SIGNIFICANT UPGRADE TO K2 DFS Highlights:

SIGNIFICANT UPGRADE TO K2 DFS
Highlights:






Pre-tax NPV of $14.87m1 @ 8% Discount Rate
78%↑
IRR of 229%1 42%↑
Average C1 cash cost $791/oz Au1: 6%↓
Maximum capital draw down of $6.6m1 4%↑
Cumulative cash flow of $18.22m1: 78%↑
Financing negotitations well advanced
Overview:
Ord River Resources Limited (ASX:ORD “ORD”) is pleased to
announce a significant upgrade to the Definitive Feasibility Study
(“DFS”) on the K2 Underground Development Project, part of
the broader Plutonic Dome Gold Project (“Project”). The Project
is a Farm In/Joint Venture (“FIJVA”) with Dampier Gold Limited,
ASX:DAU (“Dampier”).
ASX Announcement:
08/10/2014
Australian Securities Exchange
Code: ORD
Board of Directors:
Frank Zhu
Managing Director
Bruce McInnes
Chairman
Sean Zhuo
Non-Exec Director
Ord currently holds a 30% interest in the Project and has elected
to sole fund an additional $1 million of expenditure before 10
February 2015 to earn an additional 15% interest. Ord can earn
up to a 75% interest in the Project. (Please refer to the
Agreements section and Table 6 below)
The updated DFS incorporated the recent K2 resource upgrade
announced 1st October 2014. The DFS assessed the economic
viability of underground mining methods to extract ore from K2
with toll treatment of ore at the nearby Northern Star Resources
(ASX: NST) owned Plutonic Processing Plant. Ord executed a
binding Ore Treatment Agreement on 24th September 2014 to
facilitate the processing of K2 ore.
ORD commissioned the study, by leading engineering and
services group, Entech Pty Ltd (“Entech”), with input from
various industry consultants.
1
Figures quoted as 100% of K2 Project basis, not based on current
ownership. Please refer to Agreements section of announcement for
further detail towards equity ownership of the Plutonic Dome Gold
Project.
Location
1|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
The K2 deposit is located 36 km from Northern Star’s Plutonic Gold Mine and
approximately 216 km NE of Meekatharra, Western Australia. Access from mine to
mill is via a network of high quality haul roads.
K2 Deposit
Northern Star Resources
Plutonic Processing Plant
Figure 1: Project Location Plan
Project History
The K2 deposit was last mined in 1997 by Resolute who had completed an underground
development Feasibility study in 1996. Resolute excavated a boxcut and established the
decline to access underground drill positions before the mine was prematurely closed
in 1998 after only minor amounts of ore extraction.
Figure 2: K2 Deposit and Existing Historical Infrastructure
Figure 3: K2 Portal
2|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Financial and Production Highlights:
Table 1: K2 Financial Summary
Project Returns
K2 DFS 01/07/14
K2 DFS 08/10/14
% Change
NPV @ 8%
$8,352,441
$14,870,142
78
NPV @ 10%
$7,946,431
$14,159,365
78
161%
229%
42
Payback Years
1.7
1.6
-6
Free Cash flow
$10,250,714
$18,224,304
78
$841/ oz
$791/ oz
-6
$1,123/ oz
$1,030/ oz
-8
C1 Cash Costs / t
$155/ t
$158/ t
2
All in Sustaining Costs
$208/ t
IRR
C1 Cash Costs / oz
All in Sustaining Costs
Mined Tonnes
200,484
$206/ t
t2
245,214
g/t2
6.9
-1
t2
22
g/t2
Head Grade
6.4
Recovered Ounces
37,0002
54,0002
8
46
Gold Price ($AUD/oz)
Assumption
Exchange Rate (AU/US)
Assumption
$1,400
$1,402
-
$0.93
$0.87
-6
Notes:
Gold Metallurgical Recovery 90%
WA State Royalty 2.5%
Northern Star Royalty 1%
Mining Recovery for stopes 90%
Mining Recovery Crown Pillar 80%
Financial figures quoted for PDGP, please refer to agreement section below which stipulates equity ownership structure of the
PDGP.
2Total
mining inventory includes Inferred Mineral Resources. See Table 3- Total Mining Inventory below.
Table 2: K2 Cash Flow Summary
Year 1 $
Year 2 $
Year 3 $
Total
Revenue
Gold Price
Spot Revenue
Royalty (Government)
Total Project Revenue
Costs
Mining
Processing
Capital Expenditure
Total Project Costs
1,402
9,554,967
238,624
9,306,343
1,402
52,243,399
1,306,085
50,937,314
1,402
6,940,489
173,512
6,766,977
68,728,856
1,718,221
67,010,634
6,509,889
2,306,603
6,954,666
15,771,157
19,679,687
8,583,934
2,879,472
31,143,093
642,084
1,029,997
200,000
1,872,081
26,831,659
11,920,533
10,034,138
48,786,331
Project Cash Flow Before Tax
(6,464,814)
19,794,221
4,894,896
18,224,304
Cumulative Cash Flow
(6,464,814)
13,329,407
18,224,304
18,224,304
3|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Mining:
The proposed underground mine will be accessed via the existing boxcut, portal and decline
development. This existing development will require some minor rehabilitation. It is proposed
that a mining contractor will be used to extract and deliver ore to Northern Star Resources’
Plutonic Processing Plant. Underground trucks will deliver ore to a specified location where a
surface haulage contractor will transport this material from the mine to the Plutonic plant.
The mine design includes rehabilitation of approximately 840m of the existing decline before
extending the decline and strike drive level arrangement. The decline is designed with a
minimum standoff of 30 metres from the main ore zone. Levels are designed at 20m level
spacing (floor to floor) implying that the stopes will be approximately 16m in height over a strike
length of 37.5m.
Figure 4: Planned Mine Development K2 Underground
The selected mining method of longitudinal open stoping with pillars has been determined to
be the optimal method for the style of mineralisation and geotechnical parameters. The mining
environment at K2 has been described as being relatively benign given the good rock mass
conditions and shallow depths.
Figure 5: Longitudinal Longhole Stoping Schematic
4|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Metallurgy & Processing:
Metallurgical test work completed concluded that K2 ore is amenable to conventional
processing methods and can be expected to yield metal recoveries in excess of 90%. A metal
recovery factor of 90% was adopted for the project, representing a value just below the lower
end of the range reported in metallurgical test work.
The Plutonic Processing Plant is located 36km from K2 via existing Haul Roads. The ore
processing schedule is based upon delivered ore being processed when made available to
Northern Star Resources’ Plutonic Processing Plant. Processing costs is all inclusive from the
point of delivery.
Site Infrastructure and Services:
Electrical power will be provided to site by a BOO (Build, Own, Operate) power station located
on the surface consisting of two 500kVa diesel generators producing power at 415V. The site
based infrastructure will be located adjacent to the box cut and includes a ROM pad, waste
dump, workshops, fuel storage and site based buildings, communications infrastructure and
explosives storage facility.
5|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Mineral Resource Estimation:
The Mineral Resource estimates were compiled by Geonomics Australia Pty Ltd (“Geonomics”)
and are in accordance with JORC 2012 (Edition) Guidelines (ASX Release, Resource Upgrade at
Plutonic Dome Project 01/10/2014). K2 contains a total mineral resource of 415,000t at 7.7g/t
for 103,000oz Au at a 3g/t Au cut-off grade.
Table 3: K2 Mineral Resource Estimation
K2 Mineral Resource Estimation
Category
Tonnes
Au (g/t)
Indicated
198,000
8.9
Contained
Gold (oz)
57,000
Inferred
217,000
6.7
47,000
Total
415,000
7.7
103,000
Note: Figures are rounded to nearest 1,000t, 0.1g/t Au and 1,000oz Au. Rounding errors may
occur
Ore Reserve Estimation:
Table 4: Ore Reserve Estimation
K2 Underground Ore Reserve
Reserve Category
Tonnes
Proven
Au (g/t)
Contained
Gold (oz)
-
0
-
Probable
150,000
7.0
34,000
Total
150,000
7.0
34,000
Notes: The Indicated Mineral Resources are inclusive of those Mineral Resources modified to
produce the Ore Reserve. Figures are rounded to nearest 1,000t, 0.1g/t Au and 1,000oz Au.
Rounding errors may occur.
An Ore Reserve estimate was conducted based on the Mineral Resource estimation conducted
by Geonomics. The Ore Reserves have been estimated by Entech Pty Ltd and is similarly in
accordance with JORC 2012 (Edition) Guidelines. The Mineral Resources are reported inclusive
of Ore Reserves. The estimation was conducted based upon the information derived from the
Definitive Feasibility Study estimation conducted at K2. Cut off grades were determined based
on unit costs from the feasibility level mining cost model.
Ore Reserves were calculated by generating detailed mining shapes for each stoping block as
well as development. The designed stope shapes included planned dilution, being waste
material that was located within the mineable stope shape. A 10% unplanned mining dilution
factor was applied and is considered to be appropriate given the ground conditions and
proposed style of mining. 95% mining recovery was applied post geological interpretation to
6|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
generate the final diluted and recovered Ore Reserve estimate. No Inferred Mineral Resources
were included in the Ore Reserve Estimation.
Infrastructure required for the proposed underground operation has been accounted for and
included in all work leading to the generation of the Ore Reserve Estimation. An 8% discount
rate was applied to the project and the NPV of the project is positive at the assumed
commodity price and exchange rate.
The financial parameters quoted are based on a Total Mining Inventory, generated during the
DFS. A detailed mine design and economic evaluation was used to generate the Ore Reserve
and Total Mining Inventory, which is completely sourced from underground mining.
The Total Mining Inventory contains some Inferred Mineral Resources. These are immediately
adjacent to, and/or below mined Ore Reserves. They have had the same modifying factors
applied as per the Probable Ore Reserve. Ord believes that it is reasonable to expect a
proportion of Inferred Resources to be upgraded when ore development and grade control
occur in these areas.
Ore Reserves and Total Mining Inventory are based on the K2 Mineral Resource reported on
the ASX by Ord -1st October 2014- “Resource Upgrade Plutonic Gold Project”. No material
change has occurred since reporting and Mineral Resources are inclusive of Ore Reserves.
Table 5: Total Mining Inventory
K2 Total Mining Inventory
Tonnes
Au (g/t)
Oz Au
Proportion
Indicated Resource Inventory
151,000
7.4
36,000
67%
Inferred Resource Inventory
94,000
6.0
18,000
33%
Total Mining Inventory
245,000
6.9
54,000
100%
Note: Figures are rounded to nearest 1,000t, 0.1g/t Au and 1,000oz Au. Rounding errors may
occur.
Geotechnical:
Ground Control Engineering Pty Ltd (“GCE”) has conducted a feasibility geotechnical assessment
of the mine design and production strategy for the Ord Resources K2 project. The design and
production strategy was provided by Entech.
The geotechnical assessment completed by GCE is based on core logging data from seventeen
previously drilled geotechnical holes. The holes were originally drilled and logged by Resolute in
1995-1996. GCE completed a site visit in April 2014 to review and validate the historic
geotechnical logging, based on inspection of existing core from the drill holes available on site.
Additionally the K2 decline was inspected to determine the amount of rehabilitation required.
7|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Permitting:
The permitting process for the K2 Project is well advanced. The water abstraction licence, works
approval and mining proposal has been approved for dewatering of K2 Open Pit and
Underground. The Mining Proposal with respect to the underground mining operation of K2
has been lodged with the Department of Mines and Petroleum of Western Australia. Further
updates will be provided upon approval of relevant statutory permitting.
Agreements:
The K2 deposit is subject to various royalty, joint ventures and other agreements with third
parties including the following:




Payment to the Western Australian State Government of 2.5% for gold production
above $450/oz Au (1.25% for below $450/oz Au); and
1% NSR payable to Northern Star Resources Ltd.
Legally binding toll treatment agreement with Northern Star Resources Ltd for the
processing of ORD’s ore from K2.
Letter of intent to negotiate an ore Agreement with Northern Star Resources to process
Trident ore.
Under the terms of the FIJVA between ORD and Dampier, ORD is required to sole fund a
minimum of $6 million in project based expenditure over a 2 year period to earn up to a 75%
interest in the Project. ORD has completed its minimum $2 million sole funding obligation
within the 9 month period after FIJVA commencement to earn a 30% interest in the Project
(please refer to table below). ORD has elected to sole fund a further $1 million over the next 5
months to earn an additional 15% interest in the Project.
Table 6: Ord River- Dampier Gold Farm In/Joint Venture- Plutonic Dome Gold Project
INTEREST TO ACQUIRE
COMMITMENT
STATUS
30% Joint Venture
interest
$2 million project expenditure to be incurred within 9
months after FIJVA commencement
Complete
Further 15% Joint
Venture interest
Next $1 million project expenditure to be incurred within
14 months after FIJVA commencement
Commenced
Further 15% Joint
Venture interest
Next $1 million project expenditure to be incurred within
19 months after FIJVA commencement
-
Further 15% Joint
Venture interest
Next $2 million project expenditure to be incurred within
24 months after FIJVA commencement
-
ORD has entered into a binding ore treatment agreement with Northern Star Resources Limited
(ASX:NST, “Northern Star”) facilitating the processing of ore from K2 which is located 36km from
Northern Star’s Plutonic Processing Facility. Access to Northern Star’s Plutonic Processing
Facility is via established haul roads.
8|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Northern Star will be paid for the processing services through the provision of gold at the point
of refining. This structure will assist greatly with the management of cash flow for Ord.
Competent person’s statement:
The information in this announcement that relates to Mineral Resources for K2 and Plutonic
Dome Project Exploration Results is based on information compiled and fairly represented by
Mr Jonathan King, consultant geologist, who is a Member of the Australian Institute of
Geoscientists and employed by Geonomics Australia Pty Ltd. Mr King has sufficient experience
relevant to the style of mineralisation and type of deposit under consideration, and to the
activity which he has undertaken, to qualify as a Competent Person as defined in the 2012
Edition of the Joint Ore Reserves Committee (JORC) Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves. Mr King consents to the inclusion in
this report of the matters based on this information in the form and context in which it appears.
Information in this announcement that relates to the Ore Reserves has been compiled by Shane
McLeay Principal Engineer – Entech Pty Ltd, who has sufficient experience relevant to the style
of mineralisation and type of deposit under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2012 Edition of the Joint Ore
Reserves Committee (JORC) Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves. Mr McLeay is a Fellow of the Australasian Institute of Mining and
Metallurgy and consents to the inclusion in the report of the matters based on his information
in the form and context in which it appears.
For further information, please contact:
Frank Zhu, Managing Director, Ord River Resources: frankzhu@ord.com.au, +61 420
318 004
9|Page
Ord River Resources Limited- www.ord.com.au – ASX:ORD
JORC Code, 2012 Edition- Table 1
Section 1, Sampling Techniques and Data
(Criteria in this section applies to all succeeding sections)
Criteria
JORC Code explanation
Comments
Sampling
techniques

Nature and quality of sampling (eg cut
channels, random chips, or specific specialised
industry standard measurement tools appropriate
to the minerals under investigation, such as down
hole gamma sondes, or handheld XRF
instruments, etc). These examples should not be
taken as limiting the broad meaning of sampling.
Samples were taken from Diamond Core and RC/RAB
chips, with drilling predominantly angled at -60⁰
towards 90⁰ (Local grid, 142⁰ MGA azimuth). Drill
spacing was on a nominal 15x10m grid for RC and
Diamond in the indicated portion of the resource to
40x40m spacing in the inferred material at depth. A
total of 1961 RAB, RC and Diamond holes are
included in the database for a total of 115,487m
drilling.
Diamond drill holes were surveyed via down hole
cameras at intervals of 30 to 50m during drilling using
an Eastman Single Shot Camera. A number of holes
were also surveyed by Sutron after drilling had
finished using either a gyro or DEMS tool.
 Include reference to measures taken to
ensure sample representivity and the appropriate
calibration of any measurement tools or systems
used.

Aspects of the determination of mineralisation
that are Material to the Public Report. In cases
where ‘industry standard’ work has been done this
would be relatively simple (eg ‘reverse circulation
drilling was used to obtain 1 m samples from
which 3 kg was pulverised to produce a 30 g
charge for fire assay’). In other cases more
explanation may be required, such as where there
is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation
types (eg submarine nodules) may warrant
disclosure of detailed information.
RC Holes were surveyed via a Single Shot Eastman
Camera at 30 to 50m. Deeper RC holes were surveyed
down the hole by Sutron on completion of drilling.
Diamond drilling was completed using truck mounted
rigs under contract by Northwest Drilling using mainly
NQ2 rods. Core was halved using a diamond core
saw, and collected generally at one metre intervals
for analysis, using geological/mineral boundaries as
main sample interval boundaries. Samples were
assayed for gold and arsenic at Amdel Laboratory
(Perth): gold analysis was conducted using a 50g
charge fire assay with AAS finish (detection limit of
0.01ppm Au)
RC Drilling was completed under contract by Drillcorp
using mainly Schramm rigs. RC holes were drilled
using a 5.5in face sampling bit and samples were
collected through a cyclone and riffle splitter both
mounted on a sample trailer, at one metre intervals.
Sampling of individual metres was done using a one
eighth riffle box splitter (the smaller split being
collected in calico bags for assaying). As with
diamond core, samples were assayed for old and
arsenic at Amdel using a 50g charge fire assay with
AAS finish. Pre-collar material was collected using
PVC bags at one metre intervals, and four metre
composite scoop sampling was then undertaken
RAB drilling was conducted under contract by
Connector Drilling, with material laid out on the
ground in one metre intervals and four metre
composite spear samples subsequently collected for
assaying. Bottom of hole samples were taken on a 2m
interval. All composite samples were assayed for low
level gold to 1ppb detection limit at Genalysis
Laboratories in Perth using a B/ETA technique (50
digest, solvent extraction, graphite furnace AAS
finish). Samples that returned greater than 0.1g/t Au
were re-sampled on one metre intervals at a later
date and submitted for low level gold analysis.
10 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
Comments
Drilling
techniques
Drill type (eg core, reverse circulation, openhole hammer, rotary air blast, auger, Bangka,
sonic, etc) and details (eg core diameter, triple or
standard tube, depth of diamond tails, facesampling bit or other type, whether core is
oriented and if so, by what method, etc).
All drilling reported in this announcement is a
combination of RAB, RC and Diamond Drilling
undertaken by previous operators of the project. As
such specific information relating to all drilling
techniques (hammer sizes etc.) has not been
accurately preserved.
Drill sample
recovery

As drilling was undertaken by previous project
operators- no record of sample recoveries were
located in exploration reports or on the original logs
during the validation process

Method of recording and assessing core and
chip sample recoveries and results assessed.
 Measures taken to maximise sample recovery
and ensure representative nature of the samples.
Diamond drill core was halved using a diamond core
saw, and collected generally at one metre intervals
for analysis, using geological/mineral boundaries as
main sample interval boundaries.
RC holes were drilled using a 5.5in face sampling bit
and samples were collected through a cyclone and
riffle splitter both mounted on a sample trailer, at one
metre intervals. Sampling of individual metres was
done using a one eighth riffle box splitter (the smaller
split being collected in calico bags for assaying).
 Whether a relationship exists between sample
recovery and grade and whether sample bias may
have occurred due to preferential loss/gain of
fine/coarse material.
Logging
 Whether core and chip samples have been
geologically and geotechnically logged to a level
of detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical
studies.

Whether logging is qualitative or quantitative
in nature. Core (or costean, channel, etc)
photography.

Subsampling
techniques
and sample
preparation

RAB drilling was conducted under contract by
Connector Drilling, with material laid out on the
ground in one metre intervals and four metre
composite spear samples subsequently collected for
assaying. Bottom of hole samples were taken on a 2m
interval.
As drilling was undertaken by previous project
operators- no further analysis is able to be
undertaken.
Further drilling activities to be
conducted by Ord will involve the use of both
diamond and RC drilling in order to understand
potential issues relating to sample recovery and
sample bias.
All RC and diamond drill holes have been logged in
detail: lithology, hardness, alteration, mineralisation,
colour, foliation, sulphides, grain size, weathering,
texture and Quartz percentage
Logging has been conducted both qualitatively or
quantitatively with full descriptions of lithologies,
alteration and mineralisation comments noted as
well as percentages estimates on veining,
weathering, quartz and numeric scale of hardness
The total length and percentage of the
relevant intersections logged.
The entire length of all RC and Diamond drill holes
have been logged in full
If core, whether cut or sawn and whether
quarter, half or all core taken.
All diamond drill holes were 1/4 core sampled at
intervals not less than 0.17 meters, not greater than
1 metres and where appropriate, to geological
contacts
 If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet or dry.
All RC samples were put through a rifle splitter and
into a pre number bag which was recorded on the log
sheets. No moisture record has been preserved.
RAB drilling was conducted under contract by
Connector Drilling, with material laid out on the
ground in one metre intervals and four metre
composite spear samples subsequently collected for
assaying. Bottom of hole samples were taken on a 2m
interval.
11 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation

For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.

Quality control procedures adopted for all
sub-sampling stages to maximise representivity of
samples.

Measures taken to ensure that the sampling is
representative of the in situ material collected,
including for instance results for field
duplicate/second-half sampling.

Quality of
assay data
and
laboratory
tests
Verification
of sampling
and
assaying

Whether sample sizes are appropriate to the
grain size of the material being sampled.
The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.
Diamond core sample intervals not less than 0.17
meters and not greater than 1 metre,
geological/mineral boundaries as main sample
interval boundaries.
RC holes were drilled using a 5.5in face sampling bit
and samples were collected through a cyclone and
riffle splitter both mounted on a sample trailer, at one
metre intervals. Sampling of individual metres was
done using a one eighth riffle box splitter (the smaller
split being collected in calico bags for assaying).
Although no QA/QC procedures were documented by
the previous operators, assay reports show random
repeat samples were submitted for approximately 1
in every 10 samples
In addition to the randomly inserted repeat samples
mentioned above, assay reports show 1 repeat
samples were assayed at the lab for anomalous
grades and two repeat samples were assayed for high
grades.
The sample sizes are considered to be appropriate for
the type, style thickness and consistency of
mineralisation. The sample size is also appropriate
for the sampling methodology employed and the
grades returned.
The assay method is designed to measure total gold
in the sample. The laboratory procedures are
appropriate for the testing of gold given the nature of
mineralisation style. No record was made of charge
size used in the assay
 For geophysical tools, spectrometers,
handheld XRF instruments, etc., the parameters
used in determining the analysis including
instrument make and model, reading times,
calibrations factors applied and their derivation,
etc.

Nature of quality control procedures adopted
(e.g. standards, blanks, duplicates, external
laboratory checks) and whether acceptable levels
of accuracy (i.e. lack of bias) and precision have
been established.
Not used for grade reporting or interpretation

No record of independent verification exists
The verification of significant intersections by
either independent or alternative company
personnel.
 The use of twinned holes.

Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.

Location of
data points
Comments
Discuss any adjustment to assay data.
 Accuracy and quality of surveys used to
locate drill holes (collar and down-hole surveys),
trenches, mine workings and other locations used
in Mineral Resource estimation.
The QC program was based around the insertion of
duplicate samples to test repeatability of reported
grades. Any subsequent exploration undertaken by
ORD will bring QA/QC standards up to modern
industry best practice not previously undertaken at
the time of drilling reported in this announcement.
No twinned holes exist within the prospect area.
Diamond drilling from underground, orientated
perpendicular to the true strike of the mineralisation
confirm the tenor of grade and intersections
observed from surface RC and diamond drilling.
Drilling predates the widespread use of field base
data loggers. Grades reported in this announcement
were cross referenced with original logs and assay
reports in annual exploration reports
No adjustments were made to assay data presented
in this report
The collars of all RC and diamond drill holes were
surveyed by the Marymia Gold Project Survey
Department.
12 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
Comments
Diamond drill holes were surveyed via down hole
cameras at intervals of 30 to 50m during drilling using
an Eastman Single Shot Camera. A number of holes
were also surveyed by Surtron after drilling had
finished using either a gyro or DEMS tool.


Data
spacing
and
distribution
Specification of the grid system used.
Quality and adequacy of topographic control.

Data spacing for reporting of Exploration
Results.
 Whether the data spacing and distribution is
sufficient to establish the degree of geological and
grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation
procedure(s) and classifications applied.

Orientation
of data in
relation to
geological
structure
Whether sample compositing has been
applied.
 Whether the orientation of sampling achieves
unbiased sampling of possible structures and the
extent to which this is known, considering the
deposit type.
 If the relationship between the drilling
orientation and the orientation of key mineralised
structures is considered to have introduced a
sampling bias, this should be assessed and
reported if material.
RC Holes were surveyed via a Single Shot Eastman
Camera at 30 to 50m. Deeper RC holes were surveyed
down the hole by Surtron on completion of drilling.
Holes were drilled on a local grid, the "Resitan Grid"
and have subsequently been converted to MGA94
z50
A surveyed Digital Terrain model was provided by
Dampier Gold (Project JV partner) to ORD which was
used to define the current working surface.
Drill spacing was on a nominal 15x10m grid for RC and
Diamond in the indicated portion of the resource to
40x40m spacing in the inferred material at depth.
The drill spacing and spatial distribution of assay
results is sufficient to support the estimation of a
mineral resource in accordance with the JORC (2012
Edition) Guidelines of material contained within this
report and appropriate for the nature and style of
mineralisation being reported
All samples included in resource calculations have
been composited to 1m intervals to mitigate the bias
in the resource estimation.
The majority of drilling is at azimuth 142⁰ which is
perpendicular to the strike of the ore body, confirmed
by diamond drilling. The orientation of the structure
slightly swings to the North-West to the north of the
K2 pit
No drilling or sampling bias has been noted
Sample
security

The measures taken to ensure sample
security.
No record has been kept relating to the security of the
samples taken by previous operators
Audits or
reviews

The results of any audits or reviews of
sampling techniques and data.
No record of audits or reviews by previous operators
has been located
13 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Section 2, Reporting of Exploration Results:
(Criteria listed in the preceding section also applies to this section)
Criteria
JORC Code explanation
Commentary
Mineral tenement and
land tenure status
·
Type, reference name/number,
location and ownership including
agreements or material issues with
third parties such as joint ventures,
partnerships, overriding royalties,
native title interests, historical sites,
wilderness or national park and
environmental settings.
The Plutonic dome project ("project") inclusive of
M52/183 where results are being reported is
subject to a Joint Venture/Farm In Agreement
with Dampier Resources Limited ("Dampier").
Under the terms of the agreement Ord River
Resources is required to sole fund at least the
initial $2 million in project within 9 months of the
Joint Venture commencement to earn a 30%
interest in the project.
Ord has announced on the 11th September
2014, the completion of the first phase and
earning 30% interest in the project. Ord has
elected to continue with sole funding an
additional $1 million to earn a cumulative 45%
interest in the project. A total of $6 million of
expenditure (inclusive of the $2 million
completed and $1 million committed) is required
to earn a 75% interest in the project.
·
The security of the tenure held
at the time of reporting along with any
known impediments to obtaining a
licence to operate in the area.
No heritage issues have been identified across
M52/183
M52/183 is a granted Mining Lease and is valid
until 03/12/2031. At this time the tenement is
believed to be in good standing. There are no
known impediments to obtaining a licence to
operate, other than those set out by statutory
requirements which have not yet been applied
for.
Exploration done by
other parties
·
Acknowledgment and appraisal
of exploration by other parties.
Exploration by previous operators includes
Dampier Gold Limited, Barrick and Resolute.
These previous parties have completed open pit
mining, geophysical data acquisition, soil
sampling and drilling across the K2 deposit. The
historical data within the database have been
appraised and is of acceptable quality.
Geology
·
Deposit type, geological setting
and style of mineralisation.
Drill hole Information
·
A summary of all information
material to the understanding of the
exploration results including a
tabulation of the following information
for all Material drill holes:
The K2 deposit is located close to the middle of
the Plutonic Well Greenstone Belt, which forms
part of the Marymia Inlier. The Marymia Inlier is
a granite-greenstone terrane situated between
the Yilgarn and Pilbara Cratons in Western
Australia. The Plutonic Well Greenstone Belt is
a north-easterly trending belt approximately
50km long and 10km wide. It consists of
predominantly mid to upper greenschist facies
metamorphosed ultramafic volcanics, tholeiitic
basalts, minor felsic volcanics and sediments.
The local Geology of K2 is composed of a series
of North-East, South-West trending mafics,
ultramafics and metasedimentary lithologies
metamorphosed to lower amphibolite facies.
Gold Mineralisation within the K2 pit showed a
strong association with lithological contacts and
high grade zones at the contact between a highFe and high-Mg amphibolite unit.
The drill holes reported in this announcement
have the following parameters applied. All drill
holes completed, including holes with no
significant gold intercepts are reported in this
announcement
14 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
Commentary
o easting and northing of the
drill hole collar
Eastings and Northings are Resitan (Local) grid.
These were converted to MG94z50 to verify
locations.
RL is AHD
o elevation or RL (Reduced
Level – elevation above sea level in
metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and
interception depth
o hole length.
Data aggregation
methods
Relationship between
mineralisation widths
and intercept lengths
Dip is the inclination of the hole from horizontal
(i.e. a hole drilled vertically down from the
surface is -90⁰). Azimuth is reported in degrees
as the direction towards which the hole is drilled.
The relevant surveying method is quoted in the
collar table of the announcement.
Down hole length of the hole is the distance from
the surface to the end of the hole, as measured
along the drill trace. Interception depth is the
distance down the hole as measured along the
drill trace. Intersection width is the downhole
distance of an intersection as measured along
the drill trace.
Hole length is the distance from the surface to
the end of the hole, as measured along the drill
trace.
·
If the exclusion of this
information is justified on the basis that
the information is not Material and this
exclusion does not detract from the
understanding of the report, the
Competent Person should clearly
explain why this is the case.
All results relating to the drill sections provided
have been stated including "No significant
intercepts". Inclusion of all historic data would
make the tables too large although data included
is representative of all drilling data.
·
In reporting Exploration Results,
weighting averaging techniques,
maximum and/or minimum grade
truncations (eg cutting of high grades)
and cut-off grades are usually Material
and should be stated.
Length weighted averages are used, uncut
grades are reported. Anomalous grades have
been top cut to 50g/t Au. Lower cut off is
nominally 0.5g/t Au with a minimum modelled
width of 2m downhole.
·
Where aggregate intercepts
incorporate short lengths of high grade
results and longer lengths of low grade
results, the procedure used for such
aggregation should be stated and
some typical examples of such
aggregations should be shown in
detail.
Sample lengths from RC/RAB drilling are all 1m
lengths. As diamond core is cut to geological
boundaries and incorporates shorter intervals,
length weighted averaging has been used to
make 1m downhole composites.
·
The assumptions used for any
reporting of metal equivalent values
should be clearly stated.
No Metal equivalents are reported.
·
These relationships are
particularly important in the reporting of
Exploration Results.
The intersection width is measured down the
hole trace and is not the true width. Cross
sections provided in the announcement allow
the relationship between true and down hole
width to be viewed.
15 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
Commentary
·
If the geometry of the
mineralisation with respect to the drill
hole angle is known, its nature should
be reported.
Observations of structures within the K2 open pit
confirm the drilling direction is optimal for the
mineralised zones at K2.
·
If it is not known and only the
down hole lengths are reported, there
should be a clear statement to this
effect (e.g. ‘down hole length, true
width not known’).
All drill results within this announcement are
downhole intervals only. True width is not known
and will be calculated from further diamond
drilling.
Diagrams
·
Appropriate maps and sections
(with scales) and tabulations of
intercepts should be included for any
significant discovery being reported
These should include, but not be
limited to a plan view of drill hole collar
locations and appropriate sectional
views.
A plan view and drill sections have been
provided in previous announcements.
Balanced reporting
·
Where comprehensive reporting
of all Exploration Results is not
practicable, representative reporting of
both low and high grades and/or
widths should be practiced to avoid
misleading reporting of Exploration
Results.
All results including those with no significant
intersections have been reported in previous
announcements.
Other substantive
exploration data
·
Other exploration data, if
meaningful and material, should be
reported including (but not limited to):
geological observations; geophysical
survey results; geochemical survey
results; bulk samples – size and
method of treatment; metallurgical test
results; bulk density, groundwater,
geotechnical and rock characteristics;
potential deleterious or contaminating
substances.
No other exploration data is considered
meaningful and material to this announcement.
Further work
·
The nature and scale of planned
further work (e.g. tests for lateral
extensions or depth extensions or
large-scale step-out drilling).
An upgrade of the definitive feasibility study is
currently underway to assist with an economic
assessment towards the development potential.
·
Diagrams clearly highlighting
the areas of possible extensions,
including the main geological
interpretations and future drilling areas,
provided this information is not
commercially sensitive.
Future drilling areas have not currently been
defined. Underground drilling will commence
after the dewatering has been completed.
16 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Section 3, Estimation and Reporting of Mineral Resources
(Criteria listed in Section 1, and where relevant Section 2 also apply to this section)
Criteria
JORC Code explanation
Commentary
Database
integrity
·
Measures taken to ensure that data has
not been corrupted by, for example,
transcription or keying errors, between its initial
collection and its use for Mineral Resource
estimation purposes.
·
Data validation procedures used.
Digital data has been imported and validated in
Micromine then cross referenced with original
exploration reports and cross sections.
Site visits
Geological
interpretation
·
Comment on any site visits undertaken
by the Competent Person and the outcome of
those visits.
·
If no site visits have been undertaken
indicate why this is the case.
The interpretation of the deposit was carried out
using a systematic approach and was of
consistent orientations and dimensions as
previous resource model used in the mining of,
and observable in, the K2 pit. Given the close
spacing of drill holes confidence in the
geological interpretation is considered high
·
Nature of the data used and of any
assumptions made.
The use of historical drilling provides a level of
uncertainty as the validation and QA/QC of
historic data is not always possible. Where
instruments susceptible to magnetism have
been used in downhole surveys azimuths have
been assigned to the survey data. Generally
this has only been applied to shallow holes
drilled from surface, with valid azimuth and dip
data available for the deeper holes used in the
resource calculation
·
The effect, if any, of alternative
interpretations on Mineral Resource estimation.
The previous resource model for K2 was
constrained around high grade zones and not
modelled to follow the controlling structure. This
has resulted in significant increase in total
tonnes and ounces
Inconsistencies in the logging of historic drill
holes made detailed geological interpretation
difficult. However the company believes this is
mitigated by the current model matching the
geological model generated in the mining of the
K2 open pit
Continuity of geology and structure are
consistent across drill hole sections and the
nugget effect is considered low given the style
of mineralisation
·
The factors affecting continuity both of
grade and geology.
Estimation
and modelling
techniques
Not applicable
·
Confidence in (or conversely, the
uncertainty of) the geological interpretation of
the mineral deposit.
·
The use of geology in guiding and
controlling Mineral Resource estimation.
Dimensions
Any errors recorded from the validation
processing in Micromine are manually checked
and correlated back to the original collection of
data. This data is then referenced against collar
maps and drill sections to confirm data
accuracy
Multiple site visits have been made by the
Competent Person
·
The extent and variability of the Mineral
Resource expressed as length (along strike or
otherwise), plan width, and depth below surface
to the upper and lower limits of the Mineral
Resource.
·
The nature and appropriateness of the
estimation technique(s) applied and key
assumptions, including treatment of extreme
grade values, domaining, interpolation
parameters and maximum distance of
extrapolation from data points. If a computer
assisted estimation method was chosen include
a description of computer software and
parameters used.
Strike of Main Lode = 455m, Width= 1.25-16m,
Depth= 100-220m. 11 distinct lodes have been
modelled in the K2 Resource
All Block model grades around the K2 pit were
estimated by Ordinary Kriging (OK) in
Micromine with Inverse Distance Weighting
method used to calculate smaller lodes at K3
and K2SE. The deposit was domained into 11
individual lodes with each lode estimated using
only the assays within that lode and snapped to
composited 1m downhole intervals.
17 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
Commentary
·
The availability of check estimates,
previous estimates and/or mine production
records and whether the Mineral Resource
estimate takes appropriate account of such
data.
The previous resource model for K2 prior to
Ord’s involvement was constrained around
high grade zones and not modelled to follow the
structure controlling mineralisation.
·
The assumptions made regarding
recovery of by-products.
·
Estimation of deleterious elements or
other non-grade variables of economic
significance (eg sulphur for acid mine drainage
characterisation).
·
In the case of block model interpolation,
the block size in relation to the average sample
spacing and the search employed.
·
Any assumptions behind modelling of
selective mining units.
·
Any assumptions about correlation
between variables.
·
Description of how the geological
interpretation was used to control the resource
estimates.
·
Discussion of basis for using or not using
grade cutting or capping.
The recent update completed by Ord
incorporates higher SG values through the
process of systematic sampling and laboratory
analysis.
No consideration has been made to byproducts
No consideration has been made to deleterious
elements or other non-grade variables of
economic significance
Block size was 5m x 5m x 2.5m (x,y,z), with a
subblock factor of 2 in each direction
Small block sizes were selected to reflect the
most probable selective mining method, which
at K2 is underground mining.
No assumptions made
Blocks were constrained within wireframes at
the boundary of mineralisation
Composite grade were top cut to 50 g/t Au to
avoid the smearing of high grade assays
through the resource
·
The process of validation, the checking
process used, the comparison of model data to
drill hole data, and use of reconciliation data if
available.
Block model grades were visually checked
against downhole assay grades. Reconciliation
data was not available for the open pit
Moisture
·
Whether the tonnages are estimated on
a dry basis or with natural moisture, and the
method of determination of the moisture
content.
Tonnages are quoted as dry tonnes
Cut-off
parameters
·
The basis of the adopted cut-off grade(s)
or quality parameters applied.
Cut off grades were chosen based on
geological continuity and possible economic
cut offs. These lower cut offs are comparable
with other deposits of a similar mineralisation
style in this geography
Mining factors
or
assumptions
·
Assumptions made regarding possible
mining methods, minimum mining dimensions
and internal (or, if applicable, external) mining
dilution. It is always necessary as part of the
process of determining reasonable prospects
for eventual economic extraction to consider
potential mining methods, but the assumptions
made regarding mining methods and
parameters when estimating Mineral Resources
may not always be rigorous. Where this is the
case, this should be reported with an
explanation of the basis of the mining
assumptions made.
·
The basis for assumptions or predictions
regarding metallurgical amenability. It is always
necessary as part of the process of determining
reasonable prospects for eventual economic
extraction to consider potential metallurgical
methods, but the assumptions regarding
metallurgical treatment processes and
parameters made when reporting Mineral
Resources may not always be rigorous. Where
this is the case, this should be reported with an
explanation of the basis of the metallurgical
assumptions made.
Mineralisation at K2SE and K3 was modelled at
a nominal 0.5 g/t Au cut off to reflect an open
cut mining scenario. In the case of K2 a 3g/t Au
cut off grade was applied to reflect the likely
underground mining scenario.
Metallurgical
factors or
assumptions
Nine composite samples were selected for
metallurgical test work from the K2 deposit by
Barrick Australia in 2005. Samples were
selected from oxide, transitional and primary
material. Recoveries all exceeded 90%. There
is no apparent link between recovery rate and
sample grade. The gold recoveries comparison
for each oxidation state are listed below:
-
Oxide: Average Recovery 94.9%
Transitional: Average Recovery
92.7%
Primary: Average Recovery 93.5%
18 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
Commentary
Environmental
factors or
assumptions
·
Assumptions made regarding possible
waste and process residue disposal options. It
is always necessary as part of the process of
determining reasonable prospects for eventual
economic extraction to consider the potential
environmental impacts of the mining and
processing operation. While at this stage the
determination of potential environmental
impacts, particularly for a greenfields project,
may not always be well advanced, the status of
early consideration of these potential
environmental impacts should be reported.
Where these aspects have not been considered
this should be reported with an explanation of
the environmental assumptions made.
Underground Mining of the K2 resource will
require dewatering of the open pit and existing
underground workings. A mining proposal and
relevant works approvals have been granted for
dewatering K2 into the historical K1 Open Pit.
Bulk density
·
Whether assumed or determined. If
assumed, the basis for the assumptions. If
determined, the method used, whether wet or
dry, the frequency of the measurements, the
nature, size and representativeness of the
samples.
Specific Gravity values of 1.98 were assigned
to ore blocks above the base of complete
weathering, 2.54 to transitional material and
2.97 below the top of fresh surface. These
results were through the analysis of historical
diamond core by SGS laboratory with relevant
industry best practices adhered to.
·
The bulk density for bulk material must
have been measured by methods that
adequately account for void spaces (vugs,
porosity, etc), moisture and differences between
rock and alteration zones within the deposit.
The bulk densities assigned take into account
void space and vug spaces with differing rock
and weathering types
·
Discuss assumptions for bulk density
estimates used in the evaluation process of the
different materials.
As mentioned above these values were lower
than measurements reported by a previous
operator, whose values seemed too high given
the lithology and grade of the mineralised
material
·
The basis for the classification of the
Mineral Resources into varying confidence
categories.
Classification is based on drill spacing, Kriging
efficiencies and grade variance to determine
inferred and indicated resource categories and
also determine where grade estimations do not
satisfy JORC classification.
·
Whether appropriate account has been
taken of all relevant factors (ie relative
confidence in tonnage/grade estimations,
reliability of input data, confidence in continuity
of geology and metal values, quality, quantity
and distribution of the data).
All relevant factors have been accounted for
including relative confidence in tonnage/grade
estimations, reliability of input data, confidence
in continuity of geology and metal values,
quality, quantity and distribution of the data)
·
Whether the result appropriately reflects
the Competent Person’s view of the deposit.
The result appropriately reflects the competent
person's view of the deposit
Audits or
reviews
·
The results of any audits or reviews of
Mineral Resource estimates.
Discussion of
relative
accuracy/
confidence
·
Where appropriate a statement of the
relative accuracy and confidence level in the
Mineral Resource estimate using an approach
or procedure deemed appropriate by the
Competent Person. For example, the
application of statistical or geostatistical
procedures to quantify the relative accuracy of
the resource within stated confidence limits, or,
if such an approach is not deemed appropriate,
a qualitative discussion of the factors that could
affect the relative accuracy and confidence of
the estimate.
This resource has not been externally audited
or reviewed. An internal peer review has been
conducted
The mineral estimate quoted is considered fair
and robust. The justifications for classification
are documented above.
Classification
19 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
Commentary
·
The statement should specify whether it
relates to global or local estimates, and, if local,
state the relevant tonnages, which should be
relevant to technical and economic evaluation.
Documentation should include assumptions
made and the procedures used.
This resource report relates to the K2 area of
the Plutonic Dome project. Further information
towards the most recent economic analysis of
the project is available in the announcement
“K2 Definitive Feasibility Study Completion” on
the 1st of July 2014.
·
These statements of relative accuracy
and confidence of the estimate should be
compared with production data, where
available.
No previous production data was available for
comparison with the resources generated
although the orientation of the resource is
consistent with previous models and
observable structures in walls of the K2 open
pit
20 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Section 4, Estimation and Reporting of Ore Reserves
Criteria
Mineral resource
Estimate for
conversion to Ore
Reserves
Site visits
Study Status
Cut-off Parameters
Mining Factors or
Assumptions
JORC Code explanation
Commentary

Description of the Mineral
Resource estimate used as a basis
for the conversion to an Ore
Reserve.

Clear statement as to whether
the Mineral Resources are reported
additional to, or inclusive of, the Ore
Reserves.

Comment on any site visits
undertaken by the
Competent Person (s) and the
outcome of those
visits.
 The type and level of study
undertaken to
enable Mineral Resources to be
converted to
Ore Reserves
 The basis of the cut-off
grade(s) or quality
parameters applied

The method and assumptions
used as reported in the PreFeasibility or Feasibility Study to
convert the Mineral Resource to an
Ore Reserve (i.e. either by
application of appropriate factors by
optimisation or by preliminary or
detailed design).
The Ore Reserve estimate is based on the Mineral
Resource estimate carried by Geonomics Australia Pty
Ltd.
The Mineral Resources are reported inclusive of Ore
Reserves.
A site visit has been conducted by the Competent Person.
The visit included inspection of potential surface
infrastructure positions as well as pre-existing decline
development and road system.
Feasibility level studies have been completed for all areas
of the K2 Underground Project. Ore Reserve estimates
are based around the assumptions completed for the K2
Project Feasibility Study.
Cut-off grades were determined based on unit costs from
the “Feasibility Level” mining cost model
The Ore Reserve estimate has been calculated by
generating detailed mining shapes for each stoping block
as well as development. Designed stope shapes include
planned dilution, being waste material that is located
within the minable stope shape. Additional unplanned
dilution is also generally incurred from the walls of stopes
due to re-distribution of stress within the rock mass as
voids are created in the mine, blast damage, poor mining
practice (such as poor blasthole drilling setup) this
additional material is also included in Ore Reserve
Estimate.

The choice, nature and
appropriateness of the selected
mining method(s) and other mining
parameters including associated
design issues such as pre-strip,
access, etc.
The selected mining methods for the K2 project is long
hole open stoping which is widely used in many
underground mines in Western Australia and is deemed
appropriate considering the nature of the ore body.

The assumptions made
regarding geotechnical parameters
(e.g. pit slopes, stope sizes, etc.),
grade control and pre-production
drilling.
In consultation with geotechnical consultants Ground
Control Engineering (GCE) geotechnical parameters have
been set out for the size of the stoping blocks as well as
support standards and development stand-off distances.
All mining shapes included in the Ore Reserve estimate
abide by the recommendations supplied by GCE.

The major assumptions made
and Mineral Resource model used
for pit and stope optimisation (if
appropriate).

The mining dilution factors used.

The mining recovery factors
used.
Stope sizes are generally 2 mW x 16 mH x 37 mL and have
been created to suit the Mineral Resource. Geotechnical
assessment of the mineralised zone is also favourable for
the selected mining method.
A 10 % unplanned dilution factor has been calculated by
Entech. Entech considers this to be appropriate given the
ground conditions and proposed style of mining
A mining recovery factor of 95% has been applied post
geological interrogation to generate the final diluted and
recovered Ore Reserve estimate. This mining recovery is
applied to allow for any ore loss due to mining related
issues such as; underbreak due to poor drilling and
blasting techniques, stope bridging or freezing or
material being left in stopes due inaccessibility.
Minimum
mining
width
for
stoping
is
1.5m.
21 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
Commentary

Any minimum mining widths
used.
No Inferred Mineral Resources have been included in the
Ore Reserve Estimate. Any Inferred Mineral Resource
contained within a mining block (stope or development)
is classified as waste and is used to dilute the overall Ore
Reserve.
Infrastructure required for the proposed K2 Project has
been accounted for and included in all work leading to
the generation of the Ore Reserve estimate. The K2
Project infrastructure includes:
o All site surface infrastructure, including:
o Offices, workshops, warehouses and associated
facilities
o Power Station
o Refuelling Facility
o All power and pumping reticulation will be fed
through decline development, ventilation rises and
service holes drilled in close proximity to the decline to
minimise cable and pipe runs along the decline path.
o Ventilation fans will be installed underground in an
access to the pre-mined K2 pit to supply fresh air to
underground workings.
o Escapeway ladderways will be installed in separate
air legged rises providing secondary means of egress
from the UG mine.

The manner in which Inferred
Mineral
Resources are utilised in mining
studies and the sensitivity of the
outcome to their inclusion.

The infrastructure requirements
of the selected mining methods
Metallurgical
Factors or
Assumptions
 The metallurgical process
proposed and the appropriateness
of that process to the style of
mineralisation.
Infrastructure required for the generation of the Ore
Reserve that is provided by NST at Plutonic Mine Site or
already in place include:
o Camp
o Airstrip
o Access Road
o Boxcut; and
o 800 m of decline development
ORD has an agreement with Northern Star Resources to
treat ore from K2 through Northern Star’s existing
Plutonic Gold Mine Processing Plant
 Whether the metallurgical
process is well tested technology or
novel in nature.
The Plutonic Processing Plant operates off CIL methods,
which is considered to be standard industry processing
methods.

The nature, amount and
representativeness of metallurgical
test work undertaken, the nature of
the metallurgical domaining applied
and the corresponding metallurgical
recovery factors applied.
Extreme Metallurgy Pty Ltd has conducted reviews of the
supplied metallurgical test work for the K2 orebody.
Extreme have provided information on the feasibility of
treatment and expected metal recovery.
 Any assumptions or allowances
made for
deleterious elements.
Metallurgical recovery factors are as follows:
O Fresh – 90%
 The existence of any bulk
sample or pilot scale test work and
the degree to which such samples
are considered representative of
the
orebody as a whole.
Bulk sampling and pilot scale testing have not been
conducted as part of this study and are not deemed
necessary. The existing Plutonic processing facility is
currently in operation treating similar ore, and K2 ore has
been mined and processed successfully in the past.
 For minerals that are defined by
a specification, has the ore reserve
estimation been based on the
appropriate mineralogy to meet the
specifications.
Minerals are not defined by a specification
22 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
Environmental
Infrastructure
Costs
JORC Code explanation
Commentary
 The status of studies of potential
environmental impacts of the mining
and processing operation. Details of
waste rock
characterisation
and
the
consideration of potential sites,
status of design options considered
and, where applicable, the status of
approvals for process residue
storage and
waste dumps should be reported.

The existence of appropriate
infrastructure: availability of land for
plant development, power, water,
transportation (particularly for bulk
commodities), labour,
accommodation; or the ease with
which the infrastructure can be
provided, or accessed.

The derivation of, or
assumptions made,
regarding projected capital costs in
the study.
Environmental impacts and hazards are being considered
as part of the DMP application process. Waste rock
characterisation and hydrogeological investigations
indicates the rock mass is considered non-acid forming.
Tailings from the K2 ore processing will be stored within
the Tailings Storage Facility (TSF) at Plutonic.
It is expected that permitting for the project will not be
unreasonably withheld.

The methodology used to
estimate operating costs.
 Allowances made for the content
of deleterious elements.

The derivation of assumptions
made of metal or commodity
price(s), for the principal
minerals and co- products.

The source of exchange rates
used in the study.

Derivation of transportation
charges.

The basis for forecasting or
source of treatment and refining
charges, penalties for failure to meet
specification, etc.

The allowances made for
royalties payable, both Government
and private.
Revenue factors
Market Assessment
 The derivation of, or
assumptions made
regarding revenue factors including
head
grade, metal or commodity price(s)
exchange
rates, transportation and treatment
charges,
penalties, net smelter returns, etc.

The derivation of assumptions
made of metal or commodity price(s),
for the principal metals, minerals and
co-products.

The demand, supply and stock
situation
for
the
particular
commodity, consumption trends and
All infrastructure required for the processing and mining
of the Ore Reserve is existing and will be operational
before the commencement of underground operations.
Capital costs have been sourced from supplier and
contractor quotes through the “feasibility study” process.
Operating costs have been based on supplier and
contractor
estimates,
equipment
manufacturer
information and labour rates.
No contingency has been provided for within these
estimates
Gold price assumptions have been calculated by taking
discounts to 4 year trailing average gold price
Based on recent average trading range between USD and
AUD.
Transport costs have been sourced from contractor
quotes through the “feasibility study” process
Processing costs have been sourced as per the Binding
Ore Treatment Agreement with Northern Star Resources
Limited.
Government Taxes and Royalties and IRC Royalties have
been provided for
.
Mine optimisation and designs used a gold price of US
$1,220 / oz and AU:US exchange rate of 1:0.87.
Final revenue modelling of the project also used a gold
price of US $1,220 / oz and AU:US exchange rate of 1:0.87
Gold price assumptions have been calculated by taking
discounts to 4 year trailing average gold prices.
Gold doré from the mine is to be sold at the Perth Mint.
23 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
JORC Code explanation
factors likely to affect supply and
demand into the future.
Economic
Social
Other
Classification

A customer and competitor
analysis along with the identification
of likely market windows for the
product.


 Price and volume forecasts and
the basis for these forecasts.




For industrial minerals the
customer
specification,
testing
and
acceptance

The inputs to the economic
analysis to produce the net present
value (NPV) in the study, the source
and confidence of these economic
inputs including estimated inflation,
discount rate, etc.
Commentary
Many local and international operations are operating at
C3 cash costs above current prices or hedges. Supply
likely curtailed if current pricing and revenues structures
maintained. Active international Reserve Bank, hedge
fund and gold fund physical transfers.
Gold price assumptions have been calculated by taking
discounts to 4 year trailing average gold prices. Gold doré
from the mine is to be sold at the Perth Mint.
No industrial minerals.
The Ore Reserve estimate is based on a financial model
for that has been prepared at a “feasibility study” level of
accuracy economic modelling.
All inputs from
underground operations, processing, transportation and
sustaining capital as well as contingencies have been
scheduled and evaluated to generate a full life of mine
cost model. Economic inputs have been sourced from
suppliers or generated from database information
relating to the relevant area of discipline. A discount rate
of 8% has been applied. The NPV of the project is positive
at the assumed commodity price.

NPV ranges and sensitivity to
variations
in
the
significant
assumptions and inputs.

The status of agreements with
key stakeholders and matters
leading to social licence to operate
To the extent relevant, the impact of
the
following on the project and/or on
the estimation and classification of
the Ore Reserves:

Any identified material naturally
occurring
risks.
The Ore Reserve is sensitive to fluctuation in gold price. A
reduction in price renders the Project cost negative

The status of material legal
agreements
and
marketing
arrangements.
Ord River Resources is required to spend a minimum of
$6million over a 2 year period to earn 75% interest in the
Plutonic Dome Gold Project. Currently Ord River
Resources holds a 30% equity interest in the Project.

The status of governmental
agreements and approvals critical to
the viability of the project, such as
mineral tenement status, and
government
and
statutory
approvals.
The basis for the classification of the
Ore
Reserves into varying confidence
categories.
 Whether the result appropriately
reflects
the Competent Person’s view of the
deposit.
To the best of the Competent Persons knowledge all
agreements are in place and are current with all key
stakeholders including traditional owner claimants. A
mining proposal for the commencement of mining
activities at K2 is to be submitted imminently.
To the best of the Competent Persons knowledge all
agreements are in place and are current with all key
stakeholders including traditional owner claimants.
The site is distant from the Western Australian Coastline,
which is prone to cyclone activity during summer. Locally
heavy rainfall occurs during this period.
The Competent Person believes the classification of the
Underground Mineral Resource and hence the
conversion to Ore Reserve is appropriate.
No Measured material has been converted to a Proven
Ore Reserve. Indicated material has been converted to a
24 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD
Criteria
Audits or reviews
Discussion of
relative
accuracy/confidence
JORC Code explanation
Commentary

The proportion of Probable Ore
Reserves that have been derived
from Measured Mineral Resources
(if any).
Probable Ore Reserve. The Ore Reserve is based on
Probable material; no Proven Ore Reserves are reported.
 The results of any audits or
reviews of Ore Reserve estimates.
Where appropriate a statement of
the relative accuracy and confidence
level in the Ore
Reserve
estimate
using
an
approach or
procedure deemed appropriate by
the
Competent Person. A qualitative
discussion of the factors which could
affect the relative
accuracy and confidence of the
estimate.

The statement should specify
whether it relates to global or local
estimates, and, if local, state the
relevant tonnages, which should be
relevant to technical and economic
evaluation. Documentation should
include assumptions made and the
procedures used.
The Ore Reserve has been peer reviewed internally and is
in line with current industry standards.

Accuracy and confidence
discussions should extend to
specific discussions of any applied
Modifying Factors that may have a
material impact on Ore Reserve
viability, or for which there are
remaining areas of uncertainty at the
current study stage.
The design, schedule and financial model on which the
Ore Reserve is based has been completed to a “feasibility
study” standard, with a corresponding level of
confidence.
All modifying factors have been applied to design mining
shapes on a global scale. Results and estimates should be
viewed on basis of +/- 15%, based on Competent Person
study assessment, audit and review.
25 | P a g e
Ord River Resources Limited- www.ord.com.au – ASX:ORD