.02 SUMMARY A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals. B. Related Sections: 1. Division 01 Section “Payment Procedures” for submitting Applications for Payment and the schedule of values. 2. Division 01 Section “Project Record Documentation” for submitting schedules and reports, including Contractor’s construction schedule. 3. Division 01 Section “Operation and Maintenance Data” for submitting operation and maintenance manuals. 1.03 DEFINITIONS A. Action Submittals: Written and graphic information and physical samples that require Architect’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as action submittals. B. Informational Submittals: Written and graphic information and physical samples that do not require Architect’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as informational submittals. C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files. D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixedlayout document format. 1.04 ACTION SUBMITTALS A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or modifications to submittals noted by the Architect and additional time for handling and reviewing submittals required by those corrections. ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 1 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor’s construction schedule. 2. Initial Submittal: Submit concurrently with start-up construction schedule. Include submittals required during the first 10 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication. 3. Final Submittal: Submit concurrently with the first complete submittal of Contractor’s construction schedule. a. Submit revised submittal schedule to reflect changes in current status and timing for submittals. 4. Format: Arrange the following information in a tabular format: a. Scheduled date for first submittal. b. Specification Section number and title. c. Submittal category: Action, informational. d. Name of subcontractor. e. Description of the Work covered. f. Scheduled date for Architect’s final release or approval. g. Scheduled dates for purchasing. h. Scheduled dates for installation. i. Activity or event number. 1.05 SUBMITTAL ADMINISTRATIVE REQUIREMENTS A. Architect’s Digital Data Files: Electronic copies of CAD Drawings of the Contract Drawings will be provided by Architect for Contractor’s use in preparing submittals. 1. Architect will furnish Contractor one set of digital data drawing files of the Contract Drawings for use in preparing Shop Drawings and Project record drawings. a. Architect makes no representations as to the accuracy or completeness of digital data drawing files as they relate to the Contract Drawings. b. Digital Drawing Software Program: The Contract Drawings are available in AutoCAD Version 2010. c. Contractor shall execute a data licensing agreement that will be supplied by Architect. d. The following plot files will by furnished for each appropriate discipline: 1) Floor plans. 2) Building Elevations. B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. 1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 2 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule. 3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals. 4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination. a. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received. C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Architect’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals. 1. Initial Review: Allow 10 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination. 2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal. 3. Resubmittal Review: Allow 10 days for review of each resubmittal. 4. Sequential Review: Where sequential review of submittals by Architect’s consultants, Owner, or other parties is indicated, allow 10 days for initial review of each submittal. 5. Concurrent Consultant Review: Where the Contract Documents indicate that submittals may be transmitted simultaneously to Architect and to Architect’s consultants, allow 10 days for review of each submittal. Submittal will be returned to Architect before being returned to Contractor. D. Identification and Information: Identify and incorporate information in each electronic submittal file as follows: 1. Assemble complete submittal package into a single indexed file with links enabling navigation to each item. 2. Name file with submittal number or other unique identifier, including revision identifier. a. File name shall use project identifier and Specification Section number followed by a decimal point and then a sequential number (e.g., ISD-061000.01 or ISD-061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., ISD061000.01.A or ISD-061000.01.A). 3. Provide means for insertion to permanently record Contractor’s review and approval markings and action taken by Architect. 4. Include the following information on an inserted cover sheet: a. Project name. b. Date. ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 3 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 c. Name and address of Architect. d. Name of Contractor. e. Name of firm or entity that prepared submittal. f. Name of subcontractor. g. Name of supplier. h. Name of manufacturer. i. Number and title of appropriate Specification Section. j. Drawing number and detail references, as appropriate. k. Location(s) where product is to be installed, as appropriate. l. Related physical samples submitted directly. m. Other necessary identification. 5. Include the following information as keywords in the electronic file metadata: a. Project name. b. Number and title of appropriate Specification Section. c. Manufacturer name. d. Product name. E. Options: Identify options requiring selection by the Architect. F. Deviations: Identify deviations from the Contract Documents on submittals. G. Transmittal: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Contracting Officer will return submittals, without review, received from sources other than Contractor. 1. Transmittal Form: Provide locations on form for the following information: a. Project name. b. Date. c. Destination (To:). d. Source (From:). e. Names of subcontractor, manufacturer, and supplier. f. Category and type of submittal. g. Submittal purpose and description. h. Specification Section number and title. i. Indication of full or partial submittal. j. Drawing number and detail references, as appropriate. k. Transmittal number, numbered consecutively. l. Submittal and transmittal distribution record. m. Remarks. n. Signature of transmitter. 2. On an attached separate sheet, prepared on Contractor’s letterhead, record relevant information, requests for data, revisions other than those requested by Architect on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal. H. Resubmittals: Make resubmittals in same form and number of copies as initial submittal. 一. Note date and content of previous submittal. 一. Note date and content of revision in label or title block and clearly indicate extent of revision. 一. Resubmit submittals until they are marked with approval notation from Architect’s action stamp. ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 4 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms. J. Use for Construction: Use only final submittals that are marked with approval notation from Architect’s action stamp. PART 2 - PRODUCTS 2.01 SUBMITTAL PROCEDURES A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections. 1. Submit electronic submittals via email as PDF electronic files. a. Architect, through Contracting Officer, will return annotated file. Annotate and retain one copy of file as an electronic Project record document file. 2. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Division 01 Section “Execution and Closeout Requirements.” 3. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. a. Provide a digital signature with digital certificate on electronically-submitted certificates and certifications where indicated. b. Provide a notarized statement on original paper copy certificates and certifications where indicated. 4. Test and Inspection Reports Submittals: Comply with requirements specified in Division 01 Section “Quality Requirements.” B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. 1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data. 2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable: a. Manufacturer’s catalog cuts. b. Manufacturer’s product specifications. c. Standard color charts. d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency. f. Application of testing agency labels and seals. g. Notation of coordination requirements. h. Availability and delivery time information. 4. For equipment, include the following in addition to the above, as applicable: ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 5 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 a. Wiring diagrams showing factory-installed wiring. b. Printed performance curves. c. Operational range diagrams. d. Clearances required to other construction, if not indicated on accompanying Shop Drawings. 5. Submit Product Data before or concurrent with Samples. 6. Submit Product Data in the following format: a. PDF electronic file. C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data, unless submittal based upon Architect’s digital data drawing files is otherwise permitted. 1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable: a. Identification of products. b. Schedules. c. Compliance with specified standards. d. Notation of coordination requirements. e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified. 2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 42 inches (750 by 1067 mm). 3. Submit Shop Drawings in the following format: a. PDF electronic file. D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed. 1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package. 2. Identification: Attach label on unexposed side of Samples that includes the following: a. Generic description of Sample. b. Product name and name of manufacturer. c. Sample source. d. Number and title of applicable Specification Section. 3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set. a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use. ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 6 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 b. Samples not incorporated into the Work, or otherwise designated as Government’s property, are the property of Contractor. 4. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. a. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer’s product line. Architect, through Contracting Officer, will return submittal with options selected. 5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection. a. Number of Samples: Submit three sets of Samples. Architect will retain one Sample set; remainder will be returned. Mark up and retain one returned Sample set as a Project record sample. 1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated. 2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations. E. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form: 1. Type of product. Include unique identifier for each product indicated in the Contract Documents. 2. Manufacturer and product name, and model number if applicable. 3. Number and name of room or space. 4. Location within room or space. 5. Submit product schedule in the following format: a. PDF electronic file. F. Contractor’s Construction Schedule: Comply with requirements specified in Division 01 Section “Construction Progress Documentation.” G. Application for Payment: Comply with requirements specified in Division 01 Section “Payment Procedures.” H. Schedule of Values: Comply with requirements specified in Division 01 Section “Payment Procedures.” ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 7 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 I. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form: 1. Name, address, and telephone number of entity performing subcontract or supplying products. 2. Number and title of related Specification Section(s) covered by subcontract. 3. Drawing number and detail references, as appropriate, covered by subcontract. 4. Submit subcontract list in the following format: a. PDF electronic file. J. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified. K. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on American Welding Society (AWS) forms. Include names of firms and personnel certified. L. Installer Certificates: Submit written statements on manufacturer’s letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project. M. Manufacturer Certificates: Submit written statements on manufacturer’s letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required. N. Product Certificates: Submit written statements on manufacturer’s letterhead certifying that product complies with requirements in the Contract Documents. O. Material Certificates: Submit written statements on manufacturer’s letterhead certifying that material complies with requirements in the Contract Documents. P. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents. Q. Product Test Reports: Submit written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency. R. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information: 一. 一. 一. 一. 一. 一. 一. Name of evaluation organization. Date of evaluation. Time period when report is in effect. Product and manufacturers’ names. Description of product. Test procedures and results. Limitations of use. ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 8 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 S. Schedule of Tests and Inspections: Comply with requirements specified in Division 01 Section “Quality Requirements.” T. Field Test Reports: Submit reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents. U. Maintenance Data: Comply with requirements specified in Division 01 Section “Operation and Maintenance Data.” PART 3 - EXECUTION 3.01 CONTRACTOR’S REVIEW A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Contracting Officer. B. Project Closeout and Maintenance/Material Submittals: Refer to requirements in Division 01 Section “Closeout Procedures.” C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor’s approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents. 3.02 ARCHITECT’S ACTION A. General: Architect will not review submittals that do not bear Contractor’s approval stamp and will return them without action. B. Action Submittals: Architect will review each submittal, make marks to indicate corrections or modifications required, and return it. Architect will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action, as follows: 1. Approved: Where the submittal is marked “Approved,” the Work covered by the submittal may proceed provided it complies with the Contract Documents. Final acceptance will depend on that compliance. 2. Approved As Corrected (do not resubmit): Where the submittal is marked “Approved As Corrected” the work covered by the submittal may proceed provided it complies both with Architect’s notations and corrections on the submittal and the Contract Documents. Final acceptance will depend on that compliance. 3. Revise and Resubmit (see notes): Where the submittal is marked “Revise and Resubmit” do not proceed with the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity for the product submitted. Revise and prepare a new submittal according to Architect’s notations and corrections. 4. Rejected: Where the submittal is marked “Rejected”, do not proceed with the Work covered by the submittal. Prepare a new submittal for a product that complies with the Contract Documents. C. Informational Submittals: Architect will review each submittal and will not return it, or will return it if it does not comply with requirements. Architect will forward each submittal to appropriate party. ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 9 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 5. Submit Specified Item: Where the submittal is marked “Submit Specified Item”, do not proceed with the Work covered by the submittal. Prepare a new submittal for a product that complies with the Contract Documents. D. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Architect. E. Incomplete submittals are not acceptable, will be considered nonresponsive, and will be returned without review. F. Submittals not required by the Contract Documents may not be reviewed and may be discarded. END OF SECTION 01 3300 ELECTRONIC SUBMITTAL PROCEDURES 01 3300 - 10 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SUBMITTAL COVERSHEET No:_ Contractor: _____________________________________________ ________ Contract: __________________ Address: ___________________________________________________ Telephone: _________________ ___________________________________________________ Fax: _______________________ School Name: ____International School at Dundee ___________________________________________ Type of Submittal: [ ] Shop Drawings [ ] Test Report [ ] Product Data [ ] Certificate [ ] Schedule [ ] Color Sample Re-submittal: [ ] No [ ] Yes [ ] Sample [ ] [ ] Warranty [ ] Submittal Description: Product Name: ___________________________________________________________________________________ Manufacturer: ___________________________________________________________________________________ Subcontractor/ Supplier: ___________________________________________________________________________________ References: Spec. Section No.: _____________________ Drawing No(s): ______________ Paragraph: __________________________ Rm. or Detail No(s): ________________ Architect’s Review Stamp Contractor Review Stamp These documents have been checked for accuracy and coordinated with job conditions and Contract requirements by this office and have been found to comply with the provisions of the Contract Documents. Name: Date: Company Name: ________________________________________________________________________ ________________________________________________________________________ Remarks: SUBMITTAL COVER PAGE 01 3301 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 4000 – QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS 1. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes administrative and procedural requirements for quality-control services. B. Quality-control services include inspections, tests, and related actions, including reports performed by Contractor, by independent agencies, and by governing authorities. They do not include contract enforcement activities performed by Architect. C. Inspection and testing services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with Contract Document requirements. D. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products. 1. 2. 3. E. Specific quality-control requirements for individual construction activities are specified in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products. Specified inspections, tests, and related actions do not limit Contractor’s quality-control procedures that facilitate compliance with Contract Documents. Requirements. Requirements for Contractor to provide quality-control services required by Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section. Related Sections: The following Sections contain requirements that relate to this Section: 1. 2. Division 1 Section “Cutting and Patching” specifies requirements for repair and restoration of construction disturbed by inspection and testing activities. Division 1 Section “Electronic Submittal Procedures” specifies requirements for development of a schedule of required tests and inspections. F. Referenced Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements, comply with the most stringent requirement. Refer uncertainties to Architect for a decision. G. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum. The actual installation may exceed the minimum within reasonable limits. Indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision. H. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, notices, receipts for fee payments, and similar documents, established for compliance with standards and regulations bearing on performance of the Work. QUALITY REQUIREMENTS 01 4000 - 1 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 I. Testing Agency Qualifications: An independent agency with the experience and capability to conduct testing and inspecting indicated; and where required by authorities having jurisdiction, that is acceptable to authorities. J. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents. K. Testing Agency Responsibilities: Cooperate with Architect, Construction Manager, and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections. 1. 2. 3. L. Associated Services: Cooperate with testing agencies and provide reasonable auxiliary services as requested. Provide the following: 1. 2. 3. 4. 5. M. Access to the Work. Incidental labor and facilities necessary to facilitate tests and inspections. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples. Facilities for storage and field curing of test samples. Security and protection for samples and for testing and inspecting equipment. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting. 1. 1.3 Promptly notify Architect, Construction Manager, and Contractor of irregularities or deficiencies in the Work observed during performance of its services. Do not release, revoke, alter, or increase requirements of the Contract Documents or approve or accept any portion of the Work. Do not perform any duties of Contractor. Schedule times for tests, inspections, obtaining samples, and similar activities. RESPONSIBILITIES A. Contractor Responsibilities: Unless otherwise indicated as the responsibility of another identified entity, Contractor shall provide inspections, tests, and other quality-control services specified elsewhere in the Contract Documents and required by authorities having jurisdiction. Costs for these services are included in the Contract Sum. 1. 2. B. Where individual Sections Specifically indicate that certain inspections, tests, and other quality-control services are the Contractor’s responsibility, the Contractor shall employ and pay a qualified independent testing agency to perform quality-control services. Costs for these services are included in the Contract Sum. Where individual Sections specifically indicate that certain inspections, tests, and other quality-control services are the Owner’s responsibility, the Owner will employ and pay a qualified independent testing agency to perform those services. Retesting: The Contractor is responsible for retesting where results of inspections, tests, or other quality-control services prove unsatisfactory and indicate noncompliance with Contract Document requirements, regardless of whether the original test was Contractor’s responsibility. QUALITY REQUIREMENTS 01 4000 - 2 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. C. 4. 5. 6. 7. 2. 3. The agency shall notify the Architect and the Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services. The agency is not authorized to release, revoke, alter or enlarge requirements of the Contract Documents or approve or accept any portion of the Work. The agency is not authorized to release, revoke, alter or enlarge requirements of the Contract Documents or approve or accept any portion of the Work. Coordination: Coordinate the sequence of activities to accommodate required services with a minimum of delay. 1. 2. 1.4 Provide access to the Work. Furnish incidental labor and facilities necessary to facilitate inspections and tests. Take adequate quantities of representative samples of materials that require testing or assist the agency in taking samples. Provide facilities for storage and curing of test samples. Deliver samples to testing laboratories. Provide the agency with a preliminary design mix proposed for use for materials mixes that require control by the testing agency. Provide security and protection of samples and test equipment at the Project Site. Duties of the testing Agency: The independent agency engaged to perform inspections, sampling, and testing of materials and construction specified in individual Sections shall cooperate with the Architect, Construction Manager, and the Contractor in performance of the agency’s duties. The testing agency shall provide qualified personnel to perform required inspections and tests. 1. E. The cost of retesting construction, revised or replaced by the Contractor, is the Contractor’s responsibility where required tests performed on original construction indicated noncompliance with Contract Document requirements. Associated Services: Cooperate with agencies performing required inspections, tests, and similar services, and provide reasonable auxiliary services as requested. Notify the agency sufficiently in advance of operations to permit assignment of personnel. Auxiliary services required include, but are not limited to, the following. 1. 2. 3. D. NOVEMBER 19TH, 2013 Coordinate activities to avoid the necessity of removing and replacing construction to accommodate inspections and tests. The Construction Manager is responsible for scheduling times for inspections tests, taking samples, and similar activities. SUBMITTALS A. Unless the Contractor is responsible for this service, the independent testing agency shall submit a certified written report, induplicate, of each inspection, test, or similar service through the Contractor. 1. 2. Submit additional copies of each written report directly to the governing authority, when the authority so directs. Report Data: Written reports of each inspection, test, or similar service include, but are not limited to, the following: a. b. c. Date of issue. Project title and number. Name, address, and telephone number of testing agency. QUALITY REQUIREMENTS 01 4000 - 3 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 d. e. f. g. h. i. j. k. l. m. 1.5 NOVEMBER 19TH, 2013 Dates and locations of samples and tests or inspections. Names of individuals making the inspection or test. Designation of the Work and test method. Identification of product and Specification Section. Complete inspection or test data. Test results and any interpretations of test results. Ambient conditions at the time of sample taking and testing. Comments or professional opinion on whether inspected or tested Work complies with Contract document requirements. Name and signature of laboratory inspector. Recommendations on retesting. QUALITY ASSURANCE A. Qualifications for Service Agencies: Engage inspection and testing service agencies, including independent testing laboratories, that are pre-qualified as complying with the American Council of Independent Laboratories “Recommended Requirements for Independent Laboratory Qualification” and that specialize in the types of inspections and test to be performed. 1. Each independent inspection and testing agency engaged on the Project shall be authorized by authorities having jurisdiction to operate in the state where the project is located. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 REPAIR AND PROTECTION A. General: Upon completion of inspection, testing, sample taking and similar services, repair damaged construction and restore substrates and finishes. Comply with Contract Document requirements for Division 1 Section “Cutting and Patching.” B. Protect construction exposed by or for quality-control service activities, and protect repaired construction. C. Repair and protection is Contractor’s responsibility, regardless of the assignment of responsibility for inspection, testing, or similar services. END OF SECTION 01 4000 QUALITY REQUIREMENTS 01 4000 - 4 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 5000 – TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes requirements for temporary facilities and controls, including temporary utilities, support facilities, and security and protection facilities. B. Temporary utilities include, but are not limited to, the following: 1. 2. 3. 4. 5. 6. 7. 8. Sewers and drainage. Water Service and distribution. Sanitary facilities, including toilets, wash facilities, and drinking-water facilities. Heating and cooling facilities. Ventilation. Electric power service. Lighting. Telephone service. C. Security and protection facilities include, but are not limited to, the following: 1. Temporary partitions. 2. Fire protection. D. Unless work of this section is indicated to be provided under a specific contract, each Prime Contractor must provide, maintain and remove required temporary facilities necessary to perform his own construction activities. 1.2 QUALITY ASSURANCE A. Regulations: Comply with industry standards and applicable laws and regulations of authorities having jurisdiction including, but not limited to, the following: 1. 2. 3. 4. 5. B. Standards: Comply with NFPA 241 “Standard for Safeguarding Construction, Alterations, and Demolition Operations,” ANSI A10 Series standards for “Safety Requirements for Construction and Demolition,” and NECA Electrical Design Library “Temporary Electrical Facilities.” 1. C. Building code requirements. Health and safety regulations. Utility company regulations. Police, fire department, and rescue squad rules. Environmental protection regulations. Electrical Service: Comply with NEMA, NECA, and UL standards and regulations for temporary electric service. Install service in compliance with NFPA 70 “National Electric Code.” Inspections: Arrange for authorities having jurisdiction to inspect and test each temporary utility before use. Obtain required certifications and permits. TEMPORARY FACILITIES AND CONTROLS 01 5000 - 1 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.3 NOVEMBER 19TH, 2013 PROJECT CONDITIONS A. Temporary Utilities: Prepare a schedule indicating dates for implementation and termination of each temporary utility. At the earliest feasible time, when acceptable to the Owner, change over from use of temporary service to use of permanent service. B. Conditions of Use: Keep temporary services and facilities clean and neat in appearance. Operate in a safe and efficient manner. Relocate temporary services and facilities as the work progresses. Do not overload facilities or permit them to interfere with progress. Take necessary fire-preventive measures. Do not allow hazardous, dangerous, or unsanitary conditions, or public nuisances to develop or persist onsite. 1.4 DIVISION OF RESPONSIBILITIES A. General: These Specifications assign each Prime Contractor specific responsibilities for certain temporary facilities used by other Prime Contractors and other entities at the site. B. Prime Contractor is responsible for the following: 1. 2. 3. 4. 5. 6. 7. 8. 1.5 Installation, operation, maintenance and removal of each temporary facility considered as its own normal construction activity, as well as the costs and use charges except as listed below. Plug-in electric power cords and extension cords, supplementary plug-in task lighting, and special lighting necessary exclusively for its own activities. Its own storage and fabrication sheds. Hoisting requirements, including hoisting loads in excess of 2 tons, hoisting material or equipment into spaces below grade, and hoisting requirements outside the building enclosure. Collection and disposal of its own hazardous, dangerous, unsanitary, or other harmful waste material. Secure lock-up of its own tools, materials and equipment. Construction aids and miscellaneous services and facilities necessary exclusively for its own construction activities. Maintaining temporary facilities provided by said Prime Contractor. USE CHARGES A. General: Cost or use charges for temporary facilities are not chargeable to Owner or Architect and shall be included in the Contract Sum. Allow other entities to use temporary services and facilities without cost, including, but not limited to, the following: 1. 2. 3. 4. 5. 6. 7. B. The Construction Manager. Other Contractors. Owners construction forces. Occupants of Project. Architect. Testing Agencies. Personnel of authorities having jurisdiction. Water Service: Use water from the Owner’s existing water system without metering and without payment of use charges. Access to water shall be approved by the Owner. TEMPORARY FACILITIES AND CONTROLS 01 5000 - 2 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 C. NOVEMBER 19TH, 2013 Electric Power Service: Temporary electric power including set-up and maintenance is the responsibility of the General Contractor. PART 2 - PRODUCTS 2.1 MATERIALS A. General: Provide new materials. If acceptable to the Architect, the Contractor may use undamaged, previously used materials in serviceable condition. Provide materials suitable for use intended. B. Lumber and Plywood: Comply with requirements in Division 6 Section “Rough Carpentry.” 1. 2. 3. 4. C. For job-built temporary offices, shops, and sheds within the construction area, provide UL-labeled, fire-treated lumber and plywood for framing, sheathing, and siding. For signs and directory boards, provide exterior-type, Grade B-B high density concrete form overlay plywood of sizes and thicknesses indicated. For vision barriers, provide minimum 3/8-inch-thick exterior plywood. For safety barriers, sidewalk bridges, and similar uses, provide minimum 5/8-inch-thick exterior plywood. Paint: Comply with requirements of Division 9 Section “Painting.” 1. Paint surfaces exposed to view from Owner occupied areas. D. Tarpaulins: Provide waterproof, fire-resistant, UL-labeled tarpaulins with flame-spread rating of 15 or less. For temporary enclosures, provide translucent, nylon-reinforced, laminated polyethylene or polyvinyl chloride, fire-retardant tarpaulins. E. Water: Provide potable water approved by local health authorities. F. Open-Mesh Chain Link Fencing: Provide 0.120-inch-thick, galvanized steel posts, and 2.875" dia. Gate posts. Provide lockable gates. Furnish keys to the Owner, Architect, Architect’s Site Representative and necessary construction personnel. PART 3 - EXECUTION 3.1 INSTALLATION GENERAL A. Use qualified personnel for installation of temporary facilities. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the work. Relocate and modify facilities as required. B. General Contractor shall provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities. TEMPORARY FACILITIES AND CONTROLS 01 5000 - 3 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.2 NOVEMBER 19TH, 2013 TEMPORARY UTILITY INSTALLATION A. Use qualified personnel for installation of temporary facilities. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the work. Relocate and modify facilities as required. B. General Contractor shall provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities. 1. 3.3 Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services. CONTRACTOR FIELD OFFICES A. General contractors and subcontractors may with permission from the architect and/or construction manager establish a field office for their own use. Said offices for the individual prime contractors, subcontractors, specialty contractors and the like shall be of such size and design as approved by the owner and architect and shall be located in the Contractors fenced staging area at the South East corner of the site. Each representative contractor will arrange for telephone service and electric service, if required, directly with the utility company. (No field offices or storage trailers will be allowed by the buildings.) B. Maintain, in the contractor’s field office, all articles for First Aid treatment; further, the contractor shall establish standing arrangements for the immediate removal and hospital treatment of any employees and other persons on the job site who may be injured or who may become ill during the course work. 3.4 TEMPORARY AND PERMANENT SERVICES, GENERAL A. The Contractor’s use of any permanent system or service of the building or portions thereof shall be subject to the Owners approval. B. The Contractor shall be responsible for any and all damage to permanent services used, and shall make good any and all damage to the satisfaction of the owner, prior to final completion and acceptance. C. NOTE - In accordance with OSHA and other applicable regulations, the representative Contractors performing erection of structural steel, precast concrete and such other “skeleton” type work are solely responsible for the netting, guard rail protection and such other safety devices as deemed necessary to protect the workers and public from harm. 3.5 TEMPORARY TOILET FACILITIES A. 3.6 The GENERAL CONTRACTOR shall provide suitable toilet facilities at approved locations complying with all state and local requirements. TEMPORARY WATER A. The Contractor shall: TEMPORARY FACILITIES AND CONTROLS 01 5000 - 4 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 2. 3. 4. 5. 6. B. 2. Provide all hose and other extensions from connections installed by the Contractor and all labor, materials and supplies required to supply water to the work. Prevent water damage to the work. STORAGE FACILITIES A. The Contractor and each subcontractor shall provide temporary storage shanties, tool houses and other facilities as required for his own use. B. Materials delivered to the site shall be safely stored and adequately protected against loss or damage. Particular care shall be taken to protect and cover materials that are liable to be damaged by the elements. 3.8 3.9 Provide and maintain a temporary water system of size and capacity as required below to supply the needs of all Contractors for the work. Provide no less than two 3/4 inch hose bibs conveniently located at each location. Provide and pay for all connections and permits. Install such temporary water system so that service shall be available at the commencement of the work. The permanent water risers and lines may be used for temporary water supply. The permanent services shall be turned over to the Owner in perfect condition. Any repairs required due to temporary use shall be made at the sole expense of the plumbing contractor. Protect temporary and permanent lines against any damage. Remove all temporary lines when directed by the Architect when such lines are no longer required. Contractor shall: 1. 3.7 NOVEMBER 19TH, 2013 RUBBISH CONTAINER A. Contractor shall provide suitable rubbish container device(s) for his own use (both demolition and construction debris), properly maintained and serviced, replaced as required and protected from access by the public fencing as may be specified herein or approved by the Architect. B. Contractor and Subcontractor shall sweep up and gather together daily all his own rubbish and removed materials and place same in containers. JANITORIAL SERVICE/DAILY CLEANUP A. B. C. D. The Contractor shall furnish daily janitorial services for the project and perform any required maintenance of facilities as deemed necessary by the Architect during the entire life of the contract. Toilet facilities shall be kept clean and sanitary at all times. Services shall be accomplished to the satisfaction of the Architect. The Contractor shall provide daily trash collection and cleanup of the project area and shall dispose of all discarded debris, and the like in a manner approved by the Architect and Construction Manager. The General Work Contractor shall place foot wiping carpet at all entrances, exits to the work areas and provide daily cleaning for all dust and footprints from the corridors, stairs, and the like, caused by construction. TEMPORARY FACILITIES AND CONTROLS 01 5000 - 5 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.10 A. 3.11 A. 3.12 A. 3.13 A. 3.14 NOVEMBER 19TH, 2013 BURNING Burning will not be permitted. TEMPORARY ROADWAYS - NOT USED MAINTENANCE OF PERMANENT ROADWAYS The General Work Contractor shall immediately remove dirt and debris which may collect on permanent roadways created by their work, deliveries, manpower, equipment, etc. FIRE PREVENTION CONTROL All Contractors shall comply with the safety provisions of the National Fire Protection Association’s “National Fire Codes” pertaining to the work and, particularly, in connection with any cutting or welding performed as part of the work. TEMPORARY FIRE PROTECTION A. Contractor shall take all possible precautions for the prevention of fires. Where flame cutting torches, blow torches, or welding tools are required to be used within the building, their use shall be as approved by the Prime Contractor at the site. When welding tools or torches of any type are in use, have available in the immediate vicinity of the work a fire extinguisher of the dry chemical 20 lbs. Type. The fire extinguisher(s) shall be provided and maintained by the Contractor doing such work. B. Fuel for cutting and heating torches shall be gas only and shall be contained in Underwriters laboratory approved containers. C. Storage of gas shall be in locations as approved by the Owner and subject to Fire Department regulations and requirements. D. No volatile liquids shall be used for cleaning agents or as fuels for motorized equipment or tools within a building except with the express approval of the Owner and/or Architect and in accordance with local codes. On-site bulk storage of volatile liquids shall be outside the buildings at locations directed by the Owner, who shall determine the extent of volatile liquid allowed within the building at any given time. E. The Contractor shall comply with the following requirements relating to compressed gas: 1. 2. Where compressed gas of any type is used for any purpose at the site, it shall be contained in cylinders complying with ICC regulations. Gases of different types shall not be stored together except when in use and when such proximity is required. All gas cylinders shall be stored in sheds constructed of noncombustible materials. Sheds shall be well ventilated and without electric lights or fixtures and shall be located as far from other buildings as is practicable. All gas cylinders not in actual use, or in proposed immediate use, shall be removed from the building under construction or reconstruction. Empty gas cylinders shall be removed prior to bringing in a replacement cylinder. TEMPORARY FACILITIES AND CONTROLS 01 5000 - 6 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3. 4. 5. 6. F. 2. 3. 4. 5. 6. 7. 8. 9. 3.15 A. Cylinders shall at all times be supported and braced in an upright position. When not in use, the protective cap shall be screwed over the valve. All persons required to handle gas cylinders or to act as temporary firemen (Fire Watchers) shall be able to read, write and understand the English language; they shall also be required by the Contractor to read Part 3 of Pamphlet P-1 “Safe Handling of Compressed Gases” published by the Compressed Gas Association, 500 Fifth Avenue, New York, NY 10036. Where local ordinances are in effect regarding gas cylinders, (their use, appurtenances and handling), such ordinances shall supplement the requirements of this paragraph. All personnel engaged in fire watch shall be certified by the Local Fire Department having jurisdiction. LP-Gas Heating will not be permitted in enclosed areas below grade. Any cylinder not having the proper ICC markings or reinspection marking, or any cylinder with a leak shall be isolated immediately away from any building and the supplier shall be immediately notified; such other precautions as may be required to prevent damage or injury shall also be taken by the Contractor. The Contractor shall comply with the following requirements relating to welding and cutting: 1. G. NOVEMBER 19TH, 2013 All cutting and/or welding (electric or gas) must be done only by skilled, certified and licensed personnel. During welding or cutting operations, a contractor’s man shall act as a fire watcher. The fire watcher shall have proper eye protection and suitable fire fighting equipment including fire extinguisher (bearing current inspection Certificate), protective gloves and any other equipment deemed necessary. Welding or cutting shall not be done near flammable liquid, vapors or tanks containing such material. Where cutting or welding is done above or adjacent to (within two feet) combustible material or persons, a shield of incombustible material shall be installed to protect against fire or injury to sparks or hot metal. Tanks supplying gases for welding or cutting are to be placed in an upright position securely fastened, and close as practical to the operation. Tanks, actives or spares, shall be protected from excess heat and shall not be placed in stairways, hallways or exits. When not in use, protective valve cap shall be screwed on the cylinder. Adequate fire extinguishing equipment shall be maintained at all welding or cutting operations. The Contractor shall secure all required inspections. All equipment, hoses, gauges, pressure reducing valves, torches, etc., shall be maintained in good working order and all defective equipment shall immediately be removed from the job. No person shall be permitted to do any welding or cutting until his name, address and current license number have been submitted in writing to the Owner. Contractors for work outside the building shall commence operations promptly on award of Contract, and shall be responsible for same being kept clear of materials and debris in connection with their own work and that of other Contractors. If a Contractor for outside work allows other contractors to deposit material and debris over its lines, the Contractor shall be responsible for all delay and extra cost occasioned thereby. DISCONTINUE, CHANGES AND REMOVAL Contractor shall: TEMPORARY FACILITIES AND CONTROLS 01 5000 - 7 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 2. 3. 3.16 A. Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment from that specified that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption. 2. 3. 4. A. 3.18 Discontinue all temporary services required by the Contract when so directed by the Architect. The discontinuance of any such temporary service prior to the completion of the work shall not render the Owner liable for any additional cost entailed thereby and each Contractor shall thereafter furnish, at no additional cost to the Owner, any and all temporary service required by such Contractors work. Remove and relocate such temporary facilities as directed by the Architect without additional cost to the Owner, and shall restore the site and the work to a condition satisfactory to the Owner. VENTILATION AND HUMIDITY CONTROL FOR CONSTRUCTION: 1. 3.17 NOVEMBER 19TH, 2013 Contractor shall be responsible for their own temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Ventilate enclosed area to dissipate humidity, and to prevent accumulation of dust, fumes, vapors or gases. Provide equipment as necessary for air and fresh exchange for the work area per OSHA standards. Remove temporary ventilation equipment prior to the completion of construction. VENTILATION AND HUMIDITY CONTROL FOR BUILDING: The Contractor shall provide temporary ventilation required for permanently or temporarily enclosed portions of building or for protecting existing construction from adverse effects of high humidity. Select equipment from that specified that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption. PROJECT SIGNS: A. Identification Signs: Provide Project identification signs as indicated on Drawings. B. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project. 3.19 A. ENVIRONMENTAL PROTECTION: Each Prime Contractor shall provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects. Avoid using tools and equipment that produce harmful noise. Restrict use of noise making tools and equipment to hours that will minimize complaints from persons or firms near Project site. TEMPORARY FACILITIES AND CONTROLS 01 5000 - 8 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.20 A. TEMPORARY PARTITIONS: Contractor shall erect and maintain dustproof partitions and temporary enclosures to limit dust and dirt migration and to separate areas from fumes and noise. 1. 2. Construct dustproof partitions of not less than nominal 4-inch (100-mm) studs, 5/8-inch (16-mm) gypsum wallboard with joints taped on occupied side, and ½-inch (13-mm) fireretardant plywood on construction side. Construct dustproof, floor-to-ceiling partitions of not less than nominal 4-inch (100-mm) studs, 2 layers of 3-mil (0.07-mm) polyethylene sheets, inside and outside temporary enclosure. Cover floor with 2 layers of 3-mil (0.07-mm) polyethylene sheets, extending sheets 18 inches (460 mm) up the side walls. Overlap and tape full length joints. Cover floor with 3/4-inch (19-mm0 fire-retardant plywood. a. 3. 4. 5. 6. 3.21 NOVEMBER 19TH, 2013 Construct a vestibule and airlock at each entrance to temporary enclosure with not less than 48 inches (1219 mm) between doors. Maintain water-dampened foot mats in vestibule. Sound insulate partitions to provide noise protection to occupied areas. Seal joints and perimeter. Equip partitions with dustproof doors and security locks. Protect air-handling equipment. Weatherstrip openings. AREAS OF SPECIAL PROTECTION: A. Operations of the Contractors may not block, hinder, impede, or otherwise inhibit the safe and expeditious exiting of the building’s occupants during an emergency. B. In the event of an emergency (designated by the sounding of the fire alarm system) all construction activities must immediately cease. Contractor’s work force will evacuate themselves from work areas and remain outside of work areas until the “all clear” is given. No work operations will be tolerated during the evacuation of the building or during an emergency. 3.22 A. 3.23 ENVIRONMENTAL PROTECTION: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations, and minimize the possibility that air, waterways, and subsoil might be contaminated or polluted or that other undesirable effects might result. Avoid use of tools and equipment that produce harmful noise. Restrict use of noise-making tools and equipment to hours that will minimize complaints from persons or firms near the site. OPERATION, TERMINATION, AND REMOVAL A. Supervision: Enforce strict discipline in use of temporary facilities. Limit availability of temporary facilities to essential and intended uses to minimize waste and abuse. B. Maintenance: Maintain facilities in good operating condition until removal. Protect from damage by freezing temperatures and similar elements. TEMPORARY FACILITIES AND CONTROLS 01 5000 - 9 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 2. C. NOVEMBER 19TH, 2013 Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage. Protection: Prevent water-filled piping from freezing. Maintain markers for underground lines. Protect from damage during excavation operations. Termination and Removal: Unless the Architect requests that it be maintained longer, remove each temporary facility when the need has ended, when replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with the temporary facility. Repair damaged work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired. 1. 2. Materials and facilities that constitute temporary facilities are the Contractors property. The Owner reserves the right to take possession of project identification signs. At Substantial Completion, clean and renovate permanent facilities used during the construction period including, but not limited to, the following: a. b. c. Replace air filters and clean inside of ductwork and housings. Replace significantly worn parts and parts subject to unusual operating conditions. Replace lamps burned out or noticeably dimmed by hours of use END OF SECTION 01 5000 TEMPORARY FACILITIES AND CONTROLS 01 5000 - 10 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 6000 – PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes administrative and procedural requirements governing the Contractor's selection of products for use in the Project. 1. Prime Contract: Provisions of this Section apply to the construction activities of each prime contractor. B. Related Sections: The following Sections contain requirements that relate to this Section: 1. Division 1 Section "Electronic Submittal Procedures" specifies requirements for submittal of the Contractor's Construction Schedule and the Submittal Schedule. 2. Division 1 Section “Temporary Facilities and Controls" specifies administrative procedures for handling requests for substitutions made after award of the Contract. 1.3 DEFINITIONS A. 1.4 Definitions used in this Article are not intended to change the meaning of other terms used in the Contract Documents, such as "specialties," "systems," "structure," "finishes," "accessories," and similar terms. Such terms are self-explanatory and have well-recognized meanings in the construction industry. 1. "Products" are items purchased for incorporation in the Work, whether purchased for the Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent. a. "Named Products" are items identified by the manufacturer's product name, including make or model number or other designation, shown or listed in the manufacturer's published product literature, that is current as of the date of the Contract Documents. 2. "Materials" are products substantially shaped, cut, worked, mixed, finished, refined or otherwise fabricated, processed, or installed to form a part of the Work. 3. "Equipment" is a product with operational parts, whether motorized or manually operated, that requires service connections, such as wiring or piping. QUALITY ASSURANCE A. Source Limitations: To the fullest extent possible, provide products of the same kind from a single source. 1. When specified products are available only from sources that do not, or cannot, produce a quantity adequate to complete project requirements in a timely manner, consult with the Architect to determine the most important product qualities before proceeding. Qualities may include attributes, such as visual appearance, strength, durability, or compatibility. PRODUCT REQUIREMENTS 01 6000 - 1 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 When a determination has been made, select products from sources producing products that possess these qualities, to the fullest extent possible. B. Compatibility of Options: When the Contractor is given the option of selecting between 2 or more products for use on the Project, the product selected shall be compatible with products previously selected, even if previously selected products were also options. 1. Each prime contractor is responsible for providing products and construction methods that are compatible with products and construction methods of other prime or separate contractors. 2. If a dispute arises between prime contractors over concurrently selectable, but incompatible products, the Architect will determine which products shall be retained and which are incompatible and must be replaced. C. Nameplates: Except for required labels and operating data, do not attach or imprint manufacturer's or producer's nameplates or trademarks on exposed surfaces of products that will be exposed to view in occupied spaces or on the exterior. 1. Labels: Locate required product labels and stamps on concealed surfaces or, where required for observation after installation, on accessible surfaces that are not conspicuous. 2. Equipment Nameplates: Provide a permanent nameplate on each item of serviceconnected or power-operated equipment. Locate on an easily accessible surface that is inconspicuous in occupied spaces. The nameplate shall contain the following information and other essential operating data: a. Name of product and manufacturer. b. Model and serial number. c. Capacity. d. Speed. e. Ratings. 1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING A. Deliver, store, and handle products according to the manufacturer's recommendations, using means and methods that will prevent damage, deterioration, and loss, including theft. 1. Schedule delivery to minimize long-term storage at the site and to prevent overcrowding of construction spaces. 2. Coordinate delivery with installation time to assure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses. 3. Deliver products to the site in an undamaged condition in the manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing. 4. Inspect products upon delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected. 5. Store products at the site in a manner that will facilitate inspection and measurement of quantity or counting of units. 6. Store heavy materials away from the Project structure in a manner that will not endanger the supporting construction. 7. Store products subject to damage by the elements above ground, under cover in a weather tight enclosure, with ventilation adequate to prevent condensation. Maintain temperature and humidity within range required by manufacturer's instructions. PART 2 - PRODUCTS PRODUCT REQUIREMENTS 01 6000 - 2 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2.1 NOVEMBER 19TH, 2013 PRODUCT SELECTION A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and, unless otherwise indicated, new at the time of installation. 1. Provide products complete with accessories, trim, finish, safety guards, and other devices and details needed for a complete installation and the intended use and effect. 2. Standard Products: Where available, provide standard products of types that have been produced and used successfully in similar situations on other projects. B. Product Selection Procedures: The Contract Documents and governing regulations govern product selection. Procedures governing product selection include the following: 1. Nonproprietary Specifications: When Specifications list products or manufacturers that are available and may be incorporated in the Work, but do not restrict the Contractor to use of these products only, the Contractor may propose any available product that complies with Contract requirements. Comply with Contract Document provisions concerning "substitutions" to obtain approval for use of an unnamed product. 2. Descriptive Specification Requirements: Where Specifications describe a product or assembly, listing exact characteristics required, with or without use of a brand or trade name, provide a product or assembly that provides the characteristics and otherwise complies with Contract requirements. 3. Performance Specification Requirements: Where Specifications require compliance with performance requirements, provide products that comply with these requirements and are recommended by the manufacturer for the application indicated. 4. Manufacturer's recommendations may be contained in published product literature or by the manufacturer's certification of performance. 5. Compliance with Standards, Codes, and Regulations: Where Specifications only require compliance with an imposed code, standard, or regulation, select a product that complies with the standards, codes, or regulations specified. 6. Visual Matching: Where Specifications require matching an established Sample, the Architect's decision will be final on whether a proposed product matches satisfactorily. 7. Where no product available within the specified category matches satisfactorily and complies with other specified requirements, comply with provisions of the Contract Documents concerning "substitutions" for selection of a matching product in another product category. 8. Visual Selection: Where specified product requirements include the phrase "... as selected from manufacturer's standard colors, patterns, textures ..." or a similar phrase, select a product and manufacturer that complies with other specified requirements. The Architect will select the color, pattern, and texture from the product line selected. 9. Allowances: Refer to individual Specification Sections and "Allowance" provisions in Division 1 for allowances that control product selection and for procedures required for processing such selections, if required. PART 3 - EXECUTION 3.1 INSTALLATION OF PRODUCTS A. Comply with manufacturer's instructions and recommendations for installation of products in the applications indicated. Anchor each product securely in place, accurately located and aligned with other Work. 1. Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion. END OF SECTION 01 6000 PRODUCT REQUIREMENTS 01 6000 - 3 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 7329 – CUTTING AND PATCHING PART 1 - GENERAL 1.1 SUMMARY A. This Section includes administrative and procedural requirements for cutting and patching. B. Definition: "Cutting and patching" includes cutting into existing construction to provide for the installation or performance of other work and subsequent fitting and patching required to restore surfaces to their original condition, and does not apply to new construction procedures, except when new construction is already completed and must be cut and patched due to incorrect sequencing of work and/or improper coordination. C. Multi Prime Contracts: Provisions of this Section apply to the construction activities of each prime Contractor. D. Related Sections: The following Sections contain requirements that relate to this Section: 1. 2. Division 1 Section "Execution and Product Requirements" for procedures for coordinating cutting and patching with other construction activities. Refer to other Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work. a. 1.2 Requirements of this Section apply to mechanical and electrical installations. Refer to Division 15 and 16 Sections for other requirements and limitations applicable to cutting and patching mechanical and electrical installations. RESPONSIBILITIES A. General: General Contractor is responsible to perform cutting and patching for their portion of the Work. Patching work shall restore surfaces to original condition including paint, ceramic, tile, EIFS, VCT flooring, terrazzo flooring, gypsum wallboard ceilings and walls, etc. The requirements of this section apply to all Contractors, even though certain items of work may be applicable to a specific Prime Contractor. B. Cutting and patching of completed new construction required due to out of sequence construction and/or improper coordination is the responsibility of the prime Contractor responsible for the out of sequence construction or improper coordination. Cutting and patching of new construction for these purposes shall be accomplished by the General Work Contractor and shall be paid for by the prime Contractor responsible. The Architect shall be the sole judge of the responsibility for such cutting and patching, and shall prepare change orders to delete monies from the Contract of the responsible prime Contractor and credit those monies to the Contractor for General Work. 1. The Prime Contractor shall cooperate with Architect and other Sub-Contractors to accomplish this cutting and patching with minimal disruption to construction and at reasonable costs. CUTTING AND PATCHING 01 7329 - 1 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.3 NOVEMBER 19TH, 2013 SUBMITTALS: A. Cutting and Patching Proposal: Submit a plan describing procedures well in advance of the time cutting and patching will be performed if the Owner requires approval of these procedures before proceeding. Request approval to proceed. Include the following information, as applicable, in the proposal: 1. 2. 3. 4. 5. 6. 7. 1.4 Describe the extent of cutting and patching required. Show how it will be performed and indicate why it cannot be avoided. Describe anticipated results in terms of changes to existing construction. Include changes to structural elements and operating components as well as changes in the building's appearance and other significant visual elements. List products to be used and firms or entities that will perform Work. Indicate dates when cutting and patching will be performed. Utilities: List utilities that cutting and patching procedures will disturb or affect. List utilities that will be relocated and those that will be temporarily out-of-service. Indicate how long service will be disrupted. Where cutting and patching involves adding reinforcement to structural elements, submit details and engineering calculations showing integration of reinforcement with the original structure. Approval by the Architect to proceed with cutting and patching does not waive the Architect's right to later require complete removal and replacement of unsatisfactory work. QUALITY ASSURANCE: A. Requirements for Structural Work: Do not cut and patch structural elements in a manner that would change their load-carrying capacity or load-deflection ratio. 1. Obtain approval of the cutting and patching proposal before cutting and patching the following structural elements: a. b. c. d. e. f. g. h. i. j. k. l. m. B. Foundation construction. Bearing and retaining walls. Structural concrete. Structural steel. Lintels. Timber and primary wood framing. Structural decking. Stair systems. Miscellaneous structural metals. Exterior curtain-wall construction. Equipment supports. Piping, ductwork, vessels, and equipment. Structural systems of special construction in Division 13 Sections. Operational Limitations: Do not cut and patch operating elements or related components in a manner that would result in reducing their capacity to perform as intended. Do not cut and patch operating elements or related components in a manner that would result in increased maintenance or decreased operational life or safety. CUTTING AND PATCHING 01 7329 - 2 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. Obtain approval of the cutting and patching proposal before cutting and patching the following operating elements or safety related systems: a. b. c. d. e. f. g. h. i. j. k. C. Primary operational systems and equipment. Air or smoke barriers. Water, moisture, or vapor barriers. Membranes and flashings. Fire protection systems. Noise and vibration control elements and systems. Control systems. Communication systems. Conveying systems. Electrical wiring systems. Operating systems of special construction. Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in the Architect's opinion, reduce the building's aesthetic qualities. Do not cut and patch construction in a manner that would result in visual evidence of cutting and patching. Remove and replace construction cut and patched in a visually unsatisfactory manner. 1. If possible retain the original Installer or fabricator to cut and patch the exposed Work listed below. If it is impossible to engage the original Installer or fabricator, engage another recognized experienced and specialized firm. a. b. c. d. e. f. g. h. i. j. k. l. m. n. o. p. q. 1.5 NOVEMBER 19TH, 2013 Processed concrete finishes. Stonework and stone masonry. Ornamental metal. Matched-veneer woodwork. Preformed metal panels. Firestopping. Window wall system. Stucco and ornamental plaster. Acoustical ceilings. Terrazzo. Finished wood flooring. Fluid-applied flooring. Carpeting. Aggregate wall coating. Wall covering. Swimming pool finishes. HVAC enclosures, cabinets, or covers WARRANTY: A. Existing Warranties: Replace, patch, and repair material and surfaces cut or damaged by methods and with materials in such a manner as not to void any warranties required or existing. PART 2 - PRODUCTS CUTTING AND PATCHING 01 7329 - 3 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2.1 NOVEMBER 19TH, 2013 MATERIALS, GENERAL: A. Use materials identical to existing materials. For exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible if identical materials are unavailable or cannot be used. Use materials whose installed performance will equal or surpass that of existing materials. PART 3 - EXECUTION 3.1 INSPECTION: A. Examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed before cutting. If unsafe or unsatisfactory conditions are encountered, take corrective action before proceeding. 1. 3.2 Before proceeding, meet at the Project Site with parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding. PREPARATION: A. Temporary Support: Provide temporary support of work to be cut, including shoring, lumber, plywood, etc. B. Protection: Protect existing construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of the Project that might be exposed during cutting and patching operations. C. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas. D. Avoid cutting existing pipe, conduit, or ductwork serving the building but scheduled to be removed or relocated until provisions have been made to bypass them. 3.3 PERFORMANCE: A. General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay. 1. B. Cut existing construction to provide for installation of other components or performance of other construction activities and the subsequent fitting and patching required to restore surfaces to their original condition. Cutting: Cut existing construction using methods least likely to damage elements retained or adjoining construction. Where possible, review proposed procedures with the original Installer; comply with the original Installer's recommendations. 1. In general, where cutting, use hand or small power tools designed for sawing or grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size CUTTING AND PATCHING 01 7329 - 4 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. 3. 4. 5. C. required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces. Cut through concrete and masonry using a cutting machine, such as a Carborundum saw or a diamond-core drill. Comply with requirements of applicable Division 2 Sections where cutting and patching requires excavating and backfilling. Where services are required to be removed, relocated, or abandoned, by-pass utility services, such as pipe or conduit, before cutting. Cut-off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal the remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after by-passing and cutting. Patching: Patch with durable seams that are as invisible as possible. Comply with specified tolerances. 1. 2. 3. Where feasible, inspect and test patched areas to demonstrate integrity of the installation. Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing. Where removing walls or partitions extends one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform color and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance. a. 4. 3.4 NOVEMBER 19TH, 2013 Where patching occurs in a smooth painted surface, extend final paint coat over entire unbroken surface containing the patch after the area has received primer and second coat. Patch, repair, or re-hang existing ceilings as necessary to provide an even-plane surface of uniform appearance. CLEANING: A. Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar items. Thoroughly clean piping, conduit, and similar features before applying paint or other finishing materials. Restore damaged pipe covering to its original condition. END OF SECTION 01 7329 CUTTING AND PATCHING 01 7329 - 5 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 7400 – WARRANTIES 1.1 SUMMARY A. This Section includes administrative and procedural requirements for warranties required by the Contract Documents, including manufacturer’s standard warranties on products and special warranties. 1. Refer to the General Conditions for terms of the Contractor's period for correction of the Work. B. Related Sections: The following Sections contain requirements that relate to this Section: 1. Division 1 Section "Submittals" specifies procedures for submitting warranties. 2. Division 1 Section "Execution and closeout requirements” specifies contract closeout procedures. 3. Divisions 2 through 16 Sections for specific requirements for warranties on products and installations specified to be warranted. 4. Certifications and other commitments and agreements for continuing services to Owner are specified elsewhere in the Contract Documents. C. Disclaimers and Limitations: Manufacturer's disclaimers and limitations on product warranties do not relieve the Contractor of the warranty on the Work that incorporates the products. Manufacturer's disclaimers and limitations on product warranties do not relieve suppliers, manufacturers, and subcontractors required to countersign special warranties with the Contractor. D. Single Prime Contract: contract. 1.2 General contractor is responsible for warranties related to its own DEFINITIONS A. Standard product warranties are preprinted written warranties published by individual manufacturers for particular products and are specifically endorsed by the manufacturer to the Owner. B. Special warranties are written warranties required by or incorporated in the Contract Documents, either to extend time limits provided by standard warranties or to provide greater rights for the Owner. 1.3 WARRANTY REQUIREMENTS A. Related Damages and Losses: When correcting failed or damaged warranted construction, remove and replace construction that has been damaged as a result of such failure or must be removed and replaced to provide access for correction of warranted construction. B. Reinstatement of Warranty: When Work covered by a warranty has failed and been corrected by replacement or rebuilding, reinstate the warranty by written endorsement. The reinstated warranty shall be equal to the original warranty with an equitable adjustment for depreciation. C. Replacement Cost: Upon determination that Work covered by a warranty has failed, replace or rebuild the Work to an acceptable condition complying with requirements of the Contract Documents. The Contractor is responsible for the cost of replacing or rebuilding defective Work regardless of whether the Owner has benefited from use of the Work through a portion of its anticipated useful service life. WARRANTIES 01 7400 - 1 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 D. Owner's Recourse: Expressed warranties made to the Owner are in addition to implied warranties and shall not limit the duties, obligations, rights, and remedies otherwise available under the law. Expressed warranty periods shall not be interpreted as limitations on the time in which the Owner can enforce such other duties, obligations, rights, or remedies. 1. Rejection of Warranties: The Owner reserves the right to reject warranties and to limit selection to products with warranties not in conflict with requirements of the Contract Documents. E. Where the Contract Documents require a special warranty, or similar commitment on the Work or part of the Work, the Owner reserves the right to refuse to accept the Work, until the Contractor presents evidence that entities required to countersign such commitments are willing to do so. 1.4 SUBMITTALS A. Submit written warranties to the Architect prior to the date certified for Substantial Completion. If the Architect's Certificate of Substantial Completion designates a commencement date for warranties other than the date of Substantial Completion for the Work, or a designated portion of the Work, submit written warranties upon request of the Architect. 1. When a designated portion of the Work is completed and occupied or used by the Owner, by separate agreement with the Contractor during the construction period, submit properly executed warranties to the Architect within 15 days of completion of that designated portion of the Work. B. When the Contract Documents require the Contractor, or the Contractor and a subcontractor, supplier or manufacturer to execute a special warranty, prepare a written document that contains appropriate terms and identification, ready for execution by the required parties. Submit a draft to the Owner, through the Architect, for approval prior to final execution. 1. Refer to Divisions 2 through 16 Sections for specific content requirements and particular requirements for submitting special warranties. C. Form of Submittal: At Final Completion compile 2 copies of each required warranty properly executed by the Contractor, or by the Contractor, subcontractor, supplier, or manufacturer. Organize the warranty documents into an orderly sequence based on the table of contents of the Project Manual. D. Bind warranties and bonds in heavy-duty, commercial-quality, durable 3-ring, vinyl-covered loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 81/2-by-11-inch(115-by-280-mm) paper. 1. Provide heavy paper dividers with celluloid covered tabs for each separate warranty. Mark the tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product, and the name, address, and telephone number of the Installer. 2. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project title or name, and name of the Contractor. 3. When warranted construction requires operation and maintenance manuals, provide additional copies of each required warranty, as necessary, for inclusion in each required manual. END OF SECTION 01 7400 WARRANTIES 01 7400 - 2 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 7423 – CLEANING UP PART 1 - GENERAL 1.1 DESCRIPTION OF WORK: A. The work of this section relates to the following: 1. 2. 3. B. Related Requirements Specified Elsewhere 1. 2. 3. 1.2 Maintain premises and public properties and roadways free from accumulations of waste, debris, dirt, mud and rubbish caused by operations. At completion of work, remove waste materials, rubbish tools, equipment, machinery and surplus materials, and clean all sight exposed surfaces; leave project clean and ready for occupancy. Remove all overspray caused by construction operations from adjacent construction, surfaces and vehicles. Summary of Work: Section 011000 Cutting and Patching: Section 017329 Cleaning for Specific Products or Work: the respective sections of the specifications: SAFETY REQUIREMENTS: A. Standards: Maintain project in accord with safety and insurance standards. B. Hazard Control 1. 2. 3. C. Store volatile waste in covered metal containers and remove from premises daily. Prevent accumulations of waste which create hazardous conditions. Provide adequate ventilation during use of volatile or noxious substances. Conduct cleaning and disposal operations to comply with local ordinances and anti-pollution laws. 1. 2. 3. Do not burn or bury rubbish and waste materials on project site. Do not dispose of volatile waste such as mineral spirits, oil, or paint thinner in storm or sanitary drains. Do not dispose of waste into streams or waterways. PART 2 - EXECUTION 2.1 MATERIALS: A. Use only cleaning materials recommended by manufacturer of surface to be cleaned. CLEANING UP 01 7423 - 1 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 PART 3 - EXECUTION 3.1 DURING CONSTRUCTION CONTRACT(S) SHALL: A. Execute daily cleaning to ensure that building, grounds, and public properties and roadways are maintained free from accumulations of waste materials, rubbish, dirt and mud. B. Wet down dry materials and rubbish to lay dust and prevent blowing dust. Erect dustproof barriers to keep dust from drifting through the building. C. Each day, all contractors shall affect the following: 1. 2. 3. 4. 5. 6. 7. 8. Areas of intense activity, such as cutting and sawing must be swept clean and reorganized at the end of each day. Areas of moderate activity such as installation of plumbing, ductwork, electrical work must be returned to good order at the end of each day. Debris below scaffolds (and shoring/re-shoring) must at all time, be kept sufficiently consolidated to keep walkways free of tripping hazards. These work areas must also be swept clean immediately upon removal of scaffolds. All swept up debris, waste materials, and packing must be removed and placed in the dumpster by noon of the following workday. All sorted material must be kept in good order. As portions of the work are completed, all used and excess materials must be removed promptly. Daily Clean-up and good housekeeping is the responsibility of each contractor individually and will be monitored by the Construction Manager. Contractors shall promptly comply with requests to organize scatted materials. D. Each contractor is responsible for furnishing all dumpsters or other such containers as required for collection, storage and legal disposal of all debris and rubbish resultant from the construction operation. The Construction Manager shall locate, maintain and move such containers as necessary and legally dispose of waste as containers are filled. Separate and recycle as required authorities and regulations. E. Vacuum clean interior building areas when ready to receive finish painting, and continue vacuum cleaning on an as needed basis until building is ready for Substantial Completion or occupancy. F. Handle materials in a controlled manner with as few handlings as possible; do not drop or throw materials from heights. G. Schedule cleaning operations so that dust and other containment resulting from cleaning process will not fall on wet, newly painted surfaces. 3.2 FINAL CLEANING A. Each Contractor Shall: 1. 2. CLEANING UP Employ experienced workmen, or professional cleaners, for final cleaning. In preparation for substantial completion or occupancy, conduct final inspection of sight exposed interior and exterior surfaces, and of concealed spaces. 01 7423 - 2 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3. 4. 5. B. Remove grease, dust, dirt, stains, labels, fingerprints, and other foreign materials form sight-exposed interior and exterior finished surfaces; polish surface so designated to shine finish. Maintain cleaning until project, or portion thereof, is occupied by owner. Repair, patch and touch up marred surfaces to specified finish, to match adjacent surfaces. Contractor shall complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or portion of Project: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 3.3 NOVEMBER 19TH, 2013 Wash all transparent materials including mirrors and glass in doors and windows (inside and out). Vacuum clean carpeting and epoxy flooring. Wash & wax resilient tile floors. Wash and polish all terrazzo and ceramic tile as installed new. Dust/ clean all finished surfaces including casework, window sills, toilet partitions/ accessories, hardware, specialties, etc. Restoration of any lawn areas disturbed by construction operations. Replace disposable filters on HVAC units. Clean permanent air filters. Clean ducts, blowers and coils if dusty/ soiled during construction process Final clean surfaces of all HVAC equipment including dust, paint, taping compound, mortar droppings, etc. (Unit ventilators, unit heaters, convectors, fintube, diffusers/ grills, etc). Clean light fixtures, lamps, globes & reflectors. Replace burned out bulbs, noisy starters, etc. Clean surfaces of all electrical equipment. Clean all fixtures, lavatories, water closets, and trim. RUBBISH REMOVAL A. Each contractor shall comply with all Local, State and Federal Laws, Codes and Requirements regarding recycling and trash or rubbish removal. END OF SECTION 01 7423 CLEANING UP 01 7423 - 3 of 3 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 7700 – EXECUTION AND CLOSEOUT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: 1. 2. 3. 4. 5. Inspection procedures. Project record document submittal. Operation and maintenance manual submittal. Submittal of warranties. Final cleaning. B. Closeout requirements for specific construction activities are included in the appropriate Sections. C. Single Prime Contracts: Provisions of this Section apply to the construction activities of General Contractor. 1.3 SUBSTANTIAL COMPLETION A. Preliminary Procedures: Before requesting inspection for certification of Substantial Completion, complete the following. List exceptions in the request. 1. In the Application for Payment that coincides with, or first follows, the date Substantial Completion is claimed, show 100 percent completion for the portion of the Work claimed as substantially complete. a. b. 2. 3. 4. 5. 6. Include supporting documentation for completion as indicated in these Contract Documents and a statement showing an accounting of changes to the Contract Sum. If 100 percent completion cannot be shown, include a list of incomplete items, the value of incomplete construction, and reasons the Work is not complete. Advise the Owner of pending insurance changeover requirements. Submit specific warranties, workmanship bonds, maintenance agreements, final certifications, and similar documents. Obtain and submit releases enabling the Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases. Submit record drawings, maintenance manuals, final project photographs, damage or settlement surveys, property surveys, and similar final record information. Deliver tools, spare parts, extra stock, and similar items. EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 1 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 7. 8. 9. 10. B. Make final changeover of permanent locks and transmit keys to the Owner. Advise the Owner's personnel of changeover in security provisions. Complete startup testing of systems and instruction of the Owner's operation and maintenance personnel. Discontinue and remove temporary facilities from the site, along with mockups, construction tools, and similar elements. Complete final cleanup requirements, including touchup painting. Touch up and otherwise repair and restore marred, exposed finishes. Inspection Procedures: On receipt of a request for inspection, the Architect will either proceed with inspection or advise the Contractor of unfilled requirements. The Architect will prepare the Certificate of Substantial Completion following inspection or advise the Contractors of construction that must be completed or corrected before the certificate will be issued. 1. 2. 1.4 NOVEMBER 19TH, 2013 The Architect will repeat inspection when requested and assured that the Work is substantially complete. Results of the completed inspection will form the basis of requirements for final acceptance. FINAL ACCEPTANCE A. Preliminary Procedures: Before requesting final inspection for certification of final acceptance and final payment, complete the following. List exceptions in the request. 1. 2. 3. 4. 5. 6. 7. B. Submit the final payment request with releases and supporting documentation not previously submitted and accepted. Include insurance certificates for products and completed operations where required. Submit an updated final statement, accounting for final additional changes to the Contract Sum. Submit a certified copy of the Architect's final inspection list of items to be completed or corrected, endorsed and dated by the Architect. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance and shall be endorsed and dated by the Architect. Submit final meter readings for utilities, a measured record of stored fuel, and similar data as of the date of Substantial Completion or when the Owner took possession of and assumed responsibility for corresponding elements of the Work. Submit consent of surety to final payment. Submit a final liquidated damages settlement statement. Submit evidence of final, continuing insurance coverage complying with insurance requirements. Re-inspection Procedure: The Architect will re-inspect the Work upon receipt of notice that the Work, including inspection list items from earlier inspections, has been completed, except for items whose completion is delayed under circumstances acceptable to the Architect. 1. 2. Upon completion of re-inspection, the Architect will prepare a certificate of final acceptance. If the Work is incomplete, the Architect will advise the Contractors of Work that is incomplete or of obligations that have not been fulfilled but are required for final acceptance. If necessary, re-inspection will be repeated, but may be chargeable to the Owner and back-chargeable to the Contractor in conditions within his control. EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 2 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.5 NOVEMBER 19TH, 2013 RECORD DOCUMENT SUBMITTALS A. General: Do not use record documents for construction purposes. Protect record documents from deterioration and loss in a secure, fire-resistant location. Provide access to record documents for the Architect's reference during normal working hours. B. Record Drawings: Maintain a clean, undamaged set of blue or black line white-prints of Contract Drawings and Shop Drawings. Mark the set to show the actual installation where the installation varies substantially from the Work as originally shown. Mark which drawing is most capable of showing conditions fully and accurately. Where Shop Drawings are used, record a cross-reference at the corresponding location on the Contract Drawings. Give particular attention to concealed elements that would be difficult to measure and record at a later date. 1. 2. 3. 4. C. Record Specifications: Maintain one complete copy of the Project Manual, including addenda. Include with the Project Manual one copy of other written construction documents, such as Change Orders and modifications issued in printed form during construction. 1. 2. 3. 4. D. Mark record sets with red erasable pencil. Use other colors to distinguish between variations in separate categories of the Work. Mark new information that is important to the Owner but was not shown on Contract Drawings or Shop Drawings. Note related change-order numbers where applicable. Organize record drawing sheets into manageable sets. Bind sets with durable-paper cover sheets; print suitable titles, dates, and other identification on the cover of each set. Mark these documents to show substantial variations in actual Work performed in comparison with the text of the Specifications and modifications. Give particular attention to substitutions and selection of options and information on concealed construction that cannot otherwise be readily discerned later by direct observation. Note related record drawing information and Product Data. Upon completion of the Work, submit record Specifications to the Architect for the Owner's records. Record Product Data: Maintain one copy of each Product Data submittal. Note related Change Orders and markup of record drawings and Specifications. 1. 2. 3. Mark these documents to show significant variations in actual Work performed in comparison with information submitted. Include variations in products delivered to the site and from the manufacturer's installation instructions and recommendations. Give particular attention to concealed products and portions of the Work that cannot otherwise be readily discerned later by direct observation. Upon completion of markup, submit complete set of record Product Data to the Architect for the Owner's records. E. Record Sample Submitted: Immediately prior to Substantial Completion, the Contractor shall meet with the Architect and the Owner's personnel at the Project Site to determine which Samples are to be transmitted to the Owner for record purposes. Comply with the Owner's instructions regarding delivery to the Owner's Sample storage area. F. Miscellaneous Record Submittals: Refer to other Specification Sections for requirements of miscellaneous record keeping and submittals in connection with actual performance of the Work. Immediately prior to the date or dates of Substantial Completion, complete miscellaneous records and place in good order. Identify miscellaneous records properly and EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 3 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 bind or file, ready for continued use and reference. Submit to the Architect for the Owner's records. G. Maintenance Manuals: Organize operation and maintenance data into suitable sets of manageable size. Bind properly indexed data in individual, heavy-duty, 2-3 inch, 3-ring, vinylcovered binders, with pocket folders for folded sheet information. Mark appropriate identification on front and spine of each binder. Include the following types of information: 1. Emergency instructions. 2. Spare parts list. 3. Copies of warranties. 4. Wiring diagrams. 5. Recommended "turn-around" cycles. 6. Inspection procedures. 7. Shop Drawings and Product Data. 8. Fixture lamping schedule. H. Waivers, guarantees, certification letters, AIA documents, etc.: See checklist attachment at the end of this section PART 2 - PRODUCTS 2.1 MATERIALS A. General: Comply with requirements specified in other Sections. B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible. 1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Architect for the visual and functional performance of in-place materials. PART 3 - EXECUTION 3.1 CLOSEOUT PROCEDURES A. Operation and Maintenance Instructions: Arrange for each Installer of equipment that requires regular maintenance to meet with the Owner's personnel to provide instruction in proper operation and maintenance. Provide instruction by manufacturer's representatives if installers are not experienced in operation and maintenance procedures. Include a detailed review of the following items: 1. Maintenance manuals. 2. Record documents. 3. Spare parts and materials. 4. Tools. 5. Lubricants. EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 4 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 6. 7. 8. 9. 10. 11. 12. NOVEMBER 19TH, 2013 Fuels. Identification systems. Control sequences. Hazards. Cleaning. Warranties and bonds. Maintenance agreements and similar continuing commitments. B. As part of instruction for operating equipment, demonstrate the following procedures: 1. Startup. 2. Shutdown. 3. Emergency operations. 4. Noise and vibration adjustments. 5. Safety procedures. 6. Economy and efficiency adjustments. 7. Effective energy utilization. C. Record "As-Built" Drawings 3.2 1. Upon completion of the work, and review of the record drawings by the Architect, prepare a final set of record drawings using reproducible mylar or vellum. Submit final set of transparencies to Contractor and Architect. 2. The cost of furnishing above prints and preparing these record drawings shall be included in the contract price FINAL CLEANING A. General: The General Conditions require general cleaning during construction. Regular site cleaning is included in Division 1 Section "Facilities and Temporary Controls." B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to the condition expected in a normal, commercial building cleaning and maintenance program. Comply with manufacturer's instructions. 1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion. a. Remove labels that are not permanent labels. b. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other substances that are noticeable visionobscuring materials. Replace chipped or broken glass and other damaged transparent materials. c. Clean exposed exterior and interior hard-surfaced finishes to a dust-free condition, free of stains, films, and similar foreign substances. Restore reflective surfaces to their original condition. Leave concrete floors broom clean. Vacuum carpeted surfaces. EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 5 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 d. Wipe surfaces of mechanical and electrical equipment. Remove excess lubrication and other substances. Clean plumbing fixtures to a sanitary condition. Clean light fixtures and lamps. e. Clean the site, including landscape development areas, of rubbish, litter, and other foreign substances. Sweep paved areas broom clean; remove stains, spills, and other foreign deposits. Rake grounds that are neither paved nor planted to a smooth, even-textured surface. C. Pest Control: Engage an experienced, licensed exterminator to make a final inspection and rid the Project of rodents, insects, and other pests. D. Removal of Protection: Remove temporary protection and facilities installed for protection of the Work during construction. E. Compliance: Comply with regulations of authorities having jurisdiction and safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on the Owner's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from the site and dispose of lawfully. 1. 3.3 Where extra materials of value remain after completion of associated Work, they become the Owner's property. Dispose of these materials as directed by the Owner. DEMONSTRATION AND TRAINING A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. Include a detailed review of the following: 1. 3.4 Include instruction for basis of system design and operational requirements, review of documentation, emergency procedures, operations, adjustments, troubleshooting, maintenance, and repairs. SUBSTANTIAL COMPLETION A. Preliminary Procedures: Before requesting inspection for certification of Substantial Completion, complete the following. List exceptions in the request. 1. In the Application for Payment that coincides with, or first follows, the date Substantial Completion is claimed, show 100 percent completion for the portion of the Work claimed as substantially complete. a. b. c. d. Include supporting documentation for completion as indicated in these Contract Documents and a statement showing an accounting of changes to the Contract Sum. If 100 percent completion cannot be shown, include a list of incomplete items, the value of incomplete construction, and reasons the Work is not complete. Advise the Owner of pending insurance changeover requirements. Submit specific warranties, workmanship bonds, maintenance agreements, final certifications, and similar documents. EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 6 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 e. f. g. h. i. j. k. B. Obtain and submit releases enabling the Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases. Submit record drawings, maintenance manuals, final project photographs, damage or settlement surveys, property surveys, and similar final record information. Deliver tools, spare parts, extra stock, and similar items. Make final changeover of permanent locks and transmit keys to the Owner. Advise the Owner's personnel of changeover in security provisions. Complete startup testing of systems and instruction of the Owner's operation and maintenance personnel. Discontinue and remove temporary facilities from the site, along with mockups, construction tools, and similar elements. Complete final cleanup requirements, including touchup painting. Touch up and otherwise repair and restore marred, exposed finishes. Inspection Procedures: On receipt of a request for inspection, the Architect will either proceed with inspection or advise the Contractor of unfilled requirements. The Architect will prepare the Certificate of Substantial Completion following inspection or advise the Contractor of construction that must be completed or corrected before the certificate will be issued. 1. 2. 3.5 NOVEMBER 19TH, 2013 The Architect will repeat inspection when requested and assured that the Work is substantially complete. Results of the completed inspection will form the basis of requirements for final acceptance FINAL ACCEPTANCE A. Preliminary Procedures: Before requesting final inspection for certification of final acceptance and final payment, complete the following. List exceptions in the request. 1. 2. 3. 4. 5. 6. 7. B. Submit the final payment request with releases and supporting documentation not previously submitted and accepted. Include insurance certificates for products and completed operations where required. Submit an updated final statement, accounting for final additional changes to the Contract Sum. Submit a certified copy of the Architect's final inspection list of items to be completed or corrected, endorsed and dated by the Architect. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance and shall be endorsed and dated by the Architect. Submit final meter readings for utilities, a measured record of stored fuel, and similar data as of the date of Substantial Completion or when the Owner took possession of and assumed responsibility for corresponding elements of the Work. Submit consent of surety to final payment. Submit a final liquidated damages settlement statement. Submit evidence of final, continuing insurance coverage complying with insurance requirements. Re-inspection Procedure: The Architect will re-inspect the Work upon receipt of notice that the Work, including inspection list items from earlier inspections, has been completed, except for items whose completion is delayed under circumstances acceptable to the Architect. 1. Upon completion of re-inspection, the Architect will prepare a certificate of final acceptance. If the Work is incomplete, the Architect will advise the Contractor of Work that is incomplete or of obligations that have not been fulfilled but are required for final acceptance. EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 7 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. 3.6 NOVEMBER 19TH, 2013 If necessary, re-inspection will be repeated, but may be chargeable to the Owner and back-chargeable to the Contractor in conditions within his control. RECORD DOCUMENT SUBMITTALS A. General: Do not use record documents for construction purposes. Protect record documents from deterioration and loss in a secure, fire-resistant location. Provide access to record documents for the Architect's reference during normal working hours. B. Record Drawings: Maintain a clean, undamaged set of blue or black line white-prints of Contract Drawings and Shop Drawings. Mark the set to show the actual installation where the installation varies substantially from the Work as originally shown. Mark which drawing is most capable of showing conditions fully and accurately. Where Shop Drawings are used, record a cross-reference at the corresponding location on the Contract Drawings. Give particular attention to concealed elements that would be difficult to measure and record at a later date. 1. 2. 3. 4. C. Record Specifications: Maintain one complete copy of the Project Manual, including addenda. Include with the Project Manual one copy of other written construction documents, such as Change Orders and modifications issued in printed form during construction. 1. 2. 3. 4. D. Mark these documents to show substantial variations in actual Work performed in comparison with the text of the Specifications and modifications. Give particular attention to substitutions and selection of options and information on concealed construction that cannot otherwise be readily discerned later by direct observation. Note related record drawing information and Product Data. Upon completion of the Work, submit record Specifications to the Architect for the Owner's records. Record Product Data: Maintain one copy of each Product Data submittal. Note related Change Orders and markup of record drawings and Specifications. 1. 2. 3. E. Mark record sets with red erasable pencil. Use other colors to distinguish between variations in separate categories of the Work. Mark new information that is important to the Owner but was not shown on Contract Drawings or Shop Drawings. Note related change-order numbers where applicable. Organize record drawing sheets into manageable sets. Bind sets with durable-paper cover sheets; print suitable titles, dates, and other identification on the cover of each set. Mark these documents to show significant variations in actual Work performed in comparison with information submitted. Include variations in products delivered to the site and from the manufacturer's installation instructions and recommendations. Give particular attention to concealed products and portions of the Work that cannot otherwise be readily discerned later by direct observation. Upon completion of markup, submit complete set of record Product Data to the Architect for the Owner's records. Record Sample Submitted: Immediately prior to Substantial Completion, the Contractor shall meet with the Architect and the Owner's personnel at the Project Site to determine which Samples are to be transmitted to the Owner for record purposes. Comply with the Owner's instructions regarding delivery to the Owner's Sample storage area. EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 8 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 F. Miscellaneous Record Submittals: Refer to other Specification Sections for requirements of miscellaneous record keeping and submittals in connection with actual performance of the Work. Immediately prior to the date or dates of Substantial Completion, complete miscellaneous records and place in good order. Identify miscellaneous records properly and bind or file, ready for continued use and reference. Submit to the Architect for the Owner's records. G. Maintenance Manuals: Organize operation and maintenance data into suitable sets of manageable size. Bind properly indexed data in individual, heavy-duty, 2-3 inch, 3-ring, vinylcovered binders, with pocket folders for folded sheet information. Mark appropriate identification on front and spine of each binder. Include the following types of information: 1. Emergency instructions. 2. Spare parts list. 3. Copies of warranties. 4. Wiring diagrams. 5. Recommended “turn-around” cycles. 6. Inspection procedures. 7. Shop Drawings and Product Data. 8. Fixture lamping schedule. H. Waivers, guarantees, certification letters, AIA documents, etc.: See checklist attachment at the end of this section. 3.7 CLOSEOUT CHECKLIST A. See attached checklist for required wage & supplements, lien release, guarantee / warranties, etc. END OF SECTION 01 7700 EXECUTION AND CLOSEOUT REQUIREMENTS 01 7700 - 9 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 7701 –CHECKLIST FOR PROJECT CLOSEOUT AND PROCESSING OF FINAL PAYMENT PART 1 - GENERAL 1.1 Final payment will not be processed until all items indicated are received in accordance with Section 017700 - EXECUTION AND CLOSEOUT REQUIREMENTS. 1.2 CLOSEOUT SUBMITTALS: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 1.3 [ ] Wage & Supplements Verification Form. [ ] Three (3) bound, hard cover, 3-ring binder brochures of Operation and Maintenance. Manuals for all equipment installed on the project: [ ] Typed or printed instructions covering the care and operations of equipment and systems furnished and installed. [ ] Manufacturers instruction books, diagrams, spare parts lists covering all equipment. [ ] Instruction of Owner’s Representative in care and maintenance of new equipment. [ ] All approved shop drawings. [ ] Certificates of compliance and inspection. [ ] Spare parts and Maintenance Materials. [ ] Evidence of compliance with requirements of governing authorities (Certificates of Inspection B Electrical). [ ] Certificates of insurance for products and completed operations. [ ] Notarized statement that only non-asbestos materials were installed on this project. [ ] Fully executed certificate of substantial completion: AIA G704. [ ] Contractor’s written one-year warranty and extended warranties (if any required). [ ] Project Record Documents: Section 01 7839. [ ] As-Built Drawings. EVIDENCE OF PAYMENT AND RELEASE OF LIENS: 1. 2. 3. 4. 5. [ ] Contractor’s Affidavit of Payment of Debts and Claims: AIA G706. [ ] Contractor’s Affidavit of Release of Liens - AIA G706A with: [ ] Separate written releases of waivers and liens for subcontractors, suppliers, and others with lien rights against the property of owner, together with a list of those parties. [ ] Contractor’s written release or waiver of lien upon payment to the Contractor pursuant to Connecticut State lien law. [ ] Consent of Surety to Final Payment: AIA G707. END OF SECTION 01 7701 CHECKLIST FOR PROJECT CLOSEOUT AND PROCESSING OF FINAL PAYMENT 01 7701 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 7823 – OPERATION AND MAINTENANCE DATA 1.1 SUMMARY A. 1.2 Operation and Maintenance Manuals. PRODUCTS A. Format: 1. 2. PDF electronic files with composite electronic index on digital media acceptable to Architect. Include a complete electronically linked operation and maintenance directory. Heavy-duty, three-ring, vinyl-covered, loose-leaf binders, 3 COMPLETE set(s) of copies. B. Emergency Manuals: procedures. Types of emergencies, emergency instructions, and emergency C. Operation Manuals: System, subsystem, and equipment descriptions, operating procedures, wiring diagrams, control diagrams and sequence of operation, and piped system diagrams. D. Product Maintenance Manuals: Source information, product information, maintenance procedures, repair materials and sources, and warranties and bonds. E. Systems and Equipment Maintenance Manuals: Source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranties and bonds. END OF SECTION 01 7823 OPERATION AND MAINTENANCE DATA 01 7823 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 01 7839 – PROJECT RECORD DOCUMENTS 1.1 PRODUCTS A. Record Drawings: 1. PDF electronic files of scanned record prints and three set(s) of prints. B. Record Specifications: One paper copy and Annotated PDF electronic files. C. Record Product Data: One paper copy and Annotated PDF electronic files and directories. D. Miscellaneous Record Submittals: One paper copy and Annotated PDF electronic files and directories. 1.2 PRODUCTS A. Record Prints: One set of paper copies of Contract Documents and Shop Drawings, marked to show actual installation. B. Record Digital Data Files: Corrected digital data files of the Contract Drawings, as follows: 1. 2. Format: Same as the original Contract Drawings. Format: Annotated PDF electronic file. END OF SECTION 01 7839 PROJECT RECORD DOCUMENTS 01 7839 - 1 of 1 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 02 4119 – SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. 2. 3. B. Related Sections: The following Sections contain requirements that relate to this Section: 1. 2. 3. 4. 5. C. 1.3 Demolition and removal of selected portions of a building. Demolition and removal of selected site elements. Patching and repairs. Division 1 Section "Summary of Work" for use of the building and phasing requirements. Division 1 Section "Cutting and Patching" for additional cutting and patching procedures for selective demolition operations. Division 1 Section "Facilities and Temporary Controls" for temporary utilities, temporary construction and support facilities, temporary security and protection facilities, and environmental protection measures for selective demolition operations. Division 1 Section "Execution and Closeout Requirements" for record document requirements. Division 6 Section "Rough Carpentry" for material and construction requirements for temporary enclosures. Contractor is responsible for all selective demolition of work specifically affecting their work. DEFINITIONS A. Remove: Remove and legally dispose of items except those indicated to be reinstalled, salvaged, or to remain the Owner's property. B. Remove and Salvage: Items indicated to be removed and salvaged remain the Owner's property. Remove, clean, and pack or crate items to protect against damage. Identify contents of containers and deliver to Owner's designated storage area. Equipment to be salvaged for reinstallation shall be inspected by the Owner’s representative prior to removal and conditions of said items will be recorded by the owner’s representative. C. Remove and Reinstall: Remove items indicated; clean, service, and otherwise prepare them for reuse; store and protect against damage. Reinstall items in the same locations or in locations indicated. D. Existing to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by the Architect, items may be removed to a suitable, protected storage location during selective demolition and then cleaned and reinstalled in their original locations. SELECTIVE STRUCTURE DEMOLITION 02 4119 - 1 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.4 NOVEMBER 19TH, 2013 MATERIALS OWNERSHIP A. 1.5 Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain the Owner's property, demolished materials shall become the Contractor's property and shall be removed from the site with further disposition at the Contractor's option. SUBMITTALS A. General: Submit each item in this Article according to the Conditions of the Contract and Division 1 Specification Sections, for information only, unless otherwise indicated. B. Proposed dust-control measures. C. Proposed noise-control measures. D. Schedule of selective demolition activities indicating the following: 1. 2. 3. 4. 5. 6. 7. 8. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Interruption of utility services. Coordination for shutoff, capping, and continuation of utility services. Use of elevator and stairs. Detailed sequence of selective demolition and removal work to ensure uninterrupted progress of Owner's on-site operations. Coordination of Owner's continuing occupancy of portions of existing building and of Owner's partial occupancy of completed Work. Locations of temporary partitions and means of egress. Coordination with demolition procedures or work of other contractors E. Inventory of items to be removed and salvaged. F. Inventory of items to be removed by Owner. G. Photographs or videotape, sufficiently detailed, of existing conditions of adjoining construction and site improvements that might be misconstrued as damage caused by selective demolition operations. Contractor assumes complete liability for all undocumented conditions. H. Record drawings at Project closeout according to Division 1 Section "Contract Closeout." Final payment will not be approved until all closeout documentation is properly prepared and submitted to the Owner and Architect. 1. Identify and accurately locate capped utilities and other subsurface structural, electrical, or mechanical conditions. I. Landfill records indicating receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes. J. Drawings and calculations showing temporary needle beams and shoring. Calculations and drawings shall be prepared and sealed by a Professional Engineer registered in New York State. Each contractor is responsible for their work. SELECTIVE STRUCTURE DEMOLITION 02 4119 - 2 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 06 1000 – ROUGH CARPENTRY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. 2. B. 1.3 Framing with dimension lumber. Miscellaneous wood furring, grounds, nailers, and blocking. Related Sections: The following Sections contain requirements that relate to this Section DEFINITIONS A. Rough Carpentry: Carpentry work not specified in other Sections and not exposed, unless otherwise specified. B. Exposed Framing: Dimension lumber not concealed by other construction and indicated to receive a stained or natural finish. 1.4 SUBMITTALS A. General: Submit each item in this Article according to the Conditions of the Contract and Division 1 Specification Sections. B. Product Data for the following products: 1. Metal framing anchors (if used). 2. Construction adhesives. C. Material certificates for dimension lumber specified to comply with minimum allowable unit stresses. Indicate species and grade selected for each use and design values approved by the American Lumber Standards Committee's (ALSC) Board of Review. D. Wood treatment data as follows, including chemical treatment manufacturer's instructions for handling, storing, installing, and finishing treated materials: 1. For each type of preservative-treated wood product, include certification by treating plant stating type of preservative solution and pressure process used, net amount of preservative retained, and compliance with applicable standards. 2. For waterborne-treated products, include statement that moisture content of treated materials was reduced to levels indicated before shipment to Project site. 3. For fire-retardant-treated wood products, include certification by treating plant that treated materials comply with specified standard and other requirements as well as data relative to bending strength, stiffness, and fastener-holding capacities of treated materials. E. Material test reports from a qualified independent testing agency indicating and interpreting test results relative to compliance of fire-retardant-treated wood products with requirements indicated. ROUGH CARPENTRY 06 1000 - 1 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 F. Warranty of chemical treatment manufacturer for each type of treatment. G. Research or evaluation reports of the model code organization acceptable to authorities having jurisdiction that evidence the following products' compliance with building code in effect for Project. 1. Metal framing anchors (if any). 2. Power-driven fasteners. 3. Fire-retardant-treated wood (if any). 1.5 QUALITY ASSURANCE A. 1.6 A. Single-Source Responsibility for Fire-Retardant-Treated Wood (if any): Obtain each type of fire-retardant-treated wood product from one source and by a single producer. DELIVERY, STORAGE, AND HANDLING A. Keep materials under cover and dry. Protect from weather and contact with damp or wet surfaces. Stack lumber, plywood, and other panels. Provide for air circulation within and around stacks and under temporary coverings. 1. For lumber and plywood pressure treated with waterborne chemicals, place spacers between each bundle to provide air circulation. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. 2.2 Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Wood-Preservative-Treated Materials: a. Baxter: J. H. Baxter Co. b. Chemical Specialties, Inc. c. Continental Wood Preservers, Inc. d. Hickson Corp. e. Hoover Treated Wood Products, Inc. f. Osmose Wood Preserving, Inc. 2. Fire-Retardant-Treated Materials, Interior Type A: a. Baxter: J. H. Baxter Co. b. Chemical Specialties, Inc. c. Continental Wood Preservers, Inc. d. Hickson Corp. e. Hoover Treated Wood Products, Inc. 3. Laminated-Veneer Lumber: a. Alpine Structures. b. Boise Cascade Corp. c. Georgia-Pacific Corp. d. Louisiana-Pacific Corp. e. Trus Joist MacMillan. f. Willamette Industries, Inc. LUMBER, GENERAL A. Lumber Standards: Comply with DOC PS 20, "American Softwood Lumber Standard," and with applicable grading rules of inspection agencies certified by ALSC's Board of Review. ROUGH CARPENTRY 06 1000 - 2 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Inspection Agencies: Inspection agencies, and the abbreviations used to reference them, include the following: 1. NELMA - Northeastern Lumber Manufacturers Association. 2. SPIB - Southern Pine Inspection Bureau. 3. WCLIB - West Coast Lumber Inspection Bureau. 4. WWPA - Western Wood Products Association. C. Grade Stamps: Provide lumber with each piece factory marked with grade stamp of inspection agency evidencing compliance with grading rule requirements and identifying grading agency, grade, species, moisture content at time of surfacing, and mill. 1. For exposed lumber, furnish pieces with grade stamps applied to ends or back of each piece, or omit grade stamps and provide grade-compliance certificates issued by inspection agency. D. Where nominal sizes are indicated, provide actual sizes required by DOC PS 20 for moisture content specified. Where actual sizes are indicated, they are minimum dressed sizes for dry lumber. 1. Provide dressed lumber, S4S, unless otherwise indicated. 2. Provide dry lumber with 19 percent maximum moisture content at time of dressing for 2inch nominal thickness or less, unless otherwise indicated. 2.3 WOOD-PRESERVATIVE-TREATED MATERIALS A. General: Where lumber or plywood is indicated as preservative treated or is specified to be treated, comply with applicable requirements of AWPA C2 (lumber) and AWPA C9 (plywood). Mark each treated item with the Quality Mark Requirements of an inspection agency approved by ALSC's Board of Review. 1. Do not use chemicals containing chromium or arsenic. B. Pressure treat aboveground items with waterborne preservatives to a minimum retention of 0.25 lb/cu. ft. After treatment, kiln-dry lumber and plywood to a maximum moisture content of 19 and 15 percent, respectively. Treat indicated items and the following: 1. Wood cants, nailers, curbs, equipment support bases, blocking, stripping, and similar members in connection with roofing, flashing, vapor barriers, and waterproofing. 2. Wood sills, sleepers, blocking, furring, stripping, and similar concealed members in contact with masonry or concrete. 3. Wood framing members less than 18 inches above grade. 4. Wood floor plates installed over concrete slabs directly in contact with earth. C. Complete fabrication of treated items before treatment, where possible. If cut after treatment, apply field treatment complying with AWPA M4 to cut surfaces. Inspect each piece of lumber or plywood after drying and discard damaged or defective pieces. 2.4 FIRE-RETARDANT-TREATED MATERIALS A. General: Where fire-retardant-treated wood is indicated, comply with applicable requirements of AWPA C20 (lumber) and AWPA C27 (plywood). Identify fire-retardant-treated wood with appropriate classification marking of UL; U.S. Testing; Timber Products Inspection, Inc.; or another testing and inspecting agency acceptable to authorities having jurisdiction. 1. Research or Evaluation Reports: Provide fire-retardant-treated wood acceptable to authorities having jurisdiction and for which a current model code research or evaluation report exists that evidences compliance of fire-retardant-treated wood for application indicated. ROUGH CARPENTRY 06 1000 - 3 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Interior Type A: For interior locations, use chemical formulation that produces treated lumber and plywood with the following properties under conditions present after installation: 1. Bending strength, stiffness, and fastener-holding capacities are not reduced below values published by manufacturer of chemical formulation under elevated temperature and humidity conditions simulating installed conditions when tested by a qualified independent testing agency. 2. No form of degradation occurs due to acid hydrolysis or other causes related to treatment. 3. Contact with treated wood does not promote corrosion of metal fasteners. C. Inspect each piece of treated lumber or plywood after drying and discard damaged or defective pieces. 2.5 DIMENSION LUMBER A. General: Provide dimension lumber of grades indicated according to the ALSC National Grading Rule (NGR) provisions of the inspection agency indicated. B. Provide framing of the following grade and species: 1. For structural vertical framing (2 to 4 inches thick, 2 to 4 inches wide): a. Hem Fir No. 2 or better 2. For structural horizontal framing (2 to 4 inches thick, 5 inches and wider): a. Southern yellow pine #2 Grade, 1400 psi bending stress. 2.6 MISCELLANEOUS LUMBER A. General: Provide lumber for support or attachment of other construction, including rooftop equipment curbs and support bases, cant strips, bucks, nailers, blocking, furring, grounds, stripping, and similar members. B. Fabricate miscellaneous lumber from dimension lumber of sizes indicated and into shapes shown. C. Moisture Content: 19 percent maximum for lumber items not specified to receive wood preservative treatment. D. Grade: For dimension lumber sizes, provide No. 3 or Standard grade lumber per ALSC's NGRs of any species. For board-size lumber, provide No. 3 Common grade per NELMA, NLGA, or WWPA; No. 2 grade per SPIB; or Standard grade per NLGA, WCLIB or WWPA of any species. 2.7 FASTENERS A. General: Provide fasteners of size and type indicated that comply with requirements specified in this Article for material and manufacture. 1. Where rough carpentry is exposed to weather, in ground contact, or in area of high relative humidity, provide fasteners with a hot-dip zinc coating per ASTM A 153 or of Type 304 stainless steel. B. Nails, Wire, Brads, and Staples: FS FF-N-105. C. Power-Driven Fasteners: CABO NER-272. D. Wood Screws: ASME B18.6.1. ROUGH CARPENTRY 06 1000 - 4 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 E. Lag Bolts: ASME B18.2.1. F. Bolts: Steel bolts complying with ASTM A 307, Grade A; with ASTM A 563 hex nuts and, where indicated, flat washers. 2.8 MISCELLANEOUS MATERIALS A. 2.9 Adhesives for Field Gluing Panels to Framing: Formulation complying with APA AFG-01 that is approved for use with type of construction panel indicated by both adhesive and panel manufacturers. PRESERVATIVE WOOD TREATMENT BY PRESSURE PROCESS: A. General: Where lumber or plywood is indicated as treated or preservative-treated wood or is specified herein to be treated, comply with applicable requirements of AWPA Standards C2 (Lumber) and C9 (Plywood). Mark each treated item with the AWPB or SPIB Quality Mark Requirements. B. Pressure-treat above-ground items with water-borne preservatives to a minimum retention of 0.25 pcf. For interior uses, after treatment, kiln-dry lumber and plywood to a maximum moisture content, respectively, of 19 percent and 15 percent. Treat indicated items and the following: 1. Wood cants, nailers, curbs, equipment support bases, blocking, stripping, and similar members in connection with roofing, flashing and vapor barriers. 2. Wood sills, sleepers, blocking, furring, stripping, and similar concealed members in contact with concrete. 3. Wood framing members less than 18 inches above grade. 4. Wood floor plates installed over concrete slabs directly in contact with earth. C. Pressure-treat wood members in contact with the ground or fresh water with water-borne preservatives to a minimum retention of 0.40 pcf. D. Complete fabrication of treated items prior to treatment, where possible. If cut after treatment, coat cut surfaces to comply with AWPA M4. Inspect each piece of lumber or plywood after drying and discard damaged or defective pieces. PART 3 - PRODUCTS 3.1 INSTALLATION, GENERAL A. Discard units of material with defects that impair quality of rough carpentry and that are too small to use with minimum number of joints or optimum joint arrangement. B. Set rough carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. C. Fit rough carpentry to other construction; scribe and cope as required for accurate fit. Correlate location of furring, nailers, blocking, grounds, and similar supports to allow attachment of other construction. D. Apply field treatment complying with AWPA M4 to cut surfaces of preservative-treated lumber and plywood. ROUGH CARPENTRY 06 1000 - 5 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 E. Securely attach rough carpentry work to substrate by anchoring and fastening as indicated, complying with the following: 1. CABO NER-272 for power-driven staples, P-nails, and allied fasteners. 2. Published requirements of metal framing anchor manufacturer. 3. "Recommended Nailing Schedule" of referenced framing standard and with AFPA's "National Design Specifications for Wood Construction." 4. "Table 2305.2--Fastening Schedule" of the BOCA National Building Code. F. Use common wire nails, unless otherwise indicated. Use finishing nails for finish work. Select fasteners of size that will not fully penetrate members where opposite side will be exposed to view or will receive finish materials. Make tight connections between members. Install fasteners without splitting wood; predrill as required. G. Use hot-dip galvanized or stainless-steel nails where rough carpentry is exposed to weather, in ground contact, or in area of high relative humidity. H. Countersink nail heads on exposed carpentry work and fill holes with wood filler. 3.2 WOOD GROUNDS, NAILERS, BLOCKING, AND SLEEPERS A. Install wood grounds, nailers, blocking, and sleepers where shown and where required for screeding or attaching other work. Form to shapes shown and cut as required for true line and level of attached work. Coordinate locations with other work involved. B. Attach to substrates to support applied loading. Recess bolts and nuts flush with surfaces, unless otherwise indicated. Build into masonry during installation of masonry work. Where possible, anchor to formwork before concrete placement. 3.3 INSTALLATION A. General: Install gypsum sheathing to comply with GA-253 and manufacturer’s written instructions. B. Cut boards at penetrations, edges and other obstructions of the work; fit tightly against abutting construction, except provide a d-inch (9 mm) setback where non-load-bearing construction abuts structural elements. C. Coordinate sheathing installation with flashing and joint sealant installation so these materials are installed in the sequence and manner that prevent exterior moisture from passing through completed exterior wall assembly. D. Apply fasteners so screw heads bear tightly against face of sheathing boards but do not cut into facing. E. Do not bridge building expansion joints with sheathing; cut and space edges to match spacing of structural support elements. 3.4 PROTECTION A. Protect paper-surfaced gypsum sheathing and sheathing tape that will be exposed to weather for more than 30days by covering exposed exterior surface of sheathing with a securely fastened air-infiltration barrier. Apply covering immediately after sheathing is installed. ROUGH CARPENTRY 06 1000 - 6 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.5 NOVEMBER 19TH, 2013 SECTION REQUIREMENTS A. Submittals: ICC-ES evaluation reports for [wood-preservative treated wood] [fire-retardant treated wood] [engineered wood products] [and] [metal framing anchors]. END OF SECTION 06 1000 ROUGH CARPENTRY 06 1000 - 7 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 07 4700 – ALUMINUM SOFFIT PANELS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. B. 1.3 The extent of aluminum soffit panels depicted on the drawings. Related Sections: The following Sections contain requirements that relate to this Section 1. Section 07 9200 – Joint Protection 2. Section 08 4523 – Insulated Fiberglass Wall System DEFINITIONS A. 1.4 Rough Carpentry: Carpentry work not specified in other Sections and not exposed, unless otherwise specified. SUBMITTALS A. General: Submit each item in this Article according to the Conditions of the Contract and Division 1 Specification Sections. B. Product Data for the following products: 1. Metal framing anchors (if used). 2. Construction adhesives. C. Selection Samples: Submit color chips of manufacturer’s full range of colors for Architects selection. 1.5 QUALITY ASSURANCE A. Regulatory Requirements: Provide products that comply with the following: 1. 1.6 International Conference of Building Officials (ICBO) Report No. 1478. DELIVERY, STORAGE, AND HANDLING A. Deliver products to project site in original packaging. 1. Store products in original packaging, on flat surface under cover, stacked no more than 12 boxes high. ALUMINUM SOFFIT PANELS 07 4700 - 1 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 PART 2 - PRODUCTS 2.1 MANUFACTURERS A. 2.2 Basis of Design: PAC – 850 Full Vent as manufactured by: Petersen Aluminum Corporation, 1005 Tonne Road, Elk Grove Village, IL 60007 ALUMINUM SOFFIT PANELS A. Aluminum Soffit Panels: 1. 2.3 Style: 12” o.c. Soffit Flush Panels full vented a. Thickness: Nominal 0.04”; aluminum alloy 3105-H14 b. Interlocking edges and elongated nailing hems 2. Finish: Match existing finish to rest of building. 3. Color: Match existing color to rest of building. ACCESSORIES A. General: Flashing and Trim Aluminum of same thickness, finish, and color as soffit. 1. Provide ‘J’ channel color to match soffit 2. Fascia to soffit flashing PA-305. PART 3 - PRODUCTS 3.1 EXAMINATION A. Examine substrate conditions before beginning installation of soffit products; verify dimensions and acceptability of substrate. 1. 3.2 Do not proceed with installation until unacceptable conditions have been corrected. INSTALLATION A. 3.3 In accordance with manufacturers printed and written instructions. 1. Attach panels to substrate interlocked and lapped for weathertight installation, fasteners concealed. 2. Paint or otherwise protect dissimilar metals in contact. 3. Installation of joint sealers is specified in 07 9200. CLEANING A. Clean dirt from surface of installed products, using mild soap and water. 1. After completing the installation, remove from project site excess materials and debris resulting from installation. END OF SECTION 07 4700 ALUMINUM SOFFIT PANELS 07 4700 - 2 of 2 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 07 62 00 - SHEET METAL FLASHING AND TRIM PART 1 - GENERAL 1.1 A. 1.2 A. RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY The Work of this Section consists of the provision of all plant, labor, materials, equipment, testing and services necessary to complete the work for sheet metal flashings, trims and roof specialties as shown on the schedules, keynotes, drawings, as specified herein, and as may be required by conditions and authorities having jurisdiction, including, but not limited to, the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. B. Related Requirements: 1. 2. 3. 4. 5. 1.3 Manufactured through-wall flashing with counterflashing. Manufactured reglets with counterflashing. Formed roof-drainage sheet metal fabrications. Formed low-slope roof sheet metal fabrications Entry Canopy Roof Sheet Metal Fabrications. Formed wall sheet metal fabrications. Formed copings and roof edge flashing. Reglets and counterflashing. Formed equipment support flashing. Formed overhead-piping safety pans. Section 061000 "Rough Carpentry" for wood nailers, curbs, and blocking. Section 075216 "Styrene-Butadiene-Styrene (SBS) Modified Bituminous Membrane Roofing” for materials and installation of sheet metal flashing and trim integral with roofing Section 077200 "Roof Accessories" for set-on-type curbs, equipment supports, roof hatches, vents, and other manufactured roof accessory units Section 079200 “Joint Sealants” for field-applied sealants between roof specialties and adjacent materials. Section 221006 “Plumbing Piping Specialties” for roof drains. COORDINATION A. Coordinate sheet metal flashing and trim layout and seams with sizes and locations of penetrations to be flashed, and joints and seams in adjacent materials. B. Coordinate sheet metal flashing and trim installation with adjoining roofing and wall materials, joints, and seams to provide leakproof, secure, and noncorrosive installation. SHEET METAL FLASHING AND TRIM 07 62 00 - 1 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.4 NOVEMBER 19TH, 2013 PRE-INSTALLATION MEETINGS A. Pre-installation Conference: Conduct conference at Project site. 1. 2. 3. 4. 1.5 A. ACTION SUBMITTALS Product Data: For each type of product. 1. B. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for each manufactured product and accessory. LEED Submittals: 1. 2. C. Review construction schedule. Verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays. Review special roof details, roof drainage, roof-penetration flashing, equipment curbs, and condition of other construction that affect sheet metal flashing and trim. Review requirements for insurance and certificates if applicable. Review sheet metal flashing observation and repair procedures after flashing installation. Product Data for Credit MR 4: For products having recycled content, documentation indicating percentages by weight of postconsumer and preconsumer recycled content. Include statement indicating cost for each product having recycled content. Credit MR 5: Product data for regional materials indicating location and distance from Project of material manufacturer and point of extraction, harvest, or recovery for each raw material. Include statement indicating unit cost and total cost for each regional material and the fraction by weight that is considered regional. Shop Drawings: For sheet metal flashing and trim. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Include plans, elevations, sections, and attachment details. Detail fabrication and installation layouts, expansion-joint locations, and keyed details. Distinguish between shop- and field-assembled work. Include identification of material, thickness, weight, and finish for each item and location in Project. Include details for forming, including profiles, shapes, seams, and dimensions. Include details for joining, supporting, and securing, including layout and spacing of fasteners, cleats, clips, and other attachments. Include pattern of seams. Include details of termination points and assemblies. Include details of expansion joints and expansion-joint covers, including showing direction of expansion and contraction from fixed points. Include details of roof-penetration flashing. Include details of edge conditions, including eaves, ridges, valleys, rakes, crickets, and counterflashings as applicable. Include details of special conditions. Include details of connections to adjoining work. Detail formed flashing and trim at scale of not less than 1-1/2 inches per 12 inches (1:10). D. Samples for Initial Selection: factory-applied finishes. E. Samples for Verification: For each type of exposed finish. SHEET METAL FLASHING AND TRIM For each type of sheet metal and accessory indicated with 07 62 00 - 2 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 2. 3. 4. 1.6 NOVEMBER 19TH, 2013 Sheet Metal Flashing: 12 inches (300 mm) long by actual width of unit, including finished seam and in required profile. Include fasteners, cleats, clips, closures, and other attachments. Trim, Metal Closures, Expansion Joints, Joint Intersections, and Miscellaneous Fabrications: 12 inches (300 mm) long and in required profile. Include fasteners and other exposed accessories. Unit-Type Accessories and Miscellaneous Materials: Full-size Sample. Anodized Aluminum Samples: Samples to show full range to be expected for each color required. INFORMATIONAL SUBMITTALS A. Qualification Data: For fabricator. B. Product Certificates: For each type of coping and roof edge flashing that is SPRI ES-1 tested and FM Approvals approved. C. Product Test Reports: For each product, for tests performed by a qualified testing agency. D. Sample Warranty: For special warranty. 1.7 A. 1.8 A. CLOSEOUT SUBMITTALS Maintenance Data: For sheet metal flashing and trim, and its accessories, to include in maintenance manuals. QUALITY ASSURANCE Fabricator Qualifications: Employs skilled workers who custom fabricate sheet metal flashing and trim similar to that required for this Project and whose products have a record of successful in-service performance. 1. B. For copings and roof edge flashings that are SPRI ES-1 tested and FM Approvals approved, shop shall be listed as able to fabricate required details as tested and approved. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for fabrication and installation. 1. 2. 3. Build mockup of typical roof edge, eave, including built-in gutter, fascia, fascia trim approximately 10 feet (3.0 m) long, including supporting construction cleats, seams, attachments, underlayment, and accessories. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion. SHEET METAL FLASHING AND TRIM 07 62 00 - 3 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.9 NOVEMBER 19TH, 2013 DELIVERY, STORAGE, AND HANDLING A. Do not store sheet metal flashing and trim materials in contact with other materials that might cause staining, denting, or other surface damage. Store sheet metal flashing and trim materials away from uncured concrete and masonry. B. Protect strippable protective covering on sheet metal flashing and trim from exposure to sunlight and high humidity, except to extent necessary for period of sheet metal flashing and trim installation. 1.10 A. WARRANTY Special Warranty on Finishes: Manufacturer agrees to repair finish or replace sheet metal flashing and trim that shows evidence of deterioration of factory-applied finishes within specified warranty period. 1. Exposed Panel Finish: Deterioration includes, but is not limited to, the following: a. b. c. 2. Color fading more than 5 Hunter units when tested according to ASTM D 2244. Chalking in excess of a No. 8 rating when tested according to ASTM D 4214. Cracking, checking, peeling, or failure of paint to adhere to bare metal. Finish Warranty Period: 20 years from date of Substantial Completion. PART 2 - PRODUCTS 2.1 PERFORMANCE REQUIREMENTS A. General: Sheet metal flashing and trim assemblies shall withstand wind loads, structural movement, thermally induced movement, and exposure to weather without failure due to defective manufacture, fabrication, installation, or other defects in construction. Completed sheet metal flashing and trim shall not rattle, leak, or loosen, and shall remain watertight. B. Sheet Metal Standard for Flashing and Trim: Comply with NRCA's "The NRCA Roofing Manuals” and SMACNA's "Architectural Sheet Metal Manual" requirements for dimensions and profiles shown unless more stringent requirements are indicated. C. FM Approvals Listing: Manufacture and install copings, roof edge flashings that are listed in FM Approvals' "RoofNav" and approved for windstorm classifications per wind classification, per jurisdiction. Identify materials with name of fabricator and design approved by FM Approvals. D. SPRI Wind Design Standard: Manufacture and install copings and roof edge flashings tested according to SPRI ES-1 and capable of resisting the following design pressure: 1. Design Pressure: As indicated on Drawings. E. Recycled Content of Steel-Sheet Flashing and Trim: Postconsumer recycled content plus onehalf of preconsumer recycled content not less than 25 percent. F. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes to prevent buckling, opening of joints, overstressing of components, failure of joint SHEET METAL FLASHING AND TRIM 07 62 00 - 4 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 sealants, failure of connections, and other detrimental effects. Base calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss. 1. 2.2 Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces. SHEET METAL A. General: Protect mechanical and other finishes on exposed surfaces from damage by applying strippable, temporary protective film before shipping. B. Metallic-Coated Steel Sheet: Provide zinc-coated (galvanized) steel sheet according to ASTM A 653/A 653M, G90 (Z275) coating designation coating designation, Grade 40 (Grade 275); prepainted by coil-coating process to comply with ASTM A 755/A 755M. 1. 2. Surface: Smooth, flat. Exposed Coil-Coated Finish: a. 3. 4. 2.3 Three-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less than 70 percent PVDF resin by weight in both color coat and clear topcoat. Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturers' written instructions. Color: As selected by Architect from manufacturer's full range. Concealed Finish: Pretreat with manufacturer's standard white or light-colored acrylic or polyester backer finish, consisting of prime coat and wash coat with minimum total dry film thickness of 0.5 mil (0.013 mm). UNDERLAYMENT A. Felt: ASTM D 226/D 226M, Type II (No. 30), asphalt-saturated organic felt; nonperforated. B. Slip Sheet: Rosin-sized building paper, 3 lb/100 sq. ft. (0.16 kg/sq. m) minimum. 2.4 MISCELLANEOUS MATERIALS A. General: Provide materials and types of fasteners, solder, protective coatings, sealants, and other miscellaneous items as required for complete sheet metal flashing and trim installation and as recommended by manufacturer of primary sheet metal or manufactured item unless otherwise indicated. B. Fasteners: Wood screws, annular threaded nails, self-tapping screws, self-locking rivets and bolts, and other suitable fasteners designed to withstand design loads and recommended by manufacturer of primary sheet metal or manufactured item. 1. General: Blind fasteners or self-drilling screws, gasketed, with hex-washer head. a. Exposed Fasteners: Heads matching color of sheet metal using plastic caps or factory-applied coating. Provide metal-backed EPDM or PVC sealing washers under heads of exposed fasteners bearing on weather side of metal. SHEET METAL FLASHING AND TRIM 07 62 00 - 5 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 b. 2. 3. C. Blind Fasteners: High-strength aluminum or stainless-steel rivets suitable for metal being fastened. c. Spikes and Ferrules: Same material as gutter; with spike with ferrule matching internal gutter width. Fasteners for Zinc-Coated (Galvanized) Steel Sheet: Series 300 stainless steel or hotdip galvanized steel according to ASTM A 153/A 153M or ASTM F 2329. Fasteners for Zinc Sheet: Series 300 stainless steel or hot-dip galvanized steel according to ASTM A 153/A 153M or ASTM F 2329. Solder: 1. For Zinc-Coated (Galvanized) Steel: ASTM B 32, Grade Sn50, 50 percent tin and 50 percent lead or Grade Sn60, 60 percent tin and 40 percent lead with maximum lead content of 0.2 percent. D. Sealant Tape: Pressure-sensitive, 100 percent solids, polyisobutylene compound sealant tape with release-paper backing. Provide permanently elastic, nonsag, nontoxic, nonstaining tape 1/2 inch (13 mm) wide and 1/8 inch (3 mm) thick. E. Elastomeric Sealant: ASTM C 920, elastomeric polymer sealant; of type, grade, class, and use classifications required to seal joints in sheet metal flashing and trim and remain watertight. F. Butyl Sealant: ASTM C 1311, single-component, solvent-release butyl rubber sealant; polyisobutylene plasticized; heavy bodied for hooked-type expansion joints with limited movement. G. Epoxy Seam Sealer: Two-part, noncorrosive, aluminum seam-cementing compound, recommended by aluminum manufacturer for exterior nonmoving joints, including riveted joints. H. Bituminous Coating: Cold-applied asphalt emulsion according to ASTM D 1187. I. Asphalt Roofing Cement: ASTM D 4586, asbestos free, of consistency required for application. 2.5 A. MANUFACTURED SHEET METAL FLASHING AND TRIM (See also Division 04) Reglets: Units of type, material, and profile required, formed to provide secure interlocking of separate reglet and counterflashing pieces, and compatible with flashing indicated with factorymitered and -welded corners and junctions and with interlocking counterflashing on exterior face, of same metal as reglet. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. b. c. d. 2. 3. Fry Reglet Corporation. Heckmann Building Products, Inc. Hickman, W. P. Company. Hohmann & Barnard, Inc. Material: Stainless steel, 0.019 inch (0.48 mm) thick. Surface-Mounted Type: Provide with slotted holes for fastening to substrate, with neoprene or other suitable weatherproofing washers, and with channel for sealant at top edge. SHEET METAL FLASHING AND TRIM 07 62 00 - 6 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 4. 5. 6. Concrete Type: Provide temporary closure tape to keep reglet free of concrete materials, special fasteners for attaching reglet to concrete forms, and guides to ensure alignment of reglet section ends. Masonry Type: Provide with offset top flange for embedment in masonry mortar joint. Accessories: a. b. 7. 2.6 A. NOVEMBER 19TH, 2013 Flexible-Flashing Retainer: Provide resilient plastic or rubber accessory to secure flexible flashing in reglet where clearance does not permit use of standard metal counterflashing or where Drawings show reglet without metal counterflashing. Counterflashing Wind-Restraint Clips: Provide clips to be installed before counterflashing to prevent wind uplift of counterflashing's lower edge. Finish: With manufacturer's standard color coating. LOW-SLOPE ROOF SHEET METAL FABRICATIONS Roof and Roof-to-Wall Transition and Expansion-Joint Cover: materials: Shop fabricate interior and exterior corners. 1. Zinc-Tin Alloy-Coated Stainless Steel: [0.024 inch (0.61 mm) thick. B. Base Flashing: Shop fabricate interior and exterior corners. C. Counterflashing: Shop fabricate interior and exterior corners. D. Flashing Receivers: Fabricate from the following materials: 1. Fabricate from the following Zinc-Tin Alloy-Coated Stainless Steel: 0.015 inch (0.38 mm) thick. E. Formed Roof-drainage Fabrications: Including built-in gutters (at canopy/overhang bands-see drawings.) F. Roof-Penetration Flashing: Fabricate from the following materials: 1. G. Roof-Drain Flashing: Fabricate from the following materials: 1. H. 2.7 A. Zinc-Tin Alloy-Coated Stainless Steel: [0.015 inch (0.38 mm)] <Insert dimension> thick. Include standard coping shapes and C-shaped metal coping - refer to exterior elevations for locations. WALL SHEET METAL FABRICATIONS Through-Wall Flashing: Fabricate continuous flashings in minimum 96-inch- (2400-mm-) long, but not exceeding 12-foot- (3.6-m-) long, sections, under copings, and at shelf angles. Fabricate discontinuous lintel, sill, and similar flashings to extend 6 inches (150 mm) beyond each side of wall openings; and form with 2-inch- (50-mm-) high, end dams. Fabricate from the following materials: 1. B. Zinc-Tin Alloy-Coated Stainless Steel: 0.018 inch (0.46 mm) thick. Zinc-Tin Alloy-Coated Stainless Steel: 0.015 inch (0.38 mm) thick. Formed Wall Fabrications: Including through-wall flashing and wall expansion-joint cover. SHEET METAL FLASHING AND TRIM 07 62 00 - 7 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 PART 3 - EXECUTION 3.1 EXAMINATION A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances, substrate, and other conditions affecting performance of the Work. 1. Verify compliance with requirements for installation tolerances of substrates. 2. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely anchored. 3. Verify that air- or water-resistant barriers have been installed over sheathing or backing substrate to prevent air infiltration or water penetration. B. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 UNDERLAYMENT INSTALLATION A. Felt Underlayment: Install felt underlayment, wrinkle free, using adhesive to minimize use of mechanical fasteners under sheet metal flashing and trim. Apply in shingle fashion to shed water, with lapped joints of not less than 2 inches (50 mm). B. Apply slip sheet, wrinkle free, per manufacture’s recommendations before installing sheet metal flashing and trim. 3.3 A. INSTALLATION, GENERAL. General: Anchor sheet metal flashing and trim and other components of the Work securely in place, with provisions for thermal and structural movement. Use fasteners, solder, protective coatings, separators, sealants, and other miscellaneous items as required to complete sheet metal flashing and trim system. 1. 2. 3. 4. 5. 6. Install sheet metal flashing and trim true to line, levels, and slopes. Provide uniform, neat seams with minimum exposure of solder, welds, and sealant. Install sheet metal flashing and trim to fit substrates and to result in watertight performance. Verify shapes and dimensions of surfaces to be covered before fabricating sheet metal. Space cleats not more than 12 inches (300 mm) apart. Attach each cleat with at least two fasteners. Bend tabs over fasteners. Install exposed sheet metal flashing and trim with limited oil canning, and free of buckling and tool marks. Torch cutting of sheet metal flashing and trim is not permitted. Do not use graphite pencils to mark metal surfaces. B. Metal Protection: Where dissimilar metals contact each other, or where metal contacts pressure-treated wood or other corrosive substrates, protect against galvanic action or corrosion by painting contact surfaces with bituminous coating or by other permanent separation as recommended by sheet metal manufacturer or cited sheet metal standard. C. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim. Space movement joints at maximum of 10 feet (3 m) with no joints within 24 inches (600 mm) of corner or intersection. SHEET METAL FLASHING AND TRIM 07 62 00 - 8 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 D. Fasteners: Use fastener sizes that penetrate substrate not less than recommended by fastener manufacturer to achieve maximum pull-out resistance. E. Conceal fasteners and expansion provisions where possible in exposed work and locate to minimize possibility of leakage. Cover and seal fasteners and anchors as required for a tight installation. F. Seal joints as required for watertight construction. 1. 2. 3.4 Use sealant-filled joints unless otherwise indicated. Embed hooked flanges of joint members not less than 1 inch (25 mm) into sealant. Form joints to completely conceal sealant. When ambient temperature at time of installation is between 40 and 70 deg F (4 and 21 deg C), set joint members for 50 percent movement each way. Adjust setting proportionately for installation at higher ambient temperatures. Do not install sealant-type joints at temperatures below 40 deg F (4 deg C). Prepare joints and apply sealants to comply with requirements in Section 079200 "Joint Sealants." ROOF FLASHING INSTALLATION A. General: Install sheet metal flashing and trim to comply with performance requirements, sheet metal manufacturer's written installation instructions, and cited sheet metal standard. Provide concealed fasteners where possible, and set units true to line, levels, and slopes. Install work with laps, joints, and seams that are permanently watertight and weather resistant. B. Roof Edge Flashing: Anchor to resist uplift and outward forces according to recommendations in FM Global Property Loss Prevention Data Sheet 1-49 for FM Approvals' listing for required windstorm classification. C. Copings: Anchor to resist uplift and outward forces according to recommendations in FM Global Property Loss Prevention Data Sheet 1-49 for specified FM Approvals' listing for required windstorm classification. D. Pipe or Post Counterflashing: Install counterflashing umbrella with close-fitting collar with top edge flared for elastomeric sealant, extending minimum of 4 inches (100 mm) over base flashing. Install stainless-steel draw band and tighten. E. Counterflashing: Coordinate installation of counterflashing with installation of base flashing. Insert counterflashing in reglets or receivers and fit tightly to base flashing. Extend counterflashing 4 inches (100 mm) over base flashing. Lap counterflashing joints minimum of 4 inches (100 mm). Secure in waterproof manner by means of snap-in installation and sealant or lead wedges and sealant unless otherwise indicated. F. Roof-Penetration Flashing: Coordinate installation of roof-penetration flashing with installation of roofing and other items penetrating roof. Seal with elastomeric sealant and clamp flashing to pipes that penetrate roof. 3.5 WALL FLASHING INSTALLATION A. General: Install sheet metal wall flashing to intercept and exclude penetrating moisture according to cited sheet metal standard unless otherwise indicated. Coordinate installation of wall flashing with installation of wall-opening components such as windows, doors, and louvers. B. Through-Wall Flashing: Installation of through-wall flashing is specified in Division 04 "Unit Masonry," and “Cast Stone.” SHEET METAL FLASHING AND TRIM 07 62 00 - 9 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.6 A. 3.7 NOVEMBER 19TH, 2013 MISCELLANEOUS FLASHING INSTALLATION Equipment Support Flashing: Coordinate installation of equipment support flashing with installation of roofing and equipment. Weld or seal flashing with elastomeric sealant to equipment support member. ERECTION TOLERANCES A. Installation Tolerances: Shim and align sheet metal flashing and trim within installed tolerance of 1/4 inch in 20 feet (6 mm in 6 m) on slope and location lines indicated on Drawings and within 1/8-inch (3-mm) offset of adjoining faces and of alignment of matching profiles. B. Installation Tolerances: Shim and align sheet metal flashing and trim within installed tolerances specified in MCA's "Guide Specification for Residential Metal Roofing." 3.8 CLEANING AND PROTECTION A. Clean exposed metal surfaces of substances that interfere with uniform oxidation and weathering. B. Clean and neutralize flux materials. Clean off excess solder. C. Clean off excess sealants. D. Remove temporary protective coverings and strippable films as sheet metal flashing and trim are installed unless otherwise indicated in manufacturer's written installation instructions. On completion of sheet metal flashing and trim installation, remove unused materials and clean finished surfaces as recommended by sheet metal flashing and trim manufacturer. Maintain sheet metal flashing and trim in clean condition during construction. E. Replace sheet metal flashing and trim that have been damaged or that have deteriorated beyond successful repair by finish touchup or similar minor repair procedures. 3.9 A. WASTE MANAGEMENT Coordinate with Section 01 74 19. 1. 2. 3. Separate and recycle cut-offs and waste materials and material packaging in accordance with Waste Management Plan and to the maximum extent economically feasible and place in designated areas for recycling. Set aside and protect materials suitable for reuse and/or remanufacturing. Separate and fold up metal banding; flatten and place along with other metal scrap for recycling in designated area. END OF SECTION 07 62 00 SHEET METAL FLASHING AND TRIM 07 62 00 - 10 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 07 8400-FIRESTOPPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 SUMMARY A. 1.3 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. Firestopping, as described herein, refers to materials or devices used to seal openings that have been made in fire-rated walls, ceilings or floors for the purpose of passing building service penetrants such as electrical conduits, electrical, data or communications cabling, plumbing or mechanical pipes, HVAC or mechanical ducting of any type. SYSTEM PERFORMANCE REQUIREMENTS A. General: Provide firestopping systems that are produced and installed to resist the spread of fire and heat according to the necessary requirements, and the passage of smoke and other gases. B. F-Rated Through-Penetration Firestop Systems: Provide through-penetration firestop systems with F ratings where required, as determined per ASTM E 814, but not less than that equaling or exceeding the fire-resistance rating of the constructions penetrated. C. T-Rated Through-Penetration Firestop Systems: Provide through-penetration firestop systems with T ratings, in addition to F ratings, as determined per ASTM E 814, where systems protect penetrating items exposed to contact with adjacent materials in occupiable floor areas. T-rated assemblies are required where the following conditions exist: 1. 2. 3. 4. Where firestop systems protect penetrations located outside of wall cavities. Where firestop systems protect penetrations located outside fire-resistive shaft enclosures. Where firestop systems protect penetrations located in construction containing doors required to have a temperature-rise rating. Where firestop systems protect penetrating items larger than a 4 inch diameter nominal pipe or 16 sq. in. in overall cross-sectional area. D. Fire-Resistive Joint Sealants: Provide joint sealants with fire-resistance ratings indicated, as determined per ASTM E 119, but not less than that equaling or exceeding the fire-resistance rating of the construction in which the joint occurs. E. For firestopping exposed to view, traffic, moisture, and physical damage, provide products that do not deteriorate when exposed to these conditions. 1. 2. F. For piping penetrations for plumbing systems, provide moisture-resistant throughpenetration firestop systems. For penetrations involving insulated piping, provide through-penetration firestop systems not requiring removal of insulation. For firestopping exposed to view, provide products with flame-spread values of less than 25 and smoke-developed values of less than 450, as determined per ASTM E 84. FIRESTOPPING 07 8400- 1 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.4 SUBMITTALS A. General: Submit the following according to Conditions of Contract and Division 1 Specification Sections. B. Contractor shall submit a schedule of all penetrations, openings or edge conditions in firerated assemblies, along with the specific material and/or system used to seal such penetration, opening or edge condition. Schedule shall include the following information in list form: 1. 2. 3. 4. 5. 6. 7. C. Material being penetrated. Purpose of penetration (ie: ducts, conduit, piping). Size and material of penetration. Size of opening in fire-rated assembly. Construction of assembly being penetrated. Rating of assembly being penetrated. Specific product and/or system used to seal the penetration, referenced to accompanying product data and descriptions. Product data for each type of product used. 1. 1.5 NOVEMBER 19TH, 2013 Certification by firestopping manufacturer that products supplied comply with local regulations controlling use of volatile organic compounds (VOCs) and are nontoxic to building occupants. D. Product certificates signed by manufacturers of firestopping products certifying that their products comply with specified requirements. E. Product test reports from, and based on tests performed by, a qualified testing and inspecting agency evidencing compliance of firestopping with requirements based on comprehensive testing of current products. F. Qualification data for firms and persons specified in "Quality Assurance" article to demonstrate their capabilities and experience. Include list of completed projects with project names, addresses, names of Architects and Owners, and other information specified. QUALITY ASSURANCE A. Fire-Test-Response Characteristics: Provide firestopping that complies with the following requirements and those specified under the "System Performance Requirements" article: 1. 2. Firestopping tests are performed by a qualified testing and inspecting agency. A qualified testing and inspecting agency is UL, Warnock Hersey, or another agency performing testing and follow-up inspection services for firestop systems that is acceptable to authorities having jurisdiction. Through-penetration firestop systems are identical to those tested per ASTM E 814 under conditions where positive furnace pressure differential of at least 0.01 inch of water is maintained at a distance of 0.78 inch below the fill materials surrounding the penetrating items in the test assembly. Provide rated systems complying with the following requirements: a. 3. Through-penetration firestop system products bear classification marking of qualified testing and inspecting agency, indicating rating required for each penetration. Fire-resistive joint sealant systems are identical to those tested for fire-response characteristics per ASTM E 119 under conditions where the positive furnace pressure FIRESTOPPING 07 8400- 2 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 differential is at least 0.01 inch of water, as measured 0.78 inch from the face exposed to furnace fire. Provide systems complying with the following requirements: a. 1.6 1.7 1.8 Joint sealants, including backing materials, bear classification marking of qualified testing and inspection agency, indicating rating required for each penetration. B. Installer Qualifications: Engage an experienced Installer who has completed firestopping that is similar in material, design, and extent to that indicated for Project and that has performed successfully. C. Single-Source Responsibility: Obtain through-penetration firestop systems for each kind of penetration and construction condition indicated from a single manufacturer. D. Provide firestopping products containing no detectable asbestos as determined by the method specified in 40 CFR Part 763, Subpart F, Appendix A, Section 1, "Polarized Light Microscopy." E. Coordinating Work: Coordinate construction of openings and penetrating items to ensure that designated through-penetration firestop systems are installed per specified requirements. F. Owner retains the right to employ and pay a qualified inspection agency to check installed firestopping systems for compliance with requirements. DELIVERY, STORAGE, AND HANDLING A. Deliver firestopping products to Project site in original, unopened containers or packages with intact and legible manufacturers' labels identifying product and manufacturer; date of manufacture; lot number; shelf life, if applicable; qualified testing and inspecting agency's classification marking applicable to Project; curing time; and mixing instructions for multicomponent materials. B. Store and handle firestopping materials to prevent their deterioration or damage due to moisture, temperature changes, contaminants, or other causes. PROJECT CONDITIONS A. Environmental Conditions: Do not install firestopping when ambient or substrate temperatures are outside limits permitted by firestopping manufacturers or when substrates are wet due to rain, frost, condensation, or other causes. B. Ventilation: Ventilate firestopping per firestopping manufacturers' instructions by natural means or, where this is inadequate, forced air circulation. SEQUENCING AND SCHEDULING A. Notify Owner's inspection agency at least 1 week in advance of firestopping installations; confirm dates and times on days preceding each series of installations. B. Do not cover up those firestopping installations that will become concealed behind other construction until Owner's inspection agency and authorities having jurisdiction, if required, have examined each installation. PART 2 - PRODUCTS 2.1 FIRESTOPPING, GENERAL FIRESTOPPING 07 8400- 3 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 A. Compatibility: Provide firestopping composed of components that are compatible with each other, the substrates forming openings, and the items, if any, penetrating the firestopping under conditions of service and application, as demonstrated by firestopping manufacturer based on testing and field experience. B. Accessories: Provide components for each firestopping system that are needed to install fill materials and to comply with "System Performance Requirements" article in Part 1. Use only components specified by the firestopping manufacturer and approved by the qualified testing and inspecting agency for the designated fire-resistance-rated systems. Accessories include but are not limited to the following items: 1. Permanent forming/damming/backing materials including the following: a. b. c. d. e. 2. 3. 4. 5. C. 2.2 NOVEMBER 19TH, 2013 Semirefractory fiber (mineral wool) insulation. Ceramic fiber. Sealants used in combination with other forming/damming materials to prevent leakage of fill materials in liquid state. Fire-rated formboard. Joint fillers for joint sealants. Temporary forming materials. Substrate primers. Collars. Steel sleeves. Applications: Provide firestopping systems composed of materials that comply with system performance and other requirements. FILL MATERIALS FOR THROUGH-PENETRATION FIRESTOP SYSTEMS A. Ceramic-Fiber and Mastic Coating: Ceramic fibers in bulk form formulated for use with mastic coating, and ceramic fiber manufacturer's mastic coating. B. Ceramic-Fiber Sealant: binders. C. Endothermic, Latex Compound Sealant: Single-component, endothermic, latex formulation. D. Intumescent, Latex Sealant: Single-component, intumescent, latex formulation. E. Intumescent Putty: Nonhardening, dielectric, water-resistant putty containing no solvents, inorganic fibers, or silicone compounds. F. Intumescent Wrap Strips: Single-component, elastomeric sheet with aluminum foil on one side. G. Job-Mixed Vinyl Compound: Prepackaged vinyl-based powder product for mixing with water at Project site to produce a paintable compound, passing ASTM E 136, with flame-spread and smoke-developed ratings of zero per ASTM E 84. H. Mortar: Prepackaged dry mix composed of a blend of inorganic binders, fillers, and lightweight aggregate formulated for mixing with water at Project site to form a nonshrinking, homogenous mortar. FIRESTOPPING Single-component formulation of ceramic fibers and inorganic 07 8400- 4 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 I. Pillows/Bags: Re-usable, heat-expanding pillows/bags composed of glass-fiber cloth cases filled with a combination of mineral-fiber, water-insoluble expansion agents and fire-retardant additives. J. Silicone Foam: Two-component, silicone-based liquid elastomer that, when mixed, expands and cures in place to produce a flexible, nonshrinking foam. K. Silicone Sealant: Moisture-curing, single-component, elastomeric sealant of grade indicated below: 1. 2.3 silicone-based, neutral-curing Grade: Pourable (self-leveling) formulation for openings in floors and other horizontal surfaces and nonsag formulation for openings in vertical and other surfaces requiring a nonslumping/ gunnable sealant, unless indicated firestop system limits use to nonsag grade for both opening conditions. FIRE-RESISTIVE ELASTOMERIC JOINT SEALANTS A. Elastomeric Sealant Standard: Provide manufacturer's standard chemically curing, elastomeric sealants of base polymer required that complies with ASTM C 920 requirements applicable to fire-resistive joint sealants. B. Sealant Colors: Provide color of exposed joint sealants to comply with the following: 1. 2.4 NOVEMBER 19TH, 2013 Provide selections made by Architect from manufacturer's full range of standard colors for products of type indicated. MIXING A. For those products requiring mixing prior to application, comply with firestopping manufacturer's directions for accurate proportioning of materials, water (if required), type of mixing equipment, selection of mixer speeds, mixing containers, mixing time, and other procedures needed to produce firestopping products of uniform quality with optimum performance characteristics for application indicated. PART 3 - EXECUTION 3.1 RESPONSIBILITY FOR FIRESTOPPING INSTALLATION A. Firestopping shall be provided by Contractors as follows: 1. 2. 3. 3.2 Penetrations made through existing or new fire-rated construction shall be firestopped by the Contractor making the penetration. Penetrations in new fire-rated construction built around existing or new wiring, piping, conduit, ductwork, etc., shall be firestopped by the Contractor installing the fire-rated construction. Perimeter firestopping shall be provided by Contractor installing the fire-rated construction. EXAMINATION A. Examine substrates and conditions, with Installer present, for compliance with requirements for opening configurations, penetrating items, substrates, and other conditions affecting performance of firestopping. Do not proceed with installation until unsatisfactory conditions have been corrected. FIRESTOPPING 07 8400- 5 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.3 PREPARATION A. Surface Cleaning: Clean out openings and joints immediately prior to installing firestopping to comply with recommendations of firestopping manufacturer and the following requirements: 1. 2. 3. 3.4 Remove all foreign materials from surfaces of opening and joint substrates and from penetrating items that could interfere with adhesion of firestopping. Clean opening and joint substrates and penetrating items to produce clean, sound surfaces capable of developing optimum bond with firestopping. Remove loose particles remaining from cleaning operation. Remove laitance and form release agents from concrete. B. Priming: Prime substrates where recommended by firestopping manufacturer using that manufacturer's recommended products and methods. Confine primers to areas of bond; do not allow spillage and migration onto exposed surfaces. C. Masking Tape: Use masking tape to prevent firestopping from contacting adjoining surfaces that will remain exposed upon completion of Work and that would otherwise be permanently stained or damaged by such contact or by cleaning methods used to remove smears from firestopping materials. Remove tape as soon as it is possible to do so without disturbing firestopping's seal with substrates. INSTALLING THROUGH-PENETRATION FIRESTOPS A. General: Comply with the "System Performance Requirements" article in Part 1 and the through-penetration firestop manufacturer's installation instructions and drawings pertaining to products and applications indicated. B. Install forming/damming materials and other accessories of types required to support fill materials during their application and in the position needed to produce the cross-sectional shapes and depths required to achieve fire ratings of designated through-penetration firestop systems. After installing fill materials, remove combustible forming materials and other accessories not indicated as permanent components of firestop systems. C. Install fill materials for through-penetration firestop systems by proven techniques to produce the following results: 1. 2. 3. 3.5 NOVEMBER 19TH, 2013 Completely fill voids and cavities formed by openings, forming materials, accessories, and penetrating items. Apply materials so they contact and adhere to substrates formed by openings and penetrating items. For fill materials that will remain exposed after completing Work, finish to produce smooth, uniform surfaces that are flush with adjoining finishes. INSTALLING FIRE-RESISTIVE JOINT SEALANTS A. General: Comply with the "System Performance Requirements" article in Part 1, with ASTM C 1193, and with the sealant manufacturer's installation instructions and drawings pertaining to products and applications indicated. B. Install joint fillers to provide support of sealants during application and at position required to produce the cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability and develop fire-resistance rating required. C. Install sealants by proven techniques that result in sealants directly contacting and fully wetting joint substrates, completely filling recesses provided for each joint configuration, and FIRESTOPPING 07 8400- 6 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 providing uniform, cross-sectional shapes and depths relative to joint width that optimum sealant movement capability. Install sealants at the same time joint fillers are installed. D. 3.6 3.7 Tool nonsag sealants immediately after sealant application and prior to the time skinning or curing begins. Form smooth, uniform beads of configuration indicated or required to produce fire-resistance rating, as well as to eliminate air pockets, and to ensure contact and adhesion of sealants with sides of joint. Remove excess sealant from surfaces adjacent to joint. Do not use tooling agents that discolor sealants or adjacent surfaces or are not approved by sealant manufacturer. FIELD QUALITY CONTROL A. Inspecting agency may be employed and paid by Owner to examine completed firestopping to determine, in general, if it is being installed in compliance with requirements. B. Inspecting agency will report observations promptly and in writing to Contractor and Architect. C. Do not proceed to enclose firestopping with other construction until reports of examinations are issued. D. Where deficiencies are found, repair or replace firestopping so that it complies with requirements. CLEANING A. Clean off excess fill materials and sealants adjacent to openings and joints as work progresses by methods and with cleaning materials approved by manufacturers of firestopping products and of products in which opening and joints occur. B. Protect firestopping during and after curing period from contact with contaminating substances or from damage resulting from construction operations or other causes so that they are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated firestopping immediately and install new materials to produce firestopping complying with specified requirements. END OF SECTION 07 8400 FIRESTOPPING 07 8400- 7 of 7 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 07 9200 - JOINT PROTECTION PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Compression seals and sealants, preparation of substrate, and applications including but not limited to: 1. Joints between metal door frames and walls. 2. Set door saddles in sealant bed. 3. Joints between dissimilar materials including masonry, concrete, metals, wood, plaster and gypsum board. 4. Floor (interior) joints. 5. Partition and ceiling joints. 6. Joints between fixtures/equipment and construction. .B. 1. 2. 1.2 1.3 Related Sections Section 09 2900 Gypsum Board Assemblies Section 07 8400 Firestopping SUBMITTALS A. See Division 1 – General Requirements for submittal procedures.. B. Submit product data indicating sealant chemical characteristics, performance criteria, substrate preparation, limitations, and color availability. C. Submit three samples illustrating colors selected for sealants and 6 inch sample of compression seal. D. Submit manufacturer's installation instructions. E. Submit manufacturer’s certificate that products used meet or exceed specified requirements, and that products used are compatible with backing and adjacent materials. SUSTAINABLE DESIGN SUBMITTALS A. Make submittals electronically. B. Manufacturer's Certificate: Certify products meet or exceed specified sustainable design requirements. 1. Materials Resources Certificates: a. Certify recycled material content for recycled content products. 1) Indicate post-consumer recycled content percent by weight as defined by LEED Rating System. 2) Indicate pre-consumer recycled content percent by weight as defined by LEED Rating System. 3) Indicate recycled content materials in accordance with ISO 14021. b. Certify source for local and regional materials and distance from Project site. 1) Indicate location of extraction, harvesting or recovery. 2) Indicate manufacturing or fabrication location. 2. Indoor Air Quality Certificates: a. Certify volatile organic compound content for each interior adhesive and sealant and related primer. JOINT PROTECTION 07 9200 - 1 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1) 2) C. 1.4 1.5 1.6 Indicate VOC content meets requirements of SCAQMD Rule 1168. Include data sheet indicating volatile organic compound content, in g/L, for each Product. Product Cost Data: Submit cost of products to verify compliance with Project sustainable design requirements. Exclude cost of labor and equipment to install products. 1. Provide all material costs as well as cost data for the following products: a. Products with recycled material content. b. Local and regional products. QUALITY ASSURANCE A. Applicator: Company specializing in applying the work of this Section with minimum five years experience, approved by sealant manufacturer. B. Sustainable Design Requirements: 1. Recycled Content Materials: Furnish materials with recycled content. 2. Regional Materials: Furnish materials extracted, processed, and manufactured within 500 miles of Project site. ENVIRONMENTAL REQUIREMENTS A. Do not install solvent curing sealants in enclosed building spaces. B. Maintain temperature and humidity recommended by the sealant manufacturer during and after installation. SEQUENCING AND SCHEDULING A. 1.7 NOVEMBER 19TH, 2013 Coordinate this work with all Sections referencing this Section. WARRANTY A. Interior Joints: Submit 2 year warranty against cracking, crazing, separation of the material from the substrate or other failure of the joint. PART 2 PRODUCTS 2.1 SEALANTS A. Manufacturers: 1. Tremco. 2. Sonneborn or Pecora, with chemical composition and performance characteristics identical to Tremco. B. Compatibility: Before purchase, confirm compatibility of each sealant with other materials in the system. C. Acrylic Latex Sealant: Low odor, fast-setting, color to be selected; Tremco Acrylic Latex 834. Maximum volatile organic compound content in accordance with SCAQMD Rule 1168. JOINT PROTECTION 07 9200 - 2 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 D. E. F. G. 2.2 2.3 NOVEMBER 19TH, 2013 Polyurethane Sealant (Self-leveling): Multi-component, self-leveling/slope grades, custom color as selected; THC 900/901 by Tremco. Maximum volatile organic compound content in accordance with SCAQMD Rule 1168 Polyurethane Sealant (Vertical): 3-component, +/- 50% movement, color to be selected; “Sonolastic” by Sonneborn. Maximum volatile organic compound content in accordance with SCAQMD Rule 1168 Acrylic Terpolymer Sealant: One part, high solids, solvent release cure; color to be selected; Mono-555 by Tremco. Maximum volatile organic compound content in accordance with SCAQMD Rule 1168. Mildew Resistant Silicone Sealant: Single component, neutral cure, white color, Tremsil No. 200 by Tremco. Maximum volatile organic compound content in accordance with SCAQMD Rule 1168. COMPRESSION SEALS A. Manufacturers: 1. Emseal Corporation. . 800-526-8365 www.emseal.com 2. Substitutions: See Division 1 – General Requirements for substitution procedures. B. Preformed Foam Sealant: Open-cell, urethane foam, impregnated with a non-drying, water repellent agent; factory-produced in precompressed sizes, in roll or stick form to fit joint widths, and to develop a watertight, airtight seal when compressed to the degree specified by manufacturer. 1. Properties: Permanently elastic, mildew-resistant, nonmigratory, nonstaining, compatible with joint substrates and other joint sealers. 2. Impregnating Agent: Manufacturer’s standard. 3. Density: Manufacturer’s standard “high” density. 4. Backing: Where required, provide backings suitable for intended use, compatible with joint substrates and other joint sealers, designed to work in conjunction with primary sealants in dual-sealant systems, ACCESSORIES A. Primer: Non-staining type, recommended by sealant manufacturer to suit application. Maximum volatile organic compound content in accordance with SCAQMD Rule 1168. B. Joint Cleaner: Non-corrosive and non-staining type, recommended by sealant manufacturer; compatible with joint forming materials. C. Joint Backing: Round, closed cell polyethylene foam rod; oversized 30 to 50 percent larger than joint width; Ethafoam SB manufactured by Dow Chemical. D. Bond Breaker: Pressure sensitive tape recommended by sealant manufacturer to suit application. PART 3 EXECUTION 3.1 EXAMINATION A. 3.2 Verify that surfaces and joints are ready to receive work and field measurements are as shown on Drawings and recommended by the manufacturer. PREPARATION A. B. C. D. Clean and prime joints in accordance with manufacturer's instructions. Remove loose materials and foreign matter which might impair adhesion of sealant. Verify that joint backing and release tapes are compatible with sealant. Protect elements surrounding the work of this Section from damage or disfiguration. JOINT PROTECTION 07 9200 - 3 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.3 3.4 INSTALLATION - SEALANTS A. Install sealant in accordance with manufacturer's instructions. B. Measure joint dimensions and size materials to achieve required width/depth ratios. C. Install joint backing to achieve a neck dimension no greater than 1/3 the joint width. D. Install bond breaker where joint backing is not used. E. Apply sealant within recommended application temperature ranges. Consult manufacturer when sealant cannot be applied within these temperature ranges. F. Install sealant free of air pockets, foreign embedded matter, ridges, and sags. G. Tool joints concave. H. Butter inside edge of masonry openings or surfaces of frames to be embedded with thin coat of caulking or primer recommended by manufacturer. Caulk jambs, heads, and sills neatly with a trowel. I. Metal Door Saddles: Spread caulking bed over entire seal of saddles at least 1/4 inch thick. Set saddle or sill on and remove excess material. Neatly point joints. INSTALLATION – PREFORMED FOAM SEALANTS A. 3.5 Clean adjacent soiled surfaces. Repair or replace defaced or disfigured finishes caused by work of this Section. PROTECTION OF FINISHED WORK A. 3.7 Install each length of sealant immediately after removing protective wrappings, taking care not to pull and stretch material. For application at low ambient temperatures, where expansion of sealant requires acceleration to produce seal, apply heat to sealant in accordance with manufacturer’s recommendations. CLEANING AND REPAIRING A. B. 3.6 NOVEMBER 19TH, 2013 Protect sealants until cured. SCHEDULE A. Interior joints of minimal activity, joints in hollow metal frames and at abutting surfaces, at ceiling, wall angles, and all other locations to accomplish a finished appearance: Acrylic Latex. B. Interior expansion, construction or control joints where movement must be accommodated: Acrylic Terpolymer. Design joint to be installed without need for painting. When exposed to students, install a joint cover or devise a method to protect the application. C. Interior joints at counters and fixtures: Mildew Resistant SiliconeDow 786. END OF SECTION 07 92 JOINT PROTECTION 07 9200 - 4 of 4 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 08 1113 - HOLLOW METAL DOORS AND FRAMES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.02 SUMMARY A. This Section includes steel doors and frames. B. Related Sections: The following Sections contain requirements that relate to this Section: 1. 2. Division 9 Section "Gypsum Board Assemblies" for spot grouting frames in gypsum board partitions. Division 9 Section "Painting" for field painting primed doors and frames. 1.03 SUBMITTALS A. General: Submit each item in this Article according to the Conditions of the Contract and Division 1 Specification Sections. B. Product Data for each type of door and frame specified, including details of construction, materials, dimensions, hardware preparation, core, label compliance, sound ratings, profiles, and finishes. C. Shop Drawings showing fabrication and installation of steel doors and frames. Include details of each frame type, elevations of door design types, conditions at openings, details of construction, location and installation requirements of door and frame hardware and reinforcements, and details of joints and connections. Show anchorage and accessory items. D. Door Schedule: Submit schedule of doors and frames using same reference numbers for details and openings as those on Contract Drawings. 1. Indicate coordination of glazing frames and stops with glass and glazing requirements. 1.04 QUALITY ASSURANCE A. Provide doors and frames complying with ANSI/SDI 100 "Recommended Specifications for Standard Steel Doors and Frames" and as specified. B. Fire-Rated Door Assemblies: Units that comply with NFPA 80, are identical to door and frame assemblies tested for fire-test-response characteristics per ASTM E 152, and are labeled and listed by UL, Warnock Hersey, or another testing and inspecting agency acceptable to authorities having jurisdiction. 1.05 DELIVERY, STORAGE, AND HANDLING A. Deliver doors and frames cardboard-wrapped or crated to provide protection during transit and job storage. Provide additional protection to prevent damage to finish of factory-finished doors and frames. HOLLOW METAL DOORS AND FRAMES 08 1113 - 1 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Inspect doors and frames on delivery for damage. Minor damages may be repaired provided refinished items match new work and are acceptable to Architect; otherwise, remove and replace damaged items as directed. C. Store doors and frames at building site under cover. Place units on minimum 4-inch-high wood blocking. Avoid using nonvented plastic or canvas shelters that could create a humidity chamber. If cardboard wrappers on doors become wet, remove cartons immediately. Provide minimum 1/4-inch spaces between stacked doors to promote air circulation. PART 2 - PRODUCTS 2.01 MANUFACTURERS A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated in the Work include, but are not limited to, the following: 1. Steel Doors and Frames: a. Amweld Building Products, Inc. b. Ceco Door Products. c. Republic Builders Products. d. Seelcraft (Ingersoll-Rand) 2.02 MATERIALS A. Cold-Rolled Steel Sheets: Carbon steel complying with ASTM A 366, commercial quality, or ASTM A 620, drawing quality, special killed. B. Galvanized Steel Sheets: Zinc-coated carbon steel complying with ASTM A 526, commercial quality, or ASTM A 642, drawing quality, hot-dip galvanized according to ASTM A 525, with A 60 or G 60 coating designation, mill phosphatized. C. Supports and Anchors: Fabricated from not less than 0.0478-inch-thick steel sheet; 0.0516inch-thick galvanized steel where used with galvanized steel frames. D. Inserts, Bolts, and Fasteners: Manufacturer's standard units. Where items are to be built into exterior walls, hot-dip galvanize complying with ASTM A 153, Class C or D as applicable. 2.03 DOORS (NONE REQUIRED) A. Steel Doors: Provide 1-3/4-inch-thick doors of materials and ANSI/SDI 100 grades and models specified below, or as indicated on Drawings or schedules: 1. Interior Doors: Grade III, extra heavy-duty, Model 2, seamless design, minimum 16ga thick cold-rolled steel sheet faces. 2. Exterior Doors: Grade III, extra heavy-duty, Model 2, seamless design, minimum 14ga thick galvanized steel sheet faces. 2.04 FRAMES A. Provide metal frames for doors, transoms, sidelights, borrowed lights, and other openings, according to ANSI/SDI 100, and of types and styles as shown on Drawings and schedules. Conceal fastenings, unless otherwise indicated. Fabricate frames of minimum 16ga thick cold-rolled steel sheet. 1. Fabricate frames with mitered or coped corners, continuously welded construction face and rear of frame for all applications. No knock-down type frames are allowed except where explicitly indicated as acceptable. HOLLOW METAL DOORS AND FRAMES 08 1113 - 2 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. 3. NOVEMBER 19TH, 2013 Fabricate frames for interior openings over 48 inches wide from 16ga thick steel sheet. Form exterior frames from 14ga thick galvanized steel sheet. B. Door Silencers: Except on weatherstripped frames, drill stops to receive 3 silencers on strike jambs of single-door frames and 2 silencers on heads of double-door frames. C. Plaster Guards: Provide minimum 0.0179-inch-thick steel plaster guards or mortar boxes at back of hardware cutouts where mortar or other materials might obstruct hardware operation and to close off interior of openings. D. Grout: When required in masonry construction, as specified in Division 4 Section "Unit Masonry." 2.05 FABRICATION A. Fabricate steel door and frame units to be rigid, neat in appearance, and free from defects, warp, or buckle. Where practical, fit and assemble units in manufacturer's plant. Clearly identify work that cannot be permanently factory assembled before shipment, to assure proper assembly at Project site. Comply with ANSI/SDI 100 requirements. 1. Internal Construction: One of the following manufacturer's standard core materials according to SDI standards: a. Resin-impregnated paper honeycomb. b. Rigid polyurethane conforming to ASTM C 591. c. Rigid polystyrene conforming to ASTM C 578. d. Unitized steel grid. e. Vertical steel stiffeners. f. Rigid mineral fiber with internal sound deadener on inside of face sheets. 2. Clearances: Not more than 1/8 inch at jambs and heads, except not more than 1/4 inch between non-fire-rated pairs of doors. Not more than 3/4 inch at bottom. a. Fire Doors: Provide clearances according to NFPA 80. B. Fabricate exposed faces of doors and panels, including stiles and rails of nonflush units, from only cold-rolled steel sheet. C. Tolerances: Frames." D. Fabricate concealed stiffeners, reinforcement, edge channels, louvers, and moldings from either cold- or hot-rolled steel sheet. E. Galvanized Steel Doors, Panels, and Frames: For the following locations, fabricate doors, panels, and frames from galvanized steel sheet according to SDI 112. Close top and bottom edges of doors flush as an integral part of door construction or by addition of minimum 0.0635inch-thick galvanized steel channels, with channel webs placed even with top and bottom edges. Seal joints in top edges of doors against water penetration. 1. At exterior locations. F. Exposed Fasteners: Unless otherwise indicated, provide countersunk flat or oval heads for exposed screws and bolts. G. Thermal-Rated (Insulating) Assemblies: At exterior locations and elsewhere as shown or scheduled, provide doors fabricated as thermal-insulating door and frame assemblies and tested according to ASTM C 236 or ASTM C 976 on fully operable door assemblies. Comply with SDI 117 "Manufacturing Tolerances Standard Steel Doors and HOLLOW METAL DOORS AND FRAMES 08 1113 - 3 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. NOVEMBER 19TH, 2013 Unless otherwise indicated, provide thermal-rated assemblies with U-value rating of 0.41 Btu/sq. ft. x h x deg F or better. H. Hardware Preparation: Prepare doors and frames to receive mortised and concealed hardware according to final door hardware schedule and templates provided by hardware supplier. Comply with applicable requirements of SDI 107 and ANSI A115 Series specifications for door and frame preparation for hardware. 1. For concealed overhead door closers, if any, provide space, cutouts, reinforcing, and provisions for fastening in top rail of doors or head of frames, as applicable. I. Reinforce doors and frames to receive surface-applied hardware. Drilling and tapping for surface-applied hardware may be done at Project site. J. Locate hardware as indicated on Shop Drawings or, if not indicated, according to the Door and Hardware Institute's (DHI) "Recommended Locations for Architectural Hardware for Standard Steel Doors and Frames." K. Glazing Stops: Minimum 0.0359-inch-thick steel or 0.040-inch-thick aluminum. 1. Provide nonremovable stops on outside of exterior doors and on secure side of interior doors for glass, louvers, and other panels in doors. 2. Provide screw-applied, removable, glazing beads on inside of glass, louvers, and other panels in doors. 2.06 FINISHES, GENERAL A. Comply with NAAMM's "Metal Finishes Manual" for recommendations relative to applying and designating finishes. B. Comply with SSPC-PA 1, "Paint Application Specification No. 1," for steel sheet finishes. C. Apply primers and organic finishes to doors and frames after fabrication. 2.07 GALVANIZED STEEL SHEET FINISHES A. Surface Preparation: Clean surfaces with nonpetroleum solvent so that surfaces are free of oil or other contaminants. After cleaning, apply a conversion coating of the type suited to the organic coating applied over it. Clean welds, mechanical connections, and abraded areas, and apply galvanizing repair paint specified below to comply with ASTM A 780. 1. Galvanizing Repair Paint: High-zinc-dust-content paint for regalvanizing welds in galvanized steel, with dry film containing not less than 94 percent zinc dust by weight, and complying with DOD-P-21035 or SSPC-Paint 20. B. Factory Priming for Field-Painted Finish: Where field painting after installation is indicated, apply air-dried primer specified below immediately after cleaning and pretreatment. 1. Shop Primer: Zinc-dust, zinc-oxide primer paint complying with performance requirements of FS TT-P-641, Type II. 2.08 STEEL SHEET FINISHES A. Surface Preparation: Solvent-clean surfaces to comply with SSPC-SP 1 to remove dirt, oil, grease, and other contaminants that could impair paint bond. Remove mill scale and rust, if present, from uncoated steel to comply with SSPC-SP 5 (White Metal Blast Cleaning) or SSPC-SP 8 (Pickling). HOLLOW METAL DOORS AND FRAMES 08 1113 - 4 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Pretreatment: Immediately after surface preparation, apply a conversion coating of type suited to organic coating applied over it. C. Factory Priming for Field-Painted Finish: Apply shop primer that complies with ANSI A224.1 acceptance criteria, is compatible with finish paint systems indicated, and has capability to provide a sound foundation for field-applied topcoats. Apply primer immediately after surface preparation and pretreatment. PART 3 - EXECUTION 3.01 3.1 INSTALLATION A. General: Install steel doors, frames, and accessories according to Shop Drawings, manufacturer's data, and as specified. B. Placing Frames: Comply with provisions of SDI 105, unless otherwise indicated. Set frames accurately in position, plumbed, aligned, and braced securely until permanent anchors are set. After wall construction is completed, remove temporary braces and spreaders, leaving surfaces smooth and undamaged. 1. Except for frames located in existing concrete, masonry, or gypsum board assembly construction, place frames before constructing enclosing walls and ceilings. 2. In masonry construction, install at least 3 wall anchors per jamb adjacent to hinge location on hinge jamb and at corresponding heights on strike jamb. Acceptable anchors include masonry wire anchors and masonry T-shaped anchors. 3. At existing concrete or masonry construction, install at least 3 completed opening anchors per jamb adjacent to hinge location on hinge jamb and at corresponding heights on strike jamb. Set frames and secure to adjacent construction with bolts and masonry anchorage devices. 4. In metal-stud partitions, install at least 3 wall anchors per jamb at hinge and strike levels. In steel-stud partitions, attach wall anchors to studs with screws. 5. In in-place gypsum board partitions, installation of knock-down, slip-on, drywall frames may be allowed at existing construction only, but only with prior consent of the Architect. 6. Install fire-rated frames according to NFPA 80. C. Door Installation: Fit hollow-metal doors accurately in frames, within clearances specified in ANSI/SDI 100. 1. Fire-Rated Doors: Install with clearances specified in NFPA 80. 3.02 ADJUSTING AND CLEANING A. Prime Coat Touchup: Immediately after erection, sand smooth any rusted or damaged areas of prime coat and apply touchup of compatible air-drying primer. B. Protection Removal: Immediately before final inspection, remove protective wrappings from doors and frames. END OF SECTION 08 1113 HOLLOW METAL DOORS AND FRAMES 08 1113 - 5 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 08 1255 – ALUMINUM FRAMES AND F.R.P. DOORS PART 1 - GENERAL 1.01 A. 1.02 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. The Work of this Section consists of the provision of all plant, labor, materials, equipment, testing and services necessary to complete the work for aluminum frames and fiberglass reinforced polyester (FRP) flush doors as shown on the schedules, keynotes, drawings, as specified herein, and as may be required by conditions and authorities having jurisdiction. B. Related Requirements: 1. 2. 3. 4. 1.03 A. 1.04 Section 07 9200 “Joint Protection” Section 08 4113 “Aluminum-Framed Entrances and Storefronts” Section 08 7100 "Finish Hardware" Section 08 8000 “Glazing” COORDINATION Coordinate anchorage installation for aluminum frames. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors. Deliver such items to Project site in time for installation. PERFORMANCE REQUIREMENTS FRP DOORS 1. FRP Doors: General: Provide door assemblies that have been designed and fabricated to comply with specified performance requirements, as demonstrated by testing manufacturer's corresponding standard systems: 2. Air Infiltration: For a single door 3'-0" x 7'-0", test specimen shall be tested in accordance with ASTM E 283 at pressure differential of 6.24 psf. Door shall n6t exceed 0.90 cfrn per linear foot of perimeter crack. 3. Water Resistance: For a single door 3'-0" x 7'-0", test specimen shall be tested in accordance with ASTM E 331 at pressure differential of 7.50 psf. Door shall not have water leakage. 4. Unifonn Static Load, ASTM E 330: Plus or minus 75 pounds per square foot. 5. Forced Entry Test, 300 Pound Load Applied, SFBC 3603.2 (b)(5): Passed. 6. Cyclic Load Test, SFBC PA 203: Plus or minus 53 pounds per square foot. 7. Large Missile Impact Test, SFBC PA 201: Passed. 8. Swinging Door Cycle Test, Doors & Frames,ANSI A250.4:Minimum of 20,000,000 cycles. ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 1 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 9. Salt Spray, Exterior Doors and Frames, ASTM B 117: Minimum of 500 hours. 10. Sound Transmission, Exterior Doors, STC, ASTM E 90: Minimum of 25. 11. Thermal Transmission, Exterior Doors, U-Value, AAMA 1503-98: Maximum of 0.29 BTUIhr x sfx degrees F. Minimum of 55 CRF value. 12. FRP doors shall comply with fire resistance and flammability regulations as interpreted by governing authorities, and as follows: a. Face sheets tested in accordance with ASTM E84 shall have the following ratings: 1) Smoke Developed: (a) Not greater than 320 Interior Skins (Class A). (b) Not greater than 345 Exterior Skins (Class C) 2) Flame Spread: (a) Not greater than 10 Interior Skins (Class A) (b) Not greater than 70 Exterior Skins (Class C) b. Impact Strength, FRP Doors and Panels, Nominal Value, ASTM D 256: 15.0 footpounds per inch of notch. c. Tensile Strength, FRP Doors and Panels, Nominal Value, ASTM D 638: 14,000 psi. d. Flexural Strength, FRP Doors and Panels, Nominal Value, ASTM D 790: 21,000 psi. e. Water Absorption, FRP Doors and Panels, Nominal Value, ASTM D 570: 0.20 percent after 24 hours. f. Indentation Hardness, FRP Doors and Panels, Nominal Value, ASTM D 2583: 55. g. Abrasion Resistance, Face Sheet, Taber Abrasion Test, 25 Cycles at 1,000 Gram Weight with CS-17 Wheel: Maximum of 0.029 average weight loss percentage. h. Stain Resistance, ASTM D 1308: Face sheet unaffected after exposure to red cabbage, tea, and tomato acid. Stain removed easily with mild abrasive or FRP cleaner when exposed to Sharpie ink pen and white spray paint. i. Chemical Resistance, ASTM D 543. Excellent rating. 1) Acetic acid, 5 percent solution. 2) Chlorine bleach, 10 percent solution. 3) Sodium hypochlorite, 4 to 6 percent solution. 4) Citric acid, 10 percent solution. 5) Sodium carbonate, 20 percent solution. 6) Turpentine. j. Compressive Strength, Foam Core, Nominal Value, ASTMD 1621: 84.2 psi. k. Compressive Modulus, Foam Core, Nominal Value, ASTM D 1621: 448 psi. l. Tensile Adhesion, Foam Core, Nominal Value, ASTM D 1623: 48 psi. m. Thermal and Humid Aging, Nominal Value, 158 Degrees F and 100 Percent Humidity for 14 Days, ASTM D 2126: Minus 4.89 percent volume change. 1.05 A. ACTION SUBMITTALS Product Data: For each type of product. 1. Include construction details, material descriptions, core descriptions, fire-resistance ratings, and finishes. ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 2 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Shop Drawings: Include the following: 1. Elevations of each door and frame type. 2. Details of doors, including vertical- and horizontal-edge details and metal thicknesses. 3. Frame details for each frame type, including dimensioned profiles and metal thicknesses. 4. Locations of reinforcement and preparations for hardware. 5. Details of each different wall opening condition. 6. Details of anchorages, joints, field splices, and connections. 7. Details of accessories. C. Samples for Verification: 1. Submit manufacturer’s sample of door showing face sheets, core, framing and finish. 2. Submit manufacturer’s samples of standard colors for doors. D. Schedule: Provide a schedule of door/frame work prepared by or under the supervision of supplier, using same reference numbers for details and openings as those on Drawings. Coordinate with final Door Hardware Schedule. 1.06 INFORMATIONAL SUBMITTALS A. Product Test Reports: For each type of door assembly, for tests performed by a qualified testing agency. B. Oversize Construction Certification: For assemblies required to be fire rated and exceeding limitations of labeled assemblies. C. Submit manufacturer’s standard warranty (10 years). 1.07 A. DELIVERY, STORAGE, AND HANDLING Deliver materials, packaged, or crated to provide protection during transit and Project-site storage. Do not use nonvented plastic. 1. Provide additional protection to prevent damage to factory-finished units. B. Deliver welded frames with two removable spreader bars across bottom of frames, tack welded to jambs and mullions. C. Store materials in clean, dry area, indoors. PART 2 - PRODUCTS 2.01 MANUFACTURERS 1. Provide product from one of the following subject to compliance with requirements: FRP Doors a. Kawneer Company. b. Corrim Company. c. Commercial Door systems. Aluminum Frames ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 3 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 d. e. f. B. 2.02 NOVEMBER 19TH, 2013 Kawneer Company. Tubelite Vista-Wall. Source Limitations: Obtain FRP doors from a single source manufacturer. Obtain aluminum frames from single source from single manufacturer. MATERIALS AND ACCESSORIES A. Aluminum Members: Provide alloy and temper as recommended by manufacturer for strength, corrosion resistance, and application of required finish and control of color; ASTM B 221 for extrusions, ASTM B 209 for sheet/plate, with a minimum wall thickness of 0.125". B. All materials shall be of the same manufacturer. No splitting of Door and Frame components will be permitted for aluminum frames. C. Fasteners: Provide Aluminum, non-magnetic stainless steel or other non-corrosive metal fasteners, guaranteed by the manufacturer to be compatible with the doors, frames, stops, panels, hardware, anchors, and other items being fastened. For exposed fasteners (if any), provide Phillips head flat head screws with finish matching the item to be fastened. D. Do not use exposed fasteners, except where unavoidable for the assembly of units, or unavoidable for the fastening of hardware. Provide only concealed screws in glazing stops. E. Reinforcement and Brackets: Manufacturer's standard formed or fabricated steel units, of shapes, plates, of bars, with 2.0 ounce hot-dip zinc coating, complying with ASTM A 123, applied after fabrication. F. Expansion Anchor Devices: Lead shield or toothed steel, drilling expansion bolt anchors. G. Bituminous Coating: Cold applied asphalt mastic complying with SSPC-PS 12, compounded for 30-mil thickness per coat. H. Sealants and Gaskets: Provide sealants and gaskets in the fabrication, assembly and installation of the work, which are recommended by the manufacturer to remain permanently elastic, non-shrinking, non-migrating and weatherproof. 2.03 Guard Bar: Provide on all existing sidelight glass framing members being worked on a new guard bar. Push side / interior. 1/2"x 2" extruded aluminum tube with closed ends, finish to match cladding color. Fasten with flathead, tamperproof screws same finish. 2.04 ALUMINUM FRAMING SYSTEMS A. Tubular Framing: 1. Size and Type: Model: SL-4S0, 2 inches by 4.5 inches. 2. Material: Aluminum Alloy 6063-TS, 0.12S-inch minimum wall thickness tube. 3. Aluminum Finish: Class 1 (minimum thickness 0.7 mils) integral color, medium matte finish including all trim a. Clear 215 Rl, AA-MI0CI2C22A41. 4. Perimeter Frame Members: ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 4 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 a. b. c. d. Box type with 4 enclosed sides. Factory fabricated. Open-back framing is not acceptable. Applied Door Stops: 1) 2) 3) 2.05 NOVEMBER 19TH, 2013 0.62S-inch high, with screws and weatherstripping. Pressure gasketing for weathering seal. Counterpunch fastener holes in door stop to preserve full-metal thickness under fastener head. e. Caulking: 1) Caulk joints before assembling frame members. f. Joints: 1) Secure joints with fasteners. 2) Provide hairline butt joint appearance. g. Hardware: 1) Premachine and reinforce frame members for hardware m accordance with manufacturer's standards and door hardware schedule. 2) Factory install door hardware. h. Anchors: 1) Anchors appropriate for wall conditions to anchor framing to wall materials. 2) Door Jamb and Header Mounting Holes: Maximum of 24-inch centers. 3) Secure head and sill members of transom, side lites, and similar conditions. i. Fasteners: 1) Aluminum, 18-8 stainless steel or other non-corrosive metal. 2) Compatible with items to be fastened 3) Exposed fasteners with finish matching items to be fastened. FRP DOORS A. (FRP) Flush Doors: 1. Flushline 350 series, 1 3/4" thick. 2. Constructed of aluminum alloy rails and stiles, joined with steel tie rods. 3. Stiles to be tubular shape to accept hardware as specifled. 4. Top and bottom rails to be extruded with legs for interlocking "rigidity weather bar." 5. Joinery to be 3/8" tie rods, top and bottom, bolted through an extruded spline and 3/16" riveted reinforcing angles, and secured with aircraft type nuts. Doors with mid-panels are to have an additional tie rod at the mid-panel. 6. Adjustable astragal at meeting stiles of door pairs. 7. Door sizes as indicated on the Drawings are approximate. Where doors are indicated to be installed in existing openings, field-verify existing frame opening size and provide doors sized as required to accommodate existing condition. 8. Core of flush doors shall be froth-in-place urethane foam at 5.0 lb./cu. Ft. density and shall have “0” O.D.P. = “Zero” Ozone Depletion Potential and contains no CFC’s (Cholorofluorocarbons) or HCHC’s (Hydro Chlorofluorocarbons). All doors are to be properly reinforced for hardware prior to Urethane core foaming in door. 9. Glazing gaskets shall be either EPDM elastomeric extrusions or a thermoplastic elastomer. ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 5 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Face sheets for FRP Doors are to be .120" thick with sandstone texture finish with color throughout. 1. Class A for all interior doors and interior face of exterior doors. C. Color: To be selected by Architect. D. Cutouts: 1. 2. Manufacture doors with cutouts for required vision lites, louvers, and panels. Factory install vision lites, louvers, and panels. E. Hardware: 1. Provide and factory install finish hardware for each door leaf as indicated on drawings, specified in Section 087100 Finish Hardware. 2. Pulls: 1) SL-86, 8-11116" high, 6" wide, 1-3/8" recess and 1-112" bottom opening. 3. Receive Hardware supplied in accordance with this Section, and coordinate with the Hardware requirements of this section. Report discrepancies (in writing) to the Architect immediately. 4. 5. Door Bottoms :Adjustable Sweep: 1 SL-301 For exterior doors only. Reinforce, cut, drill and tap doors and frames as required to receive Hardware, except do not drill and tap for surface mounted closers and holders, which will be applied at the jobsite. Comply with Hardware manufacturer's instructions and template requirements. Use concealed fasteners wherever possible. 6. Install all Hardware, except surface mounted closers and holders, at the fabrication plant. Remove only Hardware as required for [mal finishing or delivery to jobsite. Package and identify such Hardware and ship with doors and frames for installation at the project site. 7. Painting: All existing surfaces to remain exposed, and all disturbed areas shall be painted to match existing surfaces. F. Heavy-Duty Doors and Frames: SDI A250.8, Level 2. At locations indicated in the Door and Frame Schedule. 1. Physical Performance: Level C according to SDI A250.4. 2. All doors shall be pre-machined in accordance with templates from the hardware manufacturer. For surface applied hardware doors shall have necessary reinforcement, including the attachment of RlVNUT blind bolt fasteners. With the exception of door closures and holders, which require field applications, doors are to be shipped with hardware attached. 3. Face sheets to be locked in with extruded interlocking edges. (No Snap-On trim will be accepted.) 4. Submit Evaluation report that doors do not require thermal barrier for non rated doors. ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 6 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 PART 3 - EXECUTION 3.01 EXAMINATION A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work. B. Examine roughing-in for embedded and built-in anchors to verify actual locations before frame installation. C. Prepare written report, endorsed by Installer, listing conditions detrimental to performance of the Work. D. Proceed with installation only after unsatisfactory conditions have been corrected. 3.02 PREPARATION A. Remove welded-in shipping spreaders installed at factory. Restore exposed finish by grinding, filling, and dressing, as required to make repaired area smooth, flush, and invisible on exposed faces. B. Drill and tap doors and frames to receive nontemplated, mortised, and surface-mounted door hardware. 3.03 INSTALLATION A. General: Install FRP doors plumb, rigid, properly aligned, and securely fastened in place. Comply with Drawings and manufacturer's written instructions. B. Aluminum Frames: Install aluminum frames of size and profile indicated. 1. Set frames accurately in position; plumbed, aligned, and braced securely until permanent anchors are set. After wall construction is complete, remove temporary braces, leaving surfaces smooth and undamaged. a. Where frames are fabricated in sections because of shipping or handling limitations, field splice at approved locations by welding face joint continuously; grind, fill, dress, and make splice smooth, flush, and invisible on exposed faces. b. Install frames with removable stops located on secure side of opening. c. Install door silencers in frames before grouting. d. Remove temporary braces necessary for installation only after frames have been properly set and secured. e. Check plumb, square, and twist of frames as walls are constructed. Shim as necessary to comply with installation tolerances. f. Field apply bituminous coating to backs of frames that will be filled with grout containing antifreezing agents. 2. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to floor, and secure with postinstalled expansion anchors. a. Floor anchors may be set with power-actuated fasteners instead of postinstalled expansion anchors if so indicated and approved on Shop Drawings. ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 7 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3. 4. 5. 6. 7. 8. Metal-Stud Partitions: Solidly pack mineral-fiber insulation inside frames. Masonry Walls: Coordinate installation of frames to allow for solidly filling space between frames and masonry with grout. Concrete Walls: Solidly fill space between frames and concrete with mineral-fiber insulation. In-Place Concrete or Masonry Construction: Secure frames in place with postinstalled expansion anchors. Countersink anchors, and fill and make smooth, flush, and invisible on exposed faces. In-Place Metal or Wood-Stud Partitions: Secure slip-on drywall frames in place according to manufacturer's written instructions. Installation Tolerances: Adjust hollow-metal door frames for squareness, alignment, twist, and plumb to the following tolerances: a. b. c. d. 3.04 NOVEMBER 19TH, 2013 Squareness: Plus or minus 1/16 inch (1.6 mm), measured at door rabbet on a line 90 degrees from jamb perpendicular to frame head. Alignment: Plus or minus 1/16 inch (1.6 mm), measured at jambs on a horizontal line parallel to plane of wall. Twist: Plus or minus 1/16 inch (1.6 mm), measured at opposite face corners of jambs on parallel lines, and perpendicular to plane of wall. Plumbness: Plus or minus 1/16 inch (1.6 mm), measured at jambs at floor. ADJUSTING AND CLEANING A. Final Adjustments: Check and readjust operating hardware items immediately before final inspection. Leave work in complete and proper operating condition. Remove and replace defective work, including hollow-metal work that is warped, bowed, or otherwise unacceptable. B. Remove grout and other bonding material from hollow-metal work immediately after installation. C. Prime-Coat Touchup: Immediately after erection, sand smooth rusted or damaged areas of prime coat and apply touchup of compatible air-drying, rust-inhibitive primer. D. Metallic-Coated Surface Touchup: Clean abraded areas and repair with galvanizing repair paint according to manufacturer's written instructions. E. Factory-Finish Touchup: Clean abraded areas and repair with same material used for factory finish according to manufacturer's written instructions. F. Touchup Painting: Cleaning and touchup painting of abraded areas of paint are specified in painting Sections. 3.05 A. WASTE MANAGEMENT Coordinate with Section 01 74 19. 1. 2. 3. Separate and recycle cut-offs and waste materials and material packaging in accordance with Waste Management Plan and to the maximum extent economically feasible and place in designated areas for recycling. Set aside and protect materials suitable for reuse and/or remanufacturing. Separate and fold up metal banding; flatten and place along with other scrap for recycling. ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 8 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 END OF SECTION 08 1113 ALUMINUM FRAMES & F.R.P. DOORS 08 1255 - 9 of 9 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 08 4523 – INSULATED TRANSLUSCENT FIBERGLASS WALL SYSTEM PART 1 - GENERAL 1.1 SUMMARY A. Section includes the insulated translucent sandwich panel system and accessories as shown and specified. Work includes providing and installing: 1. Flat factory prefabricated structural insulated translucent sandwich panels 2. Aluminum installation system 3. Aluminum sill flashing B. Related Sections: 1. 2. 3. 4. Section 06 1000 - Rough Carpentry Section 07 6200 - Sheet Metal Flashing and Trim Section 07 9200 - Joint Protection Section 08 8000 - Glazing 1.2 SUBMITTALS A. Submit manufacturer’s product data. Include construction details, material descriptions, profiles and finishes of components. B. Submit shop drawings. Include elevations and details. C. Submit manufacturer's color charts showing the full range of colors available for factory-finished aluminum. 1. When requested, submit samples for each exposed finish required, in same thickness and material indicated for the work and in size indicated below. If finishes involve normal color variations, include sample sets consisting of two or more units showing the full range of variations expected. a. b. Sandwich panels: 14” x 28” units Factory finished aluminum: 5” long sections D. Submit Installer Certificate, signed by installer, certifying compliance with project qualification requirements. E. Submit product reports from a qualified independent testing agency indicating each type and class of panel system complies with the project performance requirements, based on comprehensive testing of current products. Previously completed reports will be acceptable if for current manufacturer and indicative of products used on this project. 1. Reports required are: a. b. c. International Building Code Evaluation Report Flame Spread and Smoke Developed (UL 723) – Submit UL Card Burn Extent (ASTM D 635) INSULATED TRANSLUSCENT FIBERGLASS WALL SYSTEM 08 4523 - 1 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 d. e. f. g. h. i. j. k. l. m. n. o. p. q. r. NOVEMBER 19TH, 2013 Color Difference (ASTM D 2244) Impact Strength (UL 972) Bond Tensile Strength (ASTM C 297 after aging by ASTM D 1037) Bond Shear Strength (ASTM D 1002) Beam Bending Strength (ASTM E 72) Insulation U-Factor (NFRC 100) NFRC System U-Factor Certification (NFRC 700) Solar Heat Gain Coefficient (NFRC or Calculations) Condensation Resistance Factor (AAMA 1503) Air Leakage (ASTM E 283) Structural Performance (ASTM E 330) Water Penetration (ASTM E 331) 1200°F Fire Resistance (SWRI) LEED Credits Daylight Autonomy 1.3 QUALITY ASSURANCE A. Manufacturer's Qualifications 1. Material and products shall be manufactured by a company continuously and regularly employed in the manufacture of specified materials for a period of at least ten consecutive years and which can show evidence of those materials being satisfactorily used on at least six projects of similar size, scope and location. At least three of the projects shall have been in successful use for ten years or longer. 2. Panel system must be listed by an ANSI accredited Evaluation Service, which requires quality control inspections and fire, structural and water infiltration testing of sandwich panel systems by an accredited agency. 3. Quality control inspections shall be conducted at least once each year and shall include manufacturing facilities, sandwich panel components and production sandwich panels for conformance with AC177 “Translucent Fiberglass Reinforced Plastic (FRP) Faced Panel Wall, Roof and Skylight Systems” as issued by the ICC-ES. B. Installer’s Qualifications: Installation shall be by an experienced installer, which has been in the business of installing specified panel systems for at least two consecutive years and can show evidence of satisfactory completion of projects of similar size, scope and type. 1.4 PERFORMANCE REQUIREMENTS A. The manufacturer shall be responsible for the configuration and fabrication of the complete panel system. 1. When requested, include structural analysis data signed and sealed by the qualified professional engineer responsible for their preparation. 2. Standard panel system shall have less than 0.01 cfm/ft² air leakage by ASTM E 283 at 6.24 PSF (50 mph) and no water penetration by ASTM E 331 at 15 PSF; and structural testing by ASTM E 330. 3. Structural Loads; Provide system capable of handling the following loads: a. b. Positive Wind Load: PSF Negative Wind Load: PSF INSULATED TRANSLUSCENT FIBERGLASS WALL SYSTEM 08 4523 - 2 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 1.5 DELIVERY STORAGE AND HANDLING A. Deliver panel system, components and materials in manufacturer's standard protective packaging. B. Store panels on the long edge; several inches above the ground, blocked and under cover in accordance with manufacturer's storage and handling instructions. 1.6 WARRANTY A. Submit manufacturer's and installer's written warranty agreeing to repair or replace panel system work, which fails in materials or workmanship within one year of the date of delivery. Failure of materials or workmanship shall include leakage, excessive deflection, deterioration of finish on metal in excess of normal weathering and defects in accessories, insulated translucent sandwich panels and other components of the work. PART 2 - PRODUCTS 2.1 MANUFACTURER A. The basis for this specification is for products manufactured by Kalwall Corporation. Other manufacturers may bid this project provided they comply with all of the performance requirements of this specification and submit evidence thereof. Listing other manufacturers’ names in this specification does not constitute approval of their products or relieve them of compliance with all the performance requirements contained herein. B. Kalwall Corporation, Tel: (800) 258-9777 – Fax: (603) 627-7905 – Email: info@kalwall.com 2.2 PANEL COMPONENTS A. Face Sheets 1. Translucent faces: Manufactured from glass fiber reinforced thermoset resins, formulated specifically for architectural use. a. Thermoplastic (e.g. polycarbonate, acrylic) faces are not acceptable. b. Face sheets shall not deform, deflect or drip when subjected to fire or flame. 2. Interior face sheets: a. Flame spread: Underwriters Laboratories (UL) listed, which requires periodic unannounced retesting, with flame spread rating no greater than 50 and smoke developed no greater than 250 when tested in accordance with UL 723. b. Burn extent by ASTM D 635 shall be no greater than 1”. 3. Exterior face sheets: a. Color stability: Full thickness of the exterior face sheet shall not change color more than 3 CIE Units DELTA E by ASTM D 2244 after 5 years outdoor South Florida weathering at 5° facing south, determined by the average of at least three white samples with and without a protective film or coating to ensure long-term color stability. Color stability shall be unaffected by abrasion or scratching. INSULATED TRANSLUSCENT FIBERGLASS WALL SYSTEM 08 4523 - 3 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 b. Strength: Exterior face sheet shall be uniform in strength, impenetrable by hand held pencil and repel an impact minimum of 70 ft. lbs. without fracture or tear when impacted by a 3-1/4” diameter, 5 lb. free-falling ball per UL 972. 4. Appearance: a. Exterior face sheets: Smooth _0.070”_ thick and __white___ in color. b. Interior face sheets: Smooth _0.045”_ thick and __white____ in color. c. Face sheets shall not vary more than ± 10% in thickness and be uniform in color. B. Grid Core 1. Thermally broken composite I-beam grid core shall be of 6005-T5 alloy and temper with provisions for mechanical interlocking of muntin-mullion and perimeter. Width of I-beam shall be no less than 7/16”. 2. I-beam Thermal break: Minimum 2”, thermoset fiberglass composite. C. Laminate Adhesive 1. Heat and pressure resin type adhesive engineered for structural sandwich panel use, with minimum 25-years field use. Adhesive shall pass testing requirements specified by the International Code Council “Acceptance Criteria for Sandwich Panel Adhesives.” 2. Minimum tensile strength of 750 PSI when the panel assembly is tested by ASTM C 297 after two exposures to six cycles each of the aging conditions prescribed by ASTM D 1037. 3. Minimum shear strength of the panel adhesive by ASTM D 1002 after exposure to four separate conditions: a. b. c. d. 50% Relative Humidity at 68° F: 540 PSI 182° F: 100 PSI Accelerated Aging by ASTM D 1037 at room temperature: 800 PSI Accelerated Aging by ASTM D 1037 at 182° F: 250 PSI 2.3 PANEL CONSTRUCTION A. Provide sandwich panels of flat fiberglass reinforced translucent face sheets laminated to a grid core of mechanically interlocking I-beams. The adhesive bonding line shall be straight, cover the entire width of the I-beam and have a neat, sharp edge. 1. 2. 3. 4. 5. 6. Thickness: 4” Light transmission: __20_% Solar heat gain coefficient ___0.38_. Panel U-factor by NFRC certified laboratory: 4” thermally broken grid _.55__. Complete insulated panel system shall have NFRC certified U-factor of .20_. Grid pattern: Nominal size _________; pattern __Verti-Kal__. B. Standard panels shall deflect no more than 1.0” at 30 PSF in 10’ 0” span without a supporting frame by ASTM E 72. C. Standard panels shall withstand 1200°F fire for minimum one hour without collapse or exterior flaming. D. Thermally broken panels: Minimum Condensation Resistance Factor of 85 by AAMA 1503 measured on the bond line. 2.4 BATTENS AND PERIMETER CLOSURE SYSTEM INSULATED TRANSLUSCENT FIBERGLASS WALL SYSTEM 08 4523 - 4 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 A. NOVEMBER 19TH, 2013 Closure system: Thermally broken extruded aluminum 6063-T6 and 6063-T5 alloy and temper clamp-tite screw type closure system. B. Sealing tape: Manufacturer's standard, pre-applied to closure system at the factory under controlled conditions. C. Fasteners: 300 series stainless steel screws for aluminum closures, excluding final fasteners to the building. D. Finish: 1. Manufacturer's factory applied finish, which meets the performance requirements of AAMA 2604. Color to match existing aluminum frames (selected from manufacturer's standards). PART 3 - EXECUTION 3.1 EXAMINATION A. Installer shall examine substrates, supporting structure and installation conditions. B. Do not proceed with panel installation until unsatisfactory conditions have been corrected. 3.2 PREPARATION A. Metal Protection: 1. Where aluminum will contact dissimilar metals, protect against galvanic action by painting contact surfaces with primer or by applying sealant or tape recommended by manufacturer for this purpose. 2. Where aluminum will contact concrete, masonry or pressure treated wood, protect against corrosion by painting contact surfaces with bituminous paint or method recommended by manufacturer. 3.3 INSTALLATION A. Install the panel system in accordance with the manufacturer's installation recommendations and approved shop drawings. 1. Anchor component parts securely in place by permanent mechanical attachment system. 2. Accommodate thermal and mechanical movements. 3. Set perimeter framing in a full bed of sealant compound, or with joint fillers or gaskets to provide weather-tight construction. B. Install joint sealants at perimeter joints and within the panel system in accordance with manufacturer's installation instructions. 3.4 CLEANING A. Clean the panel system inside and outside, immediately after installation. B. Refer to manufacturer's written recommendations. END OF SECTION 08 45 23 INSULATED TRANSLUSCENT FIBERGLASS WALL SYSTEM 08 4523 - 5 of 5 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 085113 - ALUMINUM WINDOWS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This Section includes fixed and/or operable aluminum-framed windows for exterior locations. B. Related Sections include the following: 1. 2. 1.3 Division 08 Section "Aluminum-Framed Entrances and Storefronts" for coordinating finish among aluminum fenestration units. Division 08 Section "Glazing" for additional glazing requirements for aluminum windows. DEFINITIONS A. Performance class designations according to AAMA/WDMA/CSA 101/I.S.2/A440-05: 1. B. AW: Architectural. Performance grade number according to AAMA/WDMA/CSA 101/I.S.2/A440-05: 1. Design pressure number in pounds force per square foot (pascals) used to determine the structural test pressure and water test pressure. C. Structural Test Pressure: For uniform load structural test, is equivalent to 150 percent of the design pressure. D. Minimum Test Size: Smallest size permitted for performance class (gateway test size) or as specified elsewhere in this section, whichever is more stringent. Products must be tested at minimum test size or at a size larger than minimum test size to comply with requirements for performance class. Downsized test reports will not be considered acceptable. 1.4 PERFORMANCE REQUIREMENTS A. General: Provide aluminum windows capable of complying with performance requirements indicated, based on testing manufacturer's windows that are representative of those specified, and that are of minimum test size indicated below: 1. B. Outswing Projected Windows: 36” x 60”. Structural Performance: Provide aluminum windows capable of withstanding the effects of the following loads, based on testing units of the minimum test size specified herein that pass ALUMINUM WINDOW 085113 - 1 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 AAMA/WDMA/CSA 101/I.S.2/A440-05, Uniform Load Structural and Uniform Load Deflection Tests: 1.5 1. Uniform Load Structural Test: 180 psf (positive and negative). 2. Uniform Load Deflection Test: 120 psf (positive and negative). SUBMITTALS A. Product Data: Include construction details, material descriptions, fabrication methods, dimensions of individual components and profiles, hardware, finishes, and operating instructions for each type of aluminum window indicated. B. Shop Drawings: Include plans, elevations, sections, details, hardware, attachments to other work, operational clearances, installation details, and the following: 1. 2. 3. 4. 5. C. Mullion details, including reinforcement and stiffeners. Joinery details. Weather-stripping details. Thermal-break details. Glazing details. Samples for Initial Selection: For units with factory-applied color finishes. 1. Include similar samples of hardware and accessories involving color selection. D. Maintenance Data: For operable window sash, operating hardware and finishes to include in maintenance manuals. E. Warranty: Special warranty specified in this Section. 1.6 QUALITY ASSURANCE A. Product Qualifications: In order to confirm that the proposed product(s) conform to the material and performance requirements contained in these specifications, bidders shall include the following with their bid. Failure to comply with these requirements shall cause the bid to automatically be rejected. 1. 2. 3. Bidder’s Acknowledgement: Bidders shall include a letter in their bid stating the manufacturer and series (model) number of the product upon which its bid has been based. Changes in product (manufacturer or series) will not be permitted after the bid. Product Test Reports: Bidders submitting bids based on products other than the Basis of Design product listed in Paragraph 2.1 must also include with their bid comprehensive test reports not more than four years old prepared by a qualified testing agency for each window type being used on the project. Test reports based on the use of downsized test units will not be accepted. Product Details: Bidders submitting bids based on products other than the Basis of Design product listed in Paragraph 2.1 must also include with their bid full size product details showing all frame and sash details, dimensions, thermal break construction, wall thicknesses and joinery. Details must accurately reflect all glazing and hardware options specified herein. ALUMINUM WINDOW 085113 - 2 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Product Requirements: For maximum performance, windows for this project must meet both the testing requirements as contained herein and the minimum material requirements specified. Windows that carry the applicable AAMA rating but do not meet the material thicknesses, depths, etc. shall not be acceptable for use on this project. C. Installer Qualifications: An installer acceptable to aluminum window manufacturer for installation of units required for this Project. D. Source Limitations: Obtain aluminum windows through one source from a single manufacturer. E. Product Options: Drawings indicate size, profiles, and dimensional requirements of aluminum windows and are based on the specific system indicated. Do not modify size and dimensional requirements. 1. F. Do not modify intended aesthetic effects, as judged solely by Architect, except with Architect's approval. If modifications are proposed, submit comprehensive explanatory data to Architect for review. Fenestration Standard: Comply with AAMA/WDMA/CSA 101/I.S.2/A440-05, "Standard/Specification for Windows, Doors, and Unit Skylights” for definitions and minimum standards of performance, materials, components, accessories, and fabrication. Comply with more stringent requirements if indicated. 1. Provide AAMA-certified aluminum windows. G. Glazing Publications: Comply with published recommendations of glass manufacturers and with GANA's "Glazing Manual" unless more stringent requirements are indicated. H. Preinstallation Conference: If requested, conduct conference at project site to review methods and procedures related to aluminum windows including, but not limited to, the following: 1. 2. 3. 4. 1.7 Review and finalize construction schedule and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays. Review, discuss, and coordinate the interrelationship of aluminum windows with other exterior wall components. Review and discuss the sequence of work required to construct a watertight and weathertight exterior building envelope. Inspect and discuss the condition of substrate and other preparatory work performed by other trades. PROJECT CONDITIONS A. Field Measurements: For retrofit installations, verify aluminum window openings by field measurements before fabrication and indicate measurements on Shop Drawings. 1. Established Dimensions: Where field measurements cannot be made without delaying the Work, establish opening dimensions and proceed with fabricating aluminum windows without field measurements. Coordinate wall construction to ensure that actual opening dimensions correspond to established dimensions. ALUMINUM WINDOW 085113 - 3 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.8 NOVEMBER 19TH, 2013 WARRANTY A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace aluminum windows that fail in materials or workmanship within specified warranty period. 1. Failures include, but are not limited to, the following: a. b. c. d. e. 2. Failure to meet performance requirements. Structural failures including excessive deflection, water leakage, or air infiltration. Faulty operation of movable sash and hardware. Deterioration of metals or other materials beyond that which is normal. Failure of insulating glass. Warranty Period: a. b. c. Window: Two years from date of Substantial Completion. Insulated Glazing: 10 years from date of Substantial Completion. Painted Metal Finishes: 1) Five years from date of Substantial Completion for AAMA 2603 Baked Enamel Finishes. 2) Twenty years from date of Substantial Completion for AAMA 2605 Superior Performance Finishes. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Basis-of-Design Product: The basis of design for these specifications is the Standard E-Series Project-Out windows as manufactured by Kalwall Corporation, Manchester, NY. B. Equivalents: Subject to compliance with all material; siteline and performance requirements outlined in these specifications, “or equal” products by other manufacturers will be considered for use subject to review by the Architect. The Architect’s decision regarding equivalency is final. 2.2 MATERIALS A. Aluminum Extrusions: Frame and sash are constructed of tubular extruded 6063-T5 aluminum. Enhanced thermal performance and mechanical strength is achieved using polyamide Insulbar® thermal strut construction. All frame and sash corners are mitered and joined using heavy internal aluminum corner gussets that are mechanically staked and epoxy sealed. All openings are double sealed using continuous EPDM bulb, foam and wedge weather stripping to insure minimum air infiltration and maximum water resistance. Snap-in aluminum glazing bead for ease of field glazing. Operating and fixed windows self-drain to the building exterior. B. Frame Depth: 2 ¾” minimum. C. Fasteners: Aluminum, nonmagnetic stainless steel, epoxy adhesive, or other materials warranted by manufacturer to be noncorrosive and compatible with aluminum window members, trim, hardware, anchors, and other components. ALUMINUM WINDOW 085113 - 4 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 2. NOVEMBER 19TH, 2013 All fasteners must be concealed except where unavoidable for application of hardware. For application of hardware, where required, use non-magnetic stainless steel phillips machine screws. D. Anchors, Clips, and Accessories: Aluminum, nonmagnetic stainless steel, or zinc-coated steel or iron complying with ASTM B 633 for SC 3 severe service conditions; provide sufficient strength to withstand design pressure indicated. E. Compression-Type Weather Stripping: Provide compressible weather stripping designed for permanently resilient sealing under bumper or wiper action and for complete concealment when aluminum window is closed. 1. F. Weather-Stripping Material: Manufacturer's standard system and materials complying with AAMA/WDMA/CSA 101/I.S.2/A440-05. Sliding-Type Weather Stripping: Provide woven-pile weather stripping of wool, polypropylene, or nylon pile and resin-impregnated backing fabric. Comply with AAMA 701/702. 1. Weather Seals: Provide weather stripping with integral barrier fin or fins of semirigid, polypropylene sheet or polypropylene-coated material. Comply with AAMA 701/702. G. Replaceable Weather Seals: Comply with AAMA 701/702. H. Sealant: For sealants required within fabricated windows, provide window manufacturer's standard, permanently elastic, nonshrinking, and nonmigrating type recommended by sealant manufacturer for joint size and movement. 2.3 WINDOW A. Window Type: Outswing Casement, Project-Out B. AAMA/WDMA Performance Requirements: Provide aluminum windows of performance indicated that comply with AAMA/WDMA/CSA 101/I.S.2/A440-05. 1. Performance Class and Grade: AW120 (casement), AW110 (projected) . C. Condensation-Resistance Factor (CRF): Provide aluminum windows tested for thermal performance according to AAMA 1503, showing a minimum CRF of 56. D. Thermal Transmittance: Provide aluminum windows with a whole-window, U-factor maximum indicated at 15-mph (24-km/h) exterior wind velocity and winter condition temperatures when tested using Solarban 60 Low-E glass according to AAMA 1503. 1. E. U-Factor: 0.46 Btu/sq. ft. x h x deg F or less. Air Infiltration: Maximum rate not more than indicated when tested according to AAMA/WDMA/CSA 101/I.S.2/A440-05, Air Infiltration Test. 1. Maximum Rate: 0.10 cfm/sq. ft. of area at an inward test pressure of 6.24 lbf/sq. ft. (300 Pa). ALUMINUM WINDOW 085113 - 5 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 F. NOVEMBER 19TH, 2013 Water Resistance: No water leakage as defined in AAMA/WDMA referenced test methods at a water test pressure equaling that indicated, when tested according to AAMA/WDMA 101/I.S.2/NAFS, Water Resistance Test. 1. Test Pressure: 20 percent of positive design pressure, but not less than 30 lbf/sq. ft.. G. Forced-Entry Resistance: according to ASTM F 588. H. Life-Cycle Testing: Test according AAMA/WDMA/CSA 101/I.S.2/A440-05. I. Operating Force and Auxiliary (Durability) Tests: AAMA/WDMA/CSA 101/I.S.2/A440-05 for operating window types indicated. 2.4 Comply with Performance Grade 10 requirements when tested to AAMA 910 and comply Comply with with INSULATED GLAZING A. Construction: All windows (except those receiving insulated panels) shall be factory glazed with hermetically sealed 1 1/8” insulating glass units with a dual seal of polyisobutylene and silicone and a desicant filled aluminum spacer. Insulated glass shall be 1 1/8” deep and must be certified for a CBA rating. Insulated glass in vents shall be structurally glazed (non-structurally glazed vents or those using any other glazing methods shall not be acceptable. 1. 2.5 Standard E-Series Window: a. Thickness: Operating sash to be glazed with 1” double glazing Kalwall panels. b. Tint: Crystal HARDWARE A. General: Provide manufacturer's standard hardware fabricated from aluminum, stainless steel, carbon steel complying with AAMA 907, or other corrosion-resistant material compatible with aluminum; designed to smoothly operate, tightly close, and securely lock aluminum windows and sized to accommodate sash or ventilator weight and dimensions. Do not use aluminum in frictional contact with other metals. B. Locks and Latches: Designed to allow unobstructed movement of the sash across adjacent sash in direction indicated and operated from the inside only. C. Project-Out Windows: Provide the following operating hardware. 1. Multi point non-locking (Euro-groove) handles standard on all operating sash (locking handles option). Handles are available in white, black or silver. 2. Hinges: Heavy-duty stainless steel 4 bar hinges; Fully adjustable friction shoes; standard projection = 45 degrees, 2.6 INSECT SCREENS A. General: Design windows and hardware to accommodate screens in a tight-fitting, removable arrangement, with a minimum of exposed fasteners and latches. Locate screens on inside of window. ALUMINUM WINDOW 085113 - 6 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 B. Aluminum Insect Screen Frames: Manufacturer's standard aluminum alloy complying with SMA 1004. Fabricate frames with mitered or coped joints or corner extrusions, concealed fasteners, and removable PVC spline/anchor concealing edge of frame. 1. 2. C. Extruded-Aluminum Tubular Framing Sections and Cross Braces: Not less than 0.050inch (1.3-mm) wall thickness. Finish: Match aluminum window members. Aluminum Wire Fabric: 18-by-16 (1.1-by-1.3-mm) mesh of 0.011-inch- (0.28-mm-) diameter, coated aluminum wire. 1. 2.7 NOVEMBER 19TH, 2013 Wire-Fabric Finish: Natural bright. FABRICATION A. Windows must be flush vent design (overlapping vents will not be acceptable). B. Vents and fixed lites must have equal sightlines. C. Vents and fixed lites must have an integral exterior bevel. D. Window sightlines cannot exceed those indicated on drawings in order to maintain the intended historic integrity. E. Fabricate aluminum windows in sizes indicated. Include a complete system for assembling components and anchoring windows. F. Fabricate aluminum windows that are reglazable without dismantling sash or ventilator framing. G. Thermally Improved Construction: Fabricate aluminum windows with an integral, concealed (products with exposed thermal barriers will not be acceptable), low-conductance thermal barrier; located between exterior materials and window members exposed on interior side; in a manner that eliminates direct metal-to-metal contact. 1. 2. 3. 4. All exterior aluminum shall be separated from interior aluminum by a rigid, structural thermal barrier. For purposes of this specification, a structural thermal barrier is defined as a system that shall transfer shear during bending and, therefore, promote composite action between the exterior and interior extrusions. No thermal short circuits shall occur between the exterior and interior. The thermal barrier shall be INSULBAR® or equal, and shall consist of two glass reinforced polyamide nylon 6/6 struts mechanically crimped in raceways extruded in the exterior and interior extrusions. Poured and debridged urethane thermal barriers shall not be permitted. H. Weather Stripping: ventilator. I. Mullions: Provide mullions and cover plates as shown, matching window units, complete with anchors for support to structure and installation of window units. Allow for erection tolerances and provide for movement of window units due to thermal expansion and building deflections, as indicated. Provide mullions and cover plates capable of withstanding design loads of window units. ALUMINUM WINDOW Provide full-perimeter weather stripping for each operable sash and 085113 - 7 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 J. Subframes: Provide subframes with anchors for window units as shown, of profile and dimensions indicated but not less than 0.093-inch thick extruded aluminum. Finish to match window units. Provide subframes capable of withstanding design loads of window units. K. Factory-Glazed Fabrication: Glaze aluminum windows in the factory where practical and possible for applications indicated. Comply with requirements in Division 08 Section "Glazing" and with AAMA/WDMA/CSA 101/I.S.2/A440-05. L. Glazing Stops: Provide snap-on glazing stops coordinated with Division 08 Section "Glazing" and glazing system indicated. Provide glazing stops to match sash and ventilator frames. M. Muntins: Where shown on drawings, muntins shall be 3/4” x 7/8” beveled extruded aluminum applied to the exterior of 1 1/8” deep insulating glass (roll formed muntins shall not be acceptable). 2.8 FINISHES, GENERAL A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes. B. Finish designations prefixed by AA comply with the system established by the Aluminum Association for designating aluminum finishes. C. Exterior of Window: 1. Superior-Performance Organic Finish: AA-C12C40R1x (Chemical Finish: cleaned with inhibited chemicals; Chemical Finish: acid-chromate-fluoride-phosphate conversion coating; Organic Coating: as specified below). Prepare, pretreat, and apply coating to exposed metal surfaces to comply with AAMA 2605 and with coating and resin manufacturer’s written instructions. a. b. D. Fluoropolymer Two-Coat System: Manufacturer’s standard [two-coat] [three-coat] thermocured system consisting of specially formulated inhibitive primer and fluoropolymer color topcoat containing not less than 70 percent polyvinylidene fluoride resin by weight; complying with AAMA 2605. Color: As selected by Architect from manufacturer’s standard colors. (Note: Exterior color may be different from interior color.) Interior of Window: 1. Baked-Enamel Finish: AA-C12C42R1x (Chemical Finish: cleaned with inhibited chemicals; Chemical Finish: acid-chromate-fluoride-phosphate conversion coating; Organic Coating: as specified below). Apply baked enamel complying with paint manufacturer's written instructions for cleaning, conversion coating, and painting. a. b. ALUMINUM WINDOW Organic Coating: Thermosetting, modified-acrylic enamel primer/topcoat system complying with AAMA 2603 Organic Coating: Thermosetting, modified-acrylic enamel primer/topcoat system complying with AAMA 2603. Color: As selected by Architect from manufacturer’s standard colors. (Note: Exterior color may be different from interior color.) 085113 - 8 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 PART 3 - EXECUTION 3.1 EXAMINATION A. Examine openings, substrates, structural support, anchorage, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of work. Verify rough opening dimensions, levelness of sill plate, and operational clearances. Examine wall flashings, vapor retarders, water and weather barriers, and other built-in components to ensure a coordinated, weathertight window installation. 1. 2. 3. 4. 3.2 Masonry Surfaces: Visibly dry and free of excess mortar, sand, and other construction debris. Wood Frame Walls: Dry, clean, sound, well nailed, free of voids, and without offsets at joints. Ensure that nail heads are driven flush with surfaces in opening and within 3 inches (76 mm) of opening. Metal Surfaces: Dry; clean; free of grease, oil, dirt, rust, corrosion, and welding slag; without sharp edges or offsets at joints. Proceed with installation only after unsatisfactory conditions have been corrected. INSTALLATION A. Comply with Drawings, Shop Drawings, and manufacturer's written instructions for installing windows, hardware, accessories, and other components. B. Install windows level, plumb, square, true to line, without distortion or impeding thermal movement, anchored securely in place to structural support. C. Set sill members in bed of sealant or with gaskets, as indicated, for weathertight construction. D. Install windows and components to drain condensation, water penetrating joints, and moisture migrating within windows to the exterior. E. Separate aluminum and other corrodible surfaces from sources of corrosion or electrolytic action at points of contact with other materials. 3.3 FACTORY TESTING A. 3.4 One window for each seventy-five manufactured shall be randomly selected by the Owner and Architect to be tested at the manufacturer’s facility for air and water infiltration in order to confirm compliance of the project’s windows with the performance requirements contained in these specifications. Bidders are to include the cost of transportation, food, and lodging for four representatives of the Owner and/or Architect to witness these tests. ADJUSTING, CLEANING, AND PROTECTION A. Adjust operating sashes and ventilators, screens, hardware, and accessories for a tight fit at contact points and weather stripping for smooth operation and weathertight closure. Lubricate hardware and moving parts. B. Manufacturer shall clean all glass and aluminum prior to shipment. ALUMINUM WINDOW 085113 - 9 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 C. Protection of newly installed windows and/or final cleaning of glass and aluminum to remove any accumulations that may have occurred during the construction period is to be the responsibility of the General Contractor or Owner. D. Comply with manufacturer’s written recommendations for final cleaning and maintenance. 3.5 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain window operating system. END OF SECTION 085113 ALUMINUM WINDOW 085113 - 10 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 08 7100 - FINISH HARDWARE PART 1 - GENERAL 1.1 SECTION INCLUDES A. 1.2 QUALITY ASSURANCE A. 1.3 The required hardware items for doors are indicated in hardware sets shown herein. Should any opening be omitted, hardware shall be provided as specified for other doors of similar locations, function, quality and design. Standards: All finish hardware shall conform to all the following standards: 1. Testing Laboratories: Underwriters Laboratory (UL) and or Warnock Hersey Fire Laboratories Division: All fire rated doors shall have hardware assemblies approved by one of the listed laboratories. Panic hardware UL Listed only. 2. National Fire Protection Association: NFPA 80 and NFPA 101. 3. Builders Hardware Manufacturers Association (BHMA). 4. American National Standards Institute (ANSI). 5. American Disabilities Act (ADA). B. All products specified shall comply with the Buy American Act. C. Supplier: Finish hardware shall be furnished by those having a minimum of 5 years of builders hardware experience and shall have in their employ at least one certified Architectural Hardware Consultants (AHC) to correctly interpret the plans, detailed drawings and specifications. SUBMITTALS A. General: Submit the following in accordance with the provisions of the general contract documents. B. Hardware Schedule: Submit three (3) copies of a vertical hardware schedule. Horizontal schedules will not be accepted. Follow Door and Hardware Institute (DHI) guide lines for scheduling. At the end of the schedule list each door number with appropriate heading number and hardware set number. Furnish initial draft of schedule at the earliest possible date, in order to facilitate the fabrication of other work. Furnish final schedule after samples, manufacturer's data sheets have been approved. C. Product Data: Submit three (3) copies of the manufacturer’s data for each item of hardware. Include whatever information may be necessary to show compliance with requirements. D. Keying Schedule: A key schedule showing all key numbers and spaces to which each permits entry, shall be provided. Consult with OWNER before submitting final key schedule. After final approval has been received, the schedule and the key cabinet, along FINISH HARDWARE 08 7100-1 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 with the key gathering envelopes containing keys for each lock endorsed with lock number and space designation, shall be turned over to the OWNERS. 1.4 1.5 1.6 E. Samples: Prior to submittal of the final hardware schedule and prior to delivery of hardware, submit one (1) sample of each exposed hardware unit. Sample will be reviewed by the ARCHITECT for design, color and texture only. Compliance with other requirements is the exclusive responsibility of the CONTRACTOR. Samples approved by the ARCHITECT shall be turned over to the OWNER for attic stock. F. Wiring Diagrams: Supplier shall furnish riser diagrams, wiring diagrams and point to point diagrams for all electrical hardware specified herein. These diagrams shall be included with the initial draft of the hardware schedule. PRODUCT HANDLING A. Handle, store, distribute, protect and install in accordance with the manufacture's instructions. Deliver packaged material in original containers with seals unbroken and labels intact. Deliver assemblies completely identified and with adequate protection for storage, handling and installation. B. Provide secure lock-up for hardware delivered to the project, but not yet installed. Control the handling and installation of hardware which are not immediately replaceable, so that completion of the work will not be delayed by hardware losses; both before and after installation. PROJECT CONDITIONS A. Coordinate hardware with other work. Tag each item or package separately, with identification related to the final hardware schedule, and include basic installation instructions in the package. Furnish hardware items of proper design for use on doors and frames of the thickness, profile, swing, security and similar requirements indicated and as necessary for proper installation and function. Deliver packaged hardware items to the proper locations for installation. B. Furnish hardware templates to each fabricator of doors, frames and other work to be factory prepared for the installation of hardware. WARRANTIES A. The hardware manufacturers shall provide full replacement warranty as listed below. -Surface Closers -Exit Devices -Locksets etc. -Balance of hardware 25 years. 3 years 1 year 1 year PART 2 - PRODUCTS 2.1 MATERIALS AND FABRICATION A. Hand of Door: The drawings show the swing or hand of each door leaf. Furnish each item of hardware for proper installation and operation of the door swing shown. FINISH HARDWARE 08 7100-2 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2.2 NOVEMBER 19TH, 2013 B. Base Metals: Produce hardware units of the basic metal and forming method indicated, using manufacturer's standard metal alloy, composition, temper and hardness but in no case of lesser quality material. C. Fasteners: Manufacture hardware to conform to published templates, generally prepared for machine screw installation. Do not provide hardware that has been prepared for selftapping sheet metal screws. D. Screws: Furnish screws for installation, with each hardware item. Finish exposed screws to match the hardware finish. E. Tools for Maintenance: Furnish a complete set of specialized tools as needed, for the OWNERS continued maintenance, removal and replacement of hardware. F. Concealed Fasteners: Provide concealed fasteners for hardware units which are exposed when the door is closed except to the extent no standard manufacturer's units are available with concealed fasteners. Use thru bolts only where necessary to adequately fasten hardware to the door. HINGES A. Unless otherwise noted, all hinges shall be full mortise five knuckle ball bearing type, template, with non-rising loose pins. All out swinging doors shall be furnished with nonremovable pins (NRP). B. All hinges for 1-3/4" thick doors shall be 4” wide in the open position. For other thickness doors hinges shall be of a width to permit unobstructed swing of the doors. C. Size and weight of hinges shall conform to the following: -Up to 36" ------------4-1/2" standard weight -Over 36" to 48" --------5" heavy weight D. Quantity of hinges shall be provided to conform to the following: -Doors up to 60" in heights ------------------2 hinges -Doors 60" to 90" in height -----------------3 hinges -Doors 90" and over ---------l hinge every 30" in height E. 2.3 LOCKSETS, LATCHSETS ETC. A. 2.4 All hinges shall be the products of one manufacturer. Unless otherwise noted, all locksets and latchsets shall be heavy-duty mortise type, function as specified in hardware sets. Furnish wrought steel box strikes. Furnish curved lip strikes with proper lip lengths as required. KEYS, KEYING CYLINDERS AND KEY CABINET A. Final keying: requirements to be determined by the Owner. A meeting must take place between the Owner, the end user, the owner's representative, and the hardware distributor prior to cylinders Being ordered, to establish the keying requirements and required keyway. FINISH HARDWARE 08 7100-3 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Key System: Perimeter Doors and doors with electrified access control: Sargent HighSecurity Key Control System. Exterior and Interior doors shall be operated by the same high level Master Key. C. Interchangeable Cores: Sargent 7300B D. Provide Concealed Key Control (CKC) keyset symbol stamping on the side of each master keyed core. Provide visual key control for all operating and master keys. E. Construction keying: provide brass keyed-alike temporary cores plus 10 operating keys for all cylinders,interior and exterior. F. Provide: Three (3) change keys for each keyed lock. Provide (3) control keys for construction cores, and (3) control keys for permanent cores. Provide 10 copies of each level Master Key, Grand Master Key, and/or Great Grand Master Key. Permanent keys and cores: secured shipment direct from point of origination to the owner. Provide bitting list, ship direct from point of origin to the owner upon project completion. G. Provide 500 keyblanks for the owners attic stock. H. Provide a key control system including envelopes. Labels, tags with self-locking key clips, receipt fonns, 3-way visible card index, temporary markers, permanent markers, and standard metal cabinet, all as recommended by system manufacturer, with capacity for 150 percent of the number oflocks required for the project. I. 2.5 Provide four hinged panel type cabinet for wall mounting. DOOR CLOSING DEVICES A. All closers shall have certification by an independent testing laboratory of 10,000,000 cycles without failure. B. Closer cylinders shall be cast iron. Closer pinions shall be dual heat treated. Pinion and piston shall be steel alloy. Piston diameter shall be minimum 1-1/2". C. Closers shall be barrier free with spring tension adjustable from size 1 to size 5. D. Closers shall maintain control of the door in all conditions. Closers shall have 3 non critical adjusting valves: latch, main and backcheck. Backcheck shall take affect at 45 (A VB) degrees of opening for parallel arm closers and 70 degrees for regular arm closers. Closers with pressure relief valves are not acceptable. E. All closers shall have forged main arms. Forearms of parallel arm closers shall be forged. Parallel arm brackets shall be forged. All parallel arm joints shall have bronze bushings with minimum 5/8" diameter pins. Cylinders, arms, brackets and mounting plates shall be powder coated. F. Provide all plates, brackets and special templates when needed for interface with particular header, door and wall conditions and neighboring hardware. Consult factory for special template ("ST" suffix to closer number) pricing. G. All closers shall be installed so that closer bodies are positioned on room side of doors to and from corridors. Out-swing doors shall have an extra heavy duty parallel arm (EDA). Parallel arm shall be used on connecting doors between rooms.B. H. All exterior closers shall have all weather fluid that does not require seasonal adjustment to control speed of door, and shall exhibit the same viscosity from -30 0 F to +1200 F. I. All closers shall have a powder coated aluminum finish on cylinder, arm and accessories. There shall be a full metal, powder coated cover. J. Furnish all brackets, drop plates and any other necessary hardware required to insure proper installation. K. All Closers shall comply with UL 10C requirements for positive pressure testing. FINISH HARDWARE 08 7100-4 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 L. All closers shall be of one manufacturer's products. All closers shall be inspected after installation by a factory representative to insure proper adjustment and operation. M. Closer Series: LCN 4041H CUSH. 2.6 PROTECTION PLATES: A. 2.7 2.8 All kick plates shall be 12” high x 2” less door width x .050 thick, beveled three sides. FLUSH BOLTS: A. Manual Flush Bolts: Shall be Trimco W3917 series; furnish 3910 dustproof strikes for all bottom bolts. Top bolts shall be furnished with proper extensions to allow for easy operation. B. Automatic Flush Bolts: Shall be Trimco 3810/3820 series; furnish 3910 dustproof strikes for all bottom bolts. Furnish wear plates as required. C. All flush bolts and coordinators shall be the products of one manufacturer. EXIT DEVICES: A. Exit Devices shall be touch bar type, as specified in hardware sets. 1. Furnish stainless steel touch bars on all exit devices 2. Touch bar and touch bar end caps shall overlap the mechanism case. 3. Touch bar sub assembly shall be minimum .160" thick, with minimum .060 supports. 4. Touch bar surface shall be minimum 2-114" high x 18" long for 36" doors, and minimum 2-114" high x 24" long for doors wider than 36". 5. Exit device touch bars shall be equipped with a fluid sound dampening feature. B. Furnish exit devices, less bottom rod, on all cross corridor pairs of doors, where doors are for compartmentalization only. C. Rim and Mortise type devices shall have %" throw latch bolt. Surface and Concealed Vertical Rod devices shall have 5/8" throw latch bolts. 1. Latch bolt security deadlocking shall be standard. D. All fire doors shall receive devices U.L. listed Fire Exit Hardware E. Furnish roller strikes, which interlock the door to the frame (499F) for all rim devices and surface vertical rod devices. F. All internal springs shall be compression type. G. Where lever trim is specifIed, levers shall match the balance ·of the project. 1. Escutcheons ·of all lever trim shall be forged brass or bronze, with (4) thru-bolts anchoring trim assembly to exit device chassis 2. Levers shall be solid forged brass or bronze 3. Lever return springs shall be compression type. 4. Cylinders shall be recessed from face of escutcheon. H. Lever trim shall be breakaway type. When rotational force of 35 ft.lbs. is applied, lever trim appears to break. Lever trim can be reset to normal function, without disassembly FINISH HARDWARE 08 7100-5 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 1. Lever shall be protected by a shear pin, which will withstand a rotational force of 55 ft.lbs. before shearing, to prevent further damage to lever. Lever shall not separate from the escutcheon. I. Where electrified latch retraction is specified, provide device with powerful continuous duty solenoid to retract the latch bolt(s) for momentary unlocking or for extended periods of time. 1. Provide appropriate power supply and power transfers, as required for the application. 2. Use only on fire exit devices when under the control of an automatic fire alarm system. 3. Coordinate with electrical specifications and drawings, and owner's security consultant. J. Where electrified trim is specified, provide device with electrically locking (fail safe) or electrically unlocking (fail secure) trim. 1. Provide appropriate power supply & power transfer(s), as required for application. 2. Use only on fIre exit devices when under the control of an automatic fIre alarm system. 3. Coordinate with electrical specifications and drawings, and owner's security consultant. K. Furnish all necessary Glass Bead Kits where exit device may interfere with raised glass beads on doors. L. Certifications: 1. Devices shall be Underwriters Laboratories™listed for Panic Hardware (FVSR) SAI63 2. Fire Devices shall be Underwriters Laboratories™ listed Fire Exit Hardware (GXHX) R450I, A Label 3. Cycle Testing: Exit devices shall be certified by an independent testing lab for 1,000,000 cycles. M. Exit Device Series & Design: Von Duprin 99 series exit devices with outside trim as specified in hardware sets. 2.9 WEATHER SEALS AND THRESHOLDS: A. Weather Seals and Thresholds: Pemco as Scheduled. B. Perimeter seals: shall be of compressible black Neoprene material. Housing shall be solid alum stock. Furnish seals on three sides of the opening. Coordinate the amount of material is required in each specifted opening. C. Seals shall be mechanically fastened to door frame. D. Door sweeps: shall be extruded aluminum and black neoprene sweep. 1. Fasten door sweeps with wood screws for wood doors and sheet metal screws for hollow metal and fiberglass reinforced doors. 2. Door sweep shall be 1 114" in overall height with a W' high neoprene sweep. 3. Mount door sweep on the exterior side of the door, with the neoprene engaged with the threshold or finish floor. E. Thresholds: shall be extruded aluminum meeting ADA requirements. They shall not exceed 114" in height with a wall thickness of .125" unless specified otherwise. Coordinate templates for any and all hardware, which may require cutouts or slots within the threshold for the proper installation of that hardware. 1. Furnish threshold with non-slip epoxy abrasive bonded within the grooves of the threshold. FINISH HARDWARE 08 7100-6 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. 3. 4. NOVEMBER 19TH, 2013 Thresholds shall extend a minimum of 1" past the exterior face of the door, and have returned closed ends. Set all thresholds in grout, and seal with silicone caulk. Fasten thresholds with expansion shield mounting at masonry sub-straight locations, and wood screws at wood substrate locations. PART 3 - EXECUTION 3.1 3.2 3.3 3.4 GENERAL A. Approval: As soon as practical after award of Contract and before a hardware schedule is prepared, and before any hardware is ordered or delivered to the project, the CONTRACTOR shall submit to the ARCHITECT for his written approval, copies of sample list, listing each of the different items of builders hardware and catalog cuts of each item. B. Templates: As soon as the hardware schedule is approved the hardware supplier shall furnish to the various fabricators, required templates for fabrication purposes. Templates shall be made available not more than (10) days after receipt of the approved hardware schedule. C. Packaging and Marking: All hardware shall be shipped with proper fastenings for secure application. Each package of hardware shall be legibly marked indicating the part of the work for which it is intended. Markings shall correspond with the item numbers shown on the approved hardware schedule. Keys shall be tagged within each package set and plainly marked on the face of the envelope with the key control number, door designation and all identification as necessary. D. Delivery: Delivery shall be made to the project site to the attention of the GENERAL CONTRACTOR. Where delivery of special hardware is required at any fabricator’s plant, the hardware supplier shall make such delivery. INSTALLATION A. Mount hardware units at heights recommended in "Recommended Locations for Builders Hardware" by BHMA, unless otherwise noted or directed by the ARCHITECT. B. Install each hardware unit in compliance with the manufacturer's recommendations. ADJUST AND CLEAN A. Adjust and check each operating item of hardware and each door to ensure proper operation or function of every unit. Lubricate moving parts with type lubrication recommended by manufacturer. Replace units that cannot be adjusted. B. Wherever hardware installation is made more than one (1) month prior to acceptance or occupancy of a space or area, return to the work during the week prior to acceptance make a final check, and adjust all hardware items in such space or area. Adjust door control devices and compensate for final operation of heating and ventilating equipment. C. Instruct OWNERS personnel in proper adjustment and maintenance of hardware and hardware finishes, during the final adjustment of hardware. HARDWARE SETS FINISH HARDWARE 08 7100-7 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 A. NOVEMBER 19TH, 2013 The following is a general listing of hardware requirements and is not intended for use as a final hardware schedule. Any items of hardware required by established standards or practices, or to meet state and local codes or proper door operation shall be furnished whether or not specifically called out in the following listed groups. LOCK SETS: OPERABLE AT ALL TIMES FROM THE INSIDE WITHOUT THE USE OF A KEY OR ANY SPECIAL KNOWLEDGE OR EFFORT HARDWARE SET # 01 Provide each DBL door(s) with the following: Qty Description Catalogue # Finish Mfr. 2 EA I EA 1 EA 2 EA 1 EA 1 EA 4 EA 2 EA 2 EA 1 EA 1 SET 1 EA 1 EA CONT.HINGE EXIT DEVICE EXIT DEVICE RECESSED PULL MORTISE CYL HOUSING RIM CYLINDER HOUSING CORE SURF ACE CLOSER KlCKPLATE RAIN GUARD GASKETING SWEEP THRESHOLD MCK-12 lID CD 9927NL-OP CD 9927 EO SL-82 BY DOOR MFG. CLEAR US26D US26D MK V VO 7300B 4041H CUSH KI050 10" X2" LDW 346C 2891ANB 18061CNB 271A AL US32D BLK SAR SAR SAR LCN RC PE PE PE PE NOTE: Two (2) mortise cylinders for cylinder dogging, one (1) cylinder used at exterior, one (1) cylinder for removable center mullion. NOTE: Contractor to fill/patch any old hardware preparations in existing frame that will remain that will no longer be used with new door / hardware. Contractor is responsible for any new mortises/hardware preparation to existing frame to accommodate new door and hardware. HARDWARE SET # 02 Provide each SGL door(s) with the following: Qty Description Catalogue # Finish Mfr. 1 EA 1 EA 1 EA 1 EA 1 EA 2 EA 1 EA 1 EA 1 EA 1 SET 1 EA 1 EA CONT.HINGE EXIT DEVICE RECESSED PULL MORTISE CYL HOUSING RIM CYL HOUSING CORES SURFACE CLOSER KICK PLATE RAIN GUARD GASKETING SWEEP THRESHOLD MCK-12 HD CD 99NL SL-82 BY DOOR MFG. CLEAR US26D MK VO FINISH HARDWARE 7300B 4041H CUSH K1050 10” X 2” LDW 346C 2891ANB 18061CNB 271A AL US32D BLK SAR SAR SAR LCN RC PE PE PE PE 08 7100-8 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 NOTE: Contractor to fill/patch any old hardware preparations in existing frame that will remain that will no longer be used with new door / hardware. Contractor is responsible for any new mortises/hardware preparation to existing frame to accommodate new door and hardware. HARDWARE SET # 02A Provide each SGL door(s) with the following: Qty Description Catalogue # Finish Mfr. 1 EA 1 EA 1 EA 1 EA 2 EA 1 EA 1 EA 1 EA 1 SET 1 EA 1 EA CONT.HINGE EXIT DEVICE RECESSED PULL MORTISE CYL HOUSING CORE SURFACE CLOSER KICK PLATE RAIN GUARD GASKETING SWEEP THRESHOLD MCK-12 HD CD 99EO SL-82 BY DOOR MFG. CLEAR US26D MK VO 7300B 4041H CUSH K1050 10” X 2” LDW 346C 2891ANB 18061CNB 271A AL US32D BLK SAR SAR LCN RC PE PE PE PE HARDWARE SET # 03 Provide each SGL door(s) with the following: Qty Description Catalogue # Finish Mfr. 1 EA 1 EA 1 EA 2 EA 1 EA 1 EA 1 EA 1 EA 1 EA CONT.HINGE MORTISE LOCK RIM CYL HOUSING CORE SURFACE CLOSER KICK PLATE RAIN GUARD SWEEP THRESHOLD MCK-12 HD 7800 CLEAR MK SAR SAR SAR LCN RC PE PE PE 7300B 4041H CUSH K1050 10” X 2” LDW 346C 18061CNB 271A AL US32D HARDWARE SET # 04 Provide each SGL door(s) with the following: Qty Description Catalogue # Finish Mfr. 2 EA 1 EA 1 EA 1 EA 3 EA 4 EA 1 EA 2 EA 2 EA 1 EA 1 SET 2 EA 1 EA CONT.HINGE EXIT DEVICE EXIT DEVICE REMOVABLE MULLION MORTISE CYL HOUSING CORES RIM CYL HOUSING SURFACE CLOSER KICK PLATE RAIN GUARD GASKETING SWEEP THRESHOLD MCK-12 HD CD99NL-OP CD99EO KR1654 CLEAR US26D US26D SP28 MK VO VO VO SAR SAR SAR LCN RC PE PE PE PE FINISH HARDWARE 7300B 4041H CUSH K1050 10” X 2” LDW 346C 2891ANB 18061CNB 271A AL US32D BLK 08 7100-9 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 HARDWARE SET # 05 Provide each DBL door(s) with the following: Qty Description Catalogue # Finish Mfr. 2 EA 2 EA 2 EA 2 EA 2 EA CONT.HINGE RECESSED PULL SURFACE CLOSER KICK PLATE PUSH PLATES MCK-12 HD SL-82 BY DOOR MFG. 4041H CUSH K1050 10” X 2” LDW CLEAR MK AL US32D LCN RC IVE END OF SECTION 08 7100 FINISH HARDWARE 08 7100-10 of 10 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 08 8000 - GLAZING PART 1 - GENERAL 1.1 A. 1.2 A. RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY The Work of this Section consists of the provision of all plant, labor, materials, equipment, testing and services necessary to complete the work of glazing for the following products and applications, including those specified in other Sections where glazing requirements are specified by reference to this Section; as shown on the schedules, keynotes, drawings, as specified herein, and as may be required by conditions and authorities having jurisdiction, including, but not limited to, the following: 1. 2. 3. 4. B. Related Sections: 1. 2. 3. 4. 1.3 Windows. Doors. Glazed curtain walls. Glazed Entrances and Storefront Framing. Section 01 9113, “General Commissioning Requirements”. Section 08 1255, "Aluminum Frames and FRP Doors" Section 08 4113, "Aluminum Framed Entrances and Storefronts” Section 08 5113, "Aluminum Windows" DEFINITIONS A. Glass Manufacturers: Firms that produce primary glass, fabricated glass, or both, as defined in referenced glazing publications. B. Glass Thicknesses: ASTM C 1036. C. Interspace: Space between lites of an insulating-glass unit that contains dehydrated air or specified gas. D. Deterioration of Coated Glass: Defects developed from normal use that are attributed to the manufacturing process and not to causes other than glass breakage and practices for maintaining and cleaning coated glass contrary to manufacturer's directions. Defects include peeling, cracking, and other indications of deterioration in metallic coating. E. Deterioration of Laminated Glass: Defects developed from normal use that are attributed to the manufacturing process and not to glass breakage and practices for maintaining and cleaning laminated glass contrary to manufacturer's directions. Defects include edge separation, delamination materially obstructing vision through glass, and blemishes exceeding those allowed by referenced laminated glass standard. GLAZING Indicated by thickness designations in millimeters according to 08 8000 - 1 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 F. 1.4 NOVEMBER 19TH, 2013 Deterioration of Insulating Glass: Failure of the hermetic seal under normal use due to causes other than glass breakage and improper practices for maintaining, and cleaning insulating glass. Evidence of failure is the obstruction of vision by dust, moisture, or film on the interior surfaces of glass. Improper practices for maintaining and cleaning glass do not comply with the manufacturer's directions PERFORMANCE REQUIREMENTS A. General: Installed glazing systems shall withstand normal thermal movement and wind and impact loads (where applicable) without failure, including loss or glass breakage attributable to the following: defective manufacture, fabrication, or installation; failure of sealants or gaskets to remain watertight and airtight; deterioration of glazing materials; or other defects in construction. B. Delegated Design: Design glass, including comprehensive engineering analysis according to ASTM E 1300 by a qualified professional engineer, using the following design criteria: C. Design Wind Pressures: Determine design wind pressures applicable to Project according to ASCE/SEI 7, based on heights above grade indicated on Drawings. Design wind loads applicable to Project from design load indicated above at 33 feet (10 m) above grade, according to ASCE 7, "Minimum Design Loads for Buildings and Other Structures": Section 6.4.2, "Analytic Procedure," based on mean roof heights above grade indicated on Drawings but not less than 40 Ibs per s.f. 1. 2. 3. 4. 5. 6. D. Glass Type Factors for Wired, Patterned, and Sandblasted Glass: 1. 2. 3. E. Short-Duration Glass Type Factor for Patterned Glass: 1.0 Long Duration Glass Type Factor for Patterned Glass: 0.6 Short-Duration Glass Type Factor for Sandblasted Glass: 0.5 Thickness of Patterned Glass: Base design of patterned glass on thickness at thinnest part of the glass (ASTM E 1300) 1. F. Wind Design Data: See Above. Basic Wind Speed: 100mph Importance Factor: 1.15 Exposure Category: C Design Snow Loads: As indicated on Drawings. Vertical Glazing: For glass surfaces sloped 15 degrees or less from vertical, design glass to resist design wind pressure based on glass type factors for short-duration load. Differential Shading: Design glass to resist thermal stresses induced by differential shading within individual glass lites. Maximum Lateral Deflection: For the following types of glass supported on all four edges, provide thickness required that limits center deflection at design wind pressure to 1150 times the short side length or 1 inch (25 mm), whichever is less. a. b. c. For monolithic-glass lites heat-treated to resist wind loads. For insulating glass. For laminated-glass lites. G. Minimum Glass Thickness for Exterior Lites: Not less than 3/16" H. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes acting on glass framing members and glazing components. GLAZING 08 8000 - 2 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 1.5 A. 1.6 NOVEMBER 19TH, 2013 Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces. PRECONSTRUCTION TESTING Preconstruction Adhesion and Compatibility Testing: Test each glazing material type, tape sealant, gasket, glazing accessory, and glass-framing member for adhesion to and compatibility with elastomeric glazing sealants. 1. Testing will not be required if data are submitted based on previous testing of current sealant products and glazing materials matching those submitted. 2. Use ASTM C 1087 to determine whether priming and other specific joint-preparation techniques are required to obtain rapid, optimum adhesion of glazing sealants to glass, tape sealants, gaskets, and glazing channel substrates. 3. Test no fewer than eight Samples of each type of material, including joint substrates, shims, sealant backings, secondary seals, and miscellaneous materials. 4. Schedule sufficient time for testing and analyzing results to prevent delaying the Work. 5. For materials failing tests, submit sealant manufacturer's written instructions for corrective measures including the use of specially formulated primers. ACTION SUBMITTALS A. Product Data: For each glass product and glazing material indicated. B. Glass Samples: For each type of glass product; 12 inches square. C. Glazing Accessory Samples: For gaskets, sealants and colored spacers, in 12-inch lengths. Install sealant Samples between two strips of material representative in color of the adjoining framing system. D. Glazing Schedule: List glass types and thicknesses for each size opening and location. Use same designations indicated on Drawings. E. Delegated-Design Submittal: For glass indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. 1.7 INFORMATIONAL SUBMITTALS A. Qualification Data: For manufacturers of laminated, insulating-glass units with, low-e coatings glass and ceramic glazing and framing system, testing agency and sealant testing agency. B. Product Certificates: For glass and glazing products, from manufacturer. C. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, for tinted glass, coated glass, laminated, insulating glass, glazing sealants and glazing gaskets. GLAZING 08 8000 - 3 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. For glazing sealants, provide test reports based on testing current sealant formulations within previous 36-month period. D. Preconstruction adhesion and compatibility test report. E. Warranties: Sample of special warranties. 1.8 NOVEMBER 19TH, 2013 QUALITY ASSURANCE A. Manufacturer Qualifications for Insulating-Glass Units with Sputter-Coated, Low-E Coatings: A qualified insulating-glass manufacturer who is approved and certified by coated-glass manufacturer. B. Installer Qualifications: A qualified installer who employs glass installers for this Project who are certified under the National Glass Association's Certified Glass Installer Program. C. Glass Testing Agency Qualifications: A qualified independent testing agency accredited according to the NFRC CAP 1 Certification Agency Program. D. Sealant Testing Agency Qualifications: An independent testing agency qualified according to ASTM C 1021 to conduct the testing indicated. E. Source Limitations for Glass: Obtain from single source from single manufacturer for each glass type. F. Source Limitations for Glazing Accessories: Obtain from single source from single manufacturer for each product and installation method. G. Glazing Publications: Comply with published recommendations of glass product manufacturers and organizations below, unless more stringent requirements are indicated. Refer to these publications for glazing terms not otherwise defined in this Section or in referenced standards. 1. GANA Publications: "Glazing Manual." GANA's "Laminated Glazing Reference Manual" and GANA's 2. AAMA Publications: AAMA GDSG-1, "Glass Design for Sloped Glazing," and AAMA TIRA7, "Sloped Glazing Guidelines." 3. IGMA Publication for Sloped Glazing: IGMA TB-3001, "Guidelines for Sloped Glazing." 4. IGMA Publication for Insulating Glass: SIGMA TM-3000, "North American Glazing Guidelines for Sealed Insulating Glass Units for Commercial and Residential Use." H. Safety Glazing Labeling: Where safety glazing labeling is indicated, permanently mark glazing with certification label of the SGCC or the manufacturer. Label shall indicate manufacturer's name, type of glass, thickness, and safety glazing standard with which glass complies. I. Insulating-Glass Certification Program: Permanently marked either on spacers or on at least one component lite of units with appropriate certification label of IGCC. J. Mockups: Build mockups to verify selections made under sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution. 1. GLAZING Install glazing in mockups specified in Division 08 Section "Aluminum-Framed Entrances and Storefronts, Aluminum Windows,” “Aluminum Curtain Wall,” to match glazing systems required for Project, including glazing methods. 08 8000 - 4 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. K. 1.9 NOVEMBER 19TH, 2013 Approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion. Pre-installation Conference: Conduct conference at Project site. 1. Review and finalize construction schedule and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays. 2. Review temporary protection requirements for glazing during and after installation. DELIVERY, STORAGE, AND HANDLING A. Protect glazing materials according to manufacturer's written instructions. Prevent damage to glass and glazing materials from condensation, temperature changes, direct exposure to sun, or other causes. B. Comply with insulating-glass manufacturer's written recommendations for venting and sealing units to avoid hermetic seal ruptures due to altitude change. 1.10 A. PROJECT CONDITIONS Environmental Limitations: Do not proceed with glazing when ambient and substrate temperature conditions are outside limits permitted by glazing material manufacturers and when glazing channel substrates are wet from rain, frost, condensation, or other causes. 1. 1.11 A. WARRANTY Manufacturer's Special Warranty for Coated-Glass Products: Manufacturer's standard form in which coated-glass manufacturer agrees to replace coated-glass units that deteriorate within specified warranty period. Deterioration of coated glass is defined as defects developed from normal use that are not attributed to glass breakage or to maintaining and cleaning coated glass contrary to manufacturer's written instructions. Defects include peeling, cracking, and other indications of deterioration in coating. 1. B. Warranty Period: 10 years from date of Substantial Completion. Manufacturer's Special Warranty on Laminated Glass: Manufacturer's standard form in which laminated-glass manufacturer agrees to replace laminated-glass units that deteriorate within specified warranty period. Deterioration of laminated glass is defined as defects developed from normal use that are not attributed to glass breakage or to maintaining and cleaning laminated glass contrary to manufacturer's written instructions. Defects include edge separation, delamination materially obstructing vision through glass, and blemishes exceeding those allowed by referenced laminated-glass standard. 1. C. Do not install glazing sealants when ambient and substrate temperature conditions are outside limits permitted by sealant manufacturer or below 40 deg F (4.4 deg C). Warranty Period: 10 years from date of Substantial Completion. Manufacturer's Special Warranty on Insulating Glass: Manufacturer's standard form in which insulating-glass manufacturer agrees to replace insulating-glass units that deteriorate within GLAZING 08 8000 - 5 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 specified warranty period. Deterioration of insulating glass is defined as failure of hermetic seal under normal use that is not attributed to glass breakage or to maintaining and cleaning insulating glass contrary to manufacturer's written instructions. Evidence of failure is the obstruction of vision by dust, moisture, or film on interior surfaces of glass. 1. Warranty Period: 10 years from date of Substantial Completion. PART 2 - PRODUCTS 2.1 A. GLASS PRODUCTS, GENERAL Thickness: Where glass thickness is indicated, it is a minimum. thicknesses as needed to comply with requirements indicated. 1. 2. Provide glass lites in Minimum Glass Thickness for Exterior Lites: Not less than 6.0 mm. Thickness of Tinted Glass: Provide same thickness for each tint color indicated throughout Project. B. Strength: Where float glass is indicated, provide annealed float glass, Kind HS heat-treated float glass, or Kind FT heat-treated float glass as needed to comply with "Performance Requirements" Article. Where heat-strengthened glass is indicated, provide Kind HS heattreated float glass or Kind FT heat-treated float glass as needed to comply with "Performance Requirements" Article. Where fully tempered glass is indicated, provide Kind FT heat-treated float glass. C. Windborne-Debris-Impact Resistance: Provide exterior glazing that passes basic-protection testing requirements in ASTM E 1996 for Wind Zone 3 in a hurricane susceptible zone if required and as tested according to ASTM E 1886. Test specimens shall be no smaller in width and length than glazing indicated for use on the Project and shall be installed in same manner as glazing indicated for use on the Project. D. Thermal and Optical Performance Properties: Provide glass with performance properties specified, as indicated in manufacturer's published test data, based on procedures indicated below: 1. 2. 3. 4. 5. 6. 2.2 A. For monolithic-glass lites, properties are based on units with lites 6.0 mm thick. For laminated-glass lites, properties are based on products of construction indicated. For insulating-glass units, properties are based on units of thickness indicated for overall unit and for each lite. U-Factors: Center-of-glazing values, according to NFRC 100 and based on LBL's WINDOW 5.2 computer program, expressed as Btu/sq. ft. x h x deg F. Solar Heat-Gain Coefficient and Visible Transmittance: Center-of-glazing values, according to NFRC 200 and based on LBL's WINDOW 5.2 computer program. Visible Reflectance: Center-of-glazing values, according to NFRC 300. GLASS PRODUCTS Float Glass: ASTM C 1036, Type I, Quality-Q3, Class I (clear) unless otherwise indicated. GLAZING 08 8000 - 6 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 B. Ultraclear Float Glass: ASTM C 1036, Type I, Quality-Q3, Class I, complying with other requirements specified and with visible light transmission not less than 91 percent and solar heat gain coefficient not less than 0.87. 1. Product Basis of Design: Subject to compliance with requirements provide PPG Industries, Inc.; Solarban 60, Starphire or equivalent product by one of the following: a. b. c. C. NOVEMBER 19TH, 2013 AFG Industries, Inc.; Krystal Klear. Guardian Industries Corp.; Ultrawhite. Pilkington North America; Optiwhite. Heat-Treated Float Glass: ASTM C 1048; Type I; Quality-Q3; Class I (clear) unless otherwise indicated; of kind and condition indicated. 1. 2. 3. Fabrication Process: By horizontal (roller-hearth) process with roll-wave distortion parallel to bottom edge of glass as installed unless otherwise indicated. For uncoated glass, comply with requirements for Condition A. For coated vision glass, comply with requirements for Condition C (other coated glass). D. Uncoated Tinted Float Glass: Class 2, complying with other requirements specified. E. Silicone-Coated Spandrel Glass: ASTM C 1048, Condition C, Type I, Quality-Q3, and complying with other requirements specified. 1. Basis-of-Design Product: Subject to compliance with requirements, provide PPG Industries, Inc alliance partner ICD High Performance Coatings, OPACI-COAT-300 or comparable product by one of the following: a. b. c. 2. 3. 4. 5. 2.3 A. Glass: Tinted float. Tint Color: Gray. Silicone Coating Color: As selected by Architect from manufacturer's full range. Spandrel coating to be applied to the inside third layer, on sandwich face of the inside face of glass. LAMINATED GLASS Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. 4. B. Guardian Industries Oldcastle Glass Viracon PPG industries Guardian Industries Oldcastle Glass Viracon. Laminated Glass: ASTM C 1172, and complying with testing requirements in 16 CFR 1201 for Category II materials, and with other requirements specified. Use materials that have a proven record of no tendency to bubble, discolor, or lose physical and mechanical properties after fabrication and installation. GLAZING 08 8000 - 7 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 2. 3. C. Construction: Laminate glass with polyvinyl butyral interlayer or cast-in-place and curedtransparent-resin interlayer to comply with interlayer manufacturer's written recommendations. Interlayer Thickness: Provide thickness not less than that indicated and as needed to comply with requirements. Interlayer Color: Clear unless otherwise indicated. Windborne-Debris-Impact-Resistant Laminated Glass: ASTM C 1172, and complying with testing requirements in 16 CFR 1201 for Category II materials, with "Windborne-Debris-Impact Resistance" Paragraph in "Glass Products, General" Article, and with other requirements specified. Use materials that have a proven record of no tendency to bubble, discolor, or lose physical and mechanical properties after fabrication and installation. 1. Construction: Laminate glass with one of the following to comply with interlayer manufacturer's written recommendations: a. b. c. d. e. 2. 3. D. 2.4 A. Interlayer Thickness: Provide thickness not less than that indicated and as needed to comply with requirements. Interlayer Color: Clear unless otherwise indicated. INSULATING GLASS Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: Guardian Industries Oldcastle Glass PPG industries Viracon. Insulating-Glass Units: Factory-assembled units consisting of sealed lites of glass separated by a dehydrated interspace, qualified according to ASTM E 2190, and complying with other requirements specified. 1. 2. 3. C. Polyvinyl butyral interlayer. Polyvinyl butyral interlayers reinforced with polyethylene terephthalate film. Ionoplast interlayer. Cast-in-place and cured-transparent-resin interlayer. Cast-in-place and cured-transparent-resin interlayer reinforced with polyethylene terephthalate film. Glass: Comply with applicable requirements in "Glass Products" Article as indicated by designations in "Laminated-Glass Types" Article. 1. 2. 3. 4. B. NOVEMBER 19TH, 2013 Sealing System: Dual seal, with manufacturer's standard primary and secondary. Spacer: Manufacturer's standard spacer material and construction based on design requirements. Desiccant: Molecular sieve or silica gel, or blend of both. Glass: Comply with applicable requirements in "Glass Products" Article and in "Laminated Glass" Article as indicated by designations in "Insulating-Glass Types" Article and in "InsulatingLaminated-Glass Types" Article. GLAZING 08 8000 - 8 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 GLAZING UNITS AND SCHEDULE GLAZING TYPE 2.11 LOCATION MONOLITHIC-GLASS TYPES A. Glass Type: Clear fully tempered float glass. 1. Thickness: 6.0 mm. (or as designated elsewhere) 2. Provide safety glazing labeling. Non-rated interior glazing within 18 inches of the finished floor, interior swinging doors, panels within a 24-inch arc of either vertical edge of a door. D. Glass Type: Ultraclear heat-strengthened float glass and fully tempered float glass, as part of insulating assembly unit. 1. Thickness: 6.0 mm. 2. Provide safety glazing labeling. Part of assembly. E. Glass Type: Patterned glass. 1. Thickness: 6.0 mm. F. Glass Type: Tempered patterned glass. 1. Thickness: [4.0] [5.0] [6.0] mm. 2. Provide safety glazing labeling. 2.12 G. LAMINATED-GLASS TYPES Glass Type: Clear laminated glass with two plies of heatstrengthened float glass and fully tempered float glass (refer to drawing for locations). 1. 2. 3. H. Exterior Windborne-part of assembly Thickness of Each Glass Ply: 6.0 mm. Interlayer Thickness: 0.060 inch (1.52 mm). Provide safety glazing labeling where required. Glass Type: Silicone-coated, Ultra Clear Low-e coated, insulating laminated spandrel glass. PPG basis of design Solarban 60 (2) Starphire + Starphire inboard laminate with Opaci-Coat silicone coating on surface #6. Color to be selected by architect. 1. 2. 3. 4. 5. 6. 7. 8. 9. GLAZING Overall Unit Thickness: 1-5/16 inch (30 mm). Thickness of Each Glass Lite: 6.0 mm. Outdoor Lite: Ultra clear heat-strengthened float glass and/or fully tempered float glass. Interspace Content: Argon. Indoor Lite: Exterior Windborne – Debris Impact Resistant Ultra clear laminated glass with two plies of heat strengthened float glass. a. Thickness of Each Glass Ply: 6.0 mm. b. Interlayer Thickness: 0.090 inch (2.29 mm). Low-E Coating: Magnetic sputtered on second (2) surface Silicone coating: Opaci-coat silicone coating on (6) sixth surface. Winter Nighttime U-Factor: .24 maximum. Summer Daytime U-Factor: .21 maximum 08 8000 - 9 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2.13 I. INSULATING-LAMINATED-GLASS TYPES Glass Type: Ultra Clear Low-e-coated, insulating laminated glass. PPG basis of design - Solarban 60 (2) Starphire + Starphire inboard laminate. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 2.5 A. 2.6 A. Exterior Fixed and Operable Glazing/windows Exterior Doors, side-lites Windborne – Debris Impact Resistant Dense Compression Gaskets: Molded or extruded gaskets of profile and hardness required to maintain watertight seal, made from one of the following: Neoprene complying with ASTM C 864. EPDM complying with ASTM C 864. Silicone complying with ASTM C 1115. Thermoplastic polyolefin rubber complying with ASTM C 1115. Soft Compression Gaskets: Extruded or molded, closed-cell, integral-skinned neoprene, EPDM, silicone, or thermoplastic polyolefin rubber gaskets complying with ASTM C 509, Type II, black; of profile and hardness required to maintain watertight seal. 1. C. Overall Unit Thickness: 1-5/16 inch (30 mm). Thickness of Outdoor Lite: 6.0 mm. Outdoor Lite: Heat-strengthened float glass/Fully tempered float glass (see locations on drawings). Interspace Content: Argon. Indoor Lite: Ultra Clear laminated glass with two plies of heat-strengthened float glass. a. Thickness of Each Glass Ply: 6.0 mm. b. Interlayer Thickness: 0.090 inch (2.29 mm). Low-E Coating: Magnetic sputtered on second surface. Visible Light Transmittance: 73 percent minimum. Winter Nighttime U-Factor: .23 maximum. Summer Daytime U-Factor: .21 maximum. Solar Heat Gain Coefficient: .39 maximum. Provide safety glazing labeling, where required GLAZING GASKETS 1. 2. 3. 4. B. NOVEMBER 19TH, 2013 Application: Use where soft compression gaskets will be compressed by inserting dense compression gaskets on opposite side of glazing or pressure applied by means of pressure-glazing stops on opposite side of glazing. Lock-Strip Gaskets: Neoprene extrusions in size and shape indicated, fabricated into frames with molded corner units and zipper lock-strips, complying with ASTM C 542, black. GLAZING SEALANTS General: 1. GLAZING Compatibility: Provide glazing sealants that are compatible with one another and with other materials they will contact, including glass products, seals of insulating-glass units, and glazing channel substrates, under conditions of service and application, as demonstrated by sealant manufacturer based on testing and field experience. 08 8000 - 10 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. 3. 4. B. Suitability: Comply with sealant and glass manufacturers' written instructions for selecting glazing sealants suitable for applications indicated and for conditions existing at time of installation. Sealants used inside the weatherproofing system, shall have a VOC content of not more than 250 g/L when calculated according to 40 CFR 59, Subpart D (EPA Method 24). Colors of Exposed Glazing Sealants: As selected by Architect from manufacturer's full range. Glazing Sealant: Neutral-curing silicone glazing sealant complying with ASTM C 920, Type S, Grade NS, Class 100/50, Use NT. 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. b. c. d. e. f. 2. C. Dow Corning Corporation; 790. GE Advanced Materials - Silicones; SilPruf LM SCS2700. May National Associates, Inc.; Bondaflex Sil 290. Pecora Corporation; 890. Sika Corporation, Construction Products Division; SikaSil-C990. Tremco Incorporated; Spectrem 1. Applications: For weather seal. Glazing Sealant: Neutral-curing silicone glazing sealant complying with ASTM C 920, Type S, Grade NS, Class 25, Use NT. 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. b. c. d. e. f. 2. D. NOVEMBER 19TH, 2013 Dow Corning Corporation; 799. GE Advanced Materials - Silicones; UltraGlaze SSG4000 May National Associates, Inc.; Bondaflex Sil 200 GPN or Bondaflex Sil 201 FC. Polymeric Systems, Inc.; PSI-631. Schnee-Morehead, Inc., an ITW company; SM5731 Poly-Glaze Plus. Tremco Incorporated; Proglaze SSG or Tremsil 600. Applications: For structural seal. Glazing Sealant: Acid-curing silicone glazing sealant complying with ASTM C 920, Type S, Grade NS, Class 25, Use NT. 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. b. c. Dow Corning Corporation; 795. General Electric; Siliglaze-II 2800 Tremco Incorporated; Spectrum 2 2. Applications: Fire and Safety Rated Glazing 3. Glazing Sealants for Fire-Rated Glazing Products: Products that are approved by testing agencies that listed and labeled fire-resistant glazing products with which they are used for applications and fire-protection ratings indicated. GLAZING 08 8000 - 11 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2.7 A. GLAZING TAPES Back-Bedding Mastic Glazing Tapes: Preformed, butyl-based, 100 percent solids elastomeric tape; nonstaining and nonmigrating in contact with nonporous surfaces; with or without spacer rod as recommended in writing by tape and glass manufacturers for application indicated; and complying with ASTM C 1281 and AAMA 800 for products indicated below: 1. 2. 3. B. AAMA 804.3 tape, where indicated. AAMA 806.3 tape, for glazing applications in which tape is subject to continuous pressure. AAMA 807.3 tape, for glazing applications in which tape is not subject to continuous pressure. Expanded Cellular Glazing Tapes: Closed-cell, PVC foam tapes; factory coated with adhesive on both surfaces; and complying with AAMA 800 for the following types: 1. 2. 2.8 NOVEMBER 19TH, 2013 AAMA 810.1, Type 1, for glazing applications in which tape acts as the primary sealant. AAMA 810.1, Type 2, for glazing applications in which tape is used in combination with a full bead of liquid sealant. MISCELLANEOUS GLAZING MATERIALS A. General: Provide products of material, size, and shape complying with referenced glazing standard, requirements of manufacturers of glass and other glazing materials for application indicated, and with a proven record of compatibility with surfaces contacted in installation. B. Cleaners, Primers, and Sealers: Types recommended by sealant or gasket manufacturer. C. Setting Blocks: Elastomeric material with a Shore, Type A durometer hardness of 85, plus or minus 5. D. Spacers: Elastomeric blocks or continuous extrusions of hardness required by glass manufacturer to maintain glass lites in place for installation indicated. E. Edge Blocks: Elastomeric material of hardness needed to limit glass lateral movement (side walking). F. Cylindrical Glazing Sealant Backing: ASTM C 1330, Type O (open-cell material), of size and density to control glazing sealant depth and otherwise produce optimum glazing sealant performance. G. Perimeter Insulation for Fire-Resistive Glazing: Product that is approved by testing agency that listed and labeled fire-resistant glazing product with which it is used for application and fireprotection rating indicated. 2.9 A. FABRICATION OF GLAZING UNITS Fabricate glazing units in sizes required to fit openings indicated for Project, with edge and face clearances, edge and surface conditions, and bite complying with written instructions of product manufacturer and referenced glazing publications, to comply with system performance requirements. GLAZING 08 8000 - 12 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 B. Clean-cut or flat-grind vertical edges of butt-glazed monolithic lites to produce square edges with slight chamfers at junctions of edges and faces. C. Grind smooth and polish exposed glass edges and corners. PART 3 - EXECUTION 3.1 A. B. 3.2 EXAMINATION Examine framing, glazing channels, and stops, with Installer present, for compliance with the following: 1. Manufacturing and installation tolerances, including those for size, squareness, and offsets at corners. 2. Presence and functioning of weep systems. 3. Minimum required face and edge clearances. 4. Effective sealing between joints of glass-framing members. Proceed with installation only after unsatisfactory conditions have been corrected. PREPARATION A. Clean glazing channels and other framing members receiving glass immediately before glazing. Remove coatings not firmly bonded to substrates. B. Examine glazing units to locate exterior and interior surfaces. Label or mark units as needed so that exterior and interior surfaces are readily identifiable. Do not use materials that will leave visible marks in the completed work. 3.3 GLAZING, GENERAL A. Comply with combined written instructions of manufacturers of glass, sealants, gaskets, and other glazing materials, unless more stringent requirements are indicated, including those in referenced glazing publications. B. Adjust glazing channel dimensions as required by Project conditions during installation to provide necessary bite on glass, minimum edge and face clearances, and adequate sealant thicknesses, with reasonable tolerances. C. Protect glass edges from damage during handling and installation. Remove damaged glass from Project site and legally dispose of off Project site. Damaged glass is glass with edge damage or other imperfections that, when installed, could weaken glass and impair performance and appearance. D. Apply primers to joint surfaces where required for adhesion of sealants, as determined by preconstruction testing. GLAZING 08 8000 - 13 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 E. Install setting blocks in sill rabbets, sized and located to comply with referenced glazing publications, unless otherwise required by glass manufacturer. Set blocks in thin course of compatible sealant suitable for heel bead. F. Do not exceed edge pressures stipulated by glass manufacturers for installing glass lites. G. Provide spacers for glass lites where length plus width is larger than 50 inches (1270 mm). 1. Locate spacers directly opposite each other on both inside and outside faces of glass. Install correct size and spacing to preserve required face clearances, unless gaskets and glazing tapes are used that have demonstrated ability to maintain required face clearances and to comply with system performance requirements. 2. Provide 1/8-inch (3-mm) minimum bite of spacers on glass and use thickness equal to sealant width. With glazing tape, use thickness slightly less than final compressed thickness of tape. H. Provide edge blocking where indicated or needed to prevent glass lites from moving sideways in glazing channel, as recommended in writing by glass manufacturer and according to requirements in referenced glazing publications. I. Set glass lites in each series with uniform pattern, draw, bow, and similar characteristics. J. Set glass lites with proper orientation so that coatings face exterior or interior as specified. K. Retain both paragraphs below if glazing with wedge-shaped gaskets are required for Project. L. Where wedge-shaped gaskets are driven into one side of channel to pressurize sealant or gasket on opposite side, provide adequate anchorage so gasket cannot walk out when installation is subjected to movement. M. Square cut wedge-shaped gaskets at corners and install gaskets in a manner recommended by gasket manufacturer to prevent corners from pulling away; seal corner joints and butt joints with sealant recommended by gasket manufacturer. 3.4 TAPE GLAZING A. Position tapes on fixed stops so that, when compressed by glass, their exposed edges are flush with or protrude slightly above sightline of stops. B. Install tapes continuously, but not necessarily in one continuous length. Do not stretch tapes to make them fit opening. C. Cover vertical framing joints by applying tapes to heads and sills first and then to jambs. Cover horizontal framing joints by applying tapes to jambs and then to heads and sills. D. Place joints in tapes at corners of opening with adjoining lengths butted together, not lapped. Seal joints in tapes with compatible sealant approved by tape manufacturer. E. Do not remove release paper from tape until right before each glazing unit is installed. F. Apply heel bead of elastomeric sealant. GLAZING 08 8000 - 14 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 G. Center glass lites in openings on setting blocks and press firmly against tape by inserting dense compression gaskets formed and installed to lock in place against faces of removable stops. Start gasket applications at corners and work toward centers of openings. H. Apply cap bead of elastomeric sealant over exposed edge of tape. 3.5 GASKET GLAZING (DRY) A. Cut compression gaskets to lengths recommended by gasket manufacturer to fit openings exactly, with allowance for stretch during installation. B. Insert soft compression gasket between glass and frame or fixed stop so it is securely in place with joints miter cut and bonded together at corners. C. Installation with Drive-in Wedge Gaskets: Center glass lites in openings on setting blocks and press firmly against soft compression gasket by inserting dense compression gaskets formed and installed to lock in place against faces of removable stops. Start gasket applications at corners and work toward centers of openings. Compress gaskets to produce a weathertight seal without developing bending stresses in glass. Seal gasket joints with sealant recommended by gasket manufacturer. D. Installation with Pressure-Glazing Stops: Center glass lites in openings on setting blocks and press firmly against soft compression gasket. Install dense compression gaskets and pressureglazing stops, applying pressure uniformly to compression gaskets. Compress gaskets to produce a weathertight seal without developing bending stresses in glass. Seal gasket joints with sealant recommended by gasket manufacturer. E. Install gaskets so they protrude past face of glazing stops. 3.6 SEALANT GLAZING (WET) A. Install continuous spacers, or spacers combined with cylindrical sealant backing, between glass lites and glazing stops to maintain glass face clearances and to prevent sealant from extruding into glass channel and blocking weep systems until sealants cure. Secure spacers or spacers and backings in place and in position to control depth of installed sealant relative to edge clearance for optimum sealant performance. B. Force sealants into glazing channels to eliminate voids and to ensure complete wetting or bond of sealant to glass and channel surfaces. C. Tool exposed surfaces of sealants to provide a substantial wash away from glass. 3.7 A. LOCK-STRIP GASKET GLAZING Comply with ASTM C 716 and gasket manufacturer's written instructions. supplementary wet seal and weep system unless otherwise indicated. GLAZING Provide 08 8000 - 15 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.8 NOVEMBER 19TH, 2013 CLEANING AND PROTECTION A. Protect exterior glass from damage immediately after installation by attaching crossed streamers to framing held away from glass. Do not apply markers to glass surface. Remove nonpermanent labels and clean surfaces. B. Protect glass from contact with contaminating substances resulting from construction operations. If, despite such protection, contaminating substances do come into contact with glass, remove substances immediately as recommended in writing by glass manufacturer. C. Examine glass surfaces adjacent to or below exterior concrete and other masonry surfaces at frequent intervals during construction, but not less than once a month, for buildup of dirt, scum, alkaline deposits, or stains; remove as recommended in writing by glass manufacturer. D. Remove and replace glass that is broken, chipped, cracked, or abraded or that is damaged from natural causes, accidents, and vandalism, during construction period. E. Wash glass on both exposed surfaces in each area of Project not more than four days before date scheduled for inspections that establish date of Substantial Completion. Wash glass as recommended in writing by glass manufacturer. 3.9 A. WASTE MANAGEMENT Coordinate with Section 01 7423. 1. Separate and recycle cut-offs and waste materials and material packaging in accordance with Waste Management Plan and to the maximum extent economically feasible and place in designated areas for recycling. 2. Set aside and protect materials suitable for reuse and/or remanufacturing. 3. Separate and fold up metal banding; flatten and place along with other metal scrap for recycling in designated area. END OF SECTION 08 8000 GLAZING 08 8000 - 16 of 16 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 09 5113 - ACOUSTICAL PANEL CEILINGS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.02 SUMMARY A. This Section includes ceilings composed of acoustical panels and exposed suspension systems. 1.03 SUBMITTALS A. General: Submit each item in this Article according to the Conditions of the Contract and Division 1 Specification Sections. B. Product data for each type of product specified. C. Coordination drawings for reflected ceiling plans drawn accurately to scale and coordinating penetrations and ceiling-mounted items. Show the following: 1. Ceiling suspension system members. 2. Method of attaching suspension system hangers to building structure. 3. Ceiling-mounted items including light fixtures; air outlets and inlets; speakers; sprinklers; and special moldings at walls, column penetrations, and other junctures of acoustical ceilings with adjoining construction. 4. Minimum Drawing Scale: 1/8 inch = 1 foot. D. Samples for initial selection in the form of manufacturer's color charts consisting of actual acoustical panels or sections of panels and sections of suspension system members showing the full range of colors, textures, and patterns available for each ceiling assembly indicated. E. Samples for verification of each type of exposed finish required, prepared on samples of size indicated below. Where finishes involve normal color and texture variations, include sample sets showing the full range of variations expected. 1. 6-inch-square samples of each acoustical panel type, pattern, and color. 2. Set of 12-inch-long samples of exposed suspension system members, including moldings, for each color and system type required. F. Qualification data for firms and persons specified in the "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified. G. Product test reports from a qualified independent testing agency that are based on its testing of current products for compliance of acoustical panel ceilings and components with requirements. H. Research reports or evaluation reports of the model code organization acceptable to authorities having jurisdiction that show compliance of acoustical panel ceilings and components with the building code in effect for the Project. ACOUSTICAL PANEL CEILINGS 09 5113 - 1 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 1.04 QUALITY ASSURANCE A. Installer Qualifications: Engage an experienced Installer who has completed acoustical panel ceilings similar in material, design, and extent to that indicated for this Project and with a record of successful in-service performance. B. Fire-Test-Response Characteristics: Provide acoustical panel ceilings that comply with the following requirements: 1. Fire-response tests are performed by a qualified testing and inspecting agency. Qualified testing and inspecting agencies include Underwriters Laboratories (UL), Warnock Hersey, or another agency that is acceptable to authorities having jurisdiction and that performs testing and follow-up services. 2. Surface-burning characteristics of acoustical panels comply with ASTM E 1264 for Class A materials as determined by testing identical products per ASTM E 84. C. Single-Source Responsibility for Ceiling Units: Obtain each type of acoustical ceiling panel from a single source with resources to provide products of consistent quality in appearance and physical properties without delaying the Work. D. Single-Source Responsibility for Suspension System: Obtain each type of suspension system from a single source with resources to provide products of consistent quality in appearance and physical properties without delaying the Work. 1.05 DELIVERY, STORAGE, AND HANDLING A. Deliver acoustical panels and suspension system components to Project site in original, unopened packages and store them in a fully enclosed space where they will be protected against damage from moisture, direct sunlight, surface contamination, and other causes. B. Before installing acoustical panels, permit them to reach room temperature and a stabilized moisture content. C. Handle acoustical panels carefully to avoid chipping edges or damaging units in any way. 1.06 PROJECT CONDITIONS A. Space Enclosure and Environmental Limitations: Do not install acoustical panel ceilings until spaces are enclosed and weatherproof, wet-work in spaces is completed and dry, work above ceilings is complete, and ambient temperature and humidity conditions are being maintained at the levels indicated for Project when occupied for its intended use. 1.07 COORDINATION A. Coordinate layout and installation of acoustical panels and suspension system components with other construction that penetrates ceilings or is supported by them, including light fixtures, HVAC equipment, fire-suppression system components (if any), and partition assemblies (if any). 1.08 EXTRA MATERIALS A. Furnish extra materials described below that match products installed, are packaged with protective covering for storage, and are identified with labels clearly describing contents. ACOUSTICAL PANEL CEILINGS 09 5113 - 2 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. NOVEMBER 19TH, 2013 Acoustical Ceiling Units: Furnish quantity of full-size units equal to 5.0 percent of amount installed. PART 2 - PRODUCTS 2.01 MANUFACTURERS A. Available Manufacturers: Subject to compliance with requirements, manufacturers whose acoustical panels may be incorporated in the Work include, but are not limited to, the following: 1. Armstrong World Industries, Inc. 2. The Celotex Corporation. 3. USG Interiors, Inc. B. Available Products: Subject to compliance with requirements, products that may be incorporated in the Work include, but are not limited to, the products specified in the Acoustical Panel Ceiling Schedule at the end of this Section. 2.02 ACOUSTICAL PANELS, GENERAL A. Acoustical Panel Standard: Provide manufacturer's standard panels of configuration indicated that comply with ASTM E 1264 classifications as designated by types, patterns, acoustical ratings, and light reflectances, unless otherwise indicated. 1. Mounting Method for Measuring Noise Reduction Coefficient (NRC): Type E-400 [plenum mounting in which face of test specimen is 15-3/4 inches away from the test surface] per ASTM E 795. B. Acoustical Panel Colors and Patterns: Match appearance characteristics indicated for each product type. C. Panel Characteristics: Comply with requirements indicated on each Acoustical Panel Ceiling Schedule at the end of this Section, including those referencing ASTM E 1264 classifications. 2.03 METAL SUSPENSION SYSTEMS, GENERAL A. Metal Suspension System Standard: Provide manufacturer's standard metal suspension systems of types, structural classifications, and finishes indicated that comply with applicable ASTM C 635 requirements. B. Finishes and Colors: indicated. C. Attachment Devices: Size for 5 times the design load indicated in ASTM C 635, Table 1, Direct Hung unless otherwise indicated. D. Wire Hangers, Braces, and Ties: Provide wires complying with the following requirements: 1. Zinc-Coated Carbon Steel Wire (Locker Rooms and Toilet Rooms): ASTM A 641, Class 1 zinc coating, soft temper. 2. Nickel-Copper Alloy Wire: ASTM B 164, nickel-copper alloy UNS N04400. 3. Size: Select wire diameter so that its stress at 3 times the hanger design load (ASTM C 635, Table 1, Direct Hung) will be less than the yield stress of wire, but provide not less than 0.106inch-diameter wire. ACOUSTICAL PANEL CEILINGS Provide manufacturer's standard factory-applied finish for type of system 09 5113 - 3 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 E. Hanger Rods (if required): Mild steel, zinc coated, or protected with rust-inhibitive paint. F. Flat Hangers (if required): Mild steel, zinc coated, or protected with rust-inhibitive paint. G. Angle Hangers (if required): Angles with legs not less than 7/8 inch wide, formed with 0.0396-inchthick galvanized-steel sheet complying with ASTM A 446, G 90 Coating Designation, with bolted connections and 5/16-inch-diameter bolts. H. Sheet-Metal Edge Moldings and Trim: Type and profile indicated, or if not indicated, manufacturer's standard moldings for edges and penetrations that fit acoustical panel edge details and suspension systems indicated; formed from sheet metal of same material and finish as that used for exposed flanges of suspension system runners. 1. For lay-in panels with reveal edge details, provide stepped-edge molding that forms reveal of same depth and width as that formed between edge of panel and flange at exposed suspension member. 2. For circular penetrations of ceiling, provide edge moldings fabricated to diameter required to fit penetration exactly. I. Hold-Down Clips for Non-Fire-Resistance-Rated Ceilings: For interior ceilings composed of acoustical panels weighing less than 1 lb per sq. ft., provide hold-down clips spaced 24 inches o.c. on all cross tees. J. Impact Clips: Where indicated, provide manufacturer's standard impact-clip system design to absorb impact forces against acoustical panels. K. Carrying Channels: Provide carrying channels as indicated on the drawings in the High School Auditorium. 2.04 NON-FIRE-RESISTANCE-RATED, DIRECT-HUNG SUSPENSION SYSTEMS A. Wide-Face, Capped, Double-Web, Steel Suspension System: Main and cross runners roll formed from prepainted or electrolytic zinc-coated, cold-rolled steel sheet, with prefinished 15/16-inch-wide metal caps on flanges; other characteristics as follows: 1. Structural Classification: Intermediate-duty system. 2. End Condition of Cross Runners: Override (stepped) or butt-edge type, as standard with manufacturer. 3. Cap Material and Finish: Steel sheet painted white. B. Wide-Face, Aluminum-Capped, Double-Web, Hot-Dip Galvanized-Steel Suspension System (Locker Rooms and Toilet Rooms): Main and cross runners roll formed from hot-dip galvanized, cold-rolled steel sheet, with prefinished 15/16-inch-wide aluminum caps on flanges; other characteristics as follows: 1. Structural Classification: Intermediate-duty system. 2. Zinc Coating: ASTM A 525, G 60. 3. Finish: Painted white. C. Available Products: Subject to compliance with requirements, suspension systems that may be incorporated in the Work include, but are not limited to, the following: 1. Wide-Face, Capped, Double-Web, Steel Suspension Systems: a. Prelude 15/16" Exposed Tee System; Armstrong World Industries, Inc. 2. Wide-Face, Aluminum-Capped, Double-Web, Hot-Dip Galvanized-Steel Suspension Systems: a. Prelude Plus; Armstrong World Industries, Inc. 2.05 ACOUSTICAL SEALANT ACOUSTICAL PANEL CEILINGS 09 5113 - 4 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 A. Acoustical Sealant for Exposed and Concealed Joints: Manufacturer's standard nonsag, paintable, nonstaining latex sealant complying with ASTM C 834 and the following requirements: 1. Product is effective in reducing airborne sound transmission through perimeter joints and openings in building construction as demonstrated by testing representative assemblies per ASTM E 90. 2. Product has flame-spread and smoke-developed ratings of less than 25 per ASTM E 84. B. Acoustical Sealant for Concealed Joints: Manufacturer's standard nondrying, nonhardening, nonskinning, nonstaining, gunnable, synthetic rubber sealant recommended for sealing interior concealed joints to reduce transmission of airborne sound. C. Available Products: Subject to compliance with requirements, acoustical sealants that may be incorporated in the Work include, but are not limited to, the following: 1. Acoustical Sealant for Exposed and Concealed Joints: a. AC-20 FTR Acoustical and Insulation Sealant; Pecora Corp. b. SHEETROCK Acoustical Sealant; United States Gypsum Company. 2. Acoustical Sealant for Concealed Joints: a. BA-98; Pecora Corp. b. Tremco Acoustical Sealant; Tremco, Inc. PART 3 - EXECUTION 3.01 EXAMINATION A. Examine substrates and structural framing to which acoustical panel ceilings attach or abut, with Installer present, for compliance with requirements specified in this and other Sections that affect ceiling installation and anchorage. Do not proceed with installation until unsatisfactory conditions have been corrected. 3.02 PREPARATION A. Coordination: Furnish layouts for cast-in-place anchors, clips, and other ceiling anchors whose installation is specified in other Sections. B. Measure each ceiling area and establish the layout of acoustical panels to balance border widths at opposite edges of each ceiling. Avoid using less-than-half-width panels at borders, and conform to the layout shown on reflected ceiling plans. 3.03 INSTALLATION A. General: Install acoustical panel ceilings to comply with publications referenced below per manufacturer's instructions and CISCA "Ceiling Systems Handbook." 1. Standard for Ceiling Suspension System Installations: Comply with ASTM C 636. 2. Standard for Ceiling Suspension Systems Requiring Seismic Restraint: Comply with ASTM E 580. B. Suspend ceiling hangers from building's structural members and as follows: 1. Install hangers plumb and free from contact with insulation or other objects within ceiling plenum that are not part of the supporting structure or of the ceiling suspension system. 2. Splay hangers only where required to miss obstructions; offset resulting horizontal forces by bracing, countersplaying, or other equally effective means. ACOUSTICAL PANEL CEILINGS 09 5113 - 5 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3. 4. 5. 6. 7. 8. 9. NOVEMBER 19TH, 2013 Where width of ducts and other construction within ceiling plenum produces hanger spacings that interfere with the location of hangers at spacings required to support standard suspension system members, install supplemental suspension members and hangers in the form of trapezes or equivalent devices. Size supplemental suspension members and hangers to support ceiling loads within performance limits established by referenced standards and publications. Secure wire hangers to ceiling suspension members and to supports above with a minimum of 3 tight turns. Connect hangers either directly to structures or to inserts, eye screws, or other devices that are secure, that are appropriate for substrate, and that will not deteriorate or otherwise fail due to age, corrosion, or elevated temperatures. Secure flat, angle, channel, and rod hangers to structure, including intermediate framing members, by attaching to inserts, eye screws, or other devices that are secure and appropriate for both the structure to which hangers are attached and the type of hanger involved. Install hangers in a manner that will not cause them to deteriorate or fail due to age, corrosion, or elevated temperatures. Do not support ceilings directly from permanent metal forms. Fasten hangers to cast-in-place hanger inserts, powder-actuated fasteners, or drilled-in anchors that extend through forms into concrete. Do not attach hangers to steel deck tabs. Do not attach hangers to steel roof deck. Attach hangers to structural members. Space hangers not more than 48 inches o.c. along each member supported directly from hangers, unless otherwise shown; and provide hangers not more than 8 inches from ends of each member. C. Install edge moldings and trim of type indicated at perimeter of acoustical ceiling area and where necessary to conceal edges of acoustical panels. 1. Apply acoustical sealant in a continuous ribbon concealed on back of vertical legs of moldings before they are installed. 2. Screw attach moldings to substrate at intervals not over 16 inches o.c. and not more than 3 inches from ends, leveling with ceiling suspension system to a tolerance of 1/8 inch in 12 feet. Miter corners accurately and connect securely. 3. Do not use exposed fasteners, including pop rivets, on moldings and trim. D. Install suspension system runners so they are square and securely interlocked with one another. Remove and replace dented, bent, or kinked members. E. Install acoustical panels with undamaged edges and fitted accurately into suspension system runners and edge moldings. Scribe and cut panels at borders and penetrations to provide neat, precise fit. 1. For square-edged panels, install panels with edges fully hidden from view by flanges of suspension system runners and moldings. 2. For reveal-edged panels on suspension system runners, install panels with bottom of reveal in firm contact with top surface of runner flanges. 3. Paint the cut panel edges remaining exposed after installation; match color of exposed panel surfaces using coating recommended for this purpose by acoustical panel manufacturer. 4. Install hold-down clips in areas indicated and in areas required by governing regulations, or for fire-resistance ratings; space as recommended by panel manufacturer, unless otherwise indicated or required. 5. Protect lighting fixtures and air ducts to comply with requirements indicated for fire-resistancerated assembly. 3.04 CLEANING A. Clean exposed surfaces of acoustical panel ceilings, including trim, edge moldings, and suspension system members. Comply with manufacturer's instructions for cleaning and touchup of minor finish ACOUSTICAL PANEL CEILINGS 09 5113 - 6 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 damage. Remove and replace ceiling components that cannot be successfully cleaned and repaired to permanently eliminate evidence of damage. 3.05 ACOUSTICAL CEILING PANEL SCHEDULE A. Acoustical Panel Ceiling Designation CL1: PROVIDE IN ALL ROOMS. 1. Acoustical Panel Characteristics: Provide panels complying with ASTM E 1264 for characteristics described below: a. Surface Texture: Medium b. Composition: Mineral Fiber c. Color: White d. Size: 48in X 24in X 5/8in and 24in X 24in X 5/8in e. Edge Profile: Square Lay-In for interface with AL Prelude Plus XL 15/16" Exposed Tee. f. Ceiling Attenuation Class (CAC): ASTM C 1414; Classified with UL label on product carton, 40 g. Flame Spread: ASTM E 1264; Fire Resistive h. Light Reflectance (LR): ASTM E 1477; White Panel: Light Reflectance: 0.88. i. Dimensional Stability: HumiGuard Max. j. Mold/Mildew Inhibitor: The front and back of the product have been treated with BioBlock, a paint that contains a special biocide that inhibits or retards the growth of mold or mildew, ASTM D 3273. k. Acceptable Product: Fine Fissured Ceramaguard, 605 as manufactured by Armstrong World Industries. Acoustical Panel Ceiling Designation CL2: PROVIDE IN ALL AREAS OTHER THAN TOILET ROOMS Acoustical Panel Characteristics: Provide panels complying with ASTM E 1264 for characteristics described below: l. Surface Texture: Medium m. Composition: Mineral Fiber n. Color: White o. Size: 48in X 24in X 5/8in and 24in X 24in X 5/8in p. Edge Profile: Square Lay-In for interface with AL Prelude Plus XL 15/16" Exposed Tee. q. Ceiling Attenuation Class (CAC-35): ASTM C 1414; Classified with UL label (class A) on product carton, 40 r. Flame Spread: ASTM E 1264; Fire Resistive s. Light Reflectance (LR): ASTM E 1477; White Panel: Light Reflectance: 0.85. t. Dimensional Stability: HumiGuard Plus. u. Mold/Mildew Inhibitor: The front and back of the product have been treated with BioBlock, a paint that contains a special biocide that inhibits or retards the growth of mold or mildew, ASTM D 3273. v. Acceptable Product: School Zone Fine Fissured, 465 and 466 as manufactured by Armstrong World Industries 2. Suspension System Type: Components: All main beams and cross tees shall be commercial quality hot-dipped galvanized (galvanized steel, aluminum, or stainless steel) as per ASTM A 653. Main beams and cross tees are double-web steel construction with type exposed flange design. Exposed surfaces chemically cleansed, capping pre-finished galvanized steel (aluminum or stainless steel) in baked polyester paint. Main beams and cross tees shall have rotary stitching (exception: extruded aluminum or stainless steel). a. Structural Classification: Intermediate-duty system. b. Color: White Aluminum and match the actual color of the selected ceiling tile. c. Acceptable Product: AL Prelude Plus XL 15/16" Exposed Tee as manufactured by Armstrong World Industries, Inc. ACOUSTICAL PANEL CEILINGS 09 5113 - 7 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 d. e. f. g. h. i. j. k. l. NOVEMBER 19TH, 2013 High Humidity Finish: Comply with ASTM C 635 requirements for Coating Classification for Severe Environment Performance where high humidity finishes are indicated. SS Prelude Plus by Armstrong World Industries, Inc. - 100% Type 304 STAINLESS Steel. AL Prelude Plus by Armstrong World Industries, Inc. - all ALUMINUM Prelude Plus XL Fire Guard by Armstrong World Industries, Inc., G-60 Hot dipped galvanized /aluminum capping Structural Classification: ASTM C 635 duty class. Color: [Stainless for SS only][White aluminum] [Clear Anodized Aluminum] Attachment Devices: Size for five times design load indicated in ASTM C 635, Table 1, Direct Hung unless otherwise indicated. Wire for Hangers and Ties: ASTM A 641, Class 1 zinc coating, soft temper, pre-stretched, with a yield stress load of at least time three design load, but not less than 12 gauge. Edge Moldings and Trim: Metal or extruded aluminum of types and profiles indicated or, if not indicated, manufacturer's standard moldings for edges and penetrations, including light fixtures, that fit type of edge detail and suspension system indicated. Provide moldings with exposed flange of the same width as exposed runner. END OF SECTION 09 5113 ACOUSTICAL PANEL CEILINGS 09 5113 - 8 of 8 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 SECTION 09 9100 - PAINTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes surface preparation and field painting of the following: 1. 2. 3. B. Paint exposed surfaces, except where the paint schedules indicate that a surface or material is not to be painted or is to remain natural. If the paint schedules do not specifically mention an item or a surface, paint the item or surface the same as similar adjacent materials or surfaces whether or not schedules indicate colors. If the schedules do not indicate color or finish, the Architect will select from standard colors and finishes available. For purposes of determining costs Contractor shall assume a minimum of four (4) colors and two (2) accent colors. 1. C. Exposed exterior items and surfaces. Exposed interior items and surfaces. Surface preparation, priming, and finish coats specified in this Section are in addition to shop priming and surface treatment specified in other Sections. Painting includes field painting of exposed bare and covered pipes and ducts (including color coding), hangers, exposed steel and iron work, and primed metal surfaces of mechanical and electrical equipment. Do not paint prefinished items, concealed surfaces, finished metal surfaces, operating parts, and labels. 1. Prefinished items include the following factory-finished components: a. b. c. d. e. f. 2. Concealed surfaces include walls or ceilings in the following generally inaccessible spaces: a. b. c. d. e. f. PAINTING Solid plastic toilet enclosures. Elevator entrance doors and frames. Elevator equipment. Finished mechanical and electrical equipment. Light fixtures. Distribution cabinets. Foundation spaces. Furred areas. Ceiling plenums. Pipe spaces. Duct shafts. Elevator shafts. 09 9100- 1 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3. Finished metal surfaces include the following: a. b. c. d. e. f. 4. D. Labels: Do not paint over Underwriters Laboratories (UL), Factory Mutual (FM), or other code-required labels or equipment name, identification, performance rating, or nomenclature plates. Division 8 Section "Hollow Metal Doors and Frames" for shop priming steel doors and frames. DEFINITIONS A. General: Standard coating terms defined in ASTM D 16 apply to this Section. 1. 2. 3. 4. 5. 1.4 Valve and damper operators. Linkages. Sensing devices. Motor and fan shafts. Related Sections: The following Sections contain requirements that relate to this Section: 1. 1.3 Color anodized aluminum. Color coated aluminum. Stainless steel Chromium plate. Copper. Bronze and brass. Operating parts include moving parts of operating equipment and the following: a. b. c. d. 5. NOVEMBER 19TH, 2013 Flat refers to a lusterless or matte finish with a gloss range below 15 when measured at an 85-degree meter. Eggshell refers to low-sheen finish with a gloss range between 5 and 20 when measured at a 60-degree meter. Satin refers to low-sheen finish with a gloss range between 15 and 35 when measured at a 60-degree meter. Semigloss refers to medium-sheen finish with a gloss range between 30 and 65 when measured at a 60-degree meter. Full gloss refers to high-sheen finish with a gloss range more than 65 when measured at a 60-degree meter. SUBMITTALS A. Product Data: For each paint system specified. Include block fillers and primers. 1. 2. 3. PAINTING Material List: Provide an inclusive list of required coating materials. Indicate each material and cross-reference specific coating, finish system, and application. Identify each material by manufacturer's catalog number and general classification. Manufacturer's Information: Provide manufacturer's technical information, including label analysis and instructions for handling, storing, and applying each coating material proposed for use. Certification by the manufacturer that products supplied comply with local regulations controlling use of volatile organic compounds (VOCs). 09 9100- 2 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 B. Samples for Initial Selection: Manufacturer's color charts showing the full range of colors available for each type of finish-coat material indicated. 1. C. After color selection, the Architect will furnish color chips for surfaces to be coated. Samples for Verification: Of each color and material to be applied, with texture to simulate actual conditions, on representative Samples of the actual substrate. 1. 2. 3. Provide stepped Samples, defining each separate coat, including block fillers and primers. Use representative colors when preparing Samples for review. Resubmit until required sheen, color, and texture are achieved. Provide a list of materials and applications for each coat of each sample. Label each sample for location and application. Submit Samples on the following substrates for the Architect's review of color and texture only: a. b. c. D. 1.5 NOVEMBER 19TH, 2013 Concrete: Provide two 4-inch- (100-mm-) square samples for each color and finish. Concrete Masonry: Provide two 4-by-8-inch (100-by-200-mm) samples of masonry, with mortar joint in the center, for each finish and color. Ferrous Metal: Provide two 4-inch- (100-mm-) square samples of flat metal and two 8-inch- (200-mm-) long samples of solid metal for each color and finish. Qualification Data: For firms and persons specified in the "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified. QUALITY ASSURANCE A. Applicator Qualifications: Engage an experienced applicator who has completed painting system applications similar in material and extent to that indicated for this Project with a record of successful in-service performance. B. Source Limitations: Obtain block fillers, primers, and undercoat materials for each coating system from the same manufacturer as the finish coats. C. Benchmark Samples (Mockups): Provide a full-coat benchmark finish sample of each type of coating and substrate required on the Project. Comply with procedures specified in PDCA P5. Duplicate finish of approved prepared samples. 1. The Architect will select one room or surface to represent surfaces and conditions for each type of coating and substrate to be painted. a. b. 2. After permanent lighting and other environmental services have been activated, apply coatings in this room or to each surface according to the Schedule or as specified. Provide required sheen, color, and texture on each surface. a. 3. PAINTING Wall Surfaces: Provide samples on at least 100 sq. ft. (9 sq. m) of wall surface. Small Areas and Items: The Architect will designate an item or area as required. After finishes are accepted, the Architect will use the room or surface to evaluate coating systems of a similar nature. Final approval of colors will be from job-applied samples. 09 9100- 3 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1.6 DELIVERY, STORAGE, AND HANDLING A. Deliver materials to the Project Site in manufacturer's original, unopened packages and containers bearing manufacturer's name and label, and the following information: 1. 2. 3. 4. 5. 6. 7. 8. B. Protect from freezing. Keep storage area neat and orderly. Remove oily rags and waste daily. Take necessary measures to ensure that workers and work areas are protected from fire and health hazards resulting from handling, mixing, and application. PROJECT CONDITIONS A. Apply water-based paints only when the temperature of surfaces to be painted and surrounding air temperatures are between 50 and 90 deg F (10 and 32 deg C). B. Apply solvent-thinned paints only when the temperature of surfaces to be painted and surrounding air temperatures are between 45 and 95 deg F (7.2 and 35 deg C). C. Do not apply paint in snow, rain, fog, or mist; or when the relative humidity exceeds 85 percent; or at temperatures less than 5 deg F (3 deg C) above the dew point; or to damp or wet surfaces. 1. 1.8 Product name or title of material. Product description (generic classification or binder type). Manufacturer's stock number and date of manufacture. Contents by volume, for pigment and vehicle constituents. Thinning instructions. Application instructions. Color name and number. VOC content. Store materials not in use in tightly covered containers in a well-ventilated area at a minimum ambient temperature of 45 deg F (7 deg C). Maintain containers used in storage in a clean condition, free of foreign materials and residue. 1. 1.7 NOVEMBER 19TH, 2013 Painting may continue during inclement weather if surfaces and areas to be painted are enclosed and heated within temperature limits specified by manufacturer during application and drying periods. EXTRA MATERIALS A. Furnish extra paint materials from the same production run as the materials applied in the quantities described below. Package paint materials in unopened, factory-sealed containers for storage and identify with labels describing contents. Deliver extra materials to the Owner. 1. Quantity: Furnish the Owner with extra paint materials in the quantities indicated below: a. b. c. d. 2. PAINTING Exterior, Full-Gloss Alkyd Enamel: 2 gal. (7.57 L) of each color applied. Interior, Flat Acrylic Paint: One case of each color applied. Interior, Low-Luster Acrylic Finish: One case of each color applied. Interior, Semigloss Acrylic Enamel: 2 gal. (7.57 L) of each color applied. Quantity: Furnish the Owner with an additional 5 percent, but not less than 1 gal. (3.785 L) or 1 case, as appropriate, of each material and color applied. 09 9100- 4 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 NOVEMBER 19TH, 2013 PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Products: Subject to compliance with requirements, provide products of PPG Industries, Inc. (PPG) listed in the paint schedules. B. Manufacturers Names: The following other acceptable manufacturers are referred to in the paint schedules by use of shortened versions of their names, which are shown in parentheses: 1. 2. 3. 2.2 Benjamin Moore & Co. (Moore). Pratt & Lambert, Inc. (P & L). M.A. Bruder & Sons (MAB) PAINT MATERIALS, GENERAL A. Material Compatibility: Provide block fillers, primers, undercoats, and finish-coat materials that are compatible with one another and the substrates indicated under conditions of service and application, as demonstrated by manufacturer based on testing and field experience. B. Material Quality: Provide manufacturer's best-quality paint material of the various coating types specified. Paint-material containers not displaying manufacturer's product identification will not be acceptable. 1. C. Proprietary Names: Use of manufacturer's proprietary product names to designate colors or materials is not intended to imply that products named are required to be used to the exclusion of equivalent products of other manufacturers. Furnish manufacturer's material data and certificates of performance for proposed substitutions. Colors: Provide color selections where listed in the Paint Schedules. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine substrates, areas, and conditions, with the Applicator present, under which painting will be performed for compliance with paint application requirements. 1. 2. B. Coordination of Work: Review other Sections in which primers are provided to ensure compatibility of the total system for various substrates. On request, furnish information on characteristics of finish materials to ensure use of compatible primers. 1. PAINTING Do not begin to apply paint until unsatisfactory conditions have been corrected and surfaces receiving paint are thoroughly dry. Start of painting will be construed as the Applicator's acceptance of surfaces and conditions within a particular area. Notify the Architect about anticipated problems using the materials specified over substrates primed by others. 09 9100- 5 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3.2 NOVEMBER 19TH, 2013 PREPARATION A. General: Remove hardware and hardware accessories, plates, machined surfaces, lighting fixtures, and similar items already installed that are not to be painted. If removal is impractical or impossible because of the size or weight of the item, provide surface-applied protection before surface preparation and painting. 1. B. Cleaning: Before applying paint or other surface treatments, clean the substrates of substances that could impair the bond of the various coatings. Remove oil and grease before cleaning. 1. C. After completing painting operations in each space or area, reinstall items removed using workers skilled in the trades involved. Schedule cleaning and painting so dust and other contaminants from the cleaning process will not fall on wet, newly painted surfaces. Surface Preparation: Clean and prepare surfaces to be painted according to manufacturer's written instructions for each particular substrate condition and as specified. 1. 2. Provide barrier coats over incompatible primers or remove and reprime. Cementitious Materials: Prepare concrete and concrete masonry block surfaces to be painted. Remove efflorescence, chalk, dust, dirt, grease, oils, and release agents. Roughen as required to remove glaze. If hardeners or sealers have been used to improve curing, use mechanical methods of surface preparation. a. b. c. 3. Ferrous Metals: Clean ungalvanized ferrous-metal surfaces that have not been shop coated; remove oil, grease, dirt, loose mill scale, and other foreign substances. Use solvent or mechanical cleaning methods that comply with the Steel Structures Painting Council's (SSPC) recommendations. a. b. c. 4. D. PAINTING Use abrasive blast-cleaning methods if recommended by paint manufacturer. Determine alkalinity and moisture content of surfaces by performing appropriate tests. If surfaces are sufficiently alkaline to cause the finish paint to blister and burn, correct this condition before application. Do not paint surfaces where moisture content exceeds that permitted in manufacturer's written instructions. Clean concrete floors to be painted with a 5 percent solution of muriatic acid or other etching cleaner. Flush the floor with clean water to remove acid, neutralize with ammonia, rinse, allow to dry, and vacuum before painting. Blast steel surfaces clean as recommended by paint system manufacturer and according to requirements of SSPC-SP 10. Treat bare and sandblasted or pickled clean metal with a metal treatment wash coat before priming. Touch up bare areas and shop-applied prime coats that have been damaged. Wirebrush, clean with solvents recommended by paint manufacturer, and touch up with the same primer as the shop coat. Galvanized Surfaces: Clean galvanized surfaces with nonpetroleum-based solvents so surface is free of oil and surface contaminants. Remove pretreatment from galvanized sheet metal fabricated from coil stock by mechanical methods. Materials Preparation: Mix and prepare paint materials according to manufacturer's written instructions. 09 9100- 6 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 2. 3. E. 3.3 NOVEMBER 19TH, 2013 Maintain containers used in mixing and applying paint in a clean condition, free of foreign materials and residue. Stir material before application to produce a mixture of uniform density. Stir as required during application. Do not stir surface film into material. If necessary, remove surface film and strain material before using. Use only thinners approved by paint manufacturer and only within recommended limits. Tinting: Tint each undercoat a lighter shade to simplify identification of each coat when multiple coats of the same material are applied. Tint undercoats to match the color of the finish coat, but provide sufficient differences in shade of undercoats to distinguish each separate coat. APPLICATION A. General: Apply paint according to manufacturer's written instructions. Use applicators and techniques best suited for substrate and type of material being applied. 1. 2. 3. 4. 5. 6. 7. 8. 9. B. Scheduling Painting: Apply first coat to surfaces that have been cleaned, pretreated, or otherwise prepared for painting as soon as practicable after preparation and before subsequent surface deterioration. 1. 2. 3. 4. C. PAINTING Paint colors, surface treatments, and finishes are indicated in the schedules. Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces, or conditions detrimental to formation of a durable paint film. Provide finish coats that are compatible with primers used. The term "exposed surfaces" includes areas visible when permanent or built-in fixtures, convector covers, covers for finned-tube radiation, grilles, and similar components are in place. Extend coatings in these areas, as required, to maintain the system integrity and provide desired protection. Paint surfaces behind movable equipment and furniture the same as similar exposed surfaces. Before the final installation of equipment, paint surfaces behind permanently fixed equipment or furniture with prime coat only. Paint interior surfaces of ducts with a flat, nonspecular black paint where visible through registers or grilles. Paint back sides of access panels and removable or hinged covers to match exposed surfaces. Finish exterior doors on tops, bottoms, and side edges the same as exterior faces. Sand lightly between each succeeding enamel or varnish coat. The number of coats and the film thickness required are the same regardless of application method. Do not apply succeeding coats until the previous coat has cured as recommended by the manufacturer. If sanding is required to produce a smooth, even surface according to manufacturer's written instructions, sand between applications. Omit primer on metal surfaces that have been shop primed and touchup painted. If undercoats or other conditions show through final coat of paint, apply additional coats until paint film is of uniform finish, color, and appearance. Give special attention to ensure edges, corners, crevices, welds, and exposed fasteners receive a dry film thickness equivalent to that of flat surfaces. Allow sufficient time between successive coats to permit proper drying. Do not recoat surfaces until paint has dried to where it feels firm, does not deform or feel sticky under moderate thumb pressure, and where application of another coat of paint does not cause the undercoat to lift or lose adhesion. Application Procedures: Apply paints and coatings by brush, roller, spray, or other applicators according to manufacturer's written instructions. 09 9100- 7 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 1. 2. 3. Brushes: Use brushes best suited for the type of material applied. Use brush of appropriate size for the surface or item being painted. Rollers: Use rollers of carpet, velvet back, or high-pile sheep's wool as recommended by the manufacturer for the material and texture required. Spray Equipment: Use airless spray equipment with orifice size as recommended by the manufacturer for the material and texture required. D. Minimum Coating Thickness: Apply paint materials no thinner than manufacturer's recommended spreading rate. Provide the total dry film thickness of the entire system as recommended by the manufacturer. E. Mechanical and Electrical Work: Painting of mechanical and electrical work is limited to items exposed in equipment rooms and in occupied spaces. F. Mechanical items to be painted include, but are not limited to, the following: 1. 2. 3. 4. 5. 6. 7. G. Piping, pipe hangers, and supports. Heat exchangers. Tanks. Ductwork. Insulation. Motors and mechanical equipment. Accessory items. Electrical items to be painted include, but are not limited to, the following: 1. 2. 3. 3.4 NOVEMBER 19TH, 2013 Conduit and fittings. Switchgear. Panelboards. H. Block Fillers: Apply block fillers to concrete masonry block at a rate to ensure complete coverage with pores filled. I. Prime Coats: Before applying finish coats, apply a prime coat of material, as recommended by the manufacturer, to material that is required to be painted or finished and that has not been prime coated by others. Recoat primed and sealed surfaces where evidence of suction spots or unsealed areas in first coat appears, to ensure a finish coat with no burn through or other defects due to insufficient sealing. J. Pigmented (Opaque) Finishes: Completely cover surfaces as necessary to provide a smooth, opaque surface of uniform finish, color, appearance, and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections will not be acceptable. K. Completed Work: Match approved samples for color, texture, and coverage. refinish, or repaint work not complying with requirements. Remove, FIELD QUALITY CONTROL A. The Owner reserves the right to invoke the following test procedure at any time and as often as the Owner deems necessary during the period when paint is being applied: 1. PAINTING The Owner will engage the services of an independent testing agency to sample the paint material being used. Samples of material delivered to the Project will be taken, identified, sealed, and certified in the presence of the Owner’s Representative. 09 9100- 8 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2. The testing agency will perform appropriate tests for the following characteristics as required by the Owner Representative: a. b. c. d. e. f. g. h. i. j. k. l. m. 3. 3.5 The Owner may direct the Contractor to stop painting if test results show material being used does not comply with specified requirements. The Contractor shall remove noncomplying paint from the site, pay for testing, and repaint surfaces previously coated with the rejected paint. If necessary, the Contractor may be required to remove rejected paint from previously painted surfaces if, on repainting with specified paint, the 2 coatings are incompatible. Cleanup: At the end of each workday, remove empty cans, rags, rubbish, and other discarded paint materials from the site. 1. After completing painting, clean glass and paint-spattered surfaces. Remove spattered paint by washing and scraping. Be careful not to scratch or damage adjacent finished surfaces. PROTECTION A. Protect work of other trades, whether being painted or not, against damage by painting. Correct damage by cleaning, repairing or replacing, and repainting, as approved by Architect. B. Provide "Wet Paint" signs to protect newly painted finishes. Remove temporary protective wrappings provided by others to protect their work after completing painting operations. 1. 3.7 Quantitative material analysis. Abrasion resistance. Apparent reflectivity. Flexibility. Washability. Absorption. Accelerated weathering. Dry opacity. Accelerated yellowness. Recoating. Skinning. Color retention. Alkali and mildew resistance. CLEANING A. 3.6 NOVEMBER 19TH, 2013 At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces. Comply with procedures specified in PDCA P1. EXTERIOR PAINT SCHEDULE A. Ferrous Metal: Provide the following finish systems over exterior ferrous metal. Primer is not required on shop-primed items. 1. PAINTING Full-Gloss, Alkyd-Enamel Finish: 2 finish coats over a rust-inhibitive primer. Primer not required for factory primed items of ferrous metal. 09 9100- 9 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 a. Primer: Rust-inhibitive metal primer applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 1.3 mils (0.033 mm). 1) 2) 3) 4) b. PPG: 6-282 Speedhide Interior/Exterior Gloss-Oil Enamel. Moore: Impervo Enamel #133. P & L: S 4500 Series Tech-Gard Maintenance Gloss Enamel. MAB: Rust-O-Lastic Alkyd Finish Coat (074 line). Zinc-Coated Metal: Provide the following finish systems over exterior zinc-coated (galvanized) metal surfaces: 1. Full-Gloss, Alkyd-Enamel Finish: 2 finish coats over a galvanized metal primer. a. Primer: Galvanized metal primer applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 1.2 mils (0.031 mm). 1) 2) 3) 4) b. PPG: 90-709 Pitt Tech One Pack Interior/Exterior Primer/Finish DTM Industrial Enamel Moore: IronClad Galvanized Metal Latex Primer #155. P & L: Z/F 1003 Suprime "3" Interior/Exterior Latex Metal Primer. MAB: HydroPrime II (073-189). First and Second Coats: Full-gloss, exterior, alkyd enamel applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 2.6 mils (0.066 mm). Color(s) as selected by Architect 1) 2) 3) 4) 3.8 PPG: 6-208 Speedhide Interior/Exterior Rust Inhibitive Steel Primer Moore: IronClad Retardo Rust-Inhibitive Paint #163. P & L: S 4551 Tech-Gard High Performance Rust-Inhibitor Primer. MAB: Rust-O-Lastic Alkyd Finish Coat (074 line). First and Second Coats: Full-gloss, exterior, alkyd enamel applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 3.0 mils (0.076 mm). Color(s) as selected by Architect. 1) 2) 3) 4) B. NOVEMBER 19TH, 2013 PPG: 6-282 Speedhide Interior/Exterior Gloss-Oil Enamel Moore: Impervo Enamel #133. P & L: S 4500 Series Tech-Gard Maintenance Gloss Enamel. MAB: Recommend using Acrylic DTM’s for this application. INTERIOR PAINT SCHEDULE A. Concrete Masonry Units: Provide the following finish systems over interior concrete masonry block units: 1. Semigloss, Acrylic-Enamel Finish: 2 finish coats over a block filler. a. Block Filler: High-performance, latex-based, block filler applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 5.0 mils (0.13 mm). 1) 2) PAINTING PPG: 6-7 Speedhide Interior/Exterior Masonry Latex Block Filler. Moore: Moorcraft Interior & Exterior Block Filler #173. 09 9100- 10 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 3) 4) b. 2) 3) 4) Flat Acrylic Finish: 2 finish coats over a primer. (Ceilings only) a. Primer: Latex-based, interior primer applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 1.2 mils (0.031 mm). 1) 2) 3) 4) b. PPG: 17-10 Quick Drying Interior Latex Primer Sealer (White) Moore: Regal First Coat Interior Latex Primer & Underbody #216 (White). P & L: Z/F 1004 Suprime "4" Interior Latex Wall Primer (White). MAB: Rich Lux Latex Sealer/Undercoater (037-154) First and Second Coats: Flat, acrylic-latex-based, interior paint applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 2.5 mils (0.064 mm). Color – White as selected by Architect. 1) 2) 3) 4) PPG: 80 Line Wallhide Interior Wall Flat Latex Paint Moore: Regal Wall Satin #215. P & L: Z/F 2000 Series Vapex Latex Flat Wall Finish. MAB: (Rich Lux Walshield (041 line) Ferrous Metal: Provide the following finish systems over ferrous metal: 1. Semigloss, Alkyd-Enamel Finish: One finish coat over an enamel undercoater and a primer. a. Primer: Quick-drying, rust-inhibitive, alkyd-based or epoxy-metal primer, as recommended by the manufacturer for this substrate, applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 1.5 mils (0.038 mm). Primer not required on factory primed ferrous metal. 1) 2) 3) 4) b. PPG: 6-208 Speedhide Interior/Exterior Rust Inhibitive Steel Primer. Moore: IronClad Retardo Rust-Inhibitive Paint #163. P & L: S 4551 Tech-Gard High Performance Rust Inhibitor Primer. MAB: Rust-O-Lastic Anti-Corrosive Primer (073 line) Undercoat: Alkyd, interior enamel undercoat or semigloss, interior, alkyd-enamel finish coat, as recommended by the manufacturer for this substrate, applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 1.2 mils (0.031 mm). 1) PAINTING PPG: 88-110 Satinhide Interior Enamel Wall & Trim Lo-Lustre Semi-Gloss Latex. Moore: Moore's Regal AquaGlo Vinyl-Acrylic Latex Enamel #333. P & L: Z/F 4100 Series Accolade Interior Semi-Gloss. MAB: Rich Lux Latex Semi-Gloss (023 line) Gypsum Board: Provide the following finish systems over interior gypsum board surfaces: 1. C. P & L: Z 98 Pro-Hide Plus Latex Block Filler. MAB Block Kote #2000 (064-140) First and Second Coats: Semigloss, acrylic-latex, interior enamel applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 2.6 mils (0.066 mm). Color(s) as selected by Architect. 1) B. NOVEMBER 19TH, 2013 PPG: 6-6 Speedhide Interior Quick-Drying Enamel Undercoater 09 9100- 11 of 12 GREENWICH PUBLIC SCHOOLS ISD GYM WINDOW REPLACEMENT KSQ ARCHITECTS PROJECT NO. 1317908.00 2) 3) 4) c. Moore: Moore's Alkyd Enamel Underbody #217. P & L: S/D 1011 Suprime "11" Interior Alkyd Wood Primer. MAB: Rich Lux Sealer/Undercoater (037-172) Finish Coat: Odorless, semigloss, alkyd, interior enamel applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 1.4 mils (0.036 mm). Color(s) as selected by Architect. 1) 2) 3) 4) D. NOVEMBER 19TH, 2013 PPG: 27 Line Wallhide Low Odor Interior Enamel Wall and Trim Semi-Gloss Oil. Moore: Satin Impervo #235. P & L: S/D 5700 Cellu-Tone Alkyd Satin Enamel. MAB: Fresh Kote Alkyd Semi-Gloss (403 line) Concrete Floors: Provide the following paint systems over interior concrete floors: a. First and Second Coats: Oderless, gloss, alkyd, interior enamel applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 4.0 mils. 1) 2) 3) 4) Moore: Moore's Porch and Floor Enamel #112. S-W: Industrial Enamel B54Z Series. ICI Dulux: 3118 Ultra-Hide Interior/Exterior Polyurethane Floor Enamel. P & L: 61 Floor Enamel. END OF SECTION 09 9100 PAINTING 09 9100- 12 of 12
© Copyright 2024