M.P. AUDYOGIK KENDRA VIKAS NIGAM (INDORE) LTD., INDORE DOCUMENT FOR PERCENTAGE RATE TENDER FOR Supply, installation, testing and commissioning of 33/11 KV External electrification work for new industrial area at Relwa khurd district Barwani Estimated Cost Rs. 3,73,60,000/- Earnest Money Rs.3,73,600 /- Managing Director Madhya Pradesh Audyogik Kendra Vikas Nigam (I) Ltd., Indore October - 2014 1 Tender Document Office of the : MPAKVN (I) Ltd., Indore NIT number and Date : 13072 dated 31.10.2014 Agreement number and Date : __________________________________________ Name of work : Name of the Contractor : Supply, installation, testing and commissioning of 33/11 KV External electrification work for new industrial area at Relwa khurd district Barwani ________________________________ __________ Probable Amount of contractor (Rs. In figure) (Rs. In words) : Rs. 3,73,60,000/: Rs. Three crore seventy three lakh sixty thousand only. Contract Amount (Rs. In figure) :_______________________________________________ (Rs. In words) :_______________________________________________ Stipulated period of completion : 11(Eleven) months including rainy season 2 Appendix 2.10 Tender Document Table of Contents Section No Section 1 Section 2 Section 3 Particulars Page No. NIT 4-6 Instructions to Bidder (ITB) 7-16 Bid Data Sheet 17-19 Annexure A to M 20-195 Table of Clauses 196-197 Part-I General Condition of Contract (GCC) 198-214 Contract Data 215-219 Annexure N to W 220-245 Part-II Special Condition of Contract (GCC) Section 4 Bill of Quantities (BOQ) Section 5 Agreement Form 246-248 249-277 277 3 SECTION 1 Notice Inviting E-tender M.P. AUDYOGIK KENDRA VIKAS NIGAM(INDORE) LTD., INDORE N.I.T. No. 13072 Dated: 31.10.2014 Online percentage rate bids for the following works are invited from registered contractor and firms of repute fulfilling registration criteria: Sr 1 Work District’s Probable Amount (Rs. In Lakh) Completion period (months) Supply, installation, testing and commissioning of 33/11 KV External electrification work for new industrial area at Relwa Khurd district Barwani Barwani (MP) 373.60 lakhs 11 (Eleven) Months (including rainy season) 1. Interested bidders can view the NIT on website http://www.mpeproc.gov.in 2. The Bid Document can be purchased only online from 10:30 on 03/11/2014 to 17:30 on 20/11/2014. 3. Amendments to NIT, if any, would be published on website only, and not in newspaper. Managing Director MPAKVN(I) Ltd., Indore 4 Notice Inviting Tender M.P. AUDYOGIK KENDRA VIKAS NIGAM (INDORE) LTD., INDORE N.I.T. No. 13072 31.10.2014 Dated: Online percentage rate bids for the following works are invited from registered contractor and firms of repute fulfilling registration criteria: Sr. No 1 Name of work District (S) Supply, Barwani( installation, MP) testing and commissioning of 33/11 KV External electrification work for new industrial area at Relwa Khurd district Barwani Probable Amount of contract (Rs. In lakh) Earnest money deposit (EMD) (in Rs.) Cost of Bid docume nt (in Rs.) 373.60 lakhs 373600/- 15000/ The Contractors (registered in appropriate class in PHED, PWD, WRD, CPWD, Railways, MES or any other state government/ central government undertaking/ organizations) who have got adequate financial resources, state of the art technology, suitable construction equipments, 5 Category of contractor Period of completion (in months) 11 Months (including rainy season) technical manpower and sufficient past experience satisfying the technical and financial criteria are eligible to apply. 1. All details relating to the bid document Can be viewed and downloaded free of cost on the website. 2. Bid Document can be purchased after making online payment of portal fees through Credit/Debit/Cash Card internet banking. 3. At the time of submission of the bid the eligible shall be required to: i) Pay the cost of bid document ii) Deposit the Earnest Money iii) Submit a check list and iv) Submit an affidavit Details can be seen in the Bid data sheet. 4. Eligibility For Bidders: (a) At the time of submission of the bid the bidder should have valid registration with the Government of Madhya Pradesh, PWD /in appropriate class/ PHED, PWD, WRD, CPWD, Railways, MES or any other state government / central government undertaking / organizations, who have got adequate financial resources, state of the art technology, suitable construction equipments, technical manpower and sufficient past experience satisfying the technical and financial criteria are eligible to apply. However, such bidders who are not registered with the Government of Madhya Pradesh and are eligible registration can also submit their bids after having applied for registration of with appropriate authority. (b) The bidder would be required to have valid registration at the time of signing of the contract. 6 (c) Failure to sign the contract by the selected bidder, for whatsoever reason, shall result in forfeiture of the earnest money deposit. 5. Pre-Qualification – Prequalification conditions, wherever applicable, are given in the Bid data sheet 6. Special Eligibility – Special Eligibility conditions, if any, are given in the bid data sheet. 7. The Bid Document can be purchased only online from 10:30 on 03/11/2014 to 17:30 on 20/11/2014. 8. Amendments to NIT, if any would be published on website only, and not in newspaper. Managing Director MPAKVN(I) Ltd., Indore SECTION 2 INSTRUCTIONS TO BIDDERS (ITB) 1. Scope of Bid Supply, installation, testing and commissioning of 33/11 KV External electrification work for new industrial area at Relwa Khurd district Barwani 2. General Quality of Work: The work shall have to be executed in accordance with the technical specifications specified in the bid data sheet/ contract data, and shall have to meet high standards of workmanship, safety and security of workman and works. 3. Procedure for Participation in E-Tendering The Procedure for Participation in E-Tendering is given in the bid data sheet. 4. One Bid Per Bidder 7 4.1 The bidder can be individual entity or a joint venture (if permitted as per bid data sheet). In case the J.V. is permitted, the requirement of joint venture shall be as per the bid data sheet. 4.2 No bidder shall be entitled to submit more than one bid whether jointly or severally. If he does so, all bids wherein the bidder has participated shall stand disqualified. 5. Cost of bidding The bidder shall bear all costs associated with the preparation and submission of his bid, and no claim whatsoever for the same shall lie on the government. 6. Site visit and examination of works The bidder is advised to visit and inspect the site of works and its surrounding and obtain for itself on its own responsibility all information that may be necessary for preparing the bid and entering into a contract for construction of the work. All costs in this respect shall have to be borne by the bidder. A. Bid Document 7. Content of bid documents The bid document comprises of the following document: 1. NIT with all amendments 2. Instructions to Bidders, Bid data Sheet with all annexure 3. Conditions of contract: i) Part I General Conditions of Contract and the contract data with all annexure; and ii) Part II Special Conditions of Contract. 4. Specifications 5. Drawings 6. Priced Bill of Quantities 7. Technical and Financial bid 8. Letter of Acceptance 9. Agreement, and 10. Any other documents, as specified 8. The bidder is expected to examine carefully all instruction, conditions of contract , the contract data, forms, terms and specifications, bill of quantities, forms and drawing in the Bid Document. Bidder shall be solely responsible for his failure to do so. 9. Pre-Bid Meeting (Where applicable) Wherever the bid data sheet provides for pre-bid meeting: 8 9.1 Details of venue, date and time would be mentioned in the Bid Data Sheet. Any change in the schedule of pre-bid meeting would be communicated on the website only, and intimation to bidders would not be given separately. 9.2 Any prospective bidder may raise his queries and/or seek clarifications in writing before or during the pre-bid meeting. The purpose of such meeting is to clarify issues and answer questions on any matter that may be raised at that stage. The Employer may, at his option, give such clarifications as are felt necessary. 9.3 Minutes of the Pre-bid meeting including the gist of the questions raised and the responses given together with any response prepared after the meeting will be hosted on the website. 9.4 Pursuant to the pre-bid meeting of the Employer deems it necessary to amend the Bid Document; it shall be done by issuing amendment to the online NIT. 10. Amendment of Bid Document 10.1 Before the deadline for submission of bids, the Employer may amend or modify the 10.2 Bid document by publication of the same on the website. 10.3 All amendments shall form part of the Bid document. 10.4 The Employer may, at its discretion, extend the last date for submission of bids by publication of the same on the website. B. Preparation of Bid 11. The bidders have to prepare their bids online, encrypt their Bid Data in the Bid Forms and submit Bid Seals (Hashes) of all the envelopes and documents related to the Bid required to be uploaded as per the time schedule mentioned in the key dates of the Notice Inviting e-Tenders after signing of the same by the Digital Signature of their authorized representative. 12. Documents Comprising the Bid The bid submitted online by the bidder shall be in the following parts: Part-1 This shall be known as online Envelope A and would apply for all bids. Online Envelope A shall contain the following as per details given in the Bid Data Sheet: i) Registration number or proof of application for registration and organizational details in format given in the Bid Data Sheet. ii) Payment of the cost of Bid Document: iii) Earnest Money; and iv) An affidavit duly notarized. Part 2- This shall be known as online Envelope B and required to be submitted only in works where pre-qualification conditions and/or special eligibility conditions are stipulated in the Bid Data Sheet. Online Envelope B shall contain a self- certified 9 sheet duly supported by documents to demonstrate fulfilment of pre-qualification conditions. Part 3 This shall be known as online Envelope C and would apply to all bids. Envelope C shall contain financial offer in the prescribed format enclosed with the Bid Data Sheet. 13. Language The bid as well as all correspondence and documents relating to the bid exchanged by the Bidder and the Employer shall be in English or Hindi. Supporting documents and printed literature that are part of Bid may be in another language provided they are accompanied by an accurate translation of the relevant passages in English. In such case, for the purposes of interpretation of the bid, such translation shall govern. 14. Technical Proposal 14.1 14.2 Only, in case of bids with pre-qualification conditions defined in the Bid Data Sheet, The Technical Proposal shall comprise of formats and requirements given in the Bid Data Sheet. All the documents / information enclosed with the Technical Proposal should be Self-attested and certified by the bidder. The Bidder shall be liable for forfeiture of his earnest money deposit, if any document/ information are found false/ fake untrue before acceptance of bid. If it is found after acceptance of the bid, the bid sanctioning authority may at his discretion forfeit his performance security/ guarantee, security deposit, enlistment deposit and take any other suitable action. 15. Financial Bid i. The bidder shall have to quote rates in format referred in Bid Data Sheet, in overall percentage, and not item wise. If the bid is in absolute amount overall percentage would be arrived at in relation to the probable amount of contract given in NIT. The overall percentage rate would apply for all items of work. ii. Percentage shall be quoted in figures as well as in works. If any difference in figures and words is found, lower of the two shall be taken as valid and correct. iii. The bidder shall have to quote rates inclusive of all duties, taxes, royalties and other levies; and the Employer shall not be liable for the same. iv. The material along with the units and rates, which shall be issued, if any, by the department to the contractor, is mentioned in the Bid Data Sheet. 16. Period of Validity of Bids The bids shall remain valid for a period specified in the Bid Data Sheet after the data of “close for biding” as prescribed by the Employer. The validity of the bid can be extended by mutual consent in writing. 17. Earnest Money Deposit (EMD) 10 17.1 17.2 17.3 17.4 17.5 17.6 The Bidder shall furnish, as part of the Bid, Earnest Money Deposit (EMD), in the amount specified in the Bid Data Sheet. The EMD shall be in the form of Fixed Deposit Receipt of a scheduled commercial bank, issued in favor of the name given In the Bid Data Sheet. The Fixed Deposit Receipt shall be valid for six months or more after the last data of receipt of bids. However, other form(s) of EMD may be allowed by the Employer by mentioning it in the Bid Data Sheet. Bid not accompanied by EMD shall be liable for rejection as non-responsive. EMD of bidder whose bids are not accepted will be returned within ten working days of the decision on the bid. EMD of the successful bidder will be discharge when the bidder has signed the agreement after furnishing the required performance security. Failure to sign the contract by the selected bidder, within the specified period, for whatsoever reason, shall result in forfeiture of the earnest money deposit. C. Submission of Bid 18. The Bidder is required to submit online bid duly signed digitally, and Envelop “A” in physical form also at the place prescribed in the Bid Data Sheet. D. Opening and Evaluation of Bid 19. Procedure 19.1 Envelope ‘A’ shall be opened first online at the time and data notified and its contents shall be checked. In cases where Envelop ‘A’ does not contain all requisite document, such bid shall be treated as non- responsive, and Envelop B and /or C of such bid shall not be opened. 19.2 Wherever Envelop ‘B’ (Technical Bid) is required to be submitted, the same shall be opened online at the time and date notified. The bidder shall have freedom to witness opening of the Envelop ’B’. Envelop ‘C’ (Financial Bid) of bidder who are not qualified in Technical Bid (Envelop ‘B’) shall not be opened. 19.3 Envelope ‘C’ (financial Bid) shall be opened online at the time and date notified. The bidder shall have freedom to witness opening of the Envelop ‘C’. 19.4 After opening Envelop ‘C’ all responsive bids shall be compared to determine the lowest evaluated bid. 11 19.5 The Employer reserves the right to accept or reject any bid, and to annul the bidding process and reject all the bids at any time prior to contract award, without incurring any liability. In all such cases reasons shall be recorded. 19.6 The Employer reserves the right of accepting the bid for the whole work or for a distinct part of it. 19.7 Verification of documents submitted by bidders may be done by employer whereas required. 20. Confidentiality E. Information relating to examination, evaluation, comparison and recommendation of contract award shall not be disclosed to bidder or any other person not officially concerned with such process until final decision on the bid. 20.2 Any attempt by a bidder to influence the Employer in the evaluation of the bids or contract award decisions may result in the rejection of his bid. Award of Contract 21. Award of Contract 20.1 The Employer shall notify the successful bidder by issuing a ‘Letter of Acceptance’ (LOA) that his bid has been accepted. 22. Performance Security 22.1 Prior to signing of the contract the bidder to whom LOA has been issued shall have to furnish performance security of the amount in the form and for the duration, etc. as specified in the Bid Data Sheet. Additional performance security, if applicable, is mentioned in the bid data sheet and shall be in the form and for the duration, etc. similar to Performance Security. 22.2 23. 23.1 Signing of contract Agreement 23.2 The signing of contract agreement shall be reckoned as intimation tocommencement of work. No separate work order shall be issued by the employer to the contractor for commencement of work. 23.3 In the event of failure of the successful bidder to submit Performance Security and Additional Performance Security, if any or sign the Contract Agreement, his EMD shall stand forfeited without prejudice to the right of the employer for taking any other action against the bidder. 24. Corrupt Practices The successful bidder shall have to furnish Performance Security and Additional Performance Security, if any, and sign the contract agreement within 15 days of issue of LOA. The Employer requires that bidders observe the highest standard of ethics during the procurement and execution of contracts. In pursuance of this policy, the Employer : 12 i. May reject the bid for award if it determines that the bidder recommended for award has, directly or through an agent, engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract; and ii. May debar the bidder declaring ineligible, either indefinitely or for a stated period of time, to participate in bid, if it at any time determines that the bidder has, directly or through an agent, engaged in corrupt, fraudulent, collusive, or coercive practices in competing for, or in executing, a contract. For the purposes of this provision, the terms set forth above are defined as follows: a. “corrupt practice” means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the action of another party; b. “fraudulent practice” means any Act or omission, including a misrepresentation, that knowingly or recklessly misleads, or attempts to mislead, a party to obtain a financial or other benefit or to avoid an obligation; c. “coercive practice” means impairing or harming, or threatening to impair or harm, directly or indirectly, any party or the property of party to influence improperly the actions of a party’ d. “Collusive practice” means an arrangement between two or more parties designed to achieve an improper purpose, including influencing improperly the action of another party. 25. guidelines to contractors for implementation of e-procurement system in Madhya Pradesh Audyogik Kendra Vikas Nigam (Indore) Ltd, GOVERNMENT OF MADHYA PRADESH Note: These will over rule the stated in the tender documents, wherever relevant and applicable. 1. Registration of Bidders on e-procurement System: All the Bidders (Contractors) registered / intending to register with Madhya Pradesh Audyogik Kendra Vikas Nigam (Indore) Ltd are required to register on the eprocurement System on the website https://www.mpeproc.gov.in and get empanelled on https://www.mpeproc.gov.in in order to participate in tenders processed by Madhya Pradesh Audyogik Kendra Vikas Nigam (Indore) Ltd using the e-procurement System. 2. The Bidders (Contractors) registered with other departments who are also eligible to participate in tenders processed by Madhya Pradesh Audyogik Kendra Vikas Nigam (Indore) Ltd are also required to be registered on the e-procurement System on https://www.mpeproc.gov.in 3. Digital Certificate: 13 The bids submitted online should be signed electronically with a Class III Digital Certificate to establish the identity of the Bidder submitting the Bid online. The bidders may obtain Class III Digital Certificates issued by an approved certifying Authority authorized by the Controller of Certifying Authorities, Government of India. A Class III Digital Certificate is issued upon receipt of mandatory identity proofs along with an Application Form. Only upon the receipt of the required documents, a Digital Certificate can be issued. Note: It may take up to 7 working days for issuance of Class III Digital Certificate; hence the bidders are advised to obtain them at the earliest. Important Note: Bid for a particular tender can be submitted during the ONLINE BID SUBMISSION stage only using the Digital Certificate that is used to encrypt the data and Upload their bids. In case, during the process of a particular tender, the bidder looses his Digital Certificate because of any problem (such as misplacement, virus attack, hardware problem, operating system problem, etc); he may not be able to submit his bid online. Hence, the bidders are advised to keep their Digital Certificates in a safe place under proper security to be used whenever required. The digital certificate issued to the Authorized User of a Partnership Firm / Private Limited Company / Public Limited Company / used for online bidding will be considered as equivalent to a no-objection certificate / power of attorney to that user. In case of Partnership Firm, majority of the Partners have to authorize a specific individual through Authority Letter signed by majority of the Partners of the Firm. In case of Private Limited Company, Public Limited Company, the Managing Director / any other person (having designated authority to authorize a specific individual) has to authorize a specific individual through Authority Letter. Unless the certificate is revoked, it will be assumed to represent adequate authority of the specific individual to bid on behalf of the Organization for online tenders as per Information Technology Act 2000. This Authorized User will be required to obtain a Digital Certificate. The Digital Signature executed through the use of Digital Certificate of this Authorized User will be binding on 14 the firm. It shall be the responsibility of Management / Partners of the concerned firm to inform the certifying authority, if the authorized User changes, and apply for a fresh digital certificate for the new authorized User. 4. Set Up of Bidders’ Computer System: In order for a Bidder to operate on the e-procurement System, the computer system of the bidder is required to be set up for Latest version of Java, Operating System, Internet Connectivity, Utilities Fonts, etc. A help file on setting up of the Computer System can be obtained form the portal.. 5. Publishing of NIT For the tenders processed using the e-procurement system, only a brief Advertisement related to the tender shall be published in the newspapers and the Detailed Notice shall be uploaded only on the e-procurement system. The contractors can view the Detailed Notice and the time schedule for all the tenders processes using the e-procurement System on the website https://www.mpeproc.gov.in 6. Key Dates The bidders are strictly advised to follow the time schedule (Key Dates) of the Tender for their side for tasks and responsibilities to participate in the tender, as all the stages of each Tender are locked before the start time and date and after the end time and date for the relevant stage of the Tender as set by the concerned Department Official. 7. Purchase of Tender Documents: The tender document can be purchased ONLY online. The tender shall be available for purchase to concerned eligible contractors immediately after online release of the tender and upto scheduled date and time as set in the key dates. Arrangements have been made for the Bidders to make payments online via Credit Card / Internet Banking. In case of online tendering, the application form for the purchase of tender documents shall not be required. The bidder can purchase the tender documents online by making online payment of tender document fees using the service of the secure electronic payments gateway (see point 7 below for further details), and should print out the system generated receipt of their reference which can be produced whenever required. 15 8. Electronic Payment Account: As the tender documents shall be available for purchase only online, bidders are required to pay the tender document fees online using the Online Payments Gateway Service integrated into the e-Procurement System. For the list of available modes of electronic payments that are presently accepted on the Online Payments Gateway Service, please check the link ‘List of e-payments accepted online’ on https://www.mpeproc.gov.in 9. Preparation of Bids and Submission of Bid Online by the Bidders: The Bidders have to prepare their Bids online, encrypt their bid data in the Bid Forms and submit Bid Seals (Hashes) of all the envelopes and documents required to be uploaded related to the Tender as per the time schedule mentioned in the key dates of the Notice Inviting Tenders after signing of the same by the Digital Signature of their authorized representative. 10. Submission of Earnest Money Deposit: The Bidders shall submit their Earnest Money Deposit as usual in a physically sealed Earnest Money Deposit envelope and the same should reach the concerned Office as stated in the Notice Inviting Tender by post. The bidders have to upload scanned copy of Earnest Money Deposit instrument along with the reference details. 11. Opening of Tenders: The concerned Department Official receiving the tenders or his duly authorized Officer shall first open the online Earnest Money Deposit envelope of all the Bidders and verify the scanned copy of the Earnest Money Deposit uploaded by the Bidders. He shall check for the validity of Earnest Money Deposit as required. He shall also verify the scanned documents uploaded by the bidders, if any, as required. In case, the requirements are incomplete, the commercial and other envelopes of the concerned Bidders received online shall not be opened. The concerned official shall then open the other envelopes submitted online by the Bidders in the presence of the Bidders or their authorized representatives who choose to be present in the order of opening. He will match the Bid seal (Hash) of each envelope and the documents uploaded, during the respective opening, with the hash submitted by the Bidders during the Bid Preparation stage. In the event of a mismatch, the Bid data in question shall be liable for a due process of verification by the Nodal Officer of e-procurement System of Public Works Department. For more details you may contact Mr N.S. Rajput, Executive Engineer MP, AKVN (I) Ltd, Indore. Telephone No 0731-2556111, 4070976. 16 Mr. Amar Singh – Officer Implementation, MPSEDC, State IT Centre, Bhopal 0755– 2462011. Call at 9893421873 ******(End of ITB)****** Bid Data Sheet General Sr. Particulars Date 17 No. 1 Office inviting tender Managing Director, M.P. Audyogik Kendra Vikas Nigam (Indore) Ltd. 2 NIT No. 13072 3 Date of NIT 31/10/2014 4 Bid documents download available from date & time 10:30 on 03/11/2014 5 Website link http:// www.mpeproc.gov.in Section 1 – NIT Clause Reference 1 2 3 4 5 6 Particulars Date Portal fees As per prevailing rates for E-tendering Cost of bid document Rs. 15000/- Cost of bid document payable at Online Cost of bid document in favor of Online Affidavit format Annexure B Pre- qualification required Yes If yes, details Annexure C Special Eligibility Yes If yes, details Annexure D Key dates Annexure A Section 2 – ITB Clause Reference 1 Particulars Date Name of work Supply, 18 installation, testing and Clause Reference Particulars Date commissioning of 33/11 KV External electrification work for new industrial area at Relwa Khurd district Barwani 2 Specifications Annexure E 3 Procedure for Participation in etendering Annexure F Whether joint venture is allowed 4 NO If yes, requirement for joint venture Annexure G ( NOT ALLOWED) Pre bid meeting to be held No Date 5 If yes, date, time & place Time from Place Envelope-A containing: 6 Managing Director, M.P. Audyogik Kendra Vikas Nigam (Indore) Ltd. i. Registration number or proof of application for registration and organization details as per Annexure H ii. Cost of Bid Document iii. EMD iv. An affidavit duly notarized as per annexure – B v. Should reach in physical form Envelope-B Technical Proposal Annexure – I and 7 Annexure – I (Format I-1 to I-5) Envelope-C Financial Bid Annexure – J 8 Materials to be issued by the department Annexure – K (Not applicable) 9 Period of validity of Bid 120 days 10 Earnest money deposit Rs. 373600/- Forms of earnest money deposit i. FDR/e-FDR ii. Demand draft of scheduled 19 Clause Reference Particulars Date commercial bank iii.Interest bearing securities of post office 6 months after the last date of receipt of bids (in case of i & iii above EMD valid for a period of 11 FDR must be drawn in favour of Managing Director, M.P. Audyogik Kendra Vikas Nigam (Indore) Ltd. Letter of Acceptance (LOA) Annexure L Amount of performance security 5% of contract amount As per the clause 22.2 of ITB, the additional performance security shall be the percent below 10% quoted by bidder for example, if the rates quoted by bidder is 18% below then additional performance security of 8% shall be deposited by bidder and total performance security in this case will be 13% which has to be deposited before execution of agreement. So, Bid data sheet clause 22 is now revised as above. Additional performance security, if any 12 Performance security in the format Annexure M Performance security in favour of Managing Director, M.P. Audyogik Kendra Vikas Nigam (Indore) Ltd. Performance security valid up to Valid contract period including defect liability period plus three months 20 Annexure –A (see clause 1, 7 of section 1 NIT) KEY DATES Sr. No Work Department Stage Bidder’s Stage 1 Purchase of tender online 2 Bid submission End date – online Start Expiry Envelopes Date Time Date Time 03/11/2014 10:30 20/11/2014 17:30 25/11/2014 17:30 3 Mandatory open (Envelope-A & B) 28/11/2014 15:30 Envelope-A &B 4 Financial Bid open (Envelope-C) 04/12/2014 15:30 Envelope-C Original term deposit receipt of earnest money deposit, demand draft for the cost of bid document and affidavit shall be submitted by the bidder so as to reach the office as prescribed in bid data sheet as list one calendar day before specified start time and date in key dates for opening of technical proposal as per key dates in bid data sheet. (The physical submission as above should be done upto 17:30 hrs on 27/11/2014) 21 Annexure – B (See clause 3 of section 1 NIT) ‘AFFIDAVIT’ (To be contained in Envelope A) (On Non judicial Stamp of Rs.100) I/we __________________________________________________________________________ who is/ are _______________________________________________________(status in the firm/company) and competent for submission of the affidavit on behalf of M/s________________________________ (contractor) do solemnly affirm and oath and state that: I/we am/are fully satisfied for the correctness of the certificates / records submitted in support of the following information in bid document which are submitted in response to notice inviting e- tender No. ________________________ for M.P. Audyogik Kendra Vikas Nigam (Indore) Ltd. 1. I/we am/are fully responsible for the correctness of following self-certified information/documents and certificates: 2. That the self-certified information given in the bid document is fully true and authentic. 3. That: a. Term deposit receipt deposited as earnest money, demand draft for cost of bid document and other relevant document provided by the Bank are authentic. b. Information regarding financial qualification and annual turnover is correct. c. Information regarding various technical qualifications is correct. 22 No close relative of the undersigned and our firm/ company is working in the department. OR Following close relatives are working in the department: Name______________________Post__________________________Present Posting____________________________ Signature with seal of the Deponent (Bidder) I/we_______________________________________________________above deponent do hereby certify that the facts mentioned above para’s 1 to 4 are correct to the best of my knowledge and belief. Verified today_________________________________(dated) at _____________________(place) Signature with seal of the Deponent (Bidder) Note: Affidavit duly notarized in original shall reach at least one calendar day before opening of the bid. Annexure – C (See clause 5 of section 1 NIT) Pre-Qualification Criteria The bidder should have: A. Financial a. Experience of having successfully executed: b. Three similar works, each costing not less than the amount equal to 20% of the probable amount of contract during the last 3 financial years; or c. Two similar works, each costing not less than the amount equal to 30% of the probable amount of contract during the last 3 financial years; or d. One similar work of aggregate cost not less than the amount equal to 50% of the probable amount of contract in any one year during the last 3 financial years; i. Average annual construction turnover on the construction works not less than 50% of the probable amount of contract during the last 3 financial years: 23 ii. Executed similar items of work in any one year during the last 3 financial years which should not be less than the minimum, physical requirement, if any, fixed for the work. iii. Bid Capacity – Bidder shall be allotted work up his available bid capacity which shall be work out as given in format one I-2 of Annexure I. B. Physical Physical qualifications for the work shall be as below Sr. No. Particulars Quantity Physical qualification required Period Yes 1 Power transformer at least 3.15 MVA, 33/11 KV 1 Nos. 2 33 KV LINE 5 Kms Annexure – D (See clause 6 of Section 1 NIT) Special Eligibility Criteria 24 The bidder should have Experience of: Two nos Power transformer at least 3.15 MVA, 33/11 KV in a grid with associated VCB's , outdoor substation, associated civil work including control room for relay penals etc. Note: above criteria are indicative, subject to suitable stipulations by the department and specific Bid 25 Annexure – E (See clause 2 of section 2 ITB & clause 10 of GCC) TECHNICAL SPECIFICATION FOR ELECTRICAL WORKS S.NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 PARTICULAR OF SPECIFICATION Technical Specification for A.C. Distribution Board Technical Specification for D.C. Distribution Board Technical Specification for 11 KV and 33 KV Vacuum Circuit Breaker Technical Specification for 11 KV and 33 KV Control and Relay Panel Technical Specification for 30V, 10 amp. Boost cum Float Battery Charger Suitable for 30V,100AH lead acid Battery Technical Specification for 30V, 10 amp Lead acid Battery Technical Specification for 1200 KVAR 11 KV Capacitor Bank Technical Specification for 33KV and 11KV Gapless Lightning Arrestor Technical Specification for 1.1 KV (LT) PVC Insulated Power Cable Technical Specification of 11KV and 33KV oil immersed CT-PT (Metering) Unit Technical Specification of Earthing Technical Specification of 11KV and 33KV Isolator’s Technical Specification of 11KV and 33KV Air Break Switches Technical Specification of 11KV and 33KV DO Fuse Unit’s Technical Specification of Hard Drawn Stranded Aluminium and Steel Cored Aluminium Conductor for overhead power Line’s Technical Specification of Three Phase 33/11 KV Step Down Power Transformer of 5 MVA Ratings Technical Specification of Distribution Transformer Technical Specification of 415V Outdoor type Street Light Control Panel Technical Specification of 11KV and 33KV Pin Insulator 26 PAGE NO. 25 – 33 33 – 42 42 – 49 49 – 60 60 – 66 66 – 72 72 – 74 74 – 79 79 – 81 82 – 91 91 – 97 97 – 101 102 – 105 106 – 110 110 – 115 115 – 130 131 – 139 139 – 144 144 – 147 20 21 22 Technical Specification of L.T. Distribution Boxes 148 – 158 SCADA Specification for new 33/11 KV Substation 158 – 159 Technical Specification of 11 KV Epoxy Cast Dry type Single 159 – 160 Phase PT’s Technical Specification of 33 KV Current Transformer 161 – 164 Technical Specification for 11KV and 33 KV MS Cross Arm 164 – 165 Technical Specification of 11/33 KV Nominal voltage HT XLPE 165 – 169 Cable Technical Specification for Street Light Poles 170 – 170 Technical Specification for Sodium Vapour Lamp 170 – 171 Technical Specification for LED 171 – 175 23 24 25 26 27 28 1. TECHNICAL SPECIFICATION FOR A. C. DISTRIBUTION BOARD SCOPE This specification covers the design, manufacturing, testing at works and supply of Indoor type A.C. Distribution Boards for Battery charger, 33/11 kV substation & 33 KV SWITCHING GRID equipments, compressors etc. The system shall be AC 3 Phase, 4 Wire, 433 Volts, 50 HZ with effectively grounded neutral. SERVICE CONDITIONS Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions. 1 Maximum ambient temperature (Degree C) 50 2 Maximum temperature in shade (Degree C) 45 3 Relative Humidity (Percent) --------10 to 100 4 Moderately Hot and Humid tropical climate conducive to rust and fungus growth STANDARDS Components mounted on the ACDB shall confirm to the latest revisions of the following Standards of table : S.NO Standard 1 IS: 13947 2 3 PARTICULAR Degree of protection provided for enclosure for low voltage control gear and switchgear & MCCB IS 5 Painting shade no. 632 C IS: 13947/1993 amended up to date Part I & Part-III Switch Fuse Disconnect or unit 4 IS 2705 amended up to date CTs 5 6 7 8 IS 8828/1996 IS 1248 IS 375 IS: 13703/1993 PartI & II MCB amended up to date Instruments Wiring HRC Fuses 27 GENERAL TECHNICAL PARTICULARS: The A C Distribution Boards shall be supplied as per this specification. The A C Distribution Boards shall be supplied as per this Rated voltage: Rated voltage for the Distribution Board and its constituent items like Switch Fuse Disconnector unit, MCBs, bus ways etc. shall be 3 phase 4 wire A.C. 433 volts, 50 Hz with solidly grounded neutral. The supply voltage may vary by ± 10% of rated voltage. All the equipments used in the Board shall operate satisfactorily at this voltage variation. The A C Distribution Boards shall be supplied as per this General requirements: Each Distribution Board shall be floor mounted having compact design and made from Sheet metal of 1.6 mm. The Board shall be closed, dust protected, weather proof and shall be made vermin proof with a special type lining e.g. Neoprene gasket, around the edges of the doors. The distribution board shall comply degree of protection IP 33 & IP55 . MCBs shall be operating vertically upward for ON/OFF operation & shall be suitable for providing fork type busbar. The entire distribution board shall have uniform finish and shall be sturdy. Each Distribution board shall have 2 compartments namely – A. Instruments compartment and B. Feeder compartment. These compartments shall have doors as described below a. For Instrument compartment, one no. door with indicating instruments, indicating lamps, selector switches, nameplate mounted on it. b. For feeders compartment, one no. inner door with one opening for handle to operate switch fuse unit and five cutouts for outgoing SFUs. One outer door with out cutouts & non breakable transparent sheet shall be provided. All doors shall be provided with mechanical interlocking arrangements along with keys. The distribution board shall have no door on rear side. Danger board ( Caution Plate) shall be fitted suitably on inner door of the DB. Danger board shall be as per CSPDCL standard format as per STANDARD. Detachable gland plates suitable for receiving the cable shall be provided at the bottom side of Distribution board with glands separate compartment of 450 mm . The ventilating louvers should be covered on inside by a perforated sheet. All sheet metal used for DB shall undergo seven tank mechanical / chemical cleaning process & painting shall be done using powder coating process. Colour of the Paint shall be admiral gray as per shade no. 632 of IS 5 on exterior and white from interior sides. Each Distribution Board shall be provided with a. One no. name plate showing the details such as manufacturer’s name, Sr No., rating etc. b. One no. danger board scripted in English and Hindi , c. One no. flush mounted 96x96mm size ammeter with selector switch 28 d. One no. flush mounted 96x96mm size voltmeter with selector switch e. One no. MCCB of 3 phase, 25 kA, 433 Volts, 200 Amp rating f. 3 nos. LED phase indicators for incoming feeder g. 3 nos. single phase LTCTs of 10VA and CT ratio 100/5A. h. 1 no timer with contactor for lighting circuit i. 5 Nos. of 32 A TPN Switch Fuse Unit with 16 A HRC Fuses. The accuracy class for all indicating and integrating meters shall be class 1. Enclosures: The enclosure shall be made of 14 SWG (2mm) steel sheets and shall be suitable for in-door installation, conforming to above degree of protection as per IS: 2147/1962. The front door shall be having locking facility. The box should be provided with single door in front and having internal locking arrangement with two keys. Extra padlock arrangement shall also be provided. The latches provided inside the door, which are locked in position by the keys, should be such that the door gets locked just by closing (for opening the door, keys will then be required). The backside cover shall be screwed type and should be fixed with 4 nos. 8mm size Allen screws at four corners. One box spinner of suitable size for the screw fitted in the box should be provided inside the box with suitable clamps. Neoprene rubber gasket shall be used on front door as well as back cover. Painting of Box All sheet steel surface of the box shall be thoroughly degreased and shall be followed by antacid cleaning so as to produce smooth and clean surface free from scale grease and dust. After cleaning, the surface shall be given phosphate coating followed by two coats of anti rust paint primer (i.e. red zinc chrome primer). After which, 2 coats of synthetic paint of light grey color (no.631 as specified in Indian Standard 5 of 1961) shall be applied on internal and external, surface of the steel structure of the box with a spray gun. The box shall be baked in the oven so as to give an elegant and durable finish to the box. Leakage Proof: The box shall be vermin proof and weatherproof. The assembly, comprising of the enclosure, framework and the circuit breaker shall be provided with earthing terminals readily accessible and of adequate size two earthing studs of 12mm dia size shall be welded to the enclosure on either side as shown in the drawing and shall be provided with locking nuts and 29 washers. All the nuts, bolts and washers should be galvanized iron. The earthing terminal shall be clearly marked. Four nos. drainpipes of ½” diameter shall be welded at the bottom of the box at Four Corners. The bottom plate shall be centrally bent to provide slope for drainage of water through the drain pipes. Ventilation louvers with wire mesh shall be provided on both the sides as per requirements. In addition to this, louvers with wire mesh of suitable sizes and numbers also required on backside cover of box. Detailed drawing showing size of openings and size of brass mesh shall be submitted by the bidder for approval prior to manufacture. Danger Board: Specifications are shown in Technical Specifications of the package. Knock-out Holes: Knockout holes for incoming and outgoing cables will be provided. The holes shall be suitable to accommodate XLPE aluminium conductor LT cable of appropriate size. These holes should be provided direct contact with and gets out by the metal edges. The holes should be in alignment with the terminals of incomer and outgoing MCBs so that the cable may be directly crimped with lugs. Bending of cable inside the box for terminal connection should not be required. BUS BAR AND CABLING: (i) The incoming single core cable shall enter from backside (top) of the enclosure. All outgoing cables shall enter from the sides of the enclosures. (ii) Electrolytic grade copper shall be used for bus bar and links used interconnection of incoming and outgoing feeders. (iii) Bimetallic / suitable connectors are required for connecting the SFU and MCCB terminals to Bus Bar. WIRING All wiring shall be carried out with 1100 V grade stranded copper wires. The minimum size of the stranded conductor used for internal wiring shall be as follows: All circuits except CT circuits 2.5 sqmm CT circuits 2.5 sq. mm (minimum number of strands shall be 3 per conductor). All internal wiring shall be securely supported, neatly arranged readily accessible and connected to equipment terminals and terminal blocks. Wire terminations shall be made with Solder less crimping type of tinned copper lugs which firmly grip the conductor and insulation. Insulated sleeves shall be provided at all the wire terminations. Engraved core identification plastic ferrules marked to correspond with the wiring diagram shall be fitted at both ends of each wire. Ferrules shall fit tightly on the wires shall not fall off when the wires and shall not fall off when the wire is disconnected from terminal blocks. 30 All wires directly connected to trip circuit breaker shall be distinguished by the addition of a red coloured unlettered ferrule. Number 6 & 9 shall not be included for ferrules purposes. All terminals including spare terminals of auxiliary equipment shall be wired upto terminal blocks. Each equipment shall have its own central control cabinet in which all contacts including spare contacts from all poles shall be wired out. Inter-pole cabling for all equipment’s shall be carried out by the Contractor. Indicating Lamps Indicating lamps shall be of low wattage LED cluster type. The lamps shall be provided with translucent lamp covers which shall diffuse coloured light to give the specified indications. The lamp covers shall be unbreakable and moulded from heatresistant fast coloured material. Necessary wiring shall be provided accordingly. Major Components: Busbars Bus bar used in ACDB shall be fork type with suitable size of copper strip without joints. This busbar shall be directly mounted on MCCB. Total 4 nos. of busbars are to be provided with following details. I. One No. 4 Pole fork type touch proof bus bar to connect 3 Ph. TPN MCCBs. Incoming cable for ACDB shall be terminated on terminal connectors provided at the bottom. Connection between incomer terminals and MCCB shall be with 50 sq. mm copper cable. Outgoing of Switch Fuse disconnect or unit shall be connected with 35 square mm copper cable. For all 32 A rated MCBs, 16sq.mm. stranded cable shall be used. Earthing arrangement shall be as per this specifications. Incoming circuit Incoming circuit shall have one no. 3 phase, 433 volt MCCB of nominal current rating of 32 Amps , 4 POLE conforming to IS: 13947/1993 amended up to date and 3 No. LT resin cast CTs having CT ratio of 200/5A with burden 10VA & accuracy class 1. Switch Fuse Disconnector unit shall be as per CSPDCL standard format as per STANDARD To receive incoming cable, one no. 4 way bolted type connector of suitable size shall be provided. Incoming cable for incomer LT XLPE, suitable size shall be provided. Outgoing circuits : Total 5 Nos. (minimum) 10 amp outgoing circuits shall be provided Breaking capacity (in KA) 25 KA termination by Tinned copper lugs suitable for size of cable. SFUs shall comply following specifications as per IS. II. a) Rated voltage & freq. shall be 433V & 50 Hz respectively for TPN SFUs. b) Rated current shall be 32A/16 A as mentioned above. c) Rated short circuit capacity shall be min. 25 KA. The enclosure shall be provided with proper earthing arrangement. Earthing arrangement shall consist of 2 G.I. Bolts of 12 mm (min.) with 2 spring/ plain washers and 2 check nuts. 31 PVC cable glands of adequate size shall be provided for all incoming and out going cables. Indicating Instruments Principal requirements of indicating instruments are as follows: Volt Meter. Voltmeter shall comply the following requirements Class of accuracy 1 Mounting Flush type Size 96x 96 mm Range 0-600 volts Type Panel Mounting with 3 ½ Digital Display Voltmeter shall be guaranteed for free replacement for any defects within five years from the date of supply. Volt Meter selector switch: Voltmeter Selector switch shall be a seven-position rotary type ( 6 way & off) with 3 phase to phase & 3 phase to neutral position marked clearly on 48 x 48 mm brushed aluminium plate with black handle. The Switch should be screw mounting type with finger touch proof terminals. Terminal wire should be inserted from the side of the switch terminal. Terminal screw must be captive to avoid misplace during maintenance. The switch shall be of 12 A rating with insulation level of 1100 V. Indicating Lamps: Indicating lamps shall be panel mounting type 22.5 mm with rear terminal connections having LEDs display. Lamps shall have translucent lamp covers to diffuse lights, coloured red, yellow, green or blue as specified. The amp cover shall be preferably of screw-on type, unbreakable and moulded from heat resisting material. All indications shall be bright LEDs having long life. Conventional bulbs are not acceptable. Earthing Arrangements Two nos. Earthing studs of galvanized M.S. 25 X 6 mm shall be provided for external earth connections at the bottom. These should be complete with plain washer, spring washer, nuts etc. Earthing Bolts must be welded to prevent removal of the same from the cabinet. Type Tests Certificates : MCBs & other components used in ACDB shall be fully type tested as per relevant IS and this specification. The successful Bidder shall furnish detailed type test reports before commencement of supply. The detailed Type Test Reports shall be furnished with relevant oscillogram and certified Drawings of the equipment tested. The purchaser reserves the right to demand repetition of some or all the Type tests in presence of purchaser’s representative at purchaser’s cost. All the Type Tests shall be carried out from laboratories which are accredited by the National Board of Testing and Calibration Laboratories (NABL) of Government of India such as CPRI Bangalore/ Bhopal, ERDA Baroda, to prove that the MCBs & other components used in ACDB meet requirements of the specification. The tenderer should also furnish certificate from laboratories that laboratories are having all the requisite test facility available in house. The type tests reports conducted in manufacturers own laboratory and certified by testing institute shall not be acceptable. In case these type tests are conducted beyond 5 years of the date of opening of the tender, the successful bidder shall carry out these tests at NABL approved laboratory at their own cost .& submit the same before commencement of supply. Undertaking to this effect shall be submitted along with the offer without 32 which the offer shall be liable for rejection. The successful bidder have to supply the complete material as per overall General Arrangement drawing approved by AKVN. Successful bidder shall submit the following detailed drawings along with component details/makes etc. for necessary approval. (i) General Arrangement Drawing for ACDB. (ii) ii) Wiring Diagram. (iii) Name Plate Drawing. (iv)Danger Board Drawing (v) Bill of Material Inspection All tests and inspection shall be made at the place of manufacturer. The manufacturer shall provide reasonable testing and inspection facilities and cooperation without any charge to satisfy him that the material is being supplied is in accordance with this specification. The proto of ACDB shall be inspected & checked by AKVN. his representative for approval before commencement of supply. TESTS & TEST CERTIFICATE: The type test certificates from reputed national level laboratories for the distribution box complete with suitable MCBs (as indicated in technical specification) for incoming and outgoing feeders giving the results of sample tests as per relevant BSS/ISS indicated below are required to be submitted along with the lot offered for inspection before despatch for approval in support of compliance of material to the specification and quality. Make of the MCBs to be used should be indicated in the offer. Acceptable make of MCBs are L&T, Siemens, Crompton Greaves, MAKE GIVEN IN Technical specification. a) Type test for Distribution Box as per BS 214/1959. b) All type & routine tests, except the Short Circuit Breaking Capacity Test shall be carried out on the MCCBs in accordance with IS:2516(Pt-I&II Sec.I)/1977 or its latest modification. The short circuit breaking capacity test shall be carried out. c) Test Certificate in respect of Type Tests, from standard testing laboratory like C.P.R.I. etc. should invariably be furnished in support of the quality LIST OF DEVIATIONS The Contractor shall state all the deviations from tender specification in his offer, if any. The offer shall be deemed to be in conformity with tender specification unless deviations from tender specification are clearly mentioned in this section. GUARANTEED PERFORMANCE REQUIREMENTS: The vendor shall guarantee satisfactory performance of the equipment supplied under all conditions and requirement as laid down by this specification. The contactor shall warranted the equipment and material will be new and accordance with the specification. It is free from defect, material, workman ship up to guan teed period. It is necessary for contactor to replace or the new in defective portion of the equipment. The repair and new part will be furnished by contactor free of cost. PACKING, DESIGN, MATERIALS & WORKMANSHIP PACKING AND MARKING: 33 The material shall be packed as per manufacturers standard. Packing procedure shall be to the purchasers approval. The conductor shall be supplied in non-returnable strong Packing provided with lagging of adequate strength and displacement during transit, storage and subsequent handling and stringing operation in the field. The Packing shall generally conform to IS: 1778-1980, amendment No.1, June 1989, except otherwise specified hereinafter. Each packing shall have the following information stencilled on it in indelible ink along with other essential data: a) Manufacturer’s Name b) Trade mark, if any c) Identification Number d) Name of material e) Number of Packing on each item f) Gross Mass of the Packing g) Net Mass of Packing h) ISI or relevant International Standard specification mark, if any i) Name and address of the Consignees PACKING CONDITION The material Packing shall be of such constructions as to assure delivery. The material of free from displacement and damage and should be able to withstand all stresses due to handling and the stringing operation so that the material surface is not dented, scratched or damaged in any way during manufacture, transport and erection. The material shall be properly lagged on the vehicles. The material should be suitable for wheel mounting. Before pad, cardboard or other suitable material shall be secured to The material inside flanges of the packing After loading, the exposed surface should be wrapped with suitable soft material e.g. polythene sheet etc. across the flanges to protect The material from dirt, grit and damage during transportation and handling and also prevent ingress of rain water during storage/transport. All wooden / other components shall be manufactured out of seasoned wood of good quality free from defect that may materially weaken the component parts of the packing Preservative treatment for anti-termite/anti-fungus shall be applied to the entire packing with preservatives of a quality which is not harmful to the conductor. QUALITY ASSURANCE PLAN The Bidder/ Supplier/ Vendor must estalish that they are following a proper quality assurance programme for manufacture of for item . The Bidder/ Supplier/ Vendor shall invariably furnish following information along with his bid. Information shall be separately given for item Statement giving list of important raw-materials, names of sub-suppliers for the rawmaterial, list of standards according to which the raw-material is purchased and copies of test certificates thereof. Information and copies of test certificates as in (i) above in respect of bought out items. List of manufacturing facilities available. Levels of automation achieved and list of areas where manual processing exists.List of areas in manufacturing process, where stage inspections are normally carried out for quality control and details of such tests and inspetions. 34 List of testing equipments available with the Bidder/ Supplier/ Vendor for final testing of item specified and test plant limitation, if any, vis-a-vis type, special, acceptance and routine tests specified in the relevant standards. These limitations shall be very clearly brought out in schedule of deviations from specified test equipments. The successful Bidder/ Supplier/ Vendor shall within 30 days of placement of order, submit following informatuion to the Owner : List of raw-material as well as bought out accessories and the names of subsuppliers selected from the lists furnished along with Bid. Type test certificates of the raw-material and bought out accessories. Quality Assurance Plan (QAP) with hold-up points for owner’s inspection. The quality assurance plans and hold-up points shall be discussed between the owner and agency before the QAP is finalized. The successful Bidder/ Supplier/ Vendor shall submit the routine test certificates of bought out items and form raw-material at the time of routine testing of item. The bidder/ Supplier/ Vendor shall invariably furnish following information along with his offer, failing which his offer shall be rejected. (i) Statement giving list of important raw materials names of sub suppliers for the raw materials, list of standards according to which the raw materials are tested, list of tests normally carried out on raw materials in presence of supplier's representative and as routine and / or acceptance during production and on finished goods, copies of test certificates. (ii) Information and copies of test certificates as in (i) above in respect of bought out accessories. (iii) List of manufacturing facilities available. (iv)Level of automation achieved and lists of areas where manual processing exists. (v) List of areas in manufacturing process, where stage inspections are normally carried out for quality control and details of such tests and inspections. (vi)List of testing equipment available with the Supplier for final testing of Conductor specified. In the case if the suppliers does not possess all the Routine and Acceptance testing facilities the tender will be rejected. (vii) The OWNER reserves the right for factory inspection to verify the facts quoted in the offer. If any of the facts are found misleading or incorrect the offer of that SUPPLIER will be out rightly rejected and he may be black listed. (viii) Special features provided to make it maintenance free. 2. TECHNICAL SPECIFICATION FOR D C. DISTRIBUTION BOARD SCOPE This specification covers the design, manufacturing, testing at works and supply of Indoor type D.C. Distribution Boards for Battery charger, 33/11 kV substation & 33 KV SWITCHING GRID equipments, compressors etc. The system shall be DC 30 V 100 Ah battery set with effectively grounded neutral. 35 SERVICE CONDITIONS Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions. 2.1 Maximum ambient temperature (Degree C) 50 2.2 Maximum temperature in shade (Degree C) 45 2.3 Relative Humidity (Percent) --------10 to 100 2.4 Moderately Hot and Humid tropical climate conducive to rust and fungus growth STANDARDS Components mounted on the DCDB shall confirm to the latest revisions of the following Standards of table : S.NO STANDARD PARTICULAR 1 IS: 13947 Degree of protection provided for enclosure for low voltage control gear and switchgear & MCB 2 IS 5 Painting shade no. 632 3 C IS: 13947/1993 Part I amended up to date & Part-III Switch Fuse Disconnect or unit 4 5 IS 8828/1996 MCB amended up to date 6 IS 1248 Instruments 7 IS 375 Wiring 8 IS: 13703/1993 Part-I HRC Fuses & GENERAL TECHNICAL PARTICULARS: These D C Distribution Boards shall be supplied as per this specification. These D C Distribution Boards shall be supplied as per this Rated voltage: Rated voltage for the Distribution Board and its constituent items like Switch Fuse Disconnector unit, MCBs, bus ways etc. shall be DC 30 V 100 Ah battery set with effectively grounded neutral. The supply voltage may vary by ± 10% of rated voltage. All the equipments used in the Board shall operate satisfactorily at this voltage variation. These D C Distribution Boards shall be supplied as per this General requirement: Each Distribution Board shall be floor mounted having compact design and made from Sheet metal of 1.6 mm. The Board shall be closed, dust protected, weather proof and shall be made vermin proof with a special type lining e.g. Neoprene gasket, around the edges of the doors. The distribution board shall comply degree of protection IP 33 & IP55 . MCBs shall be operating vertically upward for ON/OFF operation & shall be suitable for providing fork type busbar. The entire distribution board shall have uniform finish and shall be sturdy. Each Distribution board shall have 2 compartments namely – C. Instruments compartment and D. Outgoing Feeder compartment. These compartments shall have doors as described below a. For Instrument compartment, one no. door with indicating instruments, indicating lamps, selector switches, nameplate mounted on it. 36 b. For feeders compartment, one no. inner door with one opening for handle to operate switch fuse unit and four cutouts for outgoing MCBs. One outer door without cutouts & non breakable transparent sheet shall be provided. All doors shall be provided with mechanical interlocking arrangements along with keys. The distribution board shall have no door on rear side. Danger board (Caution Plate) shall be fitted suitably on inner door of the DB. Danger board shall be as per CSPDCL standard format as per STANDRED. Detachable gland plates suitable for receiving the cable shall be provided at the bottom side of Distribution board with glands separate compartment of 450 mm . The ventilating louvers should be covered on inside by a perforated sheet. All sheet metal used for DB shall undergo seven tank mechanical / chemical cleaning process &painting shall be done using powder coating process. Colour of the Paint shall be admiral gray as per shade no. 632 of IS 5 on exterior and white from interior sides. D.C. Control and Distribution Board The DC Control and distribution board shall be equipped with MCBs. The equipment shall be capable of carrying, making and breaking the maximum possible fault current and details of the make-up of this shall be provided. Curves of battery current plotted against time under short circuit conditions shall be supplied. Outgoing distribution cables shall be connected directly to the relevant MCB/SFU. Each Distribution Board shall be provided with a. One no. name plate showing the details such as manufacturer’s name, Sr No., rating etc. b. One no. danger board scripted in English and Hindi , c. One no. flush mounted 96x96mm size ammeter with selector switch d. One no. flush mounted 96x96mm size voltmeter with selector switch e. 1 nos. LED phase indicators for incoming feeder The accuracy class for all indicating and integrating meters shall be class 1. D.C. Distribution cabinet f. The panels shall house all distribution necessary for the station d.c. circuits; they g. shall at least be of protection class IP41 with self cooling, with separate panels per h. battery system. Bottom plate of the D.C.D.B. shall be of detachable type for entry of i. outgoing feeder cables. Twenty percent spare feeders, fully equipped, shall be provided. j. The arrangement shall be as per requirement of AKVN appropriately. k. The d.c. panels shall have l. - lamp test m. - supply in feeds off n. - D.C. feeder trip (one for all feeders per panel) o. In addition, provision for having one general d.c. alarm connected to the alarm panel in the station control room shall be provided. p. D.C. ammeters and voltmeters shall be provided. 37 q. r. s. t. u. v. w. x. y. z. aa. bb. The enclosure shall be made of 14 SWG (2mm) steel sheets and shall be suitable for in-door installation, conforming to above degree of protection as per IS: 2147/1962. The front door shall be having locking facility. The box should be provided with single door in front and having internal locking arrangement with two keys. Extra padlock arrangement shall also be provided. The latches provided inside the door, which are locked in position by the keys, should be such that the door gets locked just by closing (for opening the door, keys will then be required). The backside cover shall be screwed type and should be fixed with 4 nos. 8mm size Allen screws at four corners. One box spinner of suitable size for the screw fitted in the box should be provided inside the box with suitable clamps. Neoprene rubber gasket shall be used on front door as well as back cover. Painting of Box All sheet steel surface of the box shall be thoroughly degreased and shall be followed by antacid cleaning so as to produce smooth and clean surface free from scale grease and dust. After cleaning, the surface shall be given phosphate coating followed by two coats of anti rust paint primer (i.e. red zinc chrome primer). After which, 2 coats of synthetic paint of light grey colour (no.631 as specified in Indian Standard 5 of 1961) shall be applied on internal and external, surface of the steel structure of the box with a spray gun. The box shall be baked in the oven so as to give an elegant and durable finish to the box. Leakage Proof: The box shall be vermin proof and weatherproof. The assembly, comprising of the enclosure, framework and the circuit breaker shall be provided with earthing terminals readily accessible and of adequate size two earthing studs of 12mm dia size shall be welded to the enclosure on either side as shown in the drawing and shall be provided with locking nuts and washers. All the nuts, bolts and washers should be galvanized iron. The earthing terminal shall be clearly marked. Four nos. drainpipes of ½” diameter shall be welded at the bottom of the box at Four Corners. The bottom plate shall be centrally bent to provide slope for drainage of water through the drain pipes. Ventilation louvers with wire mesh shall be provided on both the sides as per requirements. In addition to this, louvers with wire mesh of suitable sizes and numbers also required on backside cover of box. Detailed drawing showing size of openings and size of brass mesh shall be submitted by the bidder for approval prior to manufacture. Knock-out Holes: Knockout holes for incoming and outgoing cables will be provided. The holes shall be suitable to accommodate x.l.p.e aluminium conductor LT cable of appropriate size. These holes should be provided direct contact with and gets out by the metal edges. 38 cc. The holes should be in alignment with the terminals of incomer and outgoing MCBs so that the cable may be directly crimped with lugs. Bending of cable inside the box for terminal connection should not be required. D.C. Bus Bars: There shall be one charger load bus, one load bus and one emergency load bus. The charger load bus shall be rated for 200 Amp, 10kA short circuit withstand rating. Load bus bar shall be rated for 100 Amps, 10 kA short circuits withstand rating. The emergency load bus shall be rated for 50 Amps, 5 kA short circuits withstand rating. The charger load bus and load bus shall be connected through 100A MCB 39 BUS BAR AND CABLING: i) The incoming single core cable shall enter from backside (top) of the enclosure. All outgoing cables shall enter from the sides of the enclosures. ii) Electrolytic grade copper shall be used for bus bar and links used interconnection of incoming and outgoing MCBs. The minimum size acceptable are as follows :iii) Bimetallic / suitable connectors are required for connecting the MCBs terminals to Bus Bar. WIRING All wiring shall be carried out with 1100 V grade stranded copper wires. The minimum size of the stranded conductor used for internal wiring shall be as follows: All circuits except CT circuits 2.5 sqmm CT circuits 2.5 sq. mm (minimum number of strands shall be 3 per conductor). All internal wiring shall be securely supported, neatly arranged readily accessible and connected to equipment terminals and terminal blocks. Wire terminations shall be made with Solder less crimping type of tinned copper lugs which firmly grip the conductor and insulation. Insulated sleeves shall be provided at all the wire terminations. Engraved core identification plastic ferrules marked to correspond with the wiring diagram shall be fitted at both ends of each wire. Ferrules shall fit tightly on the wires shall not fall off when the wires and shall not fall off when the wire is disconnected from terminal blocks. All wires directly connected to trip circuit breaker shall be distinguished by the addition of a red coloured unlettered ferrule. Number 6 & 9 shall not be included for ferrules purposes. All terminals including spare terminals of auxiliary equipment shall be wired upto terminal blocks. Each equipment shall have its own central control cabinet in which all contacts including spare contacts from all poles shall be wired out. Inter-pole cabling for all equipment’s shall be carried out by the Contractor INDICATING LAMPS Indicating lamps shall be of low wattage LED cluster type. The lamps shall be provided with translucent lamp covers which shall diffuse coloured light to give the specified indications. The lamp covers shall be unbreakable and moulded from heatresistant fast coloured material. Necessary wiring shall be provided accordingly Major Components: Busbars Bus bar used in DCDB shall be fork type with suitable size of copper strip with out joints. This busbar shall be directly mounted on MCBs. Incoming circuit Incoming circuit shall have one no. 30 V Switch Fuse Disconnector unit of nominal current rating of 32 Amps DP conforming to IS: 13947/1993 amended up to date and 3 No. Switch Fuse Disconnector unit shall be as per MPPKVV CO LTD standard format as per STANDRED To receive incoming cable, one no. 4 way bolted type connector of suitable size shall be provided. Incoming cable for incomer LT XLPE, suitable size shall be provided.. Outgoing Circuits: 10 nos , 16 amp DP MCB. 40 One No. feeder for emergency lighting which will comprise of a emergency load bus and 3 Nos. outgoing circuits having 16 amps MCB/SFU in each circuit, 2 Nos. outgoing circuits having 30 amps MCB/SFU in each circuit each housed in D.C. panel itself. One main lighting feeder shall be connected to emergency load bus through emergency lighting contactors. The contactor will normally keep D.C. supply to the mini bus off, but in case A.C. fails it will automatically switch on the D.C. to emergency lighting. One no emergency lighting contactor rated for 415/230 V. A.C. and provided with two sets of contacts controlling D.C. emergency contactor. The DC contactor rated for 30 Volt controls D.C. emergency supply. The board shall be complete with wiring, cable glands, cable lugs for termination of outgoing and incoming circuits ,tenderer is desired to submit his own drawing for approval of the purchaser. Total 10 Nos. outgoing circuits shall be provided with MCB/SFU of different rating Short circuit capacity/ Breaking capacity (in KA) 6 KA at 0.7 P.f. terminations by Tinned copper lugs suitable for size of cable. MCBs shall comply following specifications as per IS 8828/1996. a. Rated voltage & freq. shall be 30V DC respectively for DP MCBs. b. Rated current shall be 32A/16 A as mentioned above. c. Rated short circuit capacity shall be min. 6 KA at 0.7 p.f. lag d. Service short circuit capacity shall be 6KA as per table 15 of IS: 8828 /1996. e. MCBs shall have fixed, un adjustable time / current characteristics. f. Under voltage release and shunt-trip release coils are not required. Only overload release and short circuit release shall be provided. g. Tripping time shall be as per (clause No. 8.6.1) table 6 of IS: 8828 /1996. h. MCBs shall be capable of carrying out given no. of operation cycles as per clause No. 9.11 of IS: 8828 /1996. i. Limits of temperature rise shall be as per (clause No. 9.8) table 5 of IS: 8828/1996. j. Standard range of instantaneous tripping shall be as per (clause No.5.3.5) table 2 of IS: 8828 /1996. MCB shall be suitable for mounting of fork type busbar of suitable size. MCBs shall be type tested & of approved make approved by AKVN All MCB outgoing terminals shall be terminated on terminal connectors provided at the bottom with suitable size of cable mention in bps. The enclosure shall be provided with proper earthing arrangement. Earthing arrangement shall consist of 2 G.I. Bolts of 12 mm (min.) with 2 spring/ plain washers and 2 check nuts. PVC cable glands of adequate size shall be provided for all incoming and outgoing cables. Indicating Instruments Principal requirements of indicating instruments are as follows Volt Meter. Voltmeter shall comply the following requirements Class of accuracy 1 Mounting Flush type Size 96x 96 mm 41 Range 0-600 volts Type Panel Mounting with 3 ½ Digital Display Voltmeter shall be guaranteed for free replacement for any defects within five years from the date of supply. Volt Meter selector switch: Voltmeter Selector switch shall be a seven-position rotary type ( 6 way & off) with 3 phase to phase & 3 phase to neutral position marked clearly on 48 x 48 mm brushed aluminium plate with black handle. The Switch should be screw mounting type with finger touch proof terminals. Terminal wire should be inserted from the side of the switch terminal. Terminal screw must be captive to avoid misplace during maintenance. The switch shall be of 12 A rating with insulation level of 1100 V. Indicating Lamps: Indicating lamps shall be panel mounting type 22.5 mm with rear terminal connections having LEDs display. Lamps shall have translucent lamp covers to diffuse lights, coloured red, yellow, green or blue as specified. The lamp cover shall be preferably of screw-on type, unbreakable and moulded from heat resisting material. All indications shall be bright LEDs having long life. Conventional bulbs are not acceptable. Earthing Arrangements Two nos. Earthing studs of galvanized M.S. 25 X 6 mm shall be provided for external earth connections at the bottom. These should be complete with plain washer, spring washer, nuts etc. Earthing Bolts must be welded to prevent removal of the same from the cabinet. Type Tests Certificates : MCBs & other components used in DCDB shall be fully type tested as per relevant IS and this specification. The successful Bidder shall furnish detailed type test reports before commencement of supply. The detailed Type Test Reports shall be furnished with relevant oscillogram and certified Drawings of the equipment tested. The purchaser reserves the right to demand repetition of some or all the Type tests in presence of purchaser’s representative at purchaser’s cost. All the Type Tests shall be carried out from laboratories which are accredited by the National Board of Testing and Calibration Laboratories (NABL) of Government of India such as CPRI Bangalore/ Bhopal, ERDA Baroda, to prove that the MCBs & other components used in DCDB meet requirements of the specification. The renderer should also furnish certificate from laboratories that laboratories are having all the requisite test facility available in house. The type tests reports conducted in manufacturers own laboratory and certified by testing institute shall not be acceptable. In case these type tests are conducted beyond 5 years of the date of opening of the tender, the successful bidder shall carry out these tests at NABL approved laboratory at their own cost.& submit the same before commencement of supply. Undertaking to this effect shall be submitted along with the offer without which the offer shall be liable for rejection. The successful bidder has to supply the complete material as per overall General Arrangement drawing approved by AKVN. Successful bidder shall submit the following detailed drawings along with component details/makes etc. for necessary approval. i. General Arrangement Drawing for DCDB. ii) Wiring Diagram. iii) Name Plate Drawing. iv) Danger Board Drawing 42 v) Bill of Material Inspection All tests and inspection shall be made at the place of manufacturer. The manufacturer shall provide reasonable testing and inspection facilities and cooperation without any charge to satisfy him that the material is being supplied is in accordance with this specification. The proto of DCDB shall be inspected & checked by AKVN along with his representative for approval before commencement of supply. TESTS & TEST CERTIFICATE: The type test certificates from reputed national level laboratories for the distribution box complete with suitable MCBs (as indicated in technical specification) for incoming and outgoing feeders giving the results of sample tests as per relevant BSS/ISS indicated below are required to be submitted along with the lot offered for inspection before despatch for approval in support of compliance of material to the specification and quality. Make of the MCBs to be used should be indicated in the offer. Acceptable make of MCBs are L&T, Siemens, Crompton Greaves, MAKE GIVEN IN Technical specification. a) Type test for Distribution Box as per BS 214/1959. b) All type & routine tests, except the Short Circuit Breaking Capacity Test shall be carried out on the MCCBs in accordance with IS:2516(Pt-I&II Sec.I)/1977 or its latest modification. The short circuit breaking capacity test shall be carried out. c) Test Certificate in respect of Type Tests, from standard testing laboratory like C.P.R.I. etc. should invariably be furnished in support of the quality LIST OF DEVIATIONS The Contractor shall state all the deviations from tender specification in his offer, if any. The offer shall be deemed to be in conformity with tender specification unless deviations from tender specification are clearly mentioned in this section. GUARANTEED PERFORMANCE REQUIREMENTS: The vendor shall guarantee satisfactory performance of the equipment supplied under all conditions and requirement as laid down by this specification. The contactor shall warranted the equipment and material will be new and accordance with the specification. It is free from defect, material, workman ship up to guan teed period. It is necessary for contactor to replace or the new in defective portion of the equipment. The repair and new part will be furnished by contactor free of cost. PACKING, DESIGN, MATERIALS & WORKMANSHIP PACKING AND MARKING: The material shall be packed as per manufacturers’ standard. Packing procedure shall be to the purchasers’ approval. The conductor shall be supplied in non-returnable strong Packing provided with lagging of adequate strength and displacement during transit, storage and subsequent handling and stringing operation in the field. The Packing shall generally conform to IS: 1778-1980, amendment No.1, June 1989, except otherwise specified hereinafter. Each packing shall have the following information stencilled on it in indelible ink along with other essential data: 43 I. Manufacturer’s Name II. Trade mark, if any III. Identification Number IV. Name of material V. Number of Packing on each item VI. Gross Mass of the Packing VII. Net Mass of Packing VIII. ISI or relevant International Standard specification mark, if any IX. Name and address of the Consignees PACKING CONDITION The material Packing shall be of such constructions as to assure delivery. The material of free from displacement and damage and should be able to withstand all stresses due to handling and the stringing operation so that the material surface is not dented, scratched or damaged in any way during manufacture, transport and erection. The material shall be properly lagged on the vehicles. The material should be suitable for wheel mounting. Before pad, cardboard or other suitable material shall be secured to The material inside flanges of the packing After loading, the exposed surface should be wrapped with suitable soft material e.g. polythene sheet etc. across the flanges to protect The material from dirt, grit and damage during transportation and handling and also prevent ingress of rain water during storage/transport. All wooden / other components shall be manufactured out of seasoned wood of good quality free from defect that may materially weaken the component parts of the packing Preservative treatment for anti-termite/anti-fungus shall be applied to the entire packing with preservatives of a quality which is not harmful to the conductor. QUALITY ASSURANCE PLAN The Bidder/ Supplier/ Vendor must estalish that they are following a proper quality assurance programme for manufacture of for item . The Bidder/ Supplier/ Vendor shall invariably furnish following information along with his bid. Information shall be separately given for item Statement giving list of important raw-materials, names of sub-suppliers for the rawmaterial, list of standards according to which the raw-material is purchased and copies of test certificates thereof. Information and copies of test certificates as in (i) above in respect of bought out items. List of manufacturing facilities available. Levels of automation achieved and list of areas where manual processing exists.List of areas in manufacturing process, where stage inspections are normally carried out for quality control and details of such tests and inspetions. List of testing equipments available with the Bidder/ Supplier/ Vendor for final testing of item specified and test plant limitation, if any, vis-a-vis type, special, acceptance and routine tests specified in the relevant standards. These limitations shall be very clearly brought out in schedule of deviations from specified test equipments. The successful Bidder/ Supplier/ Vendor shall within 30 days of placement of order, submit following informatuion to the Owner : List of raw-material as well as bought out accessories and the names of subsuppliers selected from the lists furnished along with Bid. Type test certificates of the raw-material and bought out accessories. 44 Quality Assurance Plan (QAP) with hold-up points for owner’s inspection. The quality assurance plans and hold-up points shall be discussed between the owner and agency before the QAP is finalized. The successful Bidder/ Supplier/ Vendor shall submit the routine test certificates of bought out items and form raw-material at the time of routine testing of item. The bidder/ Supplier/ Vendor shall invariably furnish following information along with his offer, failing which his offer shall be rejected. I. Statement giving list of important raw materials names of sub suppliers for the raw materials, list of standards according to which the raw materials are tested, list of tests normally carried out on raw materials in presence of supplier's representative and as routine and / or acceptance during production and on finished goods, copies of test certificates. II. Information and copies of test certificates as in (i) above in respect of bought out accessories. III. List of manufacturing facilities available. IV. Level of automation achieved and lists of areas where manual processing exists. V. List of areas in manufacturing process, where stage inspections are normally carried out for quality control and details of such tests and inspections. VI. List of testing equipment available with the Supplier for final testing of Conductor specified. In the case if the suppliers does not possess all the Routine and Acceptance testing facilities the tender will be rejected. VII. The OWNER reserves the right for factory inspection to verify the facts quoted in the offer. If any of the facts are found misleading or incorrect the offer of that SUPPLIER will be out rightly rejected and he may be black listed. VIII. Special features provided to make it maintenance free. 3. TECHNICAL SPECIFICATION FOR 11 KV AND 33 KV VACUUM CIRCUIT BREAKERS SCOPE This specification covers design, manufacturing, testing at manufactures works, supply of 11KV and 33 KV Vacuum Circuit Breakers complete with all accessories required for their satisfactory operation for the sub-transmission system of MPPKVVCL. The Breakers shall be used for Transformer protection or Feeder Control, in the system. TYPE AND RATING The circuit breakers shall be suitable for outdoor operation under the climatic conditions, as specified in Tender specification, without any protection from sun and rain. The circuit breakers shall have the following rating:- 45 S.No. PARTICULARS 33 KV 11 KV i) Number of Poles 3 Nos. 3 Nos. ii) Frequency 50 Cycles Cycles iii) Nominal System Voltage 33 KV 11 KV iv) Highest System Voltage 36 KV 12 KV v) Interrupting Capacity at nominal system 1500 voltage 350MVA vi) Rated Continuous Current 1250 Amps Amps vii) Short-time Current Rating for 3 Secs. 25 KA KA viii) Basic Insulation Level 170 KV ix) Power Frequency Withstand Voltage for one 70 KV Minute x) Total Break-time for any Current up to the 5 cycles (max.) rated breaking current xi) Control Circuit Voltage 30 Volt D.C. xii) Operating duty for gang operation O – 0.3 Sec – CO – 3 Min – CO xiii) The VCBs shall be suitable for one reclosing followed by one delayed re- closing and lock out 50 MVA 630 18.4 75 KV 28 KV Minimum clearances a) Between Phases 430 mm mm 280 b) Between Live Parts & Ground 3700 mm mm 2750 c) Creepage Distance 900 mm 300 mm The above are our minimum requirements. The suppliers may offer their standard design, keeping in view our minimum requirements. STANDARDS The circuit breakers shall comply with the requirements of IEC 56 or IS 13118 (1991) with latest amendment thereof, except wherein specified otherwise. Equipment, meeting any other authoritative standard, which ensures equal or better quality then the standard mentioned above, would also be acceptable. The bidders shall clearly indicate the applicable standards to which their equipments complieswith. A copy of such standard may also be enclosed. 46 GENERAL The circuit breaker shall be of porcelain clad vacuum type. The breaker, complete in all respect, shall be supplied with all accessories in-place and all internal wiring installed and terminated in the mechanism housing and the equipment shall be complete in all respects. The circuit breakers shall provide rapid and smooth interruption of current under all conditions, completely suppressing all undesirable phenomena, even under the most severe and persistent short-circuit conditions or when interrupting small currents or leading/ lagging reactive currents. The details of any device incorporated to limit or control the rate of rise of Restriking voltage across the circuit breaker contacts shall be stated. The over voltage caused by the circuit breaker switching on inductive or capacitive load shall not exceed 3.2 times the normal phase to neutral voltage. The total break-time for the circuit breaker, throughout the range of breaker operating duty, shall be stated in the tender and shall be guaranteed. The breaker shall be fit for capacitor switching for 5 MVA Bank. The breakers shall be provided with trip free mechanism. The circuit breakers shall be suitable for mounting on steel structures. The cost of necessary frames for mounting the circuit breakers shall be included in the offered prices. Strongly supported bracket or frame, for mounting associated 3 nos.11 KV / 33 KV CTs, shall also be provided. All the structures shall be hot dip galvanized with 3 dips. Please note that cantilever type supports for mechanism box are not acceptable. The mechanism box shall have firm supports from bottom. This is necessary to minimize vibration of mechanism box, which in turn may disturb various settings. The agency shall indicate clearly the vibration level of the breaker during fault / normal ON OFF operations in all three directions. The owner intends to operate 11 KV and 33 KV feeders with automatic re-closing scheme, the arrangement envisaged is as under:On the occurrence of a fault the concerned protective relay will open the circuit breaker as per its own characteristic. Thereafter, the breakers shall re-close but after pre-set time delay, which shall be adjustable (say range 4 – 10 sec. or near about). There shall be no further automatic re-closing. A simple type of re-closing relay (reputed make) for this purpose shall be provided under this kind of operation. It is also necessary that the breaker shall be suitable for this re-closing duty. The autore-closer relay is to be installed in respective indoor control panels. SPECIFICATION FOR CIRCUIT BREAKERS The circuit breakers shall consist of three identical phase units with a common operating mechanism. While offering the circuit breaker, the following details should be confirmed and furnished with the tender:i) Complete construction details of the equipment offered. It should be noted that the breakers should be suitable for out-door duty. Indoor breakers accommodated in out-door kiosks are not acceptable. ii) Type, make & source of vacuum bottles with relevant details shall be indicated in the offer, clearly. 47 iii) The capacity of breaker to interrupt inductive and capacitive currents shall be indicated in the offer (rating of capacitor bank should be stated and type test report shall be furnished). iv) Spare availability of vacuum interrupter should be confirmed by the bidder for the designed expected life of the breakers being offered. VACUUM INTERRUPTER The design of the vacuum interrupter shall be such that it gives trouble free operation under normal load and fault conditions throughout the life of the equipment. As the efficiency of the breaker depends on the degree of vacuum inside the interrupter, manufacturer shall ensure that the same is maintained consistently during service. To know the residual life of vacuum interrupter, an indicator to indicate the status of contact erosion shall be provided. The insulating ceramic body of the interrupter should have high mechanical strength and it should be capable of withstanding high temperature without any significant deterioration in its mechanical and electrical properties The metal/ alloy used for the fixed and moving contacts shall have very low resistivity and low gas content. They should be resistant to arc erosion and the contact should have no tendency to get cold-welded under the high vacuum in the interrupter. The interrupter design should ensure rapid de-ionization of the gap so that normal electrical strength of the gap is restored instantaneously. The metallic bellow or any other similar vacuum sealing arrangement should be provided at the moving contact and should have a long fatigue life. Manufacturer’s catalogue on vacuum bottle, indicating all the details shall essentially be submitted with the tender MOUNTING OF 11 KV / 33 KV C.Ts The offered steel structures for breakers to be supplied by the bidders should have provision and adequate strength to accommodate 3 nos. 11 KV / 33 KV C.Ts on it after provision of suitable supports from ground. Height of live terminals shall be 3.2 mts above ground. TEMPERATURE RISE The maximum temperature attained by any part of the equipment, when in service at site, under continuous full load conditions, exposed to the direct rays of the sun, shall not exceed 45° Centigrade, above ambient temperature. The limits of temperature rise shall be as per relevant standards. The corrections proposed shall be stated in the tender and shall be subject to approval of the owner. INSULATION OF THE CIRCUIT BREAKER The insulation to ground, the insulation between open contacts and the insulation between phases of the completely assembled circuit breaker shall be capable of withstanding satisfactorily di-electric test voltage corresponding to specified basic insulation level in the standard. INSULATORS The basic insulation level of the Insulator and insulating porcelains shall be as specified and porcelain shall be homogenous and free from cavities and other flaws. They shall be designed to have ample insulation, mechanical strength and rigidity 48 for satisfactory operation under conditions specified above. All insulators of identical ratings shall be inter-changeable. The puncture strength of the insulators shall be greater than the flash over value. The insulators shall be type tested from independent Govt. Laboratory as per relevant standards or at any recognized and reputed international laboratory or testing institutions. OPERATING MECHANISM The circuit breakers shall be designed for remote control from the control room and in addition there shall be provision for manual operation of circuit breakers during maintenance and for local tripping and closing by the normal means. The circuit breakers shall have operation control and mechanical “open” “close” indicator, in addition to facilities for remote electrical indication. The operating mechanism shall be of the spring charging type, by electric control under normal operation. The mechanism shall be trip free electrically and mechanically. The mechanism shall be capable of performing satisfactorily, the reclosing duty cycles indicated above, within the time specified. All working parts in the mechanism shall be of corrosion resistant material and all bearings, which require greasing, shall be equipped with pressured grease fittings. The mechanism shall be strong positive quick in action and shall be removable without disturbing the other parts of the circuit breaker. The mechanism and breaker shall be such that the failure of any spring will not prevent tripping and at the same time will not cause any false tripping or closing. The operating Mechanism should be motor operated spring charged type preferably without chain drive. The motor for spring charging shall be suitable to perform satisfactorily for input supply voltage of 230 Volt A.C. 50 Hz with a variation of plus 10 and minus 20 percent. The A.C. Motor should have overload protection. Provision should also be made for mounting of mechanism box at an adequate height and gear ratios shall be so chosen that one man should be able to charge the spring, without any additional efforts. CONTROL CUBICLE A common control cubicle shall be provided to house electrical, controls, monitoring devices and all other accessories, except those which must be located on individual poles. The cubicle shall be gasketed and shall have weather-proof construction, fabricated from sheet steel of minimum 2.5 mm thickness. The type test report on degree of protection test (IP-55) shall also be furnished. The cubicle shall have front access door with lock and keys, space heater, internal illumination lamp, 3 pins 5 Amp socket with individual ON-OFF switches shall be provided in the cubicle. For local operation following shall be provided:a) LOCAL / REMOTE selector switch b) TRIP / NORMAL / CLOSE control switches with pistol grip handle The control circuits shall be designed to operate on 30 Volt DC, as indicated in the schedule and it shall be possible to adopt to work on other voltages by simply changing the operating coils. The shunt tripping coils shall be designed to operate satisfactorily within 110% and 70% of the rated DC supply voltage and the shunt closing coils should operate up to 85% of the rated DC voltage. These checks shall be repeated during pre-commissioning checks at site before putting the breakers in service. AC Power supply for auxiliaries will be available at 230 Volt (+/- 10% variation) single phases 50 C/s at substation. The agency shall be required to extend this supply, using proper protection, to desired location through cable. 49 Necessary double compression type cable glands for the cables of the operating mechanism shall be provided. The cables used for operation are all un-armoured 2.5 sq. mm copper control cables of 1100 V grade. The cable glands shall be suitable for 1 no. 8 core and 2 nos. 4 core cables and cables as per site requirements. The gland plate should be made of non-magnetic materials and suitably drilled at site to suit the cable entry. The Circuit breaker shall be provided with trip free Mechanism so that tripping instructions could over-ride the closing instructions. An additional tripping coil shall also be provided in the trip circuit. The second coil shall have separate tripping lever arrangements in the mechanism, so as to avail full advantage of second trip coil. Also the two trip coils shall have separate fuses in the DC circuit, so that in the event of any short circuit/damage in any one of the trip coils, the supply is available to the other one. The circuit diagram of Control circuit of VCB along with operating instructions (DOS/ DON’T) shall be embossed on metallic plate duly laminated and the same shall be fixed on the rear door of the control cubicle from inside. WIRING Wiring shall be completed in all respects to ensure proper functioning of the control, protection, monitoring and interlocking schemes. All the wiring shall be carried out with 1100 V grade, PVC insulated stranded copper conductor of 2.5 sq. mm as per IS: 1554. Each wire shall be identified at both ends with permanent markers bearing wire numbers as per wiring diagram. Wire termination shall be done with crimping type connectors with insulating sleeves. Wires shall not be spliced between terminals. All spare contacts of auxiliary switches etc. shall be wired up to terminal blocks in the control cubicle. TERMINAL BLOCKS Terminal blocks shall be of 1100 V grade, box clamp type ELMEX 10 sq. mm or approved equivalent. Not more than two wires shall be connected to any terminal. Spare terminals, equal in number to 20% of active terminals, shall be provided. Terminal block shall be such located to allow easy access. Wiring shall be so arranged that individual wires of an external cable can be connected to consecutive terminals. TERMINAL CONNECTORS 6 Nos. Terminal bi-metallic connector suitable for Dog conductors shall be supplied with each breaker. For ensuring quality and uniformity, the owner may decide to specify the design of terminal connector, the material of terminal connector and thickness of clamps. Further compliance of which will have to be done by the agency without any extra cost. Suitable earth connector for earthing connections shall also be supplied. The connector drawing shall be got approved from the owner. AUXILIARY CONTACTS Eight numbers each of auxiliary contacts both of the normally open and normally closed types shall be provided in each circuit breaker for use in the remote indication and control scheme of the circuit breaker and for providing safety interlocking. Special contacts for use with trip coils, which permit for relative adjustment with respect to the travel of the circuit breaker contact, shall also be provided, wherever 50 required. There shall be provision to add more auxiliary contacts at a later date, if required. ACCESSORIES The vacuum circuit breaker shall be supplied as a complete unit with internal wiring installed and terminated in mechanism box and equipped with the following accessories :1 Motor operated spring charged mechanism 1 No. (Motor voltage – 230 V AC) 2 Trip coil suitable for 30 V DC 2 Nos. 3 Closing Coil suitable for 30 V DC 1 No. 4 Pistol grip C.B. Control switch having Trip/ Normal/ 1 No. Close position 5 Local/ Remote selector switch 1 No. 6 Spring Charged indicator 1 No. 7 Manual operating handle for maintenance 1 No. 8 Facility for manual charging of spring 1 No. 9 Operation counter 1 No. 10 Auxiliary contacts (8 NO-8 NC) 1 Set 11 Anti-pumping device suitable for 30 V DC 1 No. 12 Terminal connectors suitable for connecting Dog 6 Nos. Conductor 13 Cubicle illuminating lamp with cage and switch 1 No. 14 Spare terminals connectors 20% of Total Terminals 15 Mechanical ON/OFF Indicator 1 No. 16 MCB for both AC and DC supply 1 No. each 17 Space heater and ON-OFF switch in the mechanism box 1 No. 18 Power Type 3 Pin Socket with ON-OFF switch 1 Set 19 Earthing Terminals 2 Nos. 20 LED indicating lamps Complete set Other standard accessories which are not specifically mentioned above, but are required for efficient and trouble free operation of breaker, should also be provided, without any extra cost. Indicating Bulbs: The indicating lamps should be supplied with Low Voltage protection Circuit (LVGP) and surge suppressor circuit having LED indication. Lamp assembly should be of fire – retardant glass epoxy PCB, industrial heat resistant, fire resistant, non- Hygroscopic DMC material , chrome – plated corrosion resistant solid brass bezel , polycarbonate lens in desired colour shades of Red , Green, Amber, Yellow etc. the intensity of light should be minimum 100 mcd at 20 mA . Indication lamp should be suitable to operate on 30 V Direct Current supply source. Acceptable make are BINAY Opto Electronic Private Ltd. or equivalent. TYPE TESTS Type test certificates on VCB for the following tests, strictly as per IS 13118, with latest amendment thereof, from any of the independent Govt. Laboratory, or at any recognized and reputed international laboratory or testing institution, shall invariably furnished : Short Circuit Duty Tests 51 4. Short Time Current Rating Tests Mechanical Endurance Test Temperature Rise Test Lightning Impulse Voltage withstand Test Capacitor Switching Duty Test for Single Bank of 5 MVAR capacity Power Frequency withstand Voltage Test dry & wet Degree of protection IP-55 for control cubicle The above type test certificates must accompany drawing of type tested equipment, duly signed by type testing authority. The above tests must not have been conducted on the equipment earlier than 5 years from the date of opening of bids. In case of any change in design/type of Breaker already type tested and the one offered against this specification, the owner reserves the right to demand repetition of type tests, without any extra cost. ACCEPTANCE AND ROUTINE TESTS All acceptance and routine tests, as stipulated in relevant standards, shall be carried out by the supplier, in presence of owner’s representative. Immediately after finalization of the programme of type testing, the suppliers shall give, fifteen days advance intimation to the owner, to enable him depute his representative for witnessing the tests. RATING PLATES The detailed rating plate shall be as per IS and in addition, shall indicate serial number of the equipment, manufacturer’s name, our order number and date. EXPERIENCE Minimum 3 years experience in the field of design and manufacture of the equipment offered is essential for the bidder. Details in this regards shall be clearly stipulated in the offer. GUARANTEED TECHANICAL PARTICULARS AND TECHNICAL QUESTIONNAIRE Proforma of guaranteed technical particulars and Technical Questionnaire are enclosed with the tender specification. Bidders are required to furnish clear replies to both the questionnaire and the particulars. In case of incomplete or ambiguous replies, the offer is liable to be rejected. TECHNICAL SPECIFICATION FOR INDOOR CONTROL & RELAY PANELS FOR 11 KV & 33KV VCBs SCOPE: This section contains the technical specification for the Indoor Control, indication, relay and metering panels associated with the outdoor switchgear for use at various sub-stations. The control and relay panels and other requirements specified under this section shall be complete in themselves with all main and auxiliary relays, fuses, links, switches, wiring, labels, terminals blocks, earthing terminals, foundation bolts, illumination, cable glands etc. PANEL FINISH AND COLOUR: The owner has standardized that the colour finish of control panel shall be opeline green as per colour no. 275 of BS: 381C (1948). Equivalent colour as per relevant Indian Standards or any other standard shall be acceptable. This colour finish shall be applied to all the exterior steel work of the panels. The exterior finish shall be semi-glossy only and shall not be fully glossy. The interior of the panels shall be painted with egg shell white. 52 PROTECTIVE RELAYS AND INSTRUMENTS: The protective relays shall be manufactured, tested and supplied with the guaranteed particulars, as per following Indian Standard Specifications with latest amendment thereof :i IS-3842 (Part-I) 1967 Application guide for electric relays for A.C. Systems over-current relays for Feeders and Transformers ii IS-3842 (Part-IV) 1967 Application guide for electric relays for A.C. System thermal protection relays iii IS-3231 (1965) Electric Relay for Power System Protection iv IS-1885 (Part-I & II) Electro-technical vocabulary Electrical Relays & Electrical Power System Protection v All indicating instruments shall conform to IS-722 or BS-89 The equipment meeting any other authoritative standard which ensures equal or better quality than the standards mentioned above shall also be acceptable. Equipment for which Indian Standards are not available the relevant British Standards and IEC recommendations will be applicable. STATIC/ MICRO-PROCESSOR BASED OVER CURRENT & EARTH FAULT RELAY: Static/ Micro Processor based non-directional triple pole IDMT over current and earth fault relays with 2 over current and 1 earth fault elements. However for transformer protection control panel the relay shall have all the three over current elements. Relays shall be suitable for 5 Amp. C.T. secondary current and 30 Volts DC auxiliary supply with 1.3/0.6 seconds operating time at 10 times current setting and instantaneous cut off features with setting 4 to 10 times of rated current with arrangement to by pass the features, when not required. The relay shall conform to following specifications:CURRENT SETTING RANGE: 50% to 200% in seven equal steps of 25% for over current elements. 10% to 40% in seven equal steps of 5% for earth fault element. However, setting in more than seven steps will be preferred. Further, change of settings under load condition should be possible without interruption of feeder. Resetting Current : More than 90% of setting value. Transient over reach less than 3% on maximum and 5% on minimum setting for primary source angle upto75degree .Time of operation 30 seconds at times setting. Over shoot time of maximum 80 secs. at 10 times current. Pick Up Current: 1.1 times the current rating. Operating Time: 1.3/0.6 secs at 10 times current with time multiplier 1.0. The setting should be in 10 times more, fixed calibrated steps from 0.01 to 1.0 and in between variable separately for over current and earth fault relays. Resetting Current: More than 90% of setting value. Resetting Time: Less than 5 msec. Burden: Less than 1 VA. Accuracy: Clause 5 Contacts :Two sets of NO contacts (for Trip and Annunciation) self rest type suitable for make and break having continuous rating 1250 W/VA and 30 W/VA respectively. 53 Operational Indicator: Should be provided by way of LED for, ON, O/C 1, O/C 2, E/F, and should fulfill the following requirements: Must give permanent visual signal after fault is cleared and relay has been reset. Should operate with pulse time of less than 20 m sec. Should not give indication until the trip pulse is being executed. Other: Facility to re-set indicating lamp manually should be provided. During testing / calibration of relays, facility for blocking tripping should be provided. Facility for self-monitoring / test should be provided, so that hardware and software are constantly monitored and irregularities are immediately detected and signalled. In case of non-draw out type relays test socket along with test prob should be provided, so that calibrated current and values are checked as also current can be injected through and adaptor. Since the static relay are being procured by us to replace existing Electro Mechanical relays the relays should be provided with a blanking plate of 18 SWB MS sheet having dimension of 550x250mm and duly painted with gray paint. TYPE TEST CERTIFICATES FOR RELAYS: The bidders should submit the following type test certificates in respect of relays offered by them for their control panels: KV Impulse peak voltage test on the relays. This type test report is essential for over current and earth fault relays. Type test report for vibration test to prove the stability of relays under vibration normally encountered and also vibration under abnormal conditions. Type test report for overshoot time for IDMT relays. NOTE: Regarding testing of the relays, reference may please be made to BS - 142 19. The tenders not accompanied with the above type test reports shall be rejected. PANEL CUT OUT AND DIMENSIONS i) The panels shall be fabricated from 14 SWG steel sheets free from all surface defects. The panels shall have sufficient structural reinforcement to ensure a plain surface to limit vibration and to provide rigidity during dispatch and installation. All control panels and switchgear cubicles shall be made absolutely vermin-proof and subjected to the approval of the owner. Pre-treatment & painting of panels shall be done as per the procedure detailed at Sr. No. 21 of this schedule. ii) The panels shall have the following dimensions:Height 1475 mm Width 700 mm Depth 300 mm No deviation in height/ depth will be permitted. However, width can be increased depending upon the actual requirement, which shall be subjected to approval from the owner. iii) The preferred panel cut out dimensions for mounting of the relays shall be as per Indian Standard Specification IS-4483 (Part – I & II). iii) The design, material selection and workmanship shall be such as to present a neat appearance, outside and inside with no works of welds, rivets, screw or bolt heads apparent from the exterior surface of the Control Panels. PANEL LIGHTING 54 a) For interior illumination, an incandescent lamp/ 2 feet fluorescent tube operating at 230 Volt 50 Hz with switch shall be provided in each panel. The lamp/ tube shall be located at the ceiling and guarded with protective cage. The switch shall be mounted on one of the side walls and shall be easily accessible. b) One 5 Amp. 3 Pin receiptable with plug, switch and fuse shall be provided in each control panel. AUXILIARY SUPPLY a) For each Control Panel, the owner will provide the following:i) 230 V plus 10% minus 20%, 50 Hz neutral grounded A.C. supply. ii) 30 V ± 10% D.C. Supply. b) H.R.C. fuses shall be provided by the agency for both the A.C. and D.C. power supplies. c) All H.R.C. fuses and links shall be with holder. The base of fuse holder shall be mounted on slant support and with identification labels. CONTROL WIRING a) The agency shall provide complete wiring up to the terminal block for the equipment, instrument devices mounted in the control panel strictly according to the wiring diagram prepared by the bidder based on the owner’s information and schematic diagram and get approved from the owner. b) The wiring shall be completed in all respects so as to ensure proper functioning of the control, protection and metering schemes. Agency shall supply, lay and terminate all the control cables between VCB panel, Control panel (Indoor) and CT. c) All spare contacts of relays and switches shall be wired up to the terminal block. d) The Control Panels shall be supplied completely wired ready for owner’s external connections at the terminal blocks. For CT circuits the wiring shall be carried out with 1100 V Grade PVC insulated stranded copper conductor of size 2.5 sq. mm. For PT circuits and also for control circuits, the wiring shall be carried out with 1100 Volt Grade PVC insulated stranded copper conductor of size 1.5 sq. mm. e) Colour coded wires should be used to facilitate easy tracing, as under:I. Three Phase A.C. Circuit:Red for R Phase Yellow for Y Phase Blue for B Phase Black for Neutral II. Single Phase A.C. Circuit:Red for Phase Green for Earthing Black for Neutral III. D.C. Circuit:Red for Positive Black for Negative IV. Control Wiring:Gray for annunciation and other control circuits. 55 f) Each wire shall be identified at both ends with wire designation number by plastic ferrules, as per wiring diagram based on latest revision of IS-375 to denote the different circuit functions. The agency shall take approval for the system of wire numbering. g) All wire termination shall be made with solder less compression type connectors. Wires shall not be tapped or spliced between terminal points. All wire shall have crimp type termination and direct connection at any place is not at all required. h) All series connected devices and equipment shall be wired-up in sequence. Loop-in/loop-out system of wiring shall be avoided, as far as possible and the common buses shall normally be made through the terminal block for better reliability of testing and maintenance. i) Fuses and links shall be provided for isolation of individual circuit from the bus wires without disturbing the other circuits’ and equipments. j) The DC trip and DC voltage supplies and wiring to main protective gear shall be segregated from these for back up protection and also for protective apparatus for special purposes. Each such group shall be fed through separate fuses, either direct from main supply fuses or the bus wires. k) Since a number of wires will run from one point to another, it is desired that the support arrangement should be adequate and neat. The conventional method of bunching of wire should not be adopted, since the same may create problems in case any wire is required to be removed. The wires should be accommodated in plastic channel with sliding plastic cover mounted inside the panel, suitably. Inspection/removal of wires should be possible by sliding the covers. l) Blank plastic channels should be provided by the sides of the panel to accommodate the incoming cables from switchyard through the cable glands. m) The circuit diagram of control circuit along with operating instructions (DOS/DON’TS) embossed on metallic plate duly laminated shall be provided on rear side of the door. TERMINAL BLOCKS a) Multi-way terminal blocks complete with necessary binding screws and washers for wire connections and marking strips for circuit identification shall be provided for terminating the panel wiring and outgoing cables. The terminal block shall be suitable for receiving at least 2×7/0.737 mm stranded copper conductor wire per terminal. b) Terminal blocks shall have shorting and disconnection facilities. The panelside and outgoing wires should be dis-connectable just by opening the disconnecting links which slide up or down without dislodging the wires from their position. Asea-Kirloskar type sliding links shall be provided. However, dis-connectable type terminal connectors may be limited to CT & PT circuits only. c) The terminal blocks shall be grouped according to circuit functions and each terminal block group shall have at least 20% spare terminals. CABLE ENTRY a) The control panel shall have provision of cable entry from the bottom. One no. cable gland for 8 cores and 2 nos. for 4 core 2.5 sq mm un-armoured cables duly fitted in gland plate and covered shall also be provided. The agency will arrange for necessary floor opening, below the panels to suit the 56 requirement. Agency shall also be responsible for laying of control cable in trench, floor opening below the panel, trench cutting and making the damages good as per the satisfaction of Engineer in charge inside the control room. b) The wiring through terminal blocks shall be such located so that it is convenient for floor opening. c) The control panel shall have provisions inside for fixing the multi-core cable glands which shall be included by the bidder in scope of supply. For fixing these cable glands, detachable gland plates of 4 mm thickness shall be mounted at least 200 mm above the floor level. d) The cable gland plate and rear door shall be properly gasketed. e) Rigid supports shall be provided along the terminal block for holding plastic channel. Suitable clamps may also be provided in plastic channel for holding cables. GROUNDING a) 25 mm × 6 mm copper round bus shall be provided extending along with the entire length of the panel and effectively grounding all metal structures. The earth bus should be designed for suitable inter connection with adjacent control panel which are to be placed side by side in the control room. b) Each continuous length of ground bus shall have provision of two terminals at two separate points for connection to ground. c) Potential and Current transformer neutrals shall be grounded only at the terminal blocks where they enter the control panel from the transformer. d) Wherever a circuit is shown grounded in the drawings, a single wire for the circuit shall run independently to the ground bus and connected to it. DOORS Each panel shall be completed with end enclosing sheets on both sides and door in the rear. There shall be one door with handle and also turn twist locks at top and bottom. Proper gasketing shall be provided on the door. A type test report from the recognized Govt. Laboratory on degree of protection test (IP-55) shall also be furnished with the tender. The doors should be grounded with flexible braided copper conductor of 10 sqmm. CONTROL AND RELAY PANELS The control panels required for installation at all the sub-stations shall be of simplex type. The control and indication apparatus, all meters and relays shall be mounted in the front. The instruments and relays shall be flush pattern. The labeling for the circuits shall be provided at the front control panel, as well as on the inside wall. All indicating instruments, meters and important components shall have identification labels from inside also, in addition to outside. The terminal block shall also have identification labels to them, clearly indicating phase’s identifications and also circuits and instruments identification. For example, the terminal connector shall have an identification indicating that CT circuit for metering, for protection etc. Labeling should be provided by using 2 mm thick aluminium strip embossed with desired information and fitted in the panel sheet by means of rivets. PROTECTION SCHEME The protection schemes to be supplied under this control shall cover the following equipments: a) Transformers 57 b) Overhead sub-transmission lines The protection schemes are described in the following clauses:Transformer Protection :Transformer Control Panel is required for control/ protection on both33KV and 11 KV sides of 33/ 11 KV transformers. This will be in the form of a relay set having 2 Nos. O/C and 1 No. E/F elements in11KV Control Panel. In 33 KV Control Panel the relay set shall have 3 Nos. O/C elements alongwith numerical differential protection relay. The current settings of O/C relay elements shall be from 50 to 200% and of E/F relay element from 10 to 40%. They shall be suitable to work on 30 Volt D.C. supply. The secondary rating of C.T. shall be 5 Amps. The over current and earth fault relays shall have operating time of 1.3 sec. at 10 times of plug setting current. The relays shall be of draw out type with CT shorting facility. Further, the relays shall have self re-set contacts and hand re-set flag arrangement. Besides this provision for alarm and tripping due to Buchholtz relay operation, OTI and WTI may be kept in the panel. Tripping on OTI, WTI and Buchholtz operation is also needed for both 33 KV and 11 KV transformer breakers panels. Feeder Protection:a) Feeder Control Panel is required for control/ protection of both 33 KV & 11 KV sub-transmission lines. This will be in the form of a relay having 2 Nos. O/C and 1 No. E/F elements. The current settings of O/C relay element shall be 50 to 200% and of E/F relay element 10 to 40%. They shall be suitable to work on 30 Volt D.C. supply. The secondary rating of C.T. shall be 5 Amps. The over current and earth fault relays shall have operating time of 0.6 sec. at 10 times of plug setting current (in case of 11 KV Control Panels) and 1.3 sec. at 10 times of plug setting current (in case of 33 KV Control Panels). In this case also, the relays shall be of draw out type with C.T. shorting facility. Further, the relays shall have self re-set contacts with hand reset flag arrangement. b) The feeder control panel shall also have auto re-closing scheme. The re-closing relay time shall be adjustable between 4 to 10 sec. or near about in case of 11 KV Control Panel. In case of 33 KV Control Panel the re-closing relay time shall be adjustable between 10 sec. to 60 sec. for 1 st shot and 30 to 180 sec. for 2 nd shot after the repeat of tripping pulse from the protective relay. Suitable adjustment knob for the same shall be provided on the front of the relay for this purpose. CONTROL AND INDICATING CIRCUITS The control and relay panels shall have the following instruments, relays and accessories:1 no. - 3 Pole static type / software based relay, flush pattern, having 3 Nos. O/C element (settings 50 to 200%), suitable for operation on 30 V DC and 5 Amp. CT secondary rating (for 33 KV Transformer Control Panel).The relay shall have operating time of 1.3 seconds at 10 times of plug setting current, as mentioned above. 1 no. - 3 Pole static type / software based relay, flush pattern, having 2 Nos. O/C element (settings 50 to 200%) and 1 No. E/F element (settings 10 to 40%), suitable for operation on 30 V DC and 5 Amp .CT Secondary rating (for 33 KV Feeder Control Panel, 11KVFeeder Control Panel and 11 KV Transformer Control Panel). The relay shall have operating time of 1.3/ 0.6 seconds at 10 times of plug setting current, as mentioned in above para. 58 1 Set – provision for alarm and tripping due to Buchholtz relay operation, OTI and WTI may be kept in the 33 KV transformer control panel. 1 Set - Auto re-closing relay with adjustable time delay between 4 seconds to 10 seconds. (for 11 KV Feeder Control Panel only). 1 Set - Auto re-closing relay with adjustable time delay between 10 seconds to 60 seconds for 1st shot and 30 to 180 seconds for 2 nd shot (for 33 KV Feeder Control Panel only). 1 no - Relay for OTI, WTI and Buchholtz operation tripping – both in 33 KV and 11 KV Transformer breaker panel. 1 no - Fully static energy meter for incomer and outgoing feeder energy and system parameters indication and record. 1 no - Auto/ manual selector switch (for panels with auto re-closing relays). 1 no - Circuit Breaker Control switch (Push Button type) having Trip/ Neutral/ Close positions. 4 nos - Lamps for circuit breaker “ON”, “OFF”, “TRIP CKT HEALTHY” and “AUTO TRIP” indications. LED indicating lamp complete with static circuits and features should be supplied with Low voltage protection circuit (LVGP) and surge suppressor circuit having LED indication. Lamp assembly should be of fire – retardant glass epoxy PCB , industrial heat resistant, fire resistant, non hygroscopic DMC material, chrome – plated corrosion resistant solid brass bezel, polycarbonate lens in desired colour shades of Red, Green , Amber, Yellow etc. the intensity of light should be minimum 100 mcd at 20 mA . Indication lamp should be suitable to operate on 30 V direct current supply source. Acceptable make are BINAY Opto Electronic Private Ltd. or equipment. 1 no- Ammeter 96 sqmm .Square MISC type flush pattern having class 1.0 accuracy. The ammeter shall have dual scale 0-200/100 Amps. or 0-300/150 Amps as per requirement. 1 no- Ammeter select or switch to indicate current in three R, Y and B phases. 1 no-Voltmeter 96 sqmm. Square MISC type flush pattern having class 1.0 accuracy with selector switch (for Transformer Control Panel. (The range of Voltmeter shall be 0-15 KV for 11 KV Control Panel and 0-40 KV for 33 KV Control Panel). 1 no - Alarm bell for circuit breaker trip alarm. 1 no - Alarm cancellation relay for C.B. trip alarm 2 nos - Push Buttons for alarm “ACCEPT” & “RESET” 1 no - DC Failure Visual indication by way of providing a lamp. 2 no - Push Button for testing healthy condition of trip circuit. (Separate circuits for Supervision of healthiness of two trip coils are required. Accordingly, the DC circuit complete with fuses etc. shall be separate for the two trip coils). 1 no – Illumination lamp with cage and switch. 1 no - Space heater with associated ON-OFF switch. 1 no - Power type 3 pin 5 Amps plug and socket with ON-OFF switch and fuse. A trip healthy lamp shall be provided for each circuit breaker and connected in such a way as to indicate the healthy condition of the trip circuit. The lamp should have the indication on demand when breaker is on. Such indication is also necessary when the breaker is off, but it should be possible to check the trip circuit condition 59 before closing the circuit breaker. In brief, pre and post close trip supervision facility on demand is required and shall be included. The automatic tripping of the circuit breaker due to operation of protective relays shall be indicated by a common audible alarm. The audible alarm shall be cancelled by the flag cancellation of relay, in case of relays of hand-reset type. Space shall be provided for provision of KWH meter, with proper sealing. NOTE: - Any other indications which are required for proper protection/ operation of circuit breaker should be provided in control panel, without any extra cost. RELAYS All relays except where otherwise approved ,shall be capable of breaking the maximum current which shall not be affected by vibration or by external magnetic fields. The contacts shall be of silver, platinum or other approved materials and shall be capable of repeated operation, without deterioration. All relays, which are connected to complete the tripping circuit breaker coil of the auxiliary tripping relay shall be provided with approved flag indication, which whenever possible, shall be mechanically operated type. Indicators shall also be provided on such additional relay elements as it will enable the type and phase of the fault condition to be identified. Each indicator, whether of the electrically or mechanically operated type, shall be capable of being reset by hand, without opening the relay case. Each indicator shall be so designed that it cannot move before the relay has completed its operation. It shall not be possible to operate any relay by hand without opening case. All relays shall be so arranged that on opening the case it shall be impossible for any dust, which may have collected in or upon the case to fall on the relay mechanism. Over current relays shall be of static type / software based and shall have inverse definite minimum time limit characteristics with separately adjustable time and current settings. Unless otherwise approved, the definite minimum time shall be continuously variable from 0.2 seconds and current setting range shall be variable between 50% and 200% in six equal steps of 25% each. The relay rating shall be 5 Amps. All relays shall be of draw out type and also that O/C and E/F relays shall have characteristics 1.3 second for protection of transformer on both primary as well as on secondary sides and 0.6 second characteristics for protection of 11 KV feeders. In case of 33 KV feeder protection, the characteristics operating time shall be 1.3 seconds. Further, these relays shall have self re-set contacts with hand re-set DC operated flag arrangement. All main protection relays shall be numerical and suitable for SCADA connectivity with IEC 61850 protocol. Type test certificates for relays shall be submitted. INSTRUMENTS All indicating instruments shall conform to IS – 1248 and shall be of types and sizes specified under Sr. No. 15 above. They shall be capable of carrying their full load currents continuously without heating. They shall have long clearly divided and indelibly marked scales of engraved or enamelled metal and the pointers shall be of clean outline. The pointers and scales shall be subject to approval. The marking on the dials shall be restricted to the scale marking. All indicating instruments, shall be provided with non-reflecting glass type fronts. All indicating instruments shall be of class 1.0 accuracy. Type test certificate for Ammeter and Voltmeter shall be submitted. 60 The following may be carefully noted :i) The components of alarm scheme shall be strictly in accordance with tender specification and shall be explained very clearly. The alarm scheme is required with Transformer Control Panel only. ii) The scheme incorporated should ensure that flag resetting of relay is “self-hand operated” type. Thus it should not be necessary to reset the flag at the time alarm/ annunciation is accepted in case of fault. It should be possible to separately reset the flag, after the fault is attended. The automatic tripping of the circuit breakers due to operation of protective relays shall be indicated by audible alarm. The offered alarm scheme shall be complete in all respects including one DC bell for trip alarm with a connector/ auxiliary relay suitable to handle breaking of DC bell current. The contactor/ auxiliary relay will get energized through the self-reset alarm contact of protective relay and will remain actuated by its own seal-in contact. A push button shall be provided to accept the alarm by breaking the seal-in circuit. TESTS Each control panel shall be completely assembled, wired, adjusted and tested at the factory prior to dispatch. The tests shall include wiring continuity tests, insulation tests and functional tests to ensure operation of the control scheme and individual equipment. The test procedures shall have prior approval of the owner. All instruments, meters and relays shall be tested and calibrated in accordance with relevant standards. All auxiliary instrument transformers shall be tested in accordance with procedure as laid down in relevant standards. TEST WITNESSING The tests shall be performed in presence of owner’s representative. The agency shall give at least fifteen (15) days advance notice of the date when the tests are to be carried out. TEST CERTIFICATE Copies of test certificates for all routine and acceptance tests shall be furnished to the owner for approval before despatch of the equipment from the works. Test certificates for important components used shall also be furnished along with drawings. PRE-TREATMENT AND PAINTING PROCESS The control panel sheet steel shall be subjected to pre-treatment process before painting. The process shall be carried out as under. The procedure can broadly be divided as “Metal Treatment” and “Painting”. A. METAL TREATMENT i. Degreasing This can be achieved either by immersing in hot alkaline degreasing bath or in hot dry chlorothelene solution. In case, degreasing is done by alkaline bath, rinse with cold water thoroughly. ii. Pickling iii. This is to remove rust and metal scales by immersing in diluted sulphuric acid (approximately 20%) at nearly 80°C until scale and rust are totally removed. iv. Rinse in cold water in two tanks to remove traces of acids. 61 v. Treat with phosphoric acid base neutralizer, for removal of chlorine from the above acid pickling and again wash with running water. vi. Phosphating vii. Immerse in grenadine Zinc phosphate solution for about 20 minutes at 80 to 90°C. The uniform phosphate coating of 4 to 5 gms. per sq. meter shall be achieved. viii. Swill in cold water. ix. Rinse in decxy to bath at 70 to 80°C to neutralize any traces of salts. x. Seal the above phosphate coating with hot dilute chromate solution. xi. Dry with compressed air B. PAINTING xii. Spray one coat wet on wet specially developed, “High Lusture” Zinc chromate primer and stove at 150 to 160°C for 25 to 30 minutes. Alternatively, Red-oxide primer with chromate content may be used. However, former process is preferred. xiii. Rubbing and putting :xiv. Apply putty to fill up the scar, if any, to present smooth surface and stove 15 to 20 minutes. Apply putty several times to get perfectly smooth finish. xv. Surfacing :xvi. Sand down with mechanical abrasive and stove for 20 minutes. xvii. Primer :xviii. Spray second coat of primer as per (i) above or grey primer surface wet on wet and stove for 30 to 40 minutes at 150°C. xix. Finish Paint :xx. Rub down dry and spray first coat of synthetic enamel finish paint wet on wet and stove for 30 minutes. xxi. Surfacing :xxii. Sand down or rub dry to prepare for final finish. Spray 2 coats o synthetic enamel finish paint wet on wet and stove it at 150°C for 30 minutes. NOTE :(a) Necessary stiffness may be welded between large cut outs to provide rigidity before painting process. (b) Painting process shall be done within 24 Hrs. of completion of metal treatment. (c) Small coating shall be supplied along with equipment for touching up at site. 5. TECHNICAL SPECIFICATION OF 30V, 10 AMP BATTERY CHARGER SUITABLE FOR 30V 100AH LEAD ACID BATTERY SCOPE This specification covers design, manufacturing, testing at manufacturer’s works before dispatch and supply of 30 Volt 10 Ampere Single Phase 62 Manually Controlled ,Battery Charger required for charging of 30 Volt 100 Ampere-Hour Lead Acid Battery and for feeding auxiliary supply to Switchgear equipments at 33/11 KV substations. CLIMATIC CONDITIONS The climatic conditions at site, under which the equipments shall operate satisfactorily, are mentioned as under: 45oC 4 0C 95%(sometime approaches saturation point) iv) Minimum relative humidity 10% v) Average number dust storm days per 40 days annum vi) Average number of rainy days per annum. 90 days vii) Number of months of tropical 3 months Monsoon conditions viii) Average annual rainfall 1250 mm ix) Maximum wind pressure 150 Kg/ Sq.mm x) Altitudes not exceeding 1000 meters. The limit of ambient temperature shall be 450C peak and 350C average over a period of 24 hours. i) ii) iii) Maximum temperature of air in shed Minimum temperature of air in shed Maximum relative humidity: STANDARDS Unless otherwise specified, the equipment shall conform to the latest applicable Indian standards and in particular to the following standards:1 IS:3895 Specification for Rectifier equipments in general 2 IS:13947 Specification for MCB (Part II) 3 IS:1248 Indication instruments 4 IS:2147 Degree of protection for cubicles 5 IS:375 Specification for wiring 6 IS:4540 Mono crystaline semiconductor rectifiers assemblies and equipment 7 IS:6619 Safety code for semiconductor rectifier equipments 8 IS:2026 Transformers 9 IS:4237 General requirement for switchgear and control gear for voltage not exceeding 1000 Volt 10 IS:4064 Air Break switches and fuse combination units 11 IS:6005 Code of practice for phosphating of Iron & Steel 12 IS:5 Colour for ready mix paints 13 IS:5921 Printed circuit Board 14 IS:249 Printed circuit Board 15 IS:5578 Guide for making insulated conductor The supplier shall clearly state the standards to which the equipment offered by him conforms. 6. DRAWING AND LITERATURE 63 The bidder shall furnish all such drawings, instruction manuals, descriptive literature etc., as may be necessary for the proper understanding of the functioning of the charger. The write-up should include the following:i. Technical specification of the charger. ii. Detailed circuit description of the charger. It should also include the functions of various components, protection circuits/ cards, relays along with their individual brief write-ups/ leaflets. iii. List of the main components of the charger. iv. Following details are to be clearly indicated in the circuit diagram:Make and Rating of components used v. All the fuses should be numbered and individual rating should be indicated. GENERAL DESCRIPTION The Charger shall be of simple design so as to ensure its reliable functioning and ease in maintenance/repairing. Complicated circuitry shall be avoided, as for as possible. The bidder shall indicate, as to how reliable functioning of the charger is achieved. He shall also indicate the quality control adopted for the reliable product. The battery charging equipment shall comprise of solid state silicon rectifier suitable for operation on 230/250 Volt Single Phase A.C. system. Associated transformer, regulatory resistances, switches etc. shall be accommodated in a sheet steel cubicle arranged for continuous load of 3 Amps, adjustable from 0 to 3 Amps, trickle charge of the battery and manual provision to operate at a higher voltage to recharge the battery of 100 Ah capacities quickly at 10Amp. The equipment shall comprise of:1. A.C. mains switch/ MCB 230/250 Volt Single Phase with fuses/ MCB. 2. Pilot lamp/ LED to indicate AC supply ON. 3. Ballast choke 4. Single Phase Double Wound Transformer for rectifiers 5. Main transformer single phase variac with rough and fine control to charge battery in steps of 6-12, 12-18, 18-24, 24-30, 30-36, 36-42 volts. 6. Full wave bridge connected plate/ solid state silicon rectifier. 7. Fuses for rectifier output. 8. (i) Moving Coil/Analog type Ammeter 96 mm sq flush mounting type (0-15 Amps.)for Total DC current at rectifier DC output. (ii) Moving Coil/Analog type Centre Zero Ammeter 96 mm sq flush mounting type (15-0-15 Amps.) for Battery Charge/Discharge DC current at Battery output Terminals. 9. Moving Coil Analog type Voltmeter 96 mm sq flush mounting type (050 Volts) 10. Voltmeter fuses 11. DC ON/ OFF MCB with fuses. 64 The sheet steel cubicle of the rectifier unit shall also accommodate the switches for charge rate selection, incoming from battery and various apparatus for battery control. CABINET The charger shall be enclosed in a cabinet made of sheet steel of not less than 1.5 mm thickness and should be suitable for mounting on a plane surface/ floor with ventilation louvers on two sides and finish painted with synthetic enamel paint of white on inside and opeline green on outside. Two coat of zinc primer shall be applied before finishing synthetic enamel paint. The cabinet shall have vermin proof construction. The cabinet legs shall be of adequate height and strength and should provide minimum clearance of 100 mm from ground. FRONT PANEL MOUNTINGS The following provisions conforming to relevant ISS shall be made on the front panel:a) Voltmeter to indicate battery/ charger DC voltage b) Voltmeter to indicate incoming AC voltage c) i. Ammeter to indicate total DC current ii. Ammeter to indicate Charge/Discharge current of Battery. d) Indicating LEDS to indicate:(i) Supply of power; (ii) Charger on; (iii) Input voltage less than 180 Volt. (iv) Battery reverse e) Audio/ Visual alarm to indicate:(i) Power failure; (ii) Charger failure; (iii) Battery disconnection/ failure; and (iv) DC under/Over voltage. In case of failure of charger on fault, it should give buzzer as well as LED indication. However, the buzzer alarm should be provided with a reset switch. f) The indicating instruments shall be of class 1.0 accuracy. 65 TRANSFORMER The power transformer rectifier unit of the battery charger shall be designed for adequate VA rating but in any case it should not be less than 700 VA and should be rated for 300 V at factor of safety of 3. The heat dissipation and power control system should be designed with a factor of safety of 8. Rating of silicon diode should not be less than 15 A. Please note that necessary documentary evidence, showing transformer rating of 700 VA along with test certificate from manufacturer, if bought-out, shall be enclosed, for approval of the purchaser. PROTECTION The charger should have built-in reverse polarity protection with indication lamp so as to protect the battery from high drains. The charger should also have MCB in the output circuit for protection from short circuits. LIGHT EMITTING DIODES For the purpose of indication LEDs shall be provided. SWITCHES AND FUSES Control and instruments switches shall be of toggle type. All fuses of 2Amps and Higher rating shall be of HRC type and of standard make only. LABELS All front panel mounted equipments as well as the equipments mounted inside the cabinet shall be provided with individual labels with equipment designation engraved on aluminium plate (stickers are not acceptable). WIRING The charger shall be supplied completely wired ready for purchaser’s external connections at the terminal blocks. All the wiring shall be carried out with 1100 V Grade PVC insulated standard copper conductor of 2.5 Sq mm. Wiring for Electronic Circuits shall be carried out with 1100 Volts grade suitable size stranded flexible copper conductor PVC wires. Colour coded wires should be used to facilitate easy tracing, as under :i) Single Phase A.C. Circuit:Red for Phase Green for Earthing Black for Neutral ii) D.C. Circuit:Red for Positive Black for Negative iii) Control Wiring:Gray for annunciation and other control circuits. FERRULES Embossed/Engraved core identification ferrules, marked to correspond with the wiring diagram shall be fitted at both ends of each wire. EARTHING TERMINALS The battery charger cabinet shall be provided with two separate suitable earthing terminals of good quality and adequate size. 66 TESTING The following tests shall be carried out by the manufacturers on each battery charger and copy of the test certificate for each charger shall be submitted:I Checking of wiring and continuity of circuits and visual inspection I. High voltage test on the equipment with accessories. (All equipments and wiring should be tested for with-standing the power frequency voltage of 2 KV r.m.s. for 60 seconds.) II. Checking of charging current and load currents. III. Checking of relays operation, alarm circuit operation, lamp indication, charger failure, mains failure, load fuse failure and annunciation (manufacturer’s test certificate for the instruments shall also be furnished). IV. Regulation and Ripple tests. (being unregulated type this test is not required) V. Efficiency test. VI. Burn-out/ Heat-run test (for 10 Hrs.) CIRCUIT DIAGRAM AND WRITE-UP -It is desired that the complete schematic of the charger is provided on a permanently laminated/engraved plate of suitable thickness which has to be bolted/riveted at the four corners on the inside face of rear door. In addition, one more plate of similar type and dimension shall be provided on the outside of the rear door providing guidelines and instructions for operation of the charger. The guidelines and schematic to be provided on the plates shall be as per our approval for which separate drawings shall be furnished, after award of contract TERMINALS 18.1 Separate terminals shall be provided for connecting load and battery leads to the charger. All terminals shall be of M12 size. Suitable copper lugs shall be provided by the supplier for use of the purchaser for connecting the load wiring. Two separate 4 core 2.5 Sq. mm cables (two cores twisted together for reducing voltage drop in cable) shall be used by the purchaser for connecting battery and load. Thus cable glands shall be of suitable size. 18.2 It would be the bidder’s responsibility to prove the adequacy of its design by submitting all technical particulars and relevant graphs to show suitability of charger for supplying load on continuous basis. PRINTED CIRCUIT BOARD The printed circuit boards should be made out of glass fiber re-inforced epoxy boards and should be coated with suitable protective coating for protection against humidity and corrosion. POLARITY MARKING:The polarity marking of the terminals shall be marked for identification. The positive terminal may be identified by “P” or (+) sign or red color mark and 67 the negative terminal may be identified by “N” or (-) or blue color. Terminal marking shall be permanent and non-deteriorating. GUARANTEED PARTICULARS The bidders shall essentially fill up the enclosed Schedule of Guaranteed Technical Particulars of Charger offered by him. MANUAL OF INSTRUCTIONS The manufacturer shall supply a copy of the Instruction Manual for commissioning and initial testing of the charger and maintenance during service with every charger ordered. PACKING The charger shall be securely packed in wooden crates suitable for handling during transit by rail/ road so as to avoid any loss or damage during transit GUARANTEED TECHNICAL PARTICULARS OF 30V 10AMP BATTERY CHARGER SUITABLE FOR 30 VOLT 100 AH LEAD ACID BATTERY S. No 1 2 DESCRIPTION Name of manufacturer Type of charger 3 Indicate specification to which the offered charger conforms Input supply Input current Output voltage range 4 5 6 7 8 9 10. 11 12 13 14 15 16 17 18 19 20 Output current range Maximum output current Efficiency at Normal output voltage 100% full load 75% full load 50% full load 25% full load Whether separate terminals of M-12 size for connecting load and charger leads to the battery terminals has been provided. Provision of LEDs for indication purpose Provision of Audio/ Visual alarm Provision of labels for individual components Provision of ferrules Provision of separate terminals for connecting battery and load Provision of two separate Earthing terminals Weight of the complete charger Overall dimensions of battery charger Thickness of the sheet enclosure Make and rating of Miniature Circuit Breaker for 68 PARTICULARS Manually Controlled S. No 21 22 23 24 25 26 27 28 29 30 31 32 33. 34 35 DESCRIPTION AC Input supply Make & rating of main transformer Make and type of rectifier diode Rating of rectifier diode in Amps PIV value of rectifier diode Output in Amps of complete rectifier stack Make, Type & range of Voltmeter Make, Type & range of Ammeter Make & rating of Miniature circuit breaker for DC output Make and rating of relays Make of buzzer used Make & Type of fuses used Material and size of cable used for internal wiring Whether list of main components, their make & ratings enclosed Whether all the required drawings, instruction manuals and descriptive literature enclosed with the offer Are provision of permanently/ Engraved schematic diagram and guidelines/ instructions on operation of the charger for bolting/riveting body is made. PARTICULARS NOTE:- Any other accessory which may not be included in the above list, but may be necessary for satisfactory and trouble free operation of the equipment as per standard design of the bidder should also be included in the G.T.P. and details of the same may also be furnished. 6. TECHNICAL SPECIFICATION OF 30 VOLT 100 AH LEAD ACID BATTERY 1. SCOPE This specification covers design, manufacturing, testing and supply of 30 Volt 100 AH Lead Acid Battery, for use at 33/11 KV substations for feeding auxiliary supply to Switchgear equipments at the time of interruption in mains supply. The batteries are to be supplied along with a wooden stand / rack as per description in clause -17 Below. 2. CLIMATIC CONDITIONS The climatic conditions at site, under which the equipments shall operate satisfactorily, are mentioned as under: i) ii) Maximum temperature of air in shed Minimum temperature of air in shed 69 45oC 4 0C iii) Maximum relative humidity: 95%(sometime approaches saturation point) iv) Minimum relative humidity 10% v) Average number dust storm days per annum 40 days vi) Average number of rainy days per annum. 90 days vii) Number of months of tropical Monsoon 3 months conditions viii) Average annual rainfall 1250 mm ix) Maximum wind pressure 150 Kg/ Sq. mm x) Altitudes not exceeding 1000 meters. The limit of ambient temperature shall be 45 0C peak and 35 0C average over a period of 24 hours. 3. APPLICABLE STANDARDS The cells of Lead Acid Battery shall conform to the requirement of IS:1651: 1991 with latest amendments thereof. 4. STANDARD RATINGS The standards rating for 30 volt Lead Acid Battery shall be 100 AH. 5. CELL VOLTAGE The nominal voltage of a single cell shall be 2.1 to 2.2 Volt. 6. CAPACITY AT ROOM TEMPERATURE The Battery shall comprise of 15 cells with capacity not less than 100 AH at 10 Hours rate of discharge to end voltage of 1.85 volts per cell at room temperature not exceeding 32 Degree C GENERAL DESCRIPTION 7.1 Cells shall be supplied in glass containers having ample space provided below the plate for accumulation of deposit. The glass containers shall be sufficiently robust transparent and free from flaws. The bidder may also quote for battery with hard rubber containers which shall conform to IS: 1146:1981 7.2. Lead acid battery, comprising of closed type cells shall be compete with plain tubular type positive plate assemblies, glass boxes, lids, micro porous plastic separators, polystyrene dowels and buffers, inter cell connectors of tinned copper for suitable size carrying current 30 volt 100 AH and brass/stainless steel bolts & nuts . The battery shall be offered complete with (i) inter row connectors, acid jars and packing case (ii) stands (iii) stand insulators (iv) cable sockets for end and tapping connections (v) BATTERY insulators. 7.3 The sulphuric acid and water used for the preparation and maintenance of electrolyte shall conform to IS 266:1977 and IS 1069: 1964 respectively. 7.4 The separators used shall be either wooden or synthetic. The wooden separators when used shall conform to IS 652:1960 and the synthetic separators to IS 6071:1986. 70 The venting device shall be of anti-splash type with more than one exit hole and shall allow the gases to escape freely but shall effectively prevent acid particles or spray from coming out. A suitable electrolyte level indicator indicating lower and upper limits shall be fitted to facilitate checking of electrolyte level in opaque containers. The materials used shall be acid proof and shall not deteriorate during service. The manufacture’s identification shall be embossed/impressed on the container. Where it is not possible to bolt the cell terminals directly to assemble a battery, separate copper lead (with acid resistant protective cover), copper connectors of suitable size shall be provided to enable connection of the cells. The material for bolts and nuts shall be brass/stainless steel. Bolts nuts, wisher and spring wisher for connecting the cells shall be effectively lead-coated to prevent corrosion & acid effect. Open cells shall be provided with spray arrestors of adequate area over the plates. These may be of glass sheet at least 3 mm thick and shall be adequately supported. 7. TERMINALS Separate terminals shall be provided for connecting load and charger leads to the battery terminals. All terminals shall be of M 12 size. Suitable Copper lugs shall be provided by the supplier, for use of the purchaser for connecting the load wiring of suitable length 5 Mtr. each. 8. TEMPERATURE RANGE Battery must be capable of operation at temperatures upto 55 oC for prolonged period. Minimum capacity at this temperature should not be less than 2 Amps. for 5 hours. 9. ACCESSORIES The following accessories shall be supplied with each set of battery:i) One Battery log book(one year maintenance) ii) Two copies of printed instruction sheet. iii) Cell testing Voltmeter, 3-0-3 volts scale, Industrial Grade “A” to IS:1248. iv) One no. floating Hydro Meter. v) One no. Syringe hydro meter vi) One no. Thermo meter (0 to 100 0 C) with specific gravity correction scale. vii) One set of suitable insulated spanners. viii) One no. acid resisting funnel. ix) One no. acid resisting jar. x) One pair of rubber gloves. xi) Eye glass. xii) Aprin xiii) Measurement jag 1 Lit. xiv) Petroleum jelly 200 grm. xv) Stand for holding all the above equipments in control room. NOTE :- Any more accessories other than those mentioned above which are required necessarily for the battery shall be supplied by you with the battery. 71 10. CHARGE RATE Fully discharged batteries should normally be recharged at 10 Amps. for 10 hours at room temperature. New batteries and old batteries at high temperatures may need more time. Trickle charge rate shall be about 50 to 100 mA 11. CELL DESIGNATION & MARKING The practice indicated in relevant IS or latest version shall be followed for cell designation purpose. The following information shall be indelibly and durably marked on the outside of the cell a) Manufacturer’s name and/or trade mark; b) Month and year of manufacture; c) Nominal voltage; d) Rated ampere-hour capacity; e) Country of origin; and f) Cell designation. h) Name of purchaser (MPPKVVCL LTD Indore) 12. MANUAL OF INSTRUCTIONS A copy of the instructions manual for initial treatment and the maintenance on its service shall be supplied by the manufacturer with every set of battery. 13. POLARITY MARKING The polarity of the terminals shall be marked for identification. The positive terminal may be identified by “P” or (+) sign or Red colour mark and the negative terminal may be identified by “N” or (-) sign or a Blue colour mark. Marking shall be permanent and non-deteriorating. 14. WARNING MARKING The battery/cell shall be furnished with a warning plate located at conspicuous place specifying the use of “PARTICULAR ELECTROLYTE ONLY” (in block letters) and specifying the proper fill level of the electrolyte. Marking shall be permanent and non-deteriorating. 15. PACKING The batteries shall be suitably packed in wooden crates suitable for handling during transit by rail/road, and secured to avoid any loss or damage during transit. 16. MOUNTING STAND The cells shall be accommodated in double tier stand constructed of selected timer and painted with 3 coats of acid proof paint. Necessary paint for this purpose shall be supplied. No metal fastenings shall be used. The stands shall be supported on insulators to contain necessary insulation from earth and there shall be insulators between each cell and stand. 17. TESTS The following tests shall be carried out in accordance with IS: 1651:1991 or the latest version thereof: (A) TYPE TESTS: a) Verification of constructional requirements. 72 b) Verification of marking. c) Verification of dimensions. d) Test for capacity Test for voltage during discharge e) Ampere-hour and Watt-Hour efficiency test. f) Test for loss of capacity on storage g) Endurance test (B) ACCEPTANCE TEST h) Marking & Packing i) Verification of Dimensions j) Test for capacity k) Test for voltages during discharge. (C) ROUTINE TEST The battery shall be tested after manufacture as per the requirement of IS: 1651-1991 (with latest amendment, if any). Two copies of test certificates indicating the results obtained during the tests shall be submitted. Guaranteed technical particulars of 30 volt 100 AH lead acid batteries S. No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 PARTICULARS DESCRIPTION Type of Battery Reference of IS NO Manufacturer’s Name & place of works. Normal voltage of battery. No. of cells in each battery set. Capacity of battery at 10 hours rate Voltage per cells. Type of construction (i) Positive plate (ii) Negative plate Method of connection between cells i.e. whether bolting or some other methods. Normal trickle charge rate without load Normal charge rate i) At starting ii) Finishing Voltage per cell at the end of charge at the quick charge rate. Normal charging time after complete discharge Type of material of separators Material of container Watt. hour efficiency at 10 hour rate of discharge. Voltage across battery terminal when under quick charge rate. Ampere hour efficiency at 10 hour rate of discharge Quantity of dilute acid per cell. 73 S. No 20 21 22 23 24 25 26 27 28 29 30 31 32. PARTICULARS DESCRIPTION Overall dimension of each cell. Distance between the centers of cells when erected. Weight of cell complete with electrolyte Recommended maximum period of storage before the first charge Internal resistance of the cell Amount and specific gravity of electrolyte per cell required for first filling. Expected specific gravity of electrolyte at the end of full charge Expected specific gravity of electrolyte at the end of discharge at 10 hour rate Whether separate terminals of M-12 size for connecting load and charger leads to the battery terminals has been provided. Whether dimensional drawing of one cell and lay out drawing of one complete set of battery submitted with the offer? Whether manual of erection, commissioning and maintenance of battery submitted with the offer? Whether the copy of Type Test certificates carried out on the battery submitted? Whether following accessories shall be supplied with each set of battery:(i) One Battery log book (ii) Two copies of printed instruction sheet. (iii) Cell testing Voltmeter, 3-0.3 volts scale, Industrial Grade “A”. (iv) One no. floating Hydro Meter. (v) One no. Syringe hydro meter (vi) One no. Thermo meter (0 to 100 0 C) with specific gravity correction scale. (vii) One set of suitable insulated spanners. (viii) One no. acid resisting funnel. (ix) One no. acid resisting jar. (x) One pair of rubber gloves. Details of type test certificates of 2 Volt – 100 AH Battery Cell 74 Sr.N o Name of test Claus e of IS: 1651 1. Verification of constructional requirement 12.2 2. Verification of marking 12.3 3. Verification of dimensions 12.4 4. Test for capacity 12.5 5. Test for voltage during discharge 12.10 6. Ampere-hour and Watt-hour efficiency test 12.9 7. Test for loss of capacity on storage 12.7 8. Endurance test 12.8 7. Name of testing authority & place Type test report no. & date TECHNICAL SPECIFICATION FOR 1200 KVAr, 11 KV CAPACITOR BANK This specification covers design, manufacture, testing at manufacturers works, supply and destination of 11KV Capacitor Banks, Residual Voltage Transformers, Vacuum Automatic Capacitor Switches their mounting GI structures and other associated materials. A) CAPACITOR BANKS 1. 11KV Capacitor Banks: - The rating of the Capacitor Banks will be as follows :i) 1200 KVAr at 11 KV, 3 Ph 50 HZ neutral solidly grounded systems and to be controlled with suitable vacuum circuit breaker. ii) The three phase capacitor banks shall conform to the Indian Standard 13925:98 (Part-I), 13925:94 (Part-II), IEC 871-2-87 with its latest version/amendments, if any. iii) The normal system frequency is 50 HZ and may vary between + 3% i.e. 48.5 HZ to 51.5 HZ. iv) The capacitor shall be connected to the system with nominal voltage for 11KV. The highest voltage of the system shall be 12.1 KV on sustained basis. v) The maximum continuous system rms voltage that may be applied to the capacitor shall be of the order of 10% more than the rated rms voltage of the 75 capacitor. However, the supplier of the equipments, including the breaker shall ensure that under breaker opening conditions, due to current chopping, the maximum dynamic over voltage level does not exceed 2.3 PU value of normal rated rms voltage. vi) The increase in current or reactive output of capacitor unit & bank over the rated values may be as per IS: 13925:98 with latest version/amendment, if any. vii) The standard basic unit rating of capacitors (single phase) shall be 121 KVAr at 6.98 KV and will be suitable for outdoor installation. viii) 1500 KVAr bank shall consist of 15 single phase capacitor units of 121 KVAr. Each phase shall have 5 units in parallel which are connected then in ungrounded star. ix) The power loss in capacitor shall not exceed 0.2 Watt/KVAr. x) Each capacitor unit shall be provided with built in discharge resisters, to permit the capacitor unit to discharge the capacitor to 50V or less in less than 10 minutes after disconnection from supply. xi) The container of each capacitor unit shall be provided with suitable earthing terminals clearly marked as with lifting lugs for ease in handling. xii) Each capacitor unit shall be built with number of elements comprising of high quality embossed aluminum foil acting as electrodes separated by dielectric of biaxial oriented hazy polypropylene film. Capacitor shall be vacuum impregnated with on PCB oils only. xiii) Set of three fuse barrels with leaf spring & fuse elements per bank i.e. 36 nos. in case of 1200 KVAr and 18 Nos. in case of 600 KVAr shall be supplied free of cost with each set of capacitor bank. xiv) The capacitor bank shall be designed and capable of withstanding the following power frequency and impulse test voltage :a) Nominal System Voltage b) Highest System Voltage c) Power frequency test Voltage d) Impulse test Voltage 11 KV (rms) 12.1 KV (rms) 28 KV (rms) 75 KV (Peak) NOTE - Each of the capacitor units as well as banks shall be provided with a rating plate and terminal markings as stipulated in IS: 13925:98. Elevating structures made from suitable solid steel sections should be provided to fix effective height of the lowest accessible live terminal of the capacitor bank at 3.2 meters above the grounded level. 8. TECHNICAL SPECIFICATIONS OF 33 KV and 11 KV GAPLESS LIGHTNING ARRESTORS SCOPE 76 This specification covers single phase outdoor metal oxide type gapless surge arresters for use in effectively earthed system with the transformer neutral effectively earthed with normal voltage of 11KV for 9KV Lightning arrestors and 33KV for 30KV Lightning Ar restors. The rated voltage of Arrestors shall be 9KV (rms) for 11KV system and 30KV (rms) for 33KV system. SPECIAL CONDITIONS The atmosphere at places is laden with dust in suspension during the dry months and subject to fog in cold months. The temperature variation between the daily minimum and maximum is large. Heavy lightning is usual in the area during the month of May to November. The area is also subjected to heavy monsoon rains 80% to 90% of the annual precipitation during the months of June to October. SYSTEM CONDITIONS I Nominal system voltage 33KV 11KV ii Highest system voltage 36KV 12KV iii Frequency 50Hz 50Hz iv Fault level 1500 MVA 350 MVA The system is 3-phase 50 Hz solidity grounded system with earth fault protection .The winding of transformer wherever to be protected is connected on delta formation in primary and star formation in secondary. We have provision of placing one set of surge arresters at the entry of the each line (feeder) in the substation and one set near to the transformers for 33KV system & only one set each on 11 KV Distribution transformers. The insulation level provided in our transformer is 170 KV Peak for 33 KV systems and 75 KV peak in case of 11 KV System. STANDARD The surge arresters shall strictly conform to IEC 99-4/IS-3070 Part-3 – 1993 with latest amendment if any in all respects. Maximum residual voltage shall comply with the requirement given hereunder: The surge arresters meeting any other authoritative standards, which ensure equal or better performance, than mentioned above shall be acceptable. The technical requirement has been detailed out below:The agency should offer nearest rating of surge arresters. The transformers, which are to be protected having BIL 170 KVP for 33 KV winding & 75 KVP for 11KV winding. We will be installing our LAs at a distance of 5/10 metres from transformer (another 5 metres be added towards height of LAs lead length and bushing of transformer. Considering 20% safe margin as per IEC the impulse voltage of more than 136 KVP should not appear across the 33 KV side of transformer. Similarly, impulse voltage of more than 60 KVP should not appear across 11KV winding of transformer. Required Technical Particulars No. Particulars Requirements 1. Nominal system voltage 33KV 11KV 2. Type of Arrestor Metal Oxide Metal Oxide 3. Applicable standard IEC 99/4 IEC 99/4 IS 3070 Part-III IS 3070 Pt.-III latest latest amendment amendment 77 No. Particulars 4. Rated Arrestor voltage IV rms 5. Maximum continuous operating voltage KV rms 6. Nominal discharge current rating (8/20 micro set) KA 7. Minimum discharge capability (KA/KV) 8. Long duration discharge class 9. Maximum residual voltage at nominal discharge current of 8/20 micro sec. wave, KV peak 10. Maximum steep current impulse residual voltage at nominal discharge current, KV Peak 11. Maximum switching impulse residual voltage at 500 Amp. (Peak) 12 Minimum prospective symmetrical current (KA) 13 Impulse high current short duration discharge of 4/10 micro sec. Wave (KAP) 14 Max. radio interference voltage at 1000 Hz (micro volts) 15 Overall temporary over voltage withstand capacity (KV rms) a) 1.0 Sec. b) 10.0 Sec. c) 100.0 Sec. 16 Impulse withstand voltage (KVP) 17 Current impulse withstand level Requirements 30 24 9 7.2 10.0 5.0 As per long duration discharge class 2 of IEC 99/4 2 2 85 32 93 38 70 NA 40 15 100 65 1000 - 36 34 32 170 10 9.5 75 As duty prescribed in line discharge class-I of IEC TC37/IS 3070 Part-III Class “A” N.A. 18 impulse of long duration current 75 Amp. Peak for 1000 micro secs. 18 19 Pressure relief device Disconnecting device 20 Min. Creepage distance of 900 porcelain housing (mm) Top & Bottom metal cap Hot Dip Galvanized 21 78 N.A. As per required specification IS: 3070 (Part-2) 1985 300 No. Particulars 22. Terminal arrangement 23. Earthing Terminal Requirements Built in clamping type can be adjusted Horizontal & Vertical Power off to conductor save squirrel to carbon The base of L.A. shall be provided with separate terminal / distinctly marked connection to earth for suit two for Residual voltage for 8/20 micro sec. Wave of nominal discharge current KA are specified above, however, we will prefer still lower residual voltage to ensure better protection. The requirement of energy is very specific based on our system. The firms are requested to supply nearest energy rating of LAs for both single and double shot. Current impulse withstand level – The 9 KV arrestors shall withstand 18 impulse of long duration current with a peak level of 75 Amp & duration 1000 micro secs. 30KV arrestors shall meet the duty prescribed in line discharge Class-I of IEC TC-37. Disconnecting Device The arrestor for 11KVsystem to be provided with a suitable disconnecting device. This shall be connected in series with the ground lead and should not affect the sealing system of the arrestor. The disconnecting device shall conform to the requirement specified in IS:3070 (Part-II) 1993 & IEC 99-4 (1991-II) clause 5.12, 7.6.3. Pressure Relief Device The arrestor for 33KV system should have a suitable pressure relief system in order to avoid damage to its porcelain housing. Each and every individual unit of surge arrestor shall be hermetically sealed and fully protected against ingress of moisture for which suitable rubber gaskets with effective sealing system should be used. The hermetic seal shall be effective for ensure life time service of arresters and under the service conditions specified. The agency shall furnish sectional view showing details of sealing employed. Manufacturers should device a suitable routine production testing to verify the efficiency of sealing. All the units of arresters of same rating shall be interchangeable type without adversely affecting the performance. The lightning (surge) arrestor shall be suitable for pedestal type mounting. All necessary bolts, nuts clamps etc., required for mounting on support structure shall be included in the scope for supply. All porcelain housing shall be free from lamination cavities and other flaws affecting mechanical and electrical strengths. The porcelain should be nonporous. All exposed ferrous parts shall be not dip galvanized as per IS: 2633. Line and ground terminals should be hot dip galvanized. TERMINAL CONNECTORS Terminal connectors shall be manufactured and tested as per IS: 5361 & should be type tested. The terminal connector drawings should be submitted separately for approval of owner. All casting shall be free from blowholes, surface blisters, cracks and cavities. All sharp edges and corners shall be 79 blurred and rounded off. All Current carrying parts shall be designed and manufactured to have minimum contact resistance. The contact surface must be machined smooth to obviate excessive current density. The terminal connector for connection of conductor should be suitable for squirrel to raccoon conductor with Universal take off arrangement (can be adjusted for both horizontal & vertical take-off) and should have adequate current carrying capacity. The terminal connector shall be manufactured out of aluminium alloy grade LM 9 or 25 as per IS and by gravity die casting process only. Terminal connector should have six bolts to hold the conductor a conductor hold length shall be 100mm approximately. All nuts, washers, bolts etc. shall be stainless steel/hot dip galvanized. The top metal gap and the base of the lightning arrestors shall be galvanized. The base of the Lightning Arrestor shall be provided with two separate terminals distinctly marked for connection to earth. NAME PLATE The arresters shall be provided with non-corrosive 2 mm thick metal nameplate embossed and fitted rigidly on arrestor body with indelibly marked with the following information: 1. Manufacturer’s name or trademark and Identification (serial) No. of the arrestor. 2. Rated voltage 3. Maximum continuous operating voltage 4. Type 5. Rated frequency 6. Nominal discharge current 7. Long duration discharge class 8. Pressure relief current in KA rms. 9. B.I.L. of the equipment to be protected 10. Year of manufacture 11.The nameplate should be fitted rigidly so that during life of arrestor, there should not be any possibility of removal of nameplate. Drawings The agency shall furnish two sets of following drawings for owner’s approval before commencing the supplies. General outline drawings of the complete arrestor with technical parameters. Drawings showing clearance from ground and other live objects and between adjustment poles of surge arresters required at various heights of surge arrestors .Drawings showing details of pressure relief devices. Mounting clamp details of surge arresters. Details of the terminal and ground terminal .Volt - time characteristics of surge arresters. The detailed dimensional drawing of porcelain housing shall indicate ID, OD, thickness and insulator details such as height, profile of petticoats, angle of inclination and gap between successive petticoats, total creepage distance etc. TEST & TEST CERTIFICATES Type Test Certificates The following type tests shall be made in accordance with Clause 71 of IEC 99/4/IS-3070 Part-III latest amendment. 1. Insulation withstand test 80 9. 2. Residual voltage test 3. Long duration current impulse withstand test 4. Operating duty test 5. Pressure relief test (for 30KV LAs) 6. Test of Arrestor Dis-connectors (for 9KV LAs) 7. Partial discharge test. The following additional tests are to be made in accordance with IS 3070 (partII) 1985:1. Temperature cycle test on porcelain housing 2. Porosity test for porcelain components 3. Galvanizing test on steel metal parts Acceptance Tests The following tests as per clause 8.2 of IEC 99/4 and IS-3070 Part-I/Part/III shall be done on the lower whole number of the cube root of the number of arresters to be supplied. 1. Power frequency reference voltage test at reference current on complete arresters. 2. Lightning impulse residual voltage test at nominal discharge current on complete arresters. 3. Porosity test on porcelain 4. Partial discharge test 5. Galvanizing test on exposed steel parts 6. Visual / dimensional exam 7. Routine Tests The following routine tests as per Clause 8.1 of IEC 9/4 / IS-3070 Part-1/PartIII are to be conducted by the manufacturer on offered lot for pre-despatch inspection. The lot offered without routine test reports shall not be considered & delay in acceptance of the offer will be on firm’s account: 1. Measurement of the reference voltage on the complete arresters. 2. Residual voltage test at nominal discharge current on the complete arresters or sections. 3. Test to verify the efficiency of sealing. INSPECTION All tests and inspection shall be made at the place of manufacture unless otherwise specially agreed upon by the manufacturer and the owner. The manufacturer shall offer the inspector (representing the owner) all reasonable testing facilities without charges to satisfy him that the material is supplied in accordance with the Specification. The owner has the right to have the tests carried out by an independent Agency subject to recovery of testing expenditure in case of failure, whenever there is dispute regarding the quality of supply. SPECIFICATIONS FOR 1.1 KV PVC INSULATED POWER CABLES 1. SCOPE Specifications cover the design, manufacture, testing at works, inspection and delivery at site of 1.1 kV PVC Insulated cable. The material to be offered 81 2. 3. 4. 5. 6. under the specification shall be of proven design by way of commercial operation for more than 5 years. STANDARDS IS 3975 Mild Steel wires, formed wires and tapes for armouring of cables. IS 8130 Conductor for insulated electric cables and flexible cords. IS 5831 PVC insulation and sheath of Electric Cables IS 1255 Code of Practice for Insulation and maintenance of Power Cable up to & including 33 kV rating CONDUCTOR All conductor shall be standard All conductors shall be of high electrical conductivity Aluminium conforming to requirement of IS 8130 – 1984 with latest amendments. Before stranding, the conductor shall be circular in cross section, uniform in quality, solid, smooth and free from scale, sharp edges and other defects. INSULATION The conductor shall be provided with Polyvinyl Chloride insulation applied by extrusion process. PVC insulation shall be strictly as per IS-5831 and its latest amendments. The insulation shall be both heat and moisture resistant and shall be suitable for continuous operation at conductor temperature of 90 degree C, rising momentarily to 250 degree C under short circuit conditions. It shall fit tightly to the conductor and shall be applied concentrically above the conductor in thickness, consistent with the voltage classification. No tolerance on the negative side shall be acceptable. The insulation shall be so applied that it shall be possible to remove it without damaging the conductor. The insulating material shall have excellent electrical properties with regard to resistivity, dielectric constant and loss factor and also shall have high tensile strength and resistance to abrasion. This shall not deteriorate at elevated temperatures or when immersed in water. The insulation shall be preferably fire resistant and also resistant to chemicals like acids, alkalis, oils and ozone etc. FILLERS Fillers or bedding used in multi-conductor cables shall be non-wicking and non-moisture-absorbing. Further, the compounds used with fillers shall be such as to have no deleterious effect on other components of the cable and to be stable at cable temperatures. Fillers shall be so chosen as to be compatible with the temperature ratings of the cables and shall have no deleterious effect on any other component of the cable. INNER SHEATH The laid up cores shall be provided with an inner sheath applied by extrusion process. It shall be ensured that it is as circular as possible. 82 The inner sheath material shall be of polyvinyl chloride (PVC) compound conforming to the requirements of type ST 2 compound of IS: 5831 with latest amendments. The inner sheath shall be so applied that if fits closely on the laid up cores and it should be possible to remove it without damage to the insulation. No tolerance on the negative side shall be acceptable. 7. ARMOURING The armouring shall be of galvanized steel wires for multi core cables. The galvanized steel wires shall comply with the requirements of IS: 3975 with latest amendments. No tolerance on the negative side shall be acceptable. 8. OUTER SHEATH The outer sheath material shall be of polyvinyl chloride (PVC) compound conforming to the requirements of type ST2 compound of IS: 5831 with latest amendments shall be provided over the armouring to offer a high degree of mechanical protection against abrasion. The outer sheath shall be applied by extrusion process. No tolerance on the negative side shall be acceptable. 9. CORE IDENTIFICATION Individual core of multi-core cables shall be colour coded and/or numbered for proper identification in accordance with relevant IS / manufacturer’s standard, subject to specific approval of purchaser. 10. REELS /DRUMS Cables shall be supplied in the drums made from eco-friendly material in the specified length. The Drums shall be strong, weatherproof and non-returnable. The ends of the cable shall be sealed by means of non-hygroscopic sealing material. 11. GENERAL All cables shall be suitable for installation in air, conduits, ducts, and open concrete trenches or for direct burial in either wet or dry locations for normal operating conditions. All cables shall be flexible and easy to bend, pull, handle and install. 12. TESTS & INSPECTION Cables shall be subjected to routine & acceptance tests in accordance with the IS 7098 (Part – I, in addition to physical, ageing and electrical tests at the Manufacturer’s plant in accordance with applicable standards and will be approved by 3rd party agency. 12.1 Type Test The successful bidder shall submit the following type test reports conducted on similar equipments for approval of owner. a) Annealing test (for copper) b) Tensile Test (for aluminium) c) Conductor resistance test d) Test for Armour wires e) Test for thickness of insulation check f) Physical test for insulation 83 g) Physical test for PVC sheath i. Fire resistance. ii. Cold-impact iii. Bleeding and blooming h) Partial discharge test i) Bending Test j) Dielectric power factor tests k) Heating cycle test l) Impulse withstand test m)High voltage test (water immersion test) All the following routine / acceptance tests specified in relevant standards shall be witnessed by the owner / consultant. 12.2 Acceptance Test a) Conductor resistance test b) Test for thickness of insulation and sheath c) Partial discharge test (for screened cables only) d) High voltage test (water immersion test) e) Annealing test (for copper) f) Tensile test (for aluminium) g) Wrapping test (for aluminium) h) Insulation resistance test 12.3 Routine tests a) Conductor resistance Test b) Partial discharge test (for screened cable only) c) High voltage test. 12.4 Test Certificates Five (5) copies of routine / acceptance test certificates shall be produced with the endorsement of the inspecting authority to the purchaser before effecting dispatch. 84 10. TECHNICAL SPECIFICATION OF 11KV & 33KV OIL IMMERSED CT:PT (METERING) UNITS 1. This specification cover the design, manufacture testing, inspection of out door pole mounting type 11KV and 33KV oil immersed combined CT:PT (Metering) units. 2. The metering units shall have 3 nos. CT’s to suit the requirement of 3 phase 4 wire metering. 3. 11KV and 33KV metering units shall comprise of 3 nos. CT’s conforming to IS2705:1992 and 1 No. Three phase PT’s conforming to IS-3156:1992 with latest amendments and upgraded. 4. The important guaranteed particulars of CT’s and PT’s of the combined CT:PT (Metering) units and to be offered by the tenderer. 5. The ME shall be supplied complete with first filling of EHV grade transformer oil. Only best quality of new EHV Grade transformer oil should be used with minimum BDV of 70 KV. The BDV of oil shall be recorded in the test certificate. The oil shall comply in all respect with the provision of latest version of IS-335 or IEC publication No.296 (as amended up to date) and type test certificates of oil shall be produced at the time of inspection. 6. No fuses either on HT or LT side of PT shall be provided. 7. The metering equipments shall be contained in a weather proof out door pole mounting type M.S. tank with 6 Nos. of 11KV/33KV weather proof bushings with Brass stud as per rating of CT:PT (Metering) units. 3 Nos. bushing on incoming and 3 nos. bushing on outgoing terminals for all three phase R, Y & B with M and L marking embossed/engraved on the top cover of MS tank to identity incoming and outgoing terminals of the metering unit respectively. 8. The tank should be given three coats of rust preventing paint and finished with light grey No. 631-IS-5 on all external surfaces. The internal surface of the tank shall be painted with two coats of a suitable oil-insoluble paint. 9. A suitable air release valve at the top of the tank cover shall be provided. After processing and hermetically scaling of ME, the air release value should be permanently sealed before dispatch of metering equipment. 10. (a) The PT’s shall be 3 phase star connected with HV neutral floating. The primary winding has to be designed for unearthed neutral i.e. for the highest system voltage i.e. 36 KV for 33 KV and 12 KV for 11 KV P.T. winding should have uniform insulation through the binding from terminal to neutral end, not graded insulation. This should clearly be confirmed in the offer. (b)The 11KV metering unit should be suitably designed for single phasing operation. 11. The CT secondary winding will be epoxy cast and the leads brought out through an epoxy cast terminals. 85 12. The connection between the CT and PT inside the tank will have adequately reinforced insulation to avoid infringement of clearance in air, or to the tank side insides the units. Adequate electrostatic & electromagnetic shielding should be provided to eliminate the effects of electromagnetic insulation/electrostatic charge on the CT: PT secondary windings. 13. The ME shall be fitted on HV side with outdoor type porcelain bushings of appropriate voltage & current. These bushings shall conform to IS: 2099. Further sealing arrangement be such that oil should not leak out from the bushing/ ME tank. For gasketed joints, whenever used nitric butyl rubber gaskets, neoprene or any other improved material shall be used. The gasket shall be fitted in properly machined groove with adequate space for accommodating the gasket under compression. The tenderer have to submit complete details and justify that the quality of Gaskets which will be used between the joints and also for mounting of oil level indicator will be of best quality to avoid leakage of oil. The quality of gasket should be selected keeping in mind that the ambient temperature 50 degree centigrade. 14. The end turns insulation of PT HV winding towards bushing side should be reinforced. 15. The dimensions and electrical characteristics of the bushing shall be in accordance with relevant ISS and its subsequent amendments if any. 16. The minimum electrical clearance between phases and phase to earth as specified in ISS/IE rules shall be maintained. 17. The conductor in the secondary winding of the CT shall not be less than 14 SWG. It should not less than 3.24 Sqmm. 18. Normal current density shall not be more than 1.5 Amps/ Sqmm in primary winding of the CT. 19. The primary winding shall be of adequate cross section to carry continuously the rated current plus 20% over load continuously. 20. The insulating materials for winding between HV & LV between interlayer of the winding and for end turn shall be as per relevant ISS. However, end turns have to be provided with reinforced insulation and lead connecting the bushing shall be provided extra insulation of fibre glass sleeve. 21. The metering equipment shall have a built is secondary terminal box. Entry of the cable in to the box on the unit shall be through one no. gland and check nuts, Metallic cable gland to suit 12 core 2.5 Sqmm armoured cu-cable shall be supplied with Metering Equipment. 22. Top cover of metering unit should be provided with sealing arrangement at all four corners. 23. Secondary terminals box cover should have 8 no. nuts & bolts with hole for sealing arrangement. For these, 8 nos. holes should be provided on the cover & flange of secondary terminals box at the corner & middle of each faces for fixing nut bolts. In addition to above 4 number holes (2 nos. on upper side & 2 nos. on lower side) may also be provided in the flange & top cover. 86 24. (a) The location of the secondary terminal box would be on the top of the metering unit. 25. The top of the tank will have slope to drain the rain water and avoid collecting pockets. 26. The metering unit shall be provided with non-detachable anodised aluminium plate showing position on the terminals, their marking, connecting diagram furnishing the information as specified in IS:2705 and IS:3156 i.e. type, voltage ratio, CT ratio, rated burden, class of accuracy. Sr. no. order no. & date, month and year of dispatch etc. of metering unit. Further MS plate size 125x125 mm be got welded on width side of metering unit. On this plate name of firm, order no. and date Sr. no. of the unit and month and year of dispatch should be engraved/embossed. 27. The ME shall be hermetically sealed. The ME shall be provided with conservator of adequate Capacity to facilitate expansion and contraction of oil due to change in temperature. The conservator shall be provided with oil level gauge, non-return type oil filling valve with metal cap, pressure release device but without silica gel breather. The oil level in the conservator before sealing of ME shall be made up to the required level in the conservator while the ME filled with oil is maintained at a temperature of 45 degree centigrade. The volume above the oil level in the conservator tank shall be filled with nitrogen confirming to commercial grade of IS 1747:72. Nitrogen shall be filled from the cylinder. Further an explosion diaphragm shall be provided opposite side of ME secondary terminals box which should operate at a pressure 0.4Kg/Sqcm before the pressure inside the tank reaches the tank pressure. Thus, pressure of nitrogen gas, pressure relieving device & an explosion diaphragm shall be properly Co ordinate and shall be described in the bid. The oil in the ME shall be filled under vacuum & after processing and thereafter sealed with nitrogen gas to eliminate breathing and to prevent air and moisture from entering the tank. Oil drain valve or sampling cock, if provided to facilitate factory processing and non-return type oil filling valve should be permanently sealed before dispatching the ME. The method adopted for hermetic sealing shall be described in the bid. 28. The gaskets used should be best quality having a thickness of 3 mm of more. The information about the gaskets material used on the metering unit should be mentioned in the offer. 29. The tank shall be of robust contraction having thickness of sheet enclosure minimum 5 mm. The welded joints of the metering unit shall be strengthened by providing 25x25x3mm angle all along the length and welded properly inside the tank. All joints of the tank and fitting shall be oil tight and no building shall occur during service. 30. The tank shall be reinforced by welded angle of size 25x25x3mm on all the outside wall on the edge of tank to form two equal compartment. One face of reinforcement angle should be continuous welded with the tank surface such that other side of the angle forms inverted “L”. 87 31. The mounting of the bushing on the metering equipment should be in oblique plane particularly in case of single ratio metering unit. 32. The metering unit shall be provided with a non-discharge aluminium plate showing position of the terminals and their marking furnishing the information’s as specified in IS: 2705:3156. 33. All the welded joints in the metering equipment tank should be leak proof and pressure-tested as per relevant IS. 34. On secondary side of PT four terminals shall be marked as R.Y.B. and N. 35. The metering unit shall have the following: i. Revetted Rating and Diagram plate. ii. 2 Nos. welded lifting lugs of MS plate 4 mm thick. iii. 2 Nos. base mounting channels size 75x40 mm across length of metering unit. iv. 2 Nos. Earthing terminals with lugs. v. Provision of 6 Nos. Bi-metallic clamps suitable for ACSR Dog-Conductor. The terminal connector shall conform to the latest version of IS: 5561 of equivalent International standard. The details of current take off as required by us should be detailed out in drawing and should be submitted alongwith the bid. In respect of terminal connector following should be ensured. a. The terminal connector should be made of A6 Aluminium alloy and by gravity diacaustic only. Sand castled terminal connectors are not acceptable. b. All castings shall be free from blow holes, surface blisters, cracks and cavities. All sharp edges should be rounded off. c. No Cary of clamps shall be less than 12mm thick. d. The bimetallic strips/sleeve shall be 2mm thick. e. All Nut/Bolts/washers shall be of stainless steel only. f. The conductor should be tightened by min. 4 bolts Conductor hold must not be less than 50mm. 36. Type tests & Routine Tests: (i) The tendered design of metering unit are type tested for short time current rating test, temperature rise test, lighting impulse test, accuracy test, high voltage power frequency voltage withstand test, as per ISS-2705/1992 and IS3156/1992 with latest amendments from any NABL accredited laboratory. The test certificates should not be more than five years old. (ii) Before dispatch each of completely assembled metering unit shall be subjected at the manufacturers work to the following routine tests in accordance with the details specified in IS: 2705 and IS: 3156:a. Verification of terminals marking and polarity test of CT and PT of metering unit. b. Power frequency dry withstand test on primary winding of CT and PT of metering unit. 88 c. Power frequency dry withstand test on secondary winding of CT and PT of metering unit. d. Over voltage inter turn test on CT of metering unit. e. Determination of errors of other characteristics according to requirements and class of accuracy of CT and PT of ME. f. Induced voltage test on PT of metering unit. g. Break down voltage test of transformer oil. h. Pressure test on tank of metering unit at 0.8 Kg/Sq. cm. i. Ratio & phase angle error test of CT’s of metering unit for zero burden i.e. by shorting the secondary terminals directly and on PT keeping the secondary terminals open. SCHEDULE - II – B GUARANTEED TECHNICAL PARTICULARS FOR OUTDOOR OIL IMMERSED 11 KV & 33 KV CT:PT (METERING) UNITS. (TO BE KEPT IN THE ENVELOPE PART II "COMMERCIAL TECHNICAL BID") S.No PERTICULARS . REQUIREMENT OFFERED 11KV 33KV 11KV 33KV 1 Nominal System Voltage. 11KV 33KV 2 Highest System Voltage. 12KV 36KV 3 Frequency. 50HZ 50HZ Specification of CT & PT of Metering 4 unit. (a) Current Transformer i Type To be Indicated CT ratio 200/5 A 150/5 A ii 100/5 A 100/5 A iii iv v vi vii (B) i ii iii Accuracy Class Rated output. Insulation level 0.5 0.5 15VA 15VA 28 KVrsm 70KV rms 75KV pk 170KV pk a) Short time thermal current rating 18.4 KA 25 KA for One second. b) Short time thermal current rating 18.4 KA 25 KA for two seconds. (for dual ratio metering unit.) c) Rated dynamic current As per IS: To be indicated 2705 Saturation factor To be indicated Potential Transformer Type P.T. Ratio To be indicated 11KV/ √3 33KV/ √3 110V/ √3 110V/ √3 50 50 Rated output VA/ Phase 89 iv v vi Class of accuracy Insulation level 0.5 0.5 28 KVrsm 70 KVrms 75KV pk 170 KVpk Star/Star Star/Star 1.2 times continuously & 1.5 times for 30 seconds. Winding connection Rated Voltage factor & duration vii 5 a b c 6 A i ii iii Dimension of MS tank : Height mm Breadth mm Length mm Weight of core and winding Current Transformer Core Primary Winding Secondary winding B i ii iii 7 Potential Transformer Core Primary Winding Secondary winding Weight of oil Total weight of complete metering unit including ass accessories. Resistance of primary/secondary winding at 75o C per phase. CT Winding Primary CT Winding Secondary PT Winding Primary PT Winding Secondary Maximum winding temp. (Ambient air temperature shall be taken as 45o C a) Minimum phase to phase distance 8 9 a b 10 11 12 13 14 15 16 17 To be Indicated To be Indicated To be Indicated To be Indicated To be Indicated To be Indicated 8kg 10kg 1kg To be Indicated To be Indicated To be Indicated To be Indicated 23kg 3kg 1kg 30kg To be Indicated 130kg To be Indicated To be Indicated To be Indicated To be Indicated To be Indicated 50o C 50o C 255 mm Min. b) Shortest distance between metal 190 mm 380 mm 190mm part & earth Min. a) Make & type of HT bushing To be Indicated Taijal b) Creepage distance of HV bushing 300 mm 900 mm 300 mm (min) (min) Gauge of the MS tank Min. 5mm Min. 5mm 5mm Bi- metalic terminal connector with a nut, plain washer spring washer & 6Nos. to be provided. yes check nut suitable for DOG ACSR Conductor (Dia - 14 mm) (Approx.) Type of core material To be Indicated CRGD Size & capacity of conservator tank sufficien To be Indicated t size Make & size of silica gel breather Not required N.A. 90 255 mm 430 mm 0.05 Ω 0.5 Ω 2.5 kΩ 0.7 Ω 50o C 18 a b c 19 Type and thickness of gasket used on: Top cover and tank Secondary terminal box HV and LV bushing Type of thickness of explosion vent diaphragma To be Indicated To be Indicated To be Indicated To be Indicated 20. (A) 1 : KV CT (To be indicated by the tenderer) S. Require 200/ No Particulars ------ment 5A . Cross section A area of each turn of CT winding (in sqmm.) Primary i) 73sqmm winding Secondary 3.24sqm ii) winding m B 5 mm 3 mm 5 mm sufficien t size 150/ 5A 100/ 5A ---- ---- ---- ---- 150/ 5A 100/ 5A ---- ---- ---- ---- Nos. of turns Primary 24 winding Secondary ii) 36 winding Winding C Material Primary i) Copper winding Secondary ii) Copper winding (B) 33KV CT (To be indicated by the tenderer) S. 200/ No Particulars ------5A . Cross section A area of each turn of CT winding (in sqmm.) Primary i) winding Secondary ii) winding i) B Nos. of turns 91 Primary winding Secondary ii) winding Winding C Material Primary i) winding Secondary ii) winding (C) 11KV PT & 33KV PT (To be indicated by the tenderer) S. No Particulars 11KV CT:PT Units . Cross section area of each turn of A PT winding (in sqmm.) i) i) Primary winding 0.029 sqmm ii) Secondary winding 1.1 sqmm B Nos. of turns i) Primary winding 10440 ii) Secondary winding 105 C Winding Material i) Primary winding Copper ii) Secondary winding Copper 21. i. Method of Identification of Primary terminals To be Indicated ii. a. Secondary terminals CT’s To be Indicated To be Indicated b. PT’s To be Indicated 22. i. ii. 23. i. Size and material of Primary Studs To be Indicated Secondary Studs To be Indicated Method of jumpering /connection of: Primary winding of CT/PT with primary terminals Secondary winding if CT/PT with Secondary terminals ii. 92 33KV CT:PT Units AM –BM-CM AL- BL- CL as1 –bs1 –cs1 as2 –bs2 –cs2 a –b –c 4n. 20mm Brass 6mm Brass To be Indicated To be Indicated TEST CERTIFICATE FOR 11KV CT:PT UNIT COSTOMER NAME ORDER REF. S.N FRE O. TYPE Q SYSTEM VOLTAGE/H.S.VOLTAGE CURRENT TRANSFORMER NOMINAL RATIO CLASS BURDEN PRY, TH CURRENT STC RATING NO OF CT PER UNIT REF. STANDARD NOMINAL RATIO CLASS BURDEN 0.5 15 VA 120 %OF Ip 13.5 KA FOR 1 SEC 3 I.L. OVF/TIME CONNECTION NO OF PT PER UNIT REF. STANDARD .. IS : 2705 (1992) 1.2 CON/1.5 FOR 30 SEC STAR/STAR 1 NO THREE PHASE PT IS : 3156 (1992) POTENTIAL TRANSFORMERS ON THIS UNIT WITHSTOOD FOLLOWING TEST SATISFACTORILY. 1. VERIFICATION OF TERMINAL MANKING & POLARITY. 2. HV P.F. TEST INDUCED VOLTAGE TEST) ON PRY WDG. AT 28KV FOR ONE MINUTE. WITHSTOOD 3. HV P.F. TEST ON SECONDARY WINDING 3. HV P.F. TEST ON SECONDARY AT 3 KV FOR ONE MINUTE. WITH STOOD WINDING AT 3 KV FOR ONE MINUTE. WITH STOOD 4. OVER VOLTAGE INTER TURN TEST AT 4. HV P.F. TESTON PRIMARY WDG. A 129 EXTENDED RANG SECONDARY CURRENT 6 KV FOR ONE MINUTE.(SEPARATE AMPS FOR ONE MINUTE. WITH STOOD SOURCE TEST) WITHSTOOD 5. ACCURACY TEST. (RESULT ARE GIVEN 5. ACCURACY TEST. (RESULT ARE BELOW) GIVEN BELOW) SL.NO.OF UNIT THE RETIO AND PHASE ERROR FOR CURRENT TRANSFORMER CLASS 0.5 BURDEN 15 VA TEST PF 0.8 LAG AT 100% VA/UPF AT 25% CT OF PHASE A CT OF PHASE B CT OF PHASE C 25% 100% 25% 100% 25% 100% BURDEN BURDEN BURDEN BURDEN BURDEN BURDEN R.Er Ph.Er R.Er Ph.Er R.Er Ph.Er R.Er Ph.Er R.Er Ph.Er R.Er Ph.Er ror ror ror ror ror ror ror ror ror ror ror ror % OF PRY CURRENT TRANSFORMERS ON THIS UNIT WITHSTOOD FOLLOWING TEST SATISFACTORILY. 1. VERIFICATION OF TERMINAL MANKING & POLARITY. 2. HV P.F. TEST ON PRIMARY WINDING AT 28 KV FOR ONE MINUTE. WITH STOOD 11KV/110V 0.5 50 VA 93 CURRENT % (Min. ) % (Min. ) % (Min. ) % (Min. ) % (Min. ) % 12 0 20 2 6 SL.NO.OF UNIT CURRENT% OF PRY THE RATIO AND PHASE ERROR FOR POTENTIAL TRANSFORMER CLASS 0.5 BURDEN 50 VA TEST PF 0.8 LAG. PHASE AS PHASE AC PHASE BC 25% 100% 25% 100% 25% BURDEN BURDEN BURDEN BURDEN BURDEN Ph.Er Ph.Er Ph.Er Ph.Er Ph.Er R.Er R.Er R.Er R.Er R.Er ror ror ror ror ror ror ror ror ror ror (Min. (Min. (Min. (Min. (Min. % % % % % ) ) ) ) ) 10 0 TESTED BY : 11. (Min. ) 100% BURDEN Ph.Er R.Er ror ror (Min. % ) WITNESSED BY : TECHNICAL SPECIFICATIONS OF EARTHING (AS PER IS 3043-1987) Earthing shall generally be carried out in accordance with the requirements of Indian Electricity Rules 1956 amended from time to time and relevant regulations under Electricity Supply Authority concerned. In case of high and extra high voltages, the neutral points shall be earthed by not less than two separate distinct connections with earth, each having its own electrodes substation and will be earthed at any other point provided no interference is caused by such earthing. If necessary, the neutral may be earthed through suitable impedance. As far as possible, all earth connections should be visible for inspection. Each earthing system shall be so designed, that, the testing of individual earth electrodes is possible. It is recommended that the value of any earth system resistance shall be such as to conform to the degree of shock protection desired. It is recommended, that a drawing showing the main earth connections and earth electrodes be prepared for each installation and submitted to STM Division of MPPKVVCL in all three circles. No addition to the current carrying system, either temporary or permanent, shall be made which will increase the maximum available fault current on its duration until it has been ascertained that the existing arrangement of earth electrodes, earth bus-bar etc., are capable of carrying the new value of earth fault current which may be obtained by this addition. All materials, fittings etc., used in earthing shall conform to Indian Standard Specifications, wherever they exist. 94 12 GENERAL REQUIREMENTS AND PROCEDURES FOR EARTHING AT SUBSTATIONS. The ground resistance for sub-stations should not exceed a value 2(two) ohms. The joints/connections in the earthling, system shall be welded only, except the connections, which require opening for testing/maintenance. Such connections should be bolted tightly, using spring and ring washers for proper contact pressure. The G.S. flats to be provided for the horizontally laid earth grid should have overlap welded joints, with length of welding at least twice the width of the flat, e.g., 100 MM for 50x6 MM G.S. flats. There should not be any dirt, grease, oil, enamel, paint or any such non-conductive coatings on the surfaces being joined/ connected. Only the finished joints/connections above ground may be provided with red-oxide or any other protective coating. Under ground earth electrodes and earth grid elements, when laid, should have a clean metallic surface, free from paint, enamel, grease or any such non-conductive coatings. As far as possible, all earth connections should be accessible for visual inspection. No cut-outs, links or switches, other than linked switches arranged to operate simultaneously on the earthed or earthed neutral conductor and the live wire shall be inserted in the supply system. Earth electrodes or mate should not be installed in close proximity to metal fence to avoid possibility of fence becoming live. Separate earth electrodes, isolated from the earth grid, are to be provided for grounding the fence wires. Pipes or rods used as electrodes should be in one piece, as far as possible, with a minimum allowable length of 4.5 mtrs. Except where rock or hard stratum is encountered, the pipe/rod electrodes should be driven into the ground to a minimum depth of 4.5 mtrs. The strip electrodes, forming the horizontal gild, should be buried underground to a minimum depth of 0.5 mtrs. The path of earth wire should be out of normal reach of any person, as far as possible. For high resistivity soils, above 100 Ohm- Mtrs. attempts should be made to bring the soil resistivity in the range of 50 to 60 Ohm-mtrs. By digging and treating the soil mass around the earth grid/electrodes with a mixture of salt and charcoal. In case of rocky top soil and sub-stratum, having very high resistivity, with no scope of improvement by other means, the procedure given below should be followed: 1. At least two bores of diameter little less than 40 mm, with a minimum distance of 10 mtrs. Between them, should be made in the ground at suitable locations inside the S/S yard. The boring should be done until soil sub-stratum rich in moisture and low in resistivity is encountered. G.I. pipes of 40 MM dia. should be descended in each bore, such that, the soil mass around the pipes grips them tightly, Back – filling of bores, if required, with wet soil/clay may be done to ensure this condition. The G.I. pipes in these deep bores should be interconnected with the main earthing grid of the S/S through 50x6 mm G.S. flat, with all the joints/connections and terminations being either fully welded, or clamped/bolted and welded simultaneously. The G.I. pipes in the bores should also be interconnected with each other. In extreme cases, the bores may have to be made at remote locations i.e. outside the S/S yard, with inter-connections, through 50x6 MM flats, as explained before. 2. The procedures to be observed stringently for making connections and joints between various elements of the earthing system are as follows: 95 a. G.S. flat to Structure/flat - The G.S. flat should be welded to the metallic portion (leg) of the structure after thoroughly cleaning the surfaces to be welded. The length of the welding should be at least twice the width of the G.S. flat, e.g.-minimum 100 mm for 50x6 mm G.S. flat. Exactly similar procedure is to be adopted for joints between two G.S. flats. b. G.I. wire to structure. The G.I. wire should be bolted to the structure after making an eye formation and kept tight with the help of spring and ring washer. Then, the entire arrangement should be welded. c. G.I. wire to G.S. flat- The G.I. wire should be bolted and then welded to G.S. flat, as explained above. d. G.I. rod to G.S. flat- The G.I. rod should be securely clamped to the G.S. flat with the help of bolts and washers and the entire arrangement should then be welded. e. G.I. wire to G.I. pipe – GI wire should be bolted to the G.I. pipe and then welded, keeping in view the relevant precautions, mentioned before. f. G.I. flat to G.I pipe – The GI flat should be bolted tightly to the G.I. pipe and then the connection should be welded. Before making connections and joints, it should be ensured that, the elements to be joined have a clean metallic contact surface without any non-conductive coating. Earth Grid System Grid system of interconnected conductors forming a closed loop mesh is to be installed using 50x6 mm GS flat for peripheral and branch conductors. Interconnections are made by welding them. This earth grid will be laid at a depth of about 0.5 mtr. Bonded to general mass of the earth by 4.5mtrs.Long earth electrode of solid GI rod (or pipe) of dia 25mm The G.I. pipe 40 mm. dia 4.5mtrs.Long in the earthing pits, driven vertically. It is to this earth grid that the transformer neutral, apparatus, frame work and other noncurrent carrying metal work associated like transformer tank, switchgear frame etc. are to be connected. All these connections should be made in such a way that reliable and good electrical connection is ensured. Aluminium/ other paint, enamel, grease and scale should be removed from the point of contact before connections are made. No part of the ground connection leads should be embedded in concrete. Arrangement of connection of earth connection shall be as follow: 1. Structures: Structures including frames, metal supports within the substation grid at least two legs, preferably diagonally opposite (where more than two legs are provided) on each metal structure shall be connected to earth grid with GI wire of 4mm dia or 6 mm dia. 2. Isolators/ switches: The operating handle shall be connected to earth grid independent of the structure earthing or through the steel mounting structure, through 4 mm dia G.I. wire. 3. Lightning Arrestor: The bases of lightning arrestors shall be directly connected to the earth electrodes (nods) by 4 or 6 SWG G.I. wires as short and as straight as practicable, to ensure minimum impedance. Separate earth leads should be used for L.A. in each phase. In addition there shall be as direct connections as practicable from the earthed side of the lightning arrestors to the frame of the apparatus being protected. Surge counters, could also be inserted in the circuit where lightning incidences are high, but in such cases, the lightning arrestor should be mounted on insulated base. Invariably, earth connections for lightning 96 arrestors should be separate, and in no case should they be joined looped or meshed with other conductors. For lightning arrestors mounted near transformers, earthing connections shall be done with the earthing pits and earthing leads shall be laid clear of the tank and collars in order to avoid possible oil leakage caused by arcing. The earth connection should not pass through iron pipes, as it would increase the reactive impedance of the connection. 4. Power Transformer: The tank of the transformer shall be directly connected to the main earth grid. In addition there shall be a separate and as direct a connection as practicable from the tank to the earth side of protecting LA using 4 or 6 SWG GI wire. The earthing of the neutral shall be by two separate, distinct and direct connections of 50x6 mm GS flat to earth pits, which form a part of the earth grid, and shall be run clear of the tank and collars. The transformer track rails shall be connected to earth 5. Out door VCB: At least two legs, preferably diagonally opposite of the supporting structure frame work of each circuit breaker unit shall be connected to the earth grid, through 50x6 mm G.S. flats. 6. Fencing: All metal fencing wire-mesh and fencing poles (if metallic) where provided shall be separately earthed through earth rods isolated from the main earth grid. Gates shall have each support post (if metallic) earthed by means of through earth rods isolated from the main earth grid. 7. Current transformers / potential transformers: The bases of the current transformers should be directly connected to the earth grid through 4 or 6 SWG G.I. wires. The base (neutral side) of the P.Ts. should be directly connected to the earth grid through 4 or 6 SWG G.I. wires. Separate earth leads should be used for P.Ts. in each phase. The termination of leads on the P.T. neutral should be bolted/clamped and not welded, to facilitate opening of the earth connection for testing purposes. In addition, all bolted cover plates to which bushings are attached, should be connected to the earth grid, both in case of C.Ts. and P.Ts. 8. Cables and Supports: 9. Armouring of armoured metal-sheathed cables within the station grid area shall be connected to the earth grid. 10. Substation L.T. Supply Transformer: Same as above except that the neutral earthing conductor used shall be 4 or 6 SWG G.I. wire. 11. Capacitor Banks: Same as before. Note for drawing of earthing systems for 33/11 kV Substations: 1. The earth rods (19 nos.) shall be 3 mtrs. long 25 mm dia solid GI rods driven into the ground (not to be painted, enamelled, greases etc) 2. The earthing pits (3 nos.) shall consist of 4.5 mtrs. long 40 mm GI pipes buried vertically inside the ground (not to be painted enamelled grease etc.) 97 3. All joints in the earthing grid shall be welded only. The GS flats in the earth mat should be joined by overlap welded joints, with welding length at least twice the width (i.e. 100 mm) 4. The fencing/ gates are to be kept isolated from the main earthing grid and metallic portions of the fences gates (if having metallic support posts) are to be earthed separately. Separate earth pipe as per scope of work to be provided for fence Earthing. Earthing pipe should be made of 40 mm diameter ISI marked B class GI Pipe. 12 mm dia suitable holes on its circumference shall be made as per approved drawing. The pipe should be in one piece. No joints or welding would be allowed on its length. Clamps made of 50x6mm GI flat duly drilled with 12 mm size holes should be welded at the top end for connection of earth conductor. The Earthing pipe should not contain any joints in length. Pipe used shall be 40mm NB diameter, ISI marked Galvanized Mild Steel Tubes continuously welded Electric Resistance Welded ERW/High Frequency Induction welded (HFIW)/Hot finished welded (HFW) type, conforming to IS-554-1985 with latest amendment of MEDIUM quality (Class B). MANUFACTURE: GI earth pipe (40 mm diameter & 4.5metre long) shall be made of tubes which shall be made from tested quality steel manufactured by any approved process as follows: a) Electric Resistance Welded (ERW). b) High Frequency Induction Welded (HFIW) and c) Hot finished Welded (HFW). Tubes made by manual welding are not acceptable. DIMENSIONS: The dimensions and weights of tubes shall be in accordance with Table-I and Table-II of IS: 1239 (Part-I)/1990 with latest amendments, subject to tolerance permitted therein. Necessary 12 mm diameter holes across the circumference shall be provided as per approved drawing. Drawings shall be approved by the owner before start of the manufacturing work. The tube, earthing pipe shall be provided with 50x6mm GS clamps on one end, one clamp is to be welded with the pipe and another is removable to enable measurement of earth resistance of the pit. Other end of the earth pipe should be cut half in slop to make it a sharp. GALVANIZING: Tubes shall be galvanized in accordance with IS-4736-1986 with latest amendment for not dip zinc coating of Mild Steel Tubes. The minimum mass of zinc coating on the tubes shall be in accordance with clause 5.1 of IS-4736-1986 (specification for hot dip zinc) and when determined on a 100mm long test piece in accordance with IS: 6745:1972 shall be 400 g/m2. The zinc coating shall be uniform adherent reasonably smooth and free from such imperfections as flux, ash and dross inclusions, bare patches, black spots, pimples, lumpiness, rust, stains, bulky white deposits and blisters. HYDRAULIC TEST: (Before applying holes) Each tube shall withstand a test pressure of 5 M Pa maintained for at least 3 seconds without showing defects of any kind. The pressure shall be applied by approved means and maintained sufficiently long for proof and inspection. The testing apparatus shall be fitted with an accurate pressure indicator. TEST ON FINISHED TUBES AND SOCKETS: The following tests shall be conducted by the manufacturer of finished tubes and sockets. 98 1. The tensile strength of length of strip cut from selected tubes when tested in accordance with IS-1894-1972, (Method for tensile testing of steel tubes), shall be at least 320N/mm2. 2. The elongation percentage on a gauge length of 5.65/so (where so is the original cross-sectional area of test specimen) shall not be less than 20%. 3. When tested in accordance with IS-2329-1985 (Method for Bend test on Metallic tubes) the finished tube shall be capable of with standing the bend test without showing any sign of fracture or failure. Welded tubes shall be bent with the weld at 90 degree to the plane of bending. The tubes shall not be filled for this test. 4. Galvanized tubes shall be capable of being bent cold without cracking of the steel, through 90 degree round a former having a radius at the bottom of the groove equal to 8 times the outside diameter of tube. 5. Flattening Test on Tubes above 50 mm Nominal Bore: Rings not less than 40 mm in length cut from the ends of selected tubes shall be flattered between parallel plates with the weld, if any, at 90 degree (point of maximum bending) in accordance with IS-2328-1983. No opening should occur by fracture in the weld unless the distance between the plate is less than 75 percent of the original outside diameter of the pipe and no cracks or breaks in the metal elsewhere than in the weld shall occur, unless the distance between the plates is less than 60% of the original outside diameter. The test rings may have the inner and outer edges rounded. 6. GALVANISHING TEST: Weight of zinc Coating: For tubes thickness upto 6 mm the minimum weight of zinc coating, when determined on a 100 mm long test piece in accordance with IS-4736-1986 shall be 400 grm/m2. The weight of the coating expressed in gram/m2 shall be calculated by dividing the total weight of the zinc (inside plus outside) by the total area (inside plus outside) of the coated surface. Test specimen for this test shall be cut approximately 100 mm in length from opposite ends of the length of tubes selected for testing. Before cutting the test specimen, 50 mm from both ends of the samples shall be discarded. 7. Free Bore Test: A rod 230mm long and of appropriate diameter shall be passed through relevant nominal bore of the sample tubes to ensure a free bore. 8. Uniformity of Galvanized Coating: The galvanized coating when determined on a 100 mm long test piece [see V (a) (iii)] in accordance with IS-2633-1986 (Method for testing uniformity of coating on zinc coated articles) shall with stand 4 one minute dips. WORKMANSHIP: The tubes shall be cleanly finished and reasonably free from injurious defects. They shall be reasonably straight, free from cracks, surface flaws, laminations, and other defects, both internally and externally. The screw tubes and sockets shall be clean and well-cut. The ends shall be cut cleanly and square with the axis of tube. MARKING 99 The medium class of tubes shall be distinguished by Blue colour bands which shall be applied before the tubes leaves the manufacturers’ works. Tubes shall be marked with the standard mark. 12. TECHNICAL SPECIFICATIONS OF 11 KV / 33 KV ISOLATORS SCOPE This specification provides for design, manufacture, testing at manufactures works, delivery of outdoor station type 11KV and 33KV (Local) manual operating mechanism isolating without/ with earthing blades and complete in all respect with bi-metallic connectors. Operating mechanism, fixing details etc. shall be as described herein. PARTICULARS OF THE SYSTEM The isolators to be provided under this specification are intended to be used on 3 phase A.C. 50 cycles, effectively grounded system. The nominal system voltages are 11 kV & 33 kV respectively. STANDARD The Isolator shall comply in all respects with IS: 9921 or IEC Publication No.: 129. Equipment meeting any other authoritative standard which ensures an equal or better quality than the standard mentioned above will also be accepted. TYPE & RATING Isolators shall have three posts per phase, triple pole single throw, gang operated outdoor type silver plated contacts with horizontal operating blade and isolators posts arranged vertically. The isolators will be double break type. Rotating blade feature with pressure relieving contacts is necessary i.e. the isolator shall be described in detail along-with the offer. However, the design of turn & twist arrangement shall be subject to owner’s approval. (Banging type feature is not acceptable). All isolators shall operate through 90 degree from their fully closed position to fully open position, so that the break is distinct and clearly visible from the ground level. The equipment offered by the tenderer shall be designed for a normal current rating of 600 A for 11 KV & 800 A for 33 KV suitable for continuous service at the system voltage specified herein. The isolators are not required to operate under load but they must be called upon to handle magnetization currents of the power transformers and capacitive currents of bushings, bus-bars connections, very short lengths of cables and current of voltage transformers. The rated insulation strength of the equipment shall not be lower than the levels specified in IS 9921 JEC publication No. 129, which are reproduced below Standard Rated Standard Impulse One minute power declared voltage of withstand Voltage frequency withstand voltage the Isolator positive kV polarity voltage KV (RMS) kv/rms (peak) Across the To earth and Across the To earth and isolating between isolating between distance poles distance poles 11 KV 12 85 75 45 35 33 KV 36 195 170 100 75 The 11 KV and 33 KV isolators are required with post insulators but with mounting structures. The isolators should be suitable for mounting on the Boards standard 100 structures. The isolators shall be supplied with base channels along with fixing nuts, bolts and washers for mounting on the structured. TEMPRATURE RISE The maximum temperature attained by any part of the equipment when in service at site under continues full load conditions and exposed to the direct rays of Sun shall not exceed 45 degree centigrade above ambient temperature. ISOLATOR INSULATION Isolation to ground, insulation between open contacts and the insulation between phases of the completely assembled isolating switches shall be capable of withstanding the dielectric test voltage specified above. MAIN CONTACTS All isolators shall have heavy duty self-aligning and high pressure line type fixed contacts of modern design and made of hard drawn electrolytic copper. The fixed contact should be of reverse loop type. The various parts shall be accordingly finished to ensure inter- changeability of similar components. The fingers of fixed contacts shall be preferably in two pieces and each shall form the reverse loops to hold fixed contacts. The fixed contacts would be placed in ‘c’ clamp. The thickness of ‘C’ clamp shall be adequate. This channel shall be placed on a channel of adequate thickness. This channel shall be welded on an insulator mounting plate of 8mm thickness. The spring of fixed contact shall have housing to hold in place. This spring shall be made of stainless steel with adequate thickness. The pad for connection of terminal connector shall be of aluminium with thickness not less than 12 mm. The switch blades forming the moving contacts shall be made from tubular section of hard drawn electrolytic copper having outer dia not less than 38 mm and thickness 3 mm. These contacts shall be liberally dimensioned so as to withstand safely the highest short circuit and over voltage that may be encountered during service. The surfaces of the contacts shall be rendered smooth and silver plated. The thickness of silver plating shall not be less than 15 microns for 11 KV and 25 microns for 33 KV. In nut shell, the male and female contact assemblies shall be of robust construction and design of these assemblies shall ensure the same. Electro-dynamic withstands ability during short circuit without any risk of repulsion of contacts. The current density in the copper parts shall not be less than 2 Amp/sq.mm and aluminium parts shall be less than 1 Amp/sq.mm. Thermal withstand ability during short circuit. Constant contact pressure even when the live parts of the insulator stacks are subjected to tensile stresses due to linear expansion of connected bus bar of flexible conductors either because of temperature verification or strong winds wiping action during closing and opening. Self - alignment assuring closing of the switch without minute adjustment. The earthing switch should be provided with three sets of suitable type of fixed contacts below the fixed contacts assemblies of the main switch on the incoming supply side and the sets of moving contacts having ganged operation. These contacts shall be fabricated out of electrolytic copper for 33 KV isolators with earth switch and designed to withstand current on the line. Arcing contacts / Horn: Arcing contacts are not required. Auxiliary switches : Auxiliary switches are not required. 101 CONNECTORS The connectors for 11KV isolator shall be made of Aluminium alloy LM-9 or LM-25 and shall be suitable for Squirrel, Weasel and Rabbit ACSR Conductors for 11KV and Raccoon/Dog conductors for 33 KV with horizontal and vertical take-off arrangement. The details in regard to dimensions, the number of bolts to be provided, material and manufacture shall be furnished by the bidder for owner approval before manufacturing. The groove provided in the connection should be able to accommodate conductor size mentioned above smoothly. The design of clamps shall be to MPPKVVCL approval. The clamps to be offered should be manufactured by gravity die-casting method only and not by sand casting process. It is necessary that suitable clamps are offered along with the isolator and also it is obligatory to give complete technical particular of clamps along with the drawing, as per details given above and also as per following detail. The terminal connector shall be manufactured and tested as per IS: 5561. All castings shall be free from blow holes, surface blistors, cracks and cavities. All the sharp edges shall be blurred and rounded off. No part of the clamp shall be less than 12 mm thick. All current carrying parts shall be designed and manufactured to have minimum contact resistance. Connectors shall be designed to be corona free in accordance with the requirement of IS: 5561. All nuts and bolts shall be made of stainless steel only. Bimetallic sleeve/liner shall be 2 mm thick Wherever necessary, bi-metallic strip of standard quality and adequate dimension shall be used. POST INSULATOR 11KV / 33KV insulators shall be of reputed make subject to owner approval. The post insulators for the above 11 KV isolators shall comprise of three numbers 11 KV insulators per stack and 9 such stack shall be supplied with each isolator. Similarly, for 33 KV isolators, two numbers 33 KV insulators per stack and 9 stacks shall be supplied with each isolator. The insulator stack shall conform to the latest applicable Indian or IEC standard and in particulars to the IS; 2544 specification for porcelain post insulators. The porcelain used for manufactures of insulators shall be homogeneous, free from flaws or imperfections that might affect the mechanical or dielectric quality, and they shall be thoroughly vitrified, tough and impervious to moisture. The glazing of the porcelain shall be uniform brown colour, free from glisters, burns and other similar defects. Insulators of the same rating and type shall be interchangeable. The porcelain and metal parts should be assembled in such a manner that any thermal expansion differential between the metal and the porcelain parts throughout the range of temperature variation shall not loosen the parts or create undue internal stresses which may affect the electrical or mechanical strength and rigidity. Each cap and base shall be of high-grade cast steel or malleable steel casting and they shall be machine faced and smoothly galvanised. The cap and base of the insulators shall be interchangeable with each other. The tenders shall in variably enclose with the offer, the type test certificate and other relevant technical guaranteed particulars of insulators offered by them. Please note that isolators without type test certificates will not be accepted. Each 11KV / 33KV Post Insulators used in the isolators should have technical particulars as detailed below:102 11KV 33KV 1. Nominal system voltage KV (rms) 11 33 2. Highest system voltage KV (rms) 12 36 3. Dry P.F. One minute with stand KV (rms) 35 75 4. Wet PF one minute withstand KV (rms) 35 75 5. P.F. Puncture withstands test voltage KV 1.3 time the actual dry flash over voltage of the unit. 6. Impulse voltage withstand test KV (peak) 75 170 7. Visible discharge test KV voltage 9 27 8. Creepage distance mm (min) 320 580 9. Tensile strength in KN 10KN 16KN For 33 KV Isolators: In place of 33 KV Post Insulator the composition of 2 units of 22KV Post Insulators per stack complying the following parameters are acceptable:1. Nominal system voltage : 33 KV 2. Highest system voltage : 36 KV 3. Impulse voltage withstand : 170 KV 4. Power frequency wet withstand voltage : 75 KV 5. Height of stack : 500 mm 6. Creepage distance (Minimum) : 840 mm 7. Tensile Strength : 30KN 8. Bending strength : 4.5KN Operating Mechanism for 11KV / 33KV Isolators:All Isolators and earthing switches shall have separate dependent manual operation. The Isolator should be provided with padlocking arrangements for locking in both end position to avoid unintentional operation. For this purpose Godrej make 5 lever brass padlocks having high neck with three keys shall be provided. The isolating distances should be visible for isolators. The Isolators and Isolators with earth switch inclusive of their operating mechanism should be such that they cannot come out of their open or close position by gravity wind pressure, vibrations reasonable shocks or accidental touching of connecting rods of the operating mechanism. Isolators should be capable of resisting in closed position, the dynamic and thermal effects of maximum possible short circuit current at the installation point. They shall be so constructed that they do not open under the influence of the short circuit current. The operating mechanism should be of robust construction and easy to operate by a single person and conveniently located for local operation in the switchyard. Provision for earthing of operating handle by means of 8 SWG GS wire must be made. PIPES 103 Tandem pipes operating handle shall be class B ISI marked type having at least 24mm internal diameter for 11KV/33KV isolator. The operating pipe shall also be class B ISI marked with internal diameter of at least 32 mm and 38 mm for 11 KV and 33KV isolators respectively. The pipe shall be terminated in to suitable universal type joints between the insulator bottom bearing and operating mechanism. BASE CHANNEL The Isolator shall be mounted on base fabricated from steel channel section of adequate size not less than 75x40x6 mm for 11KV and 100x50x6 mm for 33KV To withstand total weight of isolator and insulator and also all the forces that may encounter by the isolator during services, suitable holes shall be provided on this base channel to facilitates it’s mounting on our standard structures. The steel channel in each phase shall be mounted in vertical position and over it two mounting plates at least 8mm thick with suitable nuts and bolts shall be provided for minor adjustment at site. CLEARANCES We have adopted the following minimum clearance for isolators in our system .The bidder should therefore keep the same in view while submitting their offers: Description Centre distance between Poles (Centre to Centre) i.e. Phase to Phase clearance 75 Cm 120 Cm 11 KV Isolator 33 KV Isolator Distance between centre lines of outer posts on same pole 60 Cm 97 m 13. TECHNICAL SPECIFICATIONS OF 11 KV & 33 KV AIR BREAK SWITCHES SCOPE This specification provides for manufacture, testing at works and supply of 11KV & 33KV AB switches. The 11KV and 33 KV AB switches shall conform to IS: 9920 (PartI to IV) AB SWITCHES The 11KV & 33KV Air Break Switches are required with two poles in each phase. The AB Switches shall be supplied complete with phase coupling shaft, operating rod and operating handle. It shall be manually gang operated and vertically break and horizontal mounting type. The equipment offered by the bidder shall be designed for a normal current rating of 400 Amps and for continuous service at the system voltage specified as under: i) 11 KV AB Switch : 11KV + 10% : 33 kV + 10% continuous50C/ssolidly Gr ounded ii) 33KV AB Switch 104 Earthed neutral system -do- The length of break in the air shall not be less than 400 mm for 11KV AB Switches and 500 mm for 33 KV AB Switches. The 11KV & 33KV AB Switches are required with post insulators. The AB switches should be suitable for mounting on the structure. The mounting structure will be arranged by the bidder. However, the AB Switches shall be supplied with base channel for mounting on the structure which will be provided by the owner. The phase to phase spacing shall be 750mm in case of 11KV AB Switches & 1200mm in case of 33KV AB Switches. POST INSULATORS The complete set of three phase AB Switches shall have stacks of post insulators. 11KV AB Switches : 3 No. 11KV Post Insulator per stack 33KV AB Switches : 3 No. 33KV Post Insulator per stack The post insulators should conform to the latest applicable Indian standards IS: 2544 Specification for Porcelain Post insulator of compact solid core or long rod insulators are also acceptable. Creepage distance should be adequate for highly polluted outdoor atmosphere in open atmosphere. The porcelain used for manufacture of AB Switches should be homogeneous free from flaws or imperfections that might affect the mechanical dielectric quality. They shall be thoroughly vitrified, tough and impervious to moisture. The glazing of the porcelain shall be of uniform brown in colour, free from blisters, burns and other similar defects. Insulators of the same rating and type shall be interchangeable. The porcelain and metal parts shall be assembled in such a manner that any thermal expansion differential between the metal and porcelain parts through the range of temperature variation shall not lose the parts or create undue internal stresses which may affect the electrical or mechanical strength. Cap and base of the insulators shall be interchangeable with each other. The cap and base shall be properly cemented with insulators to give perfect grip. Excess cementing must be avoided. Each 11KV & 33KV Post Insulators should have technical particulars as detailed below: Sr. Description 11 kV 33 kV No i Nominal system voltage kV (rms) 11 33 ii Highest system voltage kV (rms.) 12 36 iii Dry Power Frequency one kV minute withstand 35 75 voltage (rms) in KV iv Wet Power frequency one minute withstand voltage 35 75 (rms) in KV v Power Frequency puncture kV (rms) voltage 1.3 times the actual dry flashover voltage vi Impulse withstand voltage kV (Peak) 75 170 vii Visible discharge voltage kV (rms) 9 27 viii Creepage distance in mm (minimum) 320 580 The rated insulation specified below:Sl. Standard No declared voltage KV/RMS level of the AB Switches shall not be lower than the values Rated Voltage of the AB Switches Standard impulse with One Minute power frequency stand voltage (positive withstand voltage kV (rms) & negative polarity kV (Peak) 105 i ii 11KV 33KV 12KV 36KV Across the Isolating distance 85KV 195KV To earth & Across between Isolating poles distance 75KV 32KV 170KV 80KV the To earth & between poles 28KV 70KV TEMPERATURE RISE The maximum temperature attained by any part of the equipment when in service at site under continuous full load conditions and exposed to the direct rays of Sun shall not exceed 45 degree above ambient. MAIN CONTACTS AB Switches shall have heavy duty self-aligning type contacts made of hard drawn electrolytic copper/brass. The various parts should be accordingly finished to ensure interchange ability of similar components. The moving contacts of the switch shall be made from hard drawn electrolytic copper brass. This contact shall have dimensions as per drawing attached so as to withstand safely the highest short-circuit currents and over voltage that may be encountered during service. The surface of the contact shall be rounded smooth and silver-plated. In nut shell the male and female contact assemblies shall ensure. 1. Electro-dynamic withstands ability during short circuits without any risk of repulsion of contacts. 2. Thermal withstands ability during short circuits. 3. Constant contact pressure even when the lower parts of the insulator stacks are subjected to tensile stresses due to linear expansion of connected bus bar of flexible conductors either because of temperature variations or strong winds. 4. Wiping action during closing and opening. 5. Fault alignment assuring closing of the switch without minute adjustments. CONNECTORS The connectors shall be made of hard drawn electrolytic copper or brass suitable for Raccoon/Dog ACSR conductor for both 11KV & 33KV AB Switches. The connector should be 4 -bolt type. OPERATING MECHANISM All AB Switches shall have separate independent manual operation. They should be provided with ON/OFF indicators and padlocking arrangements for locking in both the end positions to avoid unintentional operation. The isolating distances should also be visible for the AB Switches. The AB Switch will be supplied with following accessories: Sl Item Size of 11KV AB Size of 33KV AB No Switch Switch i Operating Rod (GI dia) ISI Length 5.50 meter Length 5.50 mtrs dia: mark 25MM 40MM ii Phase coupling square rod Length 1800 mm Size Length 2700 mm (GI) ISI mark 25x25 mm Size 40 x 40 mm iii Hot dip galvanized 1 No. 1 No. Operating handle (GI) 106 The AB Switches shall be capable to resist any chance of opening out when in closed position. The operating Mechanism should be of robust constructions, easy to operate by single person and to be located conveniently for local operation in the switchyard. The GI pipe shall conform to ISS: 1239-68 and ISI marked by embossing. The vertical down rod should be provided with adequate joint in the mid-section to avoid bending or buckling. Additional leverage should be provided to maintain mechanical force with minimum efforts. All iron parts should be hot dip galvanized. All brass parts should be silver plated and all nuts and bolts should be hot dip galvanized. ARCING HORNS It shall be simple and replaceable type. They should be capable of interrupting linecharging current. They shall be of first make and after break type. BUSH The design and construction of bush shall embody all the features required to withstand climatic conditions specified so as to ensure dependable and effective operations specified even after long periods of inaction of these Air Break Switches. They shall be made from highly polished Bronze metal with adequate provision for periodic lubrication through nipples and vent. DESIGN, MATERIALS AND WORKMANSHIP All materials used in the construction of the equipment shall be of the appropriate class, well finished and of approved design and material. All similar parts should be accurately finished and interchangeable. Special attention shall be paid to tropical treatment to all the equipment, as it will be subjected during service to extremely severe exposure to atmospheric moisture and to long period of high ambient temperature. All current carrying parts shall be of nonferrous metal or alloys and shall be designed to limit sharp points/edges and similar sharp faces. The firm should have the following type test certificate. The type test should be from CPRI or equivalent lab:1. Test to prove capability of rated peak short circuit current and the rated short time current. The rated short time current should correspond to minimum of 10K Amp and the peak short circuit current should correspond to minimum of 25K Amps. 2. Lightning impulse voltage test with positive & negative polarity. 3. Power Frequency voltage dry test and wet test 4. Temperature rise test 5. Mill volt drop tests The above tests should be performed on the AB Switches, manufactured as per owner approved drawing with the specification. Along with the type test certificate, the certified copy of the drawing (from the testing lab) should also be kept for inspection of our officer. Also the test certificates should not be older than 5 years from the date of opening of tender. Dimension of 11 & 33KV AB Switches in (Max.).Tolerance 5%. Sl. Particulars 11KV AB Switch 33KV AB Switch i MS Channel 450x75x40 675x100x50 ii Creepage 320mm (Min) 580mm (Min) distance of 107 iii iv Post Insulator Highest of Port 254 mm shell Fixed contact assembly i) Base 165x36x8 Ii) Contact 70x30x6 Iii) GI cover 110x44 v) Spring 6 Nos. Moving Contact Assembly i Base Assembly ii Moving iii Bush iv Thickness of Grooves Connectors i Connector 368 mm 165x36x8 70x30x6 140x44 6 Nos. 135x25x8 180x25x9 Bronze Metal 7 170x40x8 290x25x14 Bronze Metal 11 60x50x8 (Moving & 60x50x8 (Moving & fix both) fix both) The bidder should provide AB Switches with terminal connectors, set of insulators, mechanical inter works and arcing horns sets. The base channel for the mounting of AB Switches shall also be included in the scope of AB Switches. The operating mechanisms together with down pipe operating handle etc. are also included in the scope of supply 14. TECHNICAL SPECIFICATIONS OF 11 KV DO FUSE UNITS SCOPE This specification provides for manufacture, testing at works before dispatch and delivery of 11 KV DO Fuse units. This covers outdoor open, drop-out expulsion type fuses suitable for installation in 50Hz 11KV distribution system. APPLICATION The D.O. Fuses are intended for use on Distribution transformers for protection/isolation of the same during overload or fault conditions. APPLICABLE STANDARD Unless otherwise modified in this specification, the drop out fuse shall conform to IS: 9385 (Part-I) to III) as amended from time to time. DROP OUT FUSES The drop-out fuses shall be expulsion type. This shall be ‘D’ type and out-door lift off type suitable for manual operation by an operating rod from the ground level. The drop out operation will be angular in vertical plane. The equipment offered, shall be suitable for 11KV three phase 50 C/S solidly grounded earthed neutral systems. It shall be designed for a normal current rating of 200 Amps. 108 The drops out fuses are required with Post Insulators. These shall be suitable for mounting on the structure. The bracket/channel hardware for DO Fuses shall be provided with adequate sizes of nuts, bolts and washer for mounting on the structures. POST INSULATORS Each 11KV DO Fuse shall have two Nos 11 KV Post Insulators. The insulator shall conform to IS: 2544 of 1973 with latest amendment. The porcelain used for manufacture of DO Fuse units shall be homogeneous, free from flaws or imperfections that might affect the mechanical or dielectric strength. They shall be thoroughly vitrified tough and impervious to moisture. The glazing of the porcelain shall be of uniform brown colour free from blisters, burns and other similar defects. Insulators of the same rating and type shall be interchangeable. The porcelains and metal parts shall be assembled in such a manner that any thermal expansion differential between the metal and porcelain parts through range of temperature variation shall not loosen parts or create undue internal stresses which may affect the electrical or mechanical strength and rigidity. Each cap and base pin shall be made of high-grade cast steel or malleable steel casting and they shall be machine faced and smoothly galvanized. The cap and base shall be properly cemented with insulators to give perfect grip. Excess use of cement shall be avoided. The agency shall invariably enclose with the offer, the type test certificate of MPPKVVCL design DO Fuse along with certified copy of the drawing and other relevant technical guaranteed particulars. Please note that offers without the type test reports / certificates will not be entertained and may be rejected. Each 11KV Post Insulators should have technical parameters as detailed below:S.No. Particulars i Nominal system voltage KV (rms) 11 ii Highest system voltage KV (rms) 12 iii Dry Power Frequency with stand voltage KV 35 (rms) iv Power Frequency puncture voltage KV (rms) 1.3 times the actual dry flashover voltage v Impulse withstand voltage KV (rms) 75 vi Visible discharge voltage KV (rms) 9 vii Creepage distance in mm (minimum) 320 viii Cantilever strength (KN) 6.60 As stated above unless otherwise modified in this specification the drop out shall conform to IS: 9385 (Part-I to III) and as amended from time to time. RATED VOLTAGE The rated voltage shall be 11KV for 11KV DO Fuses respectively. RATED CURRENT The rated current shall be 200 Amp. For 11KV DO Fuses RATED LIGHTNING IMPULSE WITHSTAND VOLTAGE VALUES FOR THE FUSE BASE The rated lightning impulse withstands voltage both for positive and negative polarities shall be as given below:109 a b To earth and between poles 75KV Peak Across the isolating distance of 85KV Peak fuse base RATED ONE MINUTE POWER FREQUENCY WITHSTAND VOLTAGE (DRY AND WET) VALUES FOR THE FUSE BASE a) To earth and between poles 28KV Peak b) Across the isolating distance of 32KV Peak fuse base RATED BREAKING CAPACITY The rated breaking capacity shall be 8KA (A symmetrical). Submission of type test certificate of rated breaking capacity in case of 11KV DO FUSE Unit is essential. MAIN CONTACTS The main contacts of the D.O. Fuse shall be suitable for heavy duty, properly aligned and made from Brass material. These shall have good finish and smooth surface and shall be silver-plated. All the sharp edges shall be rounded off. These contacts shall be so designed to withstand highest short circuit breaking current that may be encountered during service. In nutshell the contact assembly shall ensure. 1. Electrodynamics withstands ability during short circuit without any risk of repulsion of contact. 2. Thermal withstands ability during short circuits. 3. Constant contact pressure even when the lower parts of the insulator stacks are subjected to tensile stresses due to linear expansion of connected bus bar or flexible conductors either because of temperature variation or strong winds. 4. Proper alignment to ensure smooth operation of D.O. Fuse without adjustment. CONNECTORS The connectors shall be made from Brass suitable for ACSR Squirrel, Weasel, Rabbit and Raccoon. The connectors should be bolted type having 4 bolts & groove to hold the conductor. All brass parts should be silver plated for corrosion resistance and efficient current flow. All ferrous parts should be hot dip galvanized as per the latest version of IS: 2633. Nuts and bolts shall conform to IS: 1364 and should be hot dip galvanized. Spring washer should be Electro galvanized. FLY NUTS These shall be provided at both the ends of SRBP tube for tightening the fuse elements. The nut shall be provided with one flat washer of 25mm dia. The arrangement shall be made to ensure that the fuse wire runs centrally inside the SRBP tube after tightening. SPRING STRIPS The spring strips shall be of phosphone bronze multi line brush type having a high pressure contacts and should retain its tension under minimum continuous service current of 200 Amps at 90 degree C. OPERATING HOOKS The brass operating hook shall be fixed over the SRBP tube in such a way that the barrel can be removed for replacing the fuse element by operating rod from the ground level. The drop out fuse units shall operate efficiently; speed of operation shall not depend on the inclination of the fuse. However, the inclination of the fuse barrel shall be adjusted in such a way that the barrel does not drop by gravitational force. 110 D.O. BARRELS The D.O. Fuse Barrels shall be made from SRBP and shall conform to BSS: 1314. The agency shall furnish the test certificate for the fuse barrels offered for use in the drop out fuses along with each lot offered for inspection to the inspecting officer. The test certificates of SRBP barrel should indicate the following test results:i. Dimension a) External dia : b) Wall thickness : c) Internal dia : ii. Max. wrapping in 12” length of the tube : iii. Axial electric strength (Proof test in oil : The barrel should with stand this test at 90 degree C at 25KV rms 50 C/s) satisfactorily for one minute iv. Radial electric strength (Proof test in oil : -doat 90 degree C at 19KV rms 50 C/s.) v. Surface electric strength (Proof test in air : -doat room temp.(32 degree C) at 14KV rms at 50 C/s. vi. Water absorption in 14 hours : vii. Resistance to Hot Oil : viii. Cohesion between layers : ix. Machine ability : The agency should indicate the name of manufacturers of SRBP roles from where they will purchase the barrels to make available the test certificate. The barrels should have the properly to resist fire whenever the fuse is blown off. It should not catch fire easily during blowing off of fuse element inside the barrel which causes short time high temperature. DESIGN, MATERIALS AND WORKMANSHIP All materials used in the construction of the equipment shall be of the appropriate class, well finished and of approved design and material. All similar parts should be accurately finished and interchangeable. The connecting of cap and pin with insulator should be perfect to avoid any kind of loosening. After cementing the insulator should be cured adequately in water to attain good gripping. TESTS Each D.O. Fuse units shall strictly comply with requirement of all the type tests and shall be subjected to all routine tests stipulated in the relevant standard. All tests shall be made prior to despatch in the presence of the representative of the owner. No material should be despatched without prior approval of the tests certificate by the owner. Along with the inspection report of D.O. Fuse Units, the agency should invariably furnish Routine Test Certificate of DO Fuse barrels & Post insulator from their respective manufacturers. Each DO Fuse shall be provided with name plate of size 2” x 1” on steel strip in case of 11KV and size 4” x 2” on steel channel in case of 33KV and shall be either riveted bolted or pasted. The following shall be indicated on the plate:1. Name of manufacturer 2. Sl. No. of the equipment 3. Rating……………………. Amps………………….Volts 111 Please note paper should not be used for name plate. Aluminium sheet of at least 2 mm thick embossed with above marking should be provided on the equipment for identification. The material should be packed in Wooden cartoons. DIMENSION S.No. Particulars Dimension of D.O. Fuse Unit in mm 11KV 1 Drawing No. 2 G.S. Flat 245 x 25 x 6 3 G.S. Channel 4 Fuse Barrels 330x25x14 5 Lower Contact Hinge of Barrel i Connectors 60x60x6 ii Hinge Contact Length 95 iii -doWidth 85 iv Thickness of Hinge Outer 5 Inner 4 6 Barrel take out hook i Width 25 ii Thickness 4 iii Length 30 iv Inner dia meter 25 v Thickness between inner 3 mm outer dia 7 Operating Hook i Width 18 ii Thickness 3 iii Inner Radius 19 iv Outer Radius 22.5 8 Female contact i Main contact width 65 ii Strip thickness 1.5 iii Strip Length 100 iv Width 20 v Female contact height 75 9 Female contact Holder i Length 74 ii Upper width 34 iii Lower width 40 10 Creepage of insulator 320 112 15. TECHNICAL SPECIFICATIONS OF HARD DRAWN STRANDED ALUMINUM AND STEEL-CORED ALUMINUM CONDUCTOR FOR OVERHEAD POWER LINES SCOPE: This specification provides for the Manufacture, Testing before dispatch, supply and delivery of ISI marked Aluminium Conductors Galvanized Steel Reinforced (ACSR) and All Aluminium Alloy (AAA) conductors. STANDARD: The conductor shall strictly comply with the Indian Standard Specification IS: 398 (Part-I & II)/1976 & (Part-IV)/1994 with the latest amendments unless otherwise stipulated in this specification, or any other International Standards which ensure equal or better quality material and workmanship. MATERIAL: The conductors shall be of best quality and workmanship. The steel reinforced aluminium conductors shall be manufactured of hard drawn EC grade aluminium wires and high tensile galvanized steel wires of the sizes as specified in Table-I and with mechanical and electrical properties as specified in Table-II. The coating on the galvanized steel wires may be applied by the hot process or electrolytic process in accordance with IS: 4826-1968 (specifications for galvanized coating on round steel wires). AAA Conductor shall however be constructed of heat-treated aluminium magnesium silicon alloy wire. The wires shall be smooth and free from all imperfections such as spills and splits and rolling and wire drawing defects etc. resulting in reduction in cross-sectional area over the entire length. TOLERANCE: The following tolerance shall be permitted: i) Tolerance on Nominal diameter wires plus/minus 1%. ii) Tolerance on Nominal diameter of High Tensile Galvanized Steel Wires plus/minus 2%. MODULUS OF ELASTICITY AND CO-EFFICIENT OF LINEAR EXPANSION The values of the final modulus of elasticity and co-efficient of linear expansion of ACSR/AAA Conductor shall be as given hereunder: Item No. of Final modulus Co-efficient Density at temp. of 20°C Wires of Elasticity linear GN/mm2 expansion per (Practical) O° C ACSR 6/1 (Al./Steel) 79 ACSR 6/7 (Al./Steel) 76 AAAC 7 0.6324×10-6 kg/cm2 19.1×10-6 for ACSR Conductor 19.8×10-6 for ACSR Conductor 23.0x10-6 Alu. Alloy 7.8 gm/cm3 (Steel) 2.703 gm/cm3 (Aluminium) 7.8 gm/cm3 (Steel) 2.703 gm/cm3 (Aluminium) 2.7 kg/cm3 (Al. Alloy) The wires of Aluminium Alloy Conductor shall be of heat treated aluminium, magnesium, silicon alloy having composition appropriate to the technical and electrical properties as specified in Table-I of IS:398 (Pt-IV)/1994. JOINTS IN WIRES: a) No two joints shall be permitted in the aluminium stranded closer than 15 metres. 113 b) No joints shall be permitted in galvanized steel wires. c) In AAA Conductors there shall be no joint in any wire/stranded conductor containing wires except those made in the base rod or wire before final drawing. Item No. of Wires Aluminium Steel 6 Total 7 Ratio of Alu. wire Lay ratio for dia to steel wire dia aluminium wire Max. Min. 14 10 ACSR Conductor ACSR 6 13 3 14 10 Conductor AAA 6 1 7 N.A. 14 10 Conductor STRANDING The wires used in the manufacture of a stranded conductor before stranding satisfy all requirement of IS: 398 (Part-II & IV)/1976 & 1994 with its latest amendments. The lay ratio of the layer shall be within the limit given above. In all construction, the successive layers shall have opposite directions of lay. The outer most layer being right handed. The wires in each layer shall be evenly and closely stranded. LAY RATIO: The lay ratio (ratio of the axial length of a complete turn of the helix formed by an individual wire in a stranded conductor to the external diameter of the helix) shall be within the limit given above. PACKING AND MARKING: The conductor shall be wound in non-returnable reels or drums conforming to IS: 1778-1961 (Specifications for reels and drums for bare wire) or the latest version thereof. The drums shall be marked with the following details:a) Manufacturer’s Name b) Trade mark, if any c) Drum No. & Identification Number d) Size of Conductor e) Number & lengths of pieces of Conductor on each Drum f) Gross Mass of the Packing g) Net Mass of Conductor h) ISI or relevant International Standard specification mark, if any i) Name and address of the Consignees PACKING CONDITION The reels/drums shall be of such constructions as to assure delivery of conductors free from displacement and damage and should be able to withstand all stresses due to handling and the stringing operation so that the conductor surface is not dented, scratched or damaged in any way during manufacture, transport and erection. The conductor shall be properly lagged on the Drums. The conductor drum should be suitable for wheel mounting. Before reeling, cardboard or other suitable material shall be secured to the drum and inside flanges of the drums. After reeling the conductor, the exposed surface should be wrapped with suitable soft material e.g. polythene sheet etc. across the flanges to protect the conductor from dirt, grit and damage during transportation and handling and also prevent ingress of rain water during storage/transport. All wooden components shall be manufactured out of seasoned wood of good quality free from defect that may materially weaken the component parts of the Drums. 114 Preservative treatment for anti-termite/anti-fungus shall be applied to the entire drum with preservatives of a quality which is not harmful to the conductor. STANDARD LENGTH AND GROSS WEIGHT OF CONDUCTOR: The gross weight of each package shall not exceed to the following limits subject to a tolerance of + 10%. i) For Steel Reinforced Aluminium Conductor of 50 mm 2 and 1500 Kg 80 mm2 size (& equivalent sizes of 55 mm2 & 80 mm2 of AAA Conductor) (Code word Rabbit & Raccoon respectively) “The standard wire length for ACSR/AAA shall be 2 Kms. Except for 80 mm 2 of ACSR & equivalent size of AAA Conductor (code word “Raccoon”) and 50 mm 2 of ACSR & equivalent size of AAA Conductor (code word “Rabbit”), for which it shall be 1.2 Kms. and 1.5 Kms. respectively. Longer lengths shall be acceptable. Short lengths of not less than 50% of the standard lengths, as indicated above, shall be acceptable to the max. extent of 10% of the quantity ordered for each size.” TESTS Samples of individual aluminium, aluminium alloy and steel wires for tests shall be taken before stranding from not less than 10% of the spools/coils. If samples are taken after stranding they shall be obtained by cutting 1.2 metres from the outer end of the finished conductor from not more than 10% of the reels. The mechanical tests shall be carried out on single wires only and not on complete conductor. The following tests shall be carried out on Aluminium Wires as per detailed procedure given in IS: 398 (Part-II)/1976 and on Aluminium Alloy Wires as per detailed procedure given in IS: 398 (Part-IV)/1994:a) Breaking Load Test (in both i.e. ACSR/AAA Conductors) b) Elongation Test (in case of AAA Conductors only) c) Wrapping Test (in case of ACSR Conductors only) d) Resistance Test (in both i.e. ACSR/AAA Conductors) The following tests shall be carried out on galvanized steel wires as per detailed procedure given in IS: 398 (Part-II) 1976:a) Breaking Load Test b) Ductility Test (by either of the procedures viz. Torsion Test or Elongation Test) c) Wrapping Test d) Galvanizing Test (the uniformity of Galvanizing and the weight of coating shall be in accordance with IS: 4826-1968). The rejection and re-test procedure shall be followed as stipulated in IS: 398 (PartII)/1976 and IS: 398 (Part-IV)/1994. CHECKING AND VERIFICATION OF LENGTH OF CONDUCTORS The supplier/manufacturer of conductor should arrange for the inspection by the representative of the owner specially authorized for this purpose. At least 5% of the total number of Drums of conductors taken at random should be checked to ascertain the lengths of conductor adopting either of the following two methods:a) The drum along with the conductor should be weighed and six empty drums along with protective laggings & studs etc. normally used for winding the conductor should also be weighed. Net weight of the conductor should be calculated by subtracting the average weight of the six empty drums from the gross weight of the 115 conductor and drums. Having known the weight of the conductor, the length of the conductor can be computed. In case of empty conductor drums, a check weighment of every one in ten empty drums shall also be done before the conductors are wound on the drums. b) Arrangements should be made available in the works of the manufacturer for transferring the conductor from one reel to another at the same time measuring the length of the conductor so transferred by means of a meter. Percentage shortage if any in the length thus obtained and as declared by the agency in the packing list shall be applied to all the drums. CHECK MEASUREMENT Where length of conductor is verified by weighment basis the determining factor will be length/weight ratio of the sample drums verified at the firm’s premises of the lot of which the drum under measurement at the consignee’s end forms a part. Wherever at the end of the consignee, length measurement machines are available, conductors shall be accepted by verification of lengths only and where the length measurement machines are not available, conductor shall be accepted on weighment basis. In case, where the recorded weight on the drum tallies with the measured weight at consignee end, then the conductor length shall be accepted as recorded on the drum. In other cases, the determining factor will be weight/length ratio of the sample(s) inspected at the firm’s premises of the lot of which the drum under measurement at the consignees end, forms a part. The factors of weight/length ratio shall however be made available to the consignees in the dispatch instructions itself. If such factors are not available due to some reasons, actual measurement of diameter shall be made and weight/length ratio shall be obtained for the purpose of computing length. TABLE-I SIZE AND PROPERTIES OF ACSR/AAA CONDUCTORS i) For ACSR Conductors (As per IS:398 (Pt-II)/1976) Code Nomina Stranding and Section Total App. App. Word l Wire Area al Area Sectio Over all Mass Alumiof -nal Diamete nium Alumi Area r Area nium mm2 Mm mm mm2 mm2 mm2 Kg/k m Rabbit 50 6/3.3 1/3.3 52.88 61.70 10.05 214 5 5 Raccoo 80 6/4.0 1/4.0 78.83 91.97 12.27 319 n 9 9 Dog 100 6/4.7 7/1.5 105.00 118.5 14.15 394 2 7 0 ii) For AAA Conductors (As per IS:398 (Pt-IV)/1994) Sr. Actual Stranding & App. App. Calculated No. Area Wire Dia overall Mass Maximum 116 Calcula ted resistance at 20°C Ohm/k m 0.5560 App. Calculate d Breaking load KN 0.3736 26.91 0.2810 32.41 18.25 App. Calculated Dia mm2 22 mm 34 mm 55 mm 80 mm 100 mm 1 2 3 4 5 Mm 7/2.0 7/2.5 7/3.15 7/3.81 7/4.26 mm 6.0 7.5 9.45 11.43 12.78 resistance 20°C Ohm/km 1.5410 0.9900 0.6210 0.4250 0.3390 Kg/km 60.16 94.00 149.20 218.26 272.86 at breaking load KN 6.45 10.11 16.03 23.41 29.26 TABLE – II A) PROPERTIES OF ALUMINUM / STEEL WIRES USED IN THE CONSTRUCTION OF ACSR CONDUCTOR i) For Aluminium Wires Size Diameter Gross Mass Resistance Breaking Load Min. Sectional 20°C Area of Nominal Dia. Wire Nominal Min. Max. Before After standing standing 1 2 3 4 5 6 7 8 9 2 mm mm mm mm Kg/Km Ohm/Km KN KN Rabbit 3.35 3.32 3.38 8.8140 23.82 3.286 1.43 1.36 Raccoon 4.09 4.05 4.13 13.140 35.51 2.208 2.08 1.98 Dog 4.72 4.67 4.77 17.50 47.30 1.661 2.78 2.64 ii) For Steel Wires Size 1 Rabbit Raccoon Dog Diameter Gross Mass Sectional Area of nominal dia. wire Nominal Min. Max. 2 mm 3.35 4.09 1.57 4 mm 3.42 4.17 1.60 3 Mm 3.28 4.01 1.54 5 mm2 8.814 13.140 1.936 6 Kg/Km 68.75 102.48 15.10 B) PROPERTIES OF ALUMINUM ALLOY CONSTRUCTION OF AAA CONDUCTORS 117 Breaking Load Min. Before Stranding 7 KN 11.58 17.27 2.70 WIRES USED After Stranding 8 KN 11.00 16.41 2.57 IN THE Size (Codeword) Diameter Gross Mass Sectional Area of Nominal Dia. wire Resistance Breaking Load (Min.) 20°C Nominal Min. Max. 1 2 3 4 mm2 55 (Rabbit) 80 (Raccoon) 100 (Dog) (mm) 3.15 (mm) (mm) (mm2) 3.12 3.18 7.793 (Kg/Km) Ohm/Km 21.04 4.290 KN 2.41 KN 2.29 3.81 3.77 3.85 11.400 30.78 2.938 3.52 3.34 4.26 4.22 4.30 14.250 38.48 2.345 4.40 4.18 16. 5 6 7 Before After Stranding Stranding 8 9 TECHNICAL SPECIFICATION FOR THREE PHASE 33/11 KV STEP DOWN POWER TRANSFORMER OF 5 MVA RATINGS 1. SCOPE: The specification covers the design, manufacture testing and inspection before dispatch and delivery at places anywhere in M.P. as per list of consignee area stores. The specification covers oil immersed, naturally air cooled (type ON), outdoors type, three phase, 50 Hz, 33/11 KV step down power transformers of 5 MVA capacities. 2. APPLICABLE STANDARDS: (A) Unless otherwise modified in the specification, the transformers shall comply with the requirement of ISS: 2026 (latest issue) or any equivalent International Standards and REC specification 2/1973 and ISS: 2099 (latest issue) or any equivalent International Standards. The bushings used shall conform to ISS: 2099 (latest issue) or any equivalent International Standards except as modified herein. (B) Type: The transformers shall be double wound, three phase oil immersed, oil natural cooled (type ‘ON’), core type suitable for outdoor installation in tropical climate and shall be insulated with minimum DPC insulation on HV & LV windings. Insulation should be of temperature class as per the temperature rise stipulated in this specification. Climatic Conditions i) Peak outdoor temperature: 50oC ii) Maximum oil temperature: (50oC + 45oC) Attainable 95oC under max temperature & max. Load condition iii) Maximum relative humidity: 95% (sometime approaches saturation point) iv) Minimum relative humidity: 10% 118 v) Average No. Of thunderstorm 40 days vi) Average number of rainy days per annum 90 days vii) Number of months of tropical 3 months Monsoon conditions viii) Average annual rainfall 125 cm ix) Wind pressure 100 Kg/m2 x) Altitudes not exceeding 1000 meters. (C) Design and standardization: a. The transformers and accessories shall be designed to facilitate operation, inspection, maintenance and repairs. All apparatus shall also be designed to ensure satisfactory operation under such sudden variations of load and voltage as may be met with under working conditions on the system, including those due to short circuits. b. The design shall incorporate every reasonable precaution and provision for the safety of all those concerned in the operation and maintenance of the equipment keeping in view the requirement of Indian Electricity Rules. c. All material including bought out items like bushings, oil radiators, conductor and insulating materials used shall be of the best quality and of the class most suitable for working under the conditions specified and shall withstand the variation of temperature and atmospheric conditions arising under working conditions without undue distortion or deterioration or setting up of undue stresses in any part and also without affecting the strength and suitability of the various parts for the work which they have to perform. d. Corresponding parts liable to replacement shall be interchangeable. e. Cast iron shall not be used for chambers of oil filled apparatus or for any part of the equipment, which is in tension or subject to impact, stresses or where corrosion due to acidity or slugging is likely to occur. This clause is not intended to prohibit the use of suitable grades of cast iron for parts where service experience has shown it to be satisfactory e.g. large valve bodies. f. All outdoor apparatus, including bushing insulators with their mounting shall be designed so as to avoid external pockets in which water can collect and internally air could trap. g. All taper pins used in any mechanism shall be of the split type complying with IS: 2593 or any equivalent International Standards for these items. h. All connections and contacts shall be of ample section and surface for carrying continuously the specified currents without heating and fixed connection shall be secured by bolts or set screw of common size adequately locked against vibration. Lock nuts shall be used on stud connections carrying current. i. All apparatus shall be designed to minimize the risk of accidental short circuit caused by animals, birds or vermin. 3. STANDARD RATINGS: The standard ratings shall be 5000 KVA with off load taps. 119 4. CONTINUOUS MAXIMUM RATING: The transformers shall have a continuous maximum rating at the specified normal ratio, frequency and temperature rises. a. All transformers shall be capable of operation continuously in accordance with IS loading guide at their continuous maximum rating and at any ratio without exceeding temperature rise. b. Transformers with tapping ranges extending more than 9% below normal voltage shall meet the temperature rise limits specified in IS: 2026 or any equivalent International Standards. On other tapings, they shall operate continuously without injurious heating. The loading of the transformers is to be in accordance with IS: 6600 - guide for loading of oil immersed transformers natural cooled units or any equivalent International Standards. c. The transformers shall be capable of operation without danger at other than rated voltage and frequency in accordance with clause 4.3 and 4.4 of IS: 2026 (Part I) 1977 or any equivalent International Standards. 5. MAXIMUM TEMPERATURE RISE: The maximum temperature rise in each transformer tested at its continuous maximum rating shall not exceed the following limit with reference to ambient air temperature. i) Temperature of oil by thermometer : 45oC ii) Temperature of winding by test resistance : 50oC 6. NO LOAD VOLTAGE RATIO: The no load voltage ratio corresponding to the principal tapping shall be 33,000/11,000 volts. 7. MAXIMUM CURRENT DENSITY: The current density for HV and LV winding should not exceed 2.5 Amps/mm2. 8. FLUX DENSITY: OVER FLUXING: 1. Flux density should not be more than 1.55 Tesla at the rated voltage and frequency. 2. Over fluxing - Requirement in this regard shall be governed by the provision contained in clause 3.1.7 of manual on transformer Section ‘A’ (Revised 1987) of CBIP. According to this, over fluxing the transformer continuously for over 3. Fluxing factor up to 1.1. In addition to this requirement, operation of power transformer without any danger/damage up to 60 Sec. for over fluxing factor of 1.25. 9. MAXIMUM GUARANTEED NO LOAD AND LOAD LOSSES: The losses shall not exceed the value given below: Rating in MVA No Load losses Load losses at 75oC (In KW) (In KW) 5.0MVA 4.0 21.0 120 The losses specified above are maximum permissible value and no plus tolerance would be allowed .Both transformer will be required to undergo for loss measurement by independent agency like ERDA Baroda etc. before commencement of supply. 10. OIL: Transformer oil to be used for first filling shall comply with the specification indicated hereunder. Generally as per IS: 335-1993 (4th revision) or any equivalent International Standards & REC specification No.39/1985 except in so far as values indicated separately as per Board’s specification for EHV Grade Oil. New oil: Insulating oil for Transformers & Switchgears shall be as per ISS-3351993 (4th revision) or any equivalent International Standards incorporating up to date amendment and additional characteristics as incorporated below. It will be pure hydrocarbon mineral oil, clean and sufficiently free from moisture and of other foreign matter likely to impair its properties. The test results for the characteristics of the oil when tested in accordance with ISS 335-1993 (4th revision) or any equivalent International Standards incorporating up to date amendment and additional characteristic required by us shall be as hereunder: Reference to Test methods as per ISS-335-1993 read Sr Schedule of Characteristics Requirement of with latest amendment or No. (Clause 5.1 & 9.1 of ISS) Transformer Oil any equivalent International standard Oil shall be clear And transparent A representative & sample of 1 Appearance Free from oil shall be examined In 100 suspended Matter mm thick Layer at 27ºC or sediments. 2 Density at 29.5ºC (Max.) 0.89 g/cm3 IS: 1448-1977 Kinematics Viscosity (Max.) at 3 27 cst IS: 1448-1976 27ºC Interfacial tension at 27ºC 4 0.04 N/m IS: 6104-1971 (Min.) 5 Pour Point (Max.) (-) 6ºC IS: 1448-1970 6 Water Content (Max.) 50 ppm IS: 13567-1992 Flash Point Pensky Marten 7 140ºC IS: 1448-1970 (Closed)(Min.) 8 Neutralization value a] Total acidity (Max.) 0.03 mg KOH/GM IS: 1448-1967 b] Inorganic acidity/Alkalinity NIL IS: 1448-1967 9 10 Corrosive Sulpher Non-corrosive Electric Strength (Break down voltage) a] New unfiltered oil (Min.) 30 KV (rms) 121 Annexure-B IS-6972-1972 Reference to Test methods as per ISS-335-1993 read Sr Schedule of Characteristics Requirement of with latest amendment or No. (Clause 5.1 & 9.1 of ISS) Transformer Oil any equivalent International standard b] New oil after filtration 60 KV (rms) (Min.) Dielectric dissipation factor 11 0.002 IS-6262-1971 (Tan delta) at 90ºC 12 Specific resistance (resistivity) IS:6103-1971 12 a] At 90ºC (Min) 35x10 Ohm-cm b] At 27ºC (Min) 1500x1012 Ohm-cm 13 Oxidation stability a] Neutralization value after 0.40 mg KOH/gm. Annexure-C of IS-335-1993 oxidation (Max.) b] Total sludge after Oxidation 0.10% by Weight (Max.) 14 S.K. Value under consideration Annexure-C of IS-335-1993 AGEING CHARACTERISTICS Ageing characteristics after IS-12177-1987 15 accelerated ageing (open (Method-A) breaker method with copper catalyst) a] Specific Resistance (resistivity) i) At 27ºC (Min.) 2.5x1012 Ohm-cm IS: 6103-1971 12 ii) At 90ºC (Min.) 0.2x10 Ohm-cm b] Dielectric dissipation factor 0.2 IS: 6262-1971 (Tan Delta) at 90ºC (Max.) c] Total Acidity (Max.) 0.05 mg.KOH/gm. IS: 1448-1967 d] Total sludge value (Max.) 0.05% by Weight Annexure-A of IS: 12177 The oil shall 16 Presence of oxidation Inhibitor contain anti oxidant IS: 13631:1992 additives Characteristics of Oil in the Transformer (i) The important characteristics of the transformer oil after it is filled in the Transformer (within 3 months of filling) shall be as follows:No. 1 2 3 4 5 6 7 Characteristics Electric Strength (Breakdown voltage) Dielectric dissipation factor (Tan Delta at 90ºC) Specific Resistance (Resistivity) at 27ºC Flash Point, PM (Closed) Interfacial Tension at 27ºC Neutralization value (total acidity) Water content PPM 122 Specification 40 KV (Min.) 0.01 (Max.) 10x1012 Ohm.cm 140ºC (Min.) 0.03 N/m (Min.) 0.05 mg KOH/g (Max) 35 (Max.) 11. TAPS 11.1 Off-load tap transformer shall have taps ranging from +3% to -9% in steps of 3.0% each on HV winding for HV variation, to give normal 11 KV on LV side. 11.2 The tap changing switch shall be located in a convenient position so that it can be operated from ground level. The switch handle will be provided with a locking arrangement along with tap position, indication and direction for operation, thus enabling the switch to be operated and locked in position. Tap operation shall result in simultaneous positive change on all three phase, with spring loaded snap action and ensure positive pressure contact. 12. WINDING CONNECTIONS & VECTORS: 12.1 The primary winding shall be connected delta and secondary winding star as per vector symbol Dyn11 (IS: 2026) or any equivalent International Standards so as to produce positive displacement of 30 o from the primary to the secondary vector of the same phase (vector rotation assumed counterclock wise). 12.2 The neutral point of the secondary (LV winding) is intended for solidly earthed system and should be brought out to a separate insulated terminal, enabling external insertion of a current transformer in the earth lead to be connected wherever required. 12.3 All windings of transformers shall have uniform insulation when tested in accordance with ISS: 2026/1977 or any equivalent International Standards. The minimum basic impulse withstands level of windings for 1.2/50 micro sec. Full wave shall be as given below: i) 11 KV - 75 KV Peak ii) 33 KV - 170 KV Peak 13. PERCENTAGE IMPEDANCE AND TOLERANCE (OTHER THAN NO LOAD AND LOAD LOSSES) SHALL BE AS UNDER: a) Percentage impedances - Percentages impedance value for power transformers at 75oC on principal tap shall be as follows: Rating Percentage impedance value at 75oC 5000 KVA 7.15 b)Tolerance ITEM TOLERANCE Voltage ratio at no load the lower of the following values: On principal tapping a) ( + / - ) 0.5% of the declared ratio b) A percentage of the declared ratio equal to 1/10 of actual percentage impedance voltage at rated current Impedance voltage at governed Requirement in this regard shall be by Rated current the provision indicated in IS: 2026 (Part-IV) – 1977 123 (Principal tapping) Para 3.1.4.1 for principal tapping and as per Provisions contained in and Para 3.1.4.2 for other tapping or any equivalent International Standards. (+) 30% of the declared no load No load current current 14. TRANSFORMER TANK The main tank of the transformer shall be made of good quality steel sheet of adequate thickness to provide sturdy and robust construction to withstand extreme pressure conditions. The internal and external surfaces including oil filled chambers and structural steel work to be painted shall be shot or sand blasted to remove all rust and scale of foreign adhering matter or grease. All steel surfaces in contact with insulating oil shall be painted with two coats of heat resistant, oil insoluble, insulating varnish. Steel surfaces exposed to weather shall be given a primary coat of zinc chromate, second coat of oil and weather resistant varnish of colour distinct from primary and final two coats of glossy oil and weather resisting paint in accordance with the colour shade as specified. All paints shall be carefully selected to withstand extremes of weather. The paint shall not scale off or crinkle or be removed by abrasion due to normal handling. The minimum thickness of outside painting of tank shall be 20 microns and the total thickness shall be minimum 80 microns. The main tank exclusive of all accessories but with radiators shall be suitable to withstand application of vacuum up to 760 mm of HG for 1 day with drop in vacuum as per IS. Adequate reinforcement shall be provided for this purpose and to withstand vibration. 14.1 Pressure Test One transformer tank shall be subjected to a pressure corresponding to twice the normal head of oil or to the normal pressure plus 35 KN/m2 (5lb/sq.in) whichever is lower, measured at the base of the tank and will be maintained for one hour during stage inspection. The permanent deflection of flat plates, after the excess pressure has been released shall not exceed the figure specified below: Horizontal length of flat Permanent deflection Plate (in mm) (in mm.) Up to and including 750 5 751 to 1250 6.5 1251 to 1750 8 1751 to 2000 9.5 2001 to 2250 11 2251 to 2500 12.5 2501 to 3000 16 Above 3000 19 14.2 Conservator: A conservator complete with sump and drain valve shall be provided in such a position so as not to obstruct the electrical connections of the transformer 124 having a capacity between highest and lowest visible levels to meet the requirement of expansion of the total oil volume in the transformer and cooling equipment from the minimum ambient temperature of (-) 5oC to 95oC. The minimum indicated oil level shall be with the feed pipe from the tank covered with not less than 15 mm depth of oil and the indicated range of oil level shall be minimum to maximum. If the sump is formed by extending the feed pipe inside the conservator, this extension shall be for at least 25 mm. One oil gauge magnetic type with provision for low levels alarm shall be mounted on conservator to indicate the minimum normal and maximum level as given below: Minimum (-) 5oC Normal 30oC Maximum 100oC One prismatic type oil indicator should also be provided on the conservator. One end flange of the conservator shall be bolted into position so that it can be removed for cleaning purpose. The oil connection from transformer tank to the conservator vessel shall be arranged at a rising angle of 3 to 9o to the horizontal up to gas and oil actuated relay. Each conservator vessel shall be fitted with a aluminium dial cast breather in which Silica gel (at least three Kg.) is the dehydrating agent and designed so that:(a) The passage of air is through silica gel. (b) The external atmosphere is continuously in contact with silica gel. (c) The moisture absorption indicated by a change in colour of the tinted crystals can be observed from distance. Breathers shall be mounted at approximately 1400 mm. Above ground level. 14.3 RADIATORS: Arrangement for good quality sufficient number of radiators should be made to meet out the requirement of temperature rise. Following should also be given due consideration: (i) Belting of radiators to avoid vibration (ii) The gasket should be square in shape with holes for fixing radiators. Round shape gasket may be avoided. (iii) Radiator valve must indicate open and close direction clearly. (iv) Radiators must be supplied in separate packing with serial number of transformer clearly indicated on packing with paint (v) Air release valve provided on radiator should not be of PVC material. It must be of cast iron duly cut in with thread for easy release of air. 14.4 GALVANISING: a. Galvanizing where specified should be applied by the hot dipped process or by electro-galvanizing process, for all the parts other than steel, which shall consist of a thickness of 610 Gms. Zinc per square meter of surface. The zinc coating shall be smooth, clean and of uniform thickness and free from defects or sharp edge. The preparation of galvanizing and the galvanizing itself shall not adversely affect the mechanical properties of 125 the coated material. The quality will be established by tests as per IS: 2633 or any equivalent International Standards. Alternative to galvanizing, aluminizing shall also be considered b. All drilling, punching, cutting and bending and welding of parts shall be completed and all burrs shall be removed before the galvanizing process is applied. c. Surface, which is in contact with oil, shall not be galvanized or Cadmium plated. 15. FINISH: a. Before painting or filling with oil, all un galvanised parts shall be completely clean and free from rust, scale and grease and all external surface cavities on castings shall be filled by metal deposition. b. The interior of all transformer tanks and other oil filled chambers and internal structural steel works shall be cleaned and all scale and rust by shot blasting or other approved methods. This should be read alongwith clause 14 regarding requirement of painting of transformer tank. c. Except for nuts, bolts and washers, which may have to be removed for maintenance purposes, all external surfaces shall receive a minimum of three coats of paint. d. The primary coat shall be applied immediately after cleaning. The second coat shall be of oil, heat and weather resisting nature and preferable of a shade or colour easily distinguishable from the primary and final coats shall be applied after the primary coat has been touched up where necessary. The final coat shall be of a glossy oil, heat and weather resisting non-fading, BATTLE SHIP GREY paint of shade No.631 of IS: 5. Primer paint shall be red oxide zinc chrome as per IS: 104, intermediate and final coats of grey paint shall be as per IS: 2032 or any equivalent International Standards. e. Nuts, bolts and washers, which may have to be removed for maintenance purposes, shall receive minimum of one coat of paint after erection. f. The spacing of the bolt centres on the tank and its cover should be so designed that the gaskets when pressed after bolting leave no room for either ingress of moisture or leakage of oil during transportation or normal service or full load and guaranteed temperature rise conditions. 16. CORE: The core shall be constructed from high grade, non-ageing, low loss cold rolled super grain oriented silicon steel lamination of HI-B grade steel or better. All stipulations under clause-8 be considered while selecting material of core. (I) Magnetic circuit a. The design of the magnetic circuit shall be such as to avoid static discharges, development of short circuit paths within itself or of the earth clamping structure and the production of flux components at right angles to the plane of the laminations, which may cause local heating. 126 b. c. d. e. Every care shall be exercised in selection, treatment and handling of core steel to ensure that so far as is practicable from distortion, burrs or sharp edge. Although the oxide/silicate coating given on the core steel is generally adequate, laminations can be insulated by the manufacturers if considered necessary. All ducts shall be provided wherever necessary to ensure adequate cooling and efficient heat transfer. The winding structure and major insulation shall not obstruct the free flow of oil through such ducts nor permit local hot spots. Where the magnetic circuit is divided into pockets by cooling ducts parallel to the planes of the lamination or by insulating material above 0.25 mm thick tinned copper strip bridging pieces shall be inserted to maintain electrical continuity conductivity between pockets. The framework and clamping arrangement shall be earthed in accordance with Clause-19 (II) of this Technical Specification. (II)Construction of Cores a. All parts of the cores shall be of robust design capable of withstanding any shocks to which they may be subjected to during lifting, transport, installation and service. b. All steel sections used for supporting the core shall be thoroughly sand blasted and shot blasted after cutting, drilling and welding. c. Adequate provision shall be made to prevent movement of the core and winding relative to the tank during transport and installation or while in service. d. The supporting framework of the cores shall be so designed as to avoid the pressure of pockets, which would prevent complete emptying of the tank through the drain valve or cause trappings of air during oil filling. 17. TERMINAL ARRANGEMENT: 17.1 The transformers shall be fitted with shaded porcelain bushings of outdoor type suitable for solder less connectors on HV as well as LV side. The HV/LV bushing shall not be provided with arcing horns. Aluminium bushing stems and aluminium metal parts will not be accepted. 17.2 The bushings shall be filled with transformer oil, EHV grade, which shall be of non-oil communicating type with small aperture of 2 mm diameter. The HV/LV bushings shall have the characteristics as per IS: 2099 (latest issue) or any equivalent International Standards. LV neutral bushing requirement is identical to LV line bushing in all respect. The electrical characteristics of bushing insulators shall be in accordance with IS: 2099 as amended from time to time. All type and routine tests shall be carried out in accordance with IS: 2099-1986 or any equivalent International Standards. The test voltages for various tests as stipulated in ARE: 2099-1986 are reproduced below: 127 Nominal Rated Lightning System Voltage discharge Voltage Voltage Visible wet & dry One minute impulse KV KV KV KV KV -------------------------------------------------------------------------------------------------11 12 9 28 75 33 36 27 70 170 17.3 Dimensions of the LV 12 KV bushings including the neutral (11 KV side) shall conform to IS: 3347 (Part-III) or any equivalent International Standards and those of the 36 KV bushing (33KV side) shall conform to IS:3347 (PartV) or any equivalent .International Standards .Requirement of creepage distance of minimum 23mm. Per KV of rated voltage of bushing as per provision contained in Para 7 of IS: 2099-1993 or any equivalent International Standards. 17.4 Terminal connector shall be provided both for HV and LV terminal suitable for holding Dog Conductor up to capacity of 5 MVA. It should be flat in shape. Its current capacity should be 600 Amps. 17.5 Bushing studs of 33 & 11KV should be of copper and conforming to IS: 3347 or any equivalent International Standards. 18. VIBRATIONS AND NOISE: Every care shall be taken to ensure that the design and manufacture of all transformers and accessories shall be such as to reduce noise and vibration to the level obtained in good modern practice. The manufacturers will ensure that the noise level shall not be more than 3 Db above the NEMA standard publication TR-1. 19. INTERNAL EARTHING ARRANGEMENT: (I) General: - All metal parts of the transformer with the exception of the individual core laminations, core bolts and associated individual clamping plates shall be maintained at some fixed potential. (II) Earthing of core clamping structure :- The top main core clamping structure shall be connected to the tank body by a copper strip. The bottom clamping structure shall be earthed y one or more of the following methods. 1. By connection through vertical tie rods to the top structures. 2. By direct metal-to-metal contact with the tank base maintained by the weight of the core and the windings. 3. By a connection to the top structures on the same side of the core as the main earth connection to the tank. (III) Earthing of magnetic circuit: The magnetic circuit shall be earthed to the clamping structure at one point only through a disconnect cable link placed in an accessible position beneath an inspection opening in the tank core. The connection to the link shall be on the same side of that core and the main 128 earth connection. Magnetic circuits having an insulated sectional construction shall be provided with separate link for each individual section. When oil ducts or insulating barriers parallel to the plane of the laminations divide one magnetic circuit into two or more electrically separate parts, the ducts on barriers shall be bridged in accordance with Clause-16 (ii) and the magnetic circuit shall not be regarded as being of sectional construction. (IV) Size of earthing connections: All earthing connections with the exception of those from the individual cell clamping rings shall have a cross sectional area of not less than 0.8 sq.mm. Connections inserted between laminations of different section of core as per above (III) B shall have a cross sectional area of not les than 0.2 Sq.mm. (v) Leads from winding to bushing and interlock connection: The leads from winding to bushing and interlock connection should be rigid enough to withstand normal vibration and transportation shocks and short circuit stresses. They should be spaced in such a way that necessary clearances are maintained not only in air but also with oil medium at the lowest permissive electrical strength as per relevant ISS over the period of normal service. 20. ELECTRICAL CLEARANCE: -The clearance in air between live conductive parts and live conductive part in earthed structure shall be as follows: Voltage Medium Clearance phase to phase Clearance phase to earth 11000 Air 280 mm 205 mm 33000 Air 350 mm 320 mm 21. PARALLEL OPERATION: The transformers of the same service voltage shall be suitable for parallel operation, the load being shared in proportion to the capacities and percentage impedance volts, which will be within that specified in the ISS. 22. OVER LOAD CAPACITY: (A) Each transformer shall be capable of carrying sustained over loads as stated in ISS: 6600 or any equivalent International Standards (B) Type of load: - The transformer will supply a mixed power and lighting load with varying power factor from 0.6 lag to 0.8 lead due to capacitors. 23. PERFORMANCE WARRANTY:The manufacturer shall among other things warranty the following: (i) Quality and strength of material used, both electrical and mechanical. (ii) Satisfactory operation during the warranty period of 30 months from the date of receipt at Stores or 24 months from the date of commissioning. This period will be reckoned from the day all accessories are received enabling assembly testing, commissioning and commercial operation of transformers. (iii) Performance figures are to be supplied by tenderer in the schedule of guaranteed particulars. In schedule of GUARANTEED TECHNICAL PARTICULARS, all details as required in IS: 2026 shall be given. 24. TOLERANCE: The tolerance of guaranteed performance figures shall be as specified in the Clause 11.1 as per latest version of IS: 2026 or any equivalent International 129 Standards, except for the no load and load losses which is firm and shall not exceed guaranteed values. 25. WHEELS AND AXLES: The transformers of 5000 KVA rating shall be provided with 4 Nos. flanged wheels suitable for use on a 1435 mm gauge Rail track. These wheels shall be suitable for being turned through an angle of 90o and locked in that position when the tank is jacked up. Other transformers shall be provided with 4 Nos. Bidirectional flat roller suitable for use on a 1000 mm. Gauge Rail track. 26. FITTINGS & ACCESSORIES: Unless otherwise specified in the order, the following standard fittings as detailed in Schedule X attached shall be provided. The fittings shall be in accordance with the details to the extent these are specified in IS: 2026. a. Inspection cover is needed to inspect tapping connections of bushings, tapping connections of tap changer and to inspect core-earthing connection. b. Rating plate. c. Diagram plate with tap position and relative HV/LV voltage. d. Two earthing terminals. e. Lifting lugs. f. 4 jacking pads g. Conservator with top filled cap and bottom drain valve. h. Dehydrating breather of required sizes in Aluminium Die. Casting with minimum three Kg. silica gel. i. Connecting pipe with valve and Buchholz relay. j. Radiator with top air release plug and connected valves and bottom for connection to main tank. Air release valve should not be of PVC material. It should be of cast iron duly cut in with thread for easy release of air. k. HV - 3 bushings l. LV - 4 bushings m. Off circuit tap switch with lock and 2 keys. n. Thermometer (dial type) with one contact for alarm pocket for sensor of thermometer (dial type) with one contact for alarm complete with provision for its mounting is needed. o. Magnetic oil level gauge indicating three position of oil marked as follows: p. Minimum - (-50 C) q. Normal - ( 300C) r. Maximum - (1000.C) s. Oil filling hole and cap. t. Air release device on tank top. u. Pressure relief device through explosion vent diaphragm with fresh equalizer pipe air release plug. Please see foot note indicated in Schedule X “Schedule of Fittings”. 130 v. Gas and oil actuated relay. w. 2 filter valves (top valve, lower valve to be used also as drain valve). Locking arrangement should be provided on each valve to avoid theft of transformer oil by welding ‘U’ shape flat over each valve. 27. TESTS AND INSPECTION: 27.1 Type test: - The Purchaser intends to procure transformers whose design is successfully type tested for short circuit, lightning impulse test, loss measurement test and heat run test from an independent agency of national/international repute like CPRI, Bhopal/Bangalore, National Test House, Ghaziabad, ERDA, Baroda or to any recognized and reputed International Laboratory. The tenderers are required to carry out type test. The expenses to be incurred towards the following tests shall be borne by them. This may be kept in mind while quoting the price. Type test includes following tests: i. Short circuit withstand test as per clause 16.11 Part-I IS: 2026 or any equivalent International Standards. The requirement with regard to ability to withstand short circuit shall be governed by clause-8 and demonstration of ability to withstand short circuit shall be governed by clause-9 of IS: 2026(Part-I) 1977 or any equivalent International Standards. Accordingly, the symmetrical short circuit current to be used for the design and tests shall be governed by the Table-4 (IS-2026-Part-I 1977) or any equivalent International Standards and shall be 1000 MVA for the subject power transformers (highest system voltage 36 KV). The quantity preference would be given to those manufacturers who have carried out thermal ability test of 2 sec. After the dynamic withstand test of 9 shots of 0.5 seconds. ii. Lightning impulse withstand test as per Clause-13 Part-III IS: 2026 or any equivalent International Standards. iii. Temperature rise test as per Clause-4 Part-II IS: 2026 or any equivalent International Standards. One transformer of each rating shall be type tested at some independent laboratory of National/International repute like CPRI, ERDA etc. for temperature rise as per relevant ISS. However, the rise shall not be more than 50 0C for winding and 450C for oil above the ambient temperature. iv. Loss Measurement Test – With value of No Load and Load Losses obtained at 750C. 27.2 Stage inspection: The purchaser intends to ensure the quality of raw material being used and workmanship during course of manufacturing of power transformers. At time of core coil assembly, two representatives of purchaser will be deputed to carry out stage inspection. Only after clearance of stage inspection 131 manufacturer will proceed further (tanking of core coil etc.) And will be required to offer transformer for pre-delivery final inspection. 27.3 Routine Test: The following tests in addition to those listed in IS: 2026 or any equivalent International Standards shall be carried out for routine tests. These tests are required to be carried out by the supplier at the supplier’s cost on each and every unit manufactured by them and report shall be forwarded to O/o Addl CE (P) MPPKVVCL Indore at the time of offering transformer for predelivery final inspection. i. Oil leakage test - All the tanks and oil filled compartments shall be tested for oil tightness by being completely filled with air/oil of a viscosity not greater than that of insulating oil conforming to IS: 335 or any equivalent International Standards at an ambient temperature and subjected to a pressure equal to the normal pressure plus 35 KN/m2 (5lb/sq.in) measured at the base of the tank. This pressure shall be maintained for a period not less than 10 minutes during which time no leakage shall occur, Transformer tank shall be checked for loss of vacuum test as per IS. ii. Di-electric test on transformer oil. iii. Checking for pre-shrinkages - The transformer will be dried out for 16 hours at temperature between 80 to 100 0 C. The active parts shall be tightened and height of assembled unit shall be measured. The difference between two measurements shall not be less than two percent as compared to height measured at normal temperature. iv. Measurement of magnetizing current at low voltage i.e. 440V. 27.4 Acceptance Test: - the Purchaser/Representative at the firm’s works shall witness the following tests: 1. All the routine tests as mentioned in 27.3 on each and every offered transformer. 2. Further, the Purchaser’s Inspector reserves the right to carry out any other test for acceptance of offered transformers as per relevant specifications. 27.5 Inspection: All tests and inspection shall be carried out at the place of manufacture unless otherwise specifically agreed upon by the manufacturer and Purchaser at the time of purchase. The manufacturer shall offer the Inspector representing the Purchaser all reasonable facilities without charges to satisfy him that the material is being supplied in accordance with this specification. This will include Stage Inspection during manufacturing stage as well as Active Part Inspection during acceptance tests. The Purchaser has all the rights to conduct the test including type tests at his own cost by an independent agency whenever there is dispute regarding the quality of supply or interpretation of test results. In the event of failure of transformers in such tests, the expenses incurred in testing and cost of transformer etc. shall be to the Supplier’s account. 28. TEST REPORTS ON THE ANALYSIS OF RAW MATERIALS: 132 The tenderer shall indicate the source(s) of aw materials(s) called for in Schedule-VI and enclose test certificates and report on the analysis of electrolytic copper used for the winding and the steel used for core insulation material as also bought out items from sub-suppliers. The quality of material used in prototype transformer, which has passed the type tests, shall be the same in all the ordered transformers. In case it is found that inferior quality of material is used, the transformer shall not be accepted. 17. TECHNICAL SPECIFICATION FOR DISTRIBUTION TRANSFORMER 1. 2. 3. SCOPE This specification covers the technical requirements of design, manufacture, testing at works, supply of 11 KV/433 volts, 50 HZ, 200 KVA outdoor type distribution transformers complete with all accessories for efficient and troublefree operation. STANDARDS The equipment covered by this specification shall, unless otherwise stated, be designed, constructed and tested in accordance with latest revisions of relevant Indian Standards and shall confirm to the Regulations of local Statutory Authorities. IS: 2026 Power transformers IS: 10028 Code of practice for selection, installation and maintenance of transformers. IS: 2099 Bushings for alternating voltage above 1000V. IS: 3637 Gas operated relays. IS: 4257 Dimensions for clamping arrangements for porcelain transformer bushings. IS: 335 New insulating oils IS: 6600 Guide for loading of oil immersed transformer. IS: 3639 Fittings & accessories for power transformer The transformer supplied shall satisfy all the requirements of Local Statutory authorities and modifications if any required at site shall be carried out by the supplier at his own cost. GENERAL REQUIREMENTS The transformer shall be of core type, 2 winding, 3 phase oil immersed having a rating by natural air cooling and shall be suitable for outdoor installation. The 133 4. transformer and all its accessories shall be capable of withstanding for 3 seconds without damage in case of any external short circuit. 3.1 Voltage and Frequency Variations Transformer shall operate without injurious heating on any Tap under the following conditions provided increase in voltage is not accompanied by reduction in frequency. At rated KVA at any voltage within ± 10% of the rated voltage At rated current at a voltage equal to 105% of the rated voltage. A frequency variation of ± 3%. 3.2 Overloads It shall be possible to operate the transformer satisfactorily upto overloads of 150% of the rated value in confirmation with the loading guide specified in IS: 6600. There shall be no limitation imposed by bushings, tap changers, auxiliary equipments to meet this requirement. 3.3 Rated Power and Temperature Rise The transformer shall be capable of operating at rated power specified in the technical schedule on a continuous basis and with the cooling classification given at the most onerous simultaneous climatic conditions specified. The temperature rises guaranteed shall not be exceeded when the transformer is operated continuously at the rated power. 3.4 Rated Voltage and Tapping The principal tapping rated voltage shall be as specified. The tapings shall provide a variation in the transformation ratio without producing phase displacement. All tapings shall be full power tapings. The transformer shall be provided with OFF Load externally hand operated switch with OFF load Tap sets for + 5% to -7.5 % in steps of 2.5% on HV side so as to give constant voltage on LV side 3.5 Impedance Voltage and Short Circuit Impedance The impedance voltage at principal tapings shall be 4% 3.6 Short Circuit Withstand Capability The transformer shall be designed, and constructed to withstand short circuit fault level of 50KA for 1 Sec without damaging the thermal and dynamic effects of external short circuits between phases or between phase and ground. 3.7 Insulation Levels The insulation shall withstand the rated lightning impulse voltage and power frequency withstand voltages. 3.8 Winding Insulation The insulation class of winding shall be as per class F with temperature rise restricted to class B insulation. CONSTRUCTIONAL FEATURES 4.1 General 134 a) Screw, studs, nuts and bolts shall be hot dip galvanized. Exposed parts shall be designed so that water cannot collect at any point. b) Materials in contact with oil shall be such as not to contribute to the formation of acid in oil. c) All similar parts particularly the removable ones shall be interchangeable. Porcelain shall not engage directly with hard interposed between the porcelain and fittings. All porcelain clamping surface in contact with gaskets shall be accurately grounded and free from glaze. 4.2 Core a) The core shall be built up, interleaved with high grade, non-ageing, low loss, high permeability, cold rolled grain oriented, silicon steel laminations properly treated for core material. b) The final core assembly shall be rigidly clamped to ensure adequate mechanical strength and to prevent vibrations during operation. c) The frame, clamps and core bolts shall be electrically insulated from the core. Such insulation shall be capable of withstanding maximum temperature existing in the core. For this purpose, class B or better insulation shall be used. Core clamps shall be electrically connected to the tank. d) The core and windings shall be suitably braced to prevent displacement or distortion during transportation or abnormal electrical conditions in service. e) The core shall be provided with lugs suitable for lifting the complete core and coil assembly. f) All metal parts of the transformer core assembly except individual core laminations, core bolts and side-clamping plates shall be earthed. The magnetic circuit shall be earthed to the clamping structure through one removable core insulation test link only, placed in an accessible position beneath an inspection opening provided in the main tank cover. 4.3 Windings a) The coils shall be of high conductivity electrolytic aluminium conductor, properly insulated and stacked. b) Coil assembly shall be suitably supported between adjacent sections by insulating spacers and barriers which shall be permanently secured in place. c) Windings shall not contain sharp bends which might damage the insulation or produce high dielectric stresses. d) Coils shall be so insulated that the effect of impulse and power frequency voltage stresses are minimum. 135 5. e) The transformer windings shall be connected in group of vector symbols specified. All terminal and tap markings shall be in accordance with IS: 2026. 4.4 Bushings All bushings shall conform to the requirements of the latest revision of IS: 2099. The bushing ratings, impulse withstand levels and creepage distance shall be in accordance with the technical requirements attached. All bushings shall be of porcelain and shall be sound, free from defects and thoroughly vitrified. The glaze shall not depend upon insulation, shall be smooth, hard, of a uniform shade of brown and shall cover completely all exposed parts of the insulator. CONSTRUCTIONAL FEATURES FOR OIL FILLED TRANSFORMERS 5.1 Tank a) Tanks shall be of arc welded construction and fabricated from good commercial grade low carbon steel of adequate thickness. All seams shall be properly welded. b) The tanks shall have sufficient strength to withstand the following without any deformation. I. The tank together with core and oil can be lifted and transported without damage or loss of oil . II. Mechanical shock during transportation. c) The tank cover shall be bolted into the tank with weatherproof hot oil resistant, resilient gasket in between for complete oil tightness. Bushings, turrets, holes and other devices, shall be designed to prevent any leakage of water into the tank or oil from the tank. d) Tank cover shall not distort when lifted. Each tank shall be fitted with inspection covers of ample size to give easy access to internal connections of the bushings, current transformers, winding connections and earth link for testing. e) The design shall be such that the cover does not support the weight of the core and windings. f) Tank cover shall be fitted with pockets for oil temperature indicator which shall be located in the position of maximum oil temperature at maximum continuous rating. g) The under-carriage of the transformer shall be provided with channels to mount on existing double pole structure h) Each tank shall be provided with following handling facilities capable of lifting and / or moving the transformer complete and filled with oil. i. Lifting lugs of adequate capacity shall be provided on tank to lift completely assembled transformer filled with oil. ii. Jacking pads in accessible position shall be provided to enable the transformer to be raised or lowered. 136 iii. Suitable haulage holes shall be provided to the complete transformer. Lifting handle shall be provided on the tank inspection covers. I) Two numbers body earthing terminals capable of carrying maximum system earth fault current for a duration of at least equal to the period for which the main windings are designed shall be provided close to the base of the tank at diagonally opposite positions. j) Tank, tank cover, Cable Box, Marshalling Box and other associated components on the transformers shall have electrical continuity for earthing with suitable earthing clamp. 5.2 Explosion Vent The explosion vent shall be of double diaphragm type. An explosion vent of sufficient size shall be mounted on the tank to protect the tank from damage and to control the explosion of oil during an internal fault. The explosion vent shall be mounted such that pressure relief is not invalidated by the operation of valves and it shall direct the oil downwards and away from tanks and bushings. It shall be capable of maintaining the oil tightness of the equipment under all conditions of normal service. 5.3 Conservator Tank A conservator tank shall be mounted on the top above the highest point of the oil circulating system of the transformer. It shall be of ample capacity to accommodate the expansion and contraction of oil in the whole system over the extreme possible temperature range. The conservator oil outlet pipe shall be fixed above the base of the conservator to form a sump to trap condensation and sludge. One end of the conservator shall be fixed by bolts to enable the tank to be cleaned. Each conservator shall be fitted with: I. At least one oil level indicator of direct reading prismatic glass type visible from ground level. The oil level indicator shall be marked to indicate the correct oil level. II. Oil filling hole with cover. III. The conservator tank shall be vented to atmosphere through a weather proof-dehydrating breather with activated silica gel as dehydrating agent. 5.4 Cooling Units a) The cooling unit shall consist of detachable type of radiators made of pressed sheet steel of thickness not less than 1.0mm. b) Radiators shall be designed so that all painted surfaces can be thoroughly cleaned by hand and subsequently painted inside by suitable brushes. They shall be also so designed to avoid pockets in which moisture, dust or sand may collect. 137 c) Radiators shall withstand the pressure tests appropriate to the main tank. They shall be also capable of withstanding without damage the full vacuum associated with oil treatment. d) The radiators shall be provided with the following accessories. I. Bolted gasketed flanges connection at each point of connection to the main tank. II. Air release plug on top. III. Oil drain plug at bottom at convenient level. 5.5 Transformer Oil Insulating oil shall conform to IS: 335 and shall be suitable in all respects for operating the transformer at the ratings and under conditions laid down in the specification. The transformer shall be supplied with oil for first filling. An extra 10% of the total oil requirement shall be provided in non-returnable containers suitable for outdoor storage. 5.6 Oil Temperature Indicator a) Thermometer pocket and sensing element with dial type thermometer calibrated in degree Celsius, with a hard reset pointer to register the highest temperature attained, shall be provided for indicating temperature of the top layer oil in tank. b) The cover shall be equipped with a viewing aperture of adequate size fitted with clear glass. 5.7 Breathers a) Each conservator of the transformers shall be provided with a silica gel breather complete with oil seal and oil level indication window. b) Visual indication of the extent to which the silica gel has absorbed moisture shall be provided. The unit must allow simple cleaning and replacement of the desiccant and sealing oil without the use of tools, by using wing nuts or similar forms of corrosion-resistant hand-tightening devices. c) The breather shall be mounted at approximately 1000mm from bottom level and connecting pipe to the main tank by means of brackets. 5.8 Valves Each transformer shall be fitted with the following valves: I. One valve at the top and one valve at the bottom of the tank mounted diagonally opposite to each other for connection to oil circulating and filtering equipments. The lower valve shall also function as drain valve. These valves shall be fitted with blank flanges. II. Oil sampling valves at top and bottom of the tank with flange. III. 1 No. Air Release plug. 5.9 MARSHALLING BOX a) The box shall be mounted either on the transformer tank or on a separate mounting frame with brackets and shall conform to IP:55 degree of protection for the enclosure. 138 b) 6. 7. This box shall contain all auxiliary devices except those mounted on the transformer. The control terminals and connectors shall have suitable current carrying conductors. A removable bottom gland plate shall be furnished for cable entry. Cable glands and lugs shall also be provided. 2 Nos. brass stud brass to be provided on either side of the box for body earthing. Stud type terminals shall be provided for terminating control wires. 5.10 Cable Box The LV cable box shall be of outdoor type sheet steel construction, selfsupporting, with all standard facilities including the body earth terminal. Cable box shall be provided on LV side of the transformer and shall be suitable for PVC aluminium conductor cables. It shall be air-insulated unit. HV side of the transformer shall be suitable for porcelain bushings. Suitable stud bolt with three no nuts shall be provided inside the cable brass box for cable armour with necessary pad for connecting to the main earth bus. TAP CHANGER 6.1 Off Circuit Tap Changing Gear a) The off- load tap changing gear shall be provided on the H.V. windings for a variation of no load voltage as specified. b) It shall be operated by an external three-phase gang operated switch. The operating shaft shall be brought out of the tank and provided with a hand wheel so that it can be operated at a standing height from ground level. In case of linear type tap changer switch, the operating handle should conveniently be located on the tank body for ease of operation. The tap switch should have locking facility. c) A visual tap changing indicator for the tapping shall be provided and provision shall be made to padlock the handle in each tap position. The arrangement shall be such that the padlock cannot be inserted unless contacts are correctly engaged and suitable pad locking arrangement shall also be provided. d) All contacts of the tapping shall be silver plated and held in position under strong contact pressure so as to avoid constant pitting of any type whatsoever. The tapping switches shall be provided with mechanical end stops, which prevent movement beyond an end position. ACCESSORIES The following accessories in addition to specified earlier shall be provided as per IS: 2026. Rating plate Terminal marking plate Lifting lugs Earthing terminals with lugs Thermometer pocket Jacking pads 139 Undercarriage fitted with ISMC-100 for mounting 0n Four pole str. 8. NOISE AND VIBRATION Care shall be taken to ensure the design and manufacture so as to reduce noise and vibration to the level of that obtained in good modern practice. 9. PAINTING All accessories and transformer tank shall be sand blasted and grounded to produce a smooth, clean surface, free from scale, grease and rust. After cleaning, the surfaces shall be given a phosphate coating followed by a coat of high quality red oxide or yellow chromate primer. The transformer shall be finished with two coats of synthetic enamel paint of shade 631 of IS 5. The color will be furnished later by the purchaser 10. TESTS 10.1 Factory Tests a) Complete tests shall be made at the manufacturer's plant to determine the performance and operating characteristics of the assembled transformers, and their respective accessories to determine whether or not the guarantees have been met. Unless otherwise specified, all tests shall be carried out in accordance with IS: 2026, and shall include the following. 10.2 Routine Tests a) Resistance measurement of all windings on the rated voltage connection and on all taps. b) Ratio tests on the rated voltage connection and on taps. c) Polarity and phase relation tests. d) Impedance and load loss at rated current on the rated voltage connection (principal tap) and on all the taps. e) No-load loss and current at rated voltage. f) Dielectric test. g) Power frequency withstand test. h) Insulation resistance tests on winding, auxiliary devices, core and tank I Test on tap changer II Mechanical Operation Test III Insulation test on auxiliary circuits 10.3 Type Tests The Bidder shall furnish copies of type test certificates along with the Bid for similar rating of transformer already conducted. a) Temperature rise test b) Zero phase sequence test at all taps. c) Audible sound level test. d) Impulse voltage withstand test. e) However the bidder to furnish the separate rate for above type test individually as a unit rate. Bidder shall furnish the calculations for current density, flux density, losses etc in support of the design for the purchasers review. - 140 18. 1 10.4 Other Tests - Acceptance test a) Pressure tests on the tank and cooling system. b) Operational tests to show the correct functioning of all devices associated with the transformer. All routine and acceptance tests shall be witnessed by the Purchaser's Engineer. Purchaser is free to carry out stage inspection of the material / equipment at any stage during fabrication/manufacture of the material to ascertain the quality and design of the equipment. Copies of routine / acceptance test certification shall be produced with the endorsement of inspecting authority to the purchaser before effecting dispatch. 10.5 Drawings and Manual The following drawings and manual shall be submitted for the Engineer's approval after award of contract in quadruplicate. a) General arrangement of transformer showing i. Details of bushing including electrical and mechanical characteristics. ii. Conservator with its supports. iii. Explosion vent. iv. Radiator with valves, air release and oil drain plugs. v. Marshalling box. vi. Disconnection chamber and cable box connection arrangement. vii. Marshalling box wiring diagram. viii. Rating & Diagram plate drawing. ix. Buchholz relay drawing x. Indicating meter & Gas & oil operated relay catalogue and test details. xi. Indicating meter & cast oil operated relay. b) Manufacturing schedule and test schedule. c) Installation, operating and maintenance manual. 10.6 Transformer Losses The Transformer shall be designed with no load & load losses to be restricted to the values of losses as prescribed & accepted by MPPKVVCL. Transformers with higher losses than MPPKVVCL recommended losses shall not be accepted. 10.7 Installation The transformer shall be installed as per the manufactures instruction manual & shall conform to the requirements of IS 10028:1981 transformer & all other accessories shall be handled carefully in its upright position as indicated on the packing case. TECHNICAL SPECIFICATION FOR 415 V OUT DOOR TYPE STREET LIGHT CONTROL PANEL SCOPE 141 This section covers the detailed requirements for design, supply, installation, testing and commissioning of 415 Volts, 3 phase, 50 Hz 4 wire system, street/ road light feeder panel for road lights to switching ON/ OFF function. 2 TYPE OF BOARD The medium voltage panel shall comprise of the following type of switchgears as specified. The panel shall be capable of fault withstand capacity of 35 KA for duration of one second up to 150 Amp rating. The Panel shall be metal enclosed, outdoor type having incoming, sectionalisation and outgoing switchgears as specified. The design shall be cubicle type. The degree of protection for enclosure shall be IP 55. 3 GENERAL CONSTRUCTION The Panel shall be floor/ foundation mounted freestanding totally enclosed and non-extensible type. The switchboard shall be dust & vermin proof with lockable arrangement with degree of protection IP55 as per IS 2147 and shall be suitable for the climate conditions as specified. The design shall include all provisions for safety of operating and maintenance personnel. The general construction shall conform to IS: 8623 for factory assembled switchboard. The panel shall be equipped with space heater with thermostat. 3.1 CUBICLE TYPE PANEL Outdoor type panel shall be fabricated out of CRCA sheet steel 2.5 mm thick with double door arrangement out of 2 mm thk .Sheet and canopy on all four sides. Wherever necessary, such sheet steel member shall be stiffened by angle iron framework. The general arrangement shall be got approved before fabrication. Cable entries for various feeders shall be from the bottom. All cable entries shall be through gland plates of 3 mm thick. There shall be separate gland plate for each cable entry so that there will not be dislocation of already wired circuit when new feeders are added. Cable entry plates shall therefore be sectionalized. 3.2 INDICATOR LAMPS On the incomer of L.T Panel, ON phase indicator LED type lamps shall be provided suitable for operation on AC 230 Volts supply. Necessary filter G/Y/R/A shall be provided depending upon the function. All lamps shall be protected by proper HRC fuses 3.3 SMALL WIRING All small wiring controls, indication etc. shall be with suitable stranded copper conductor cables PVC insulated conforming to IS: 1554 Part 1. Wiring shall be suitably protected within the switchboard. Runs of wires shall be neatly bunched and suitably supported and clamped. Means shall be provided for easy identification of the wires. Where wires are drawn through PVC conduits, the works shall conform to IS 732. Identification ferrules shall be used at both ends of the wires. All control wiring meant for external connection is to be brought out on terminal block. All wiring shall be minimum 1.5 sq. mm and for CT circuits it shall be 4.00 sq. mm. Brass/ copper thimbles, insulation tape etc. shall be provided at joints and terminations as required. 142 3.4 BUS BAR & BUS BAR CHAMBERS 3.4.1 BUS BAR AND CONNECTIONS The bus bar shall be high conductivity Aluminium of IEC 228 grade and of adequate section having current density not less than 0.8 Amp. / Sq. mm. Set of aluminium bus bar shall be completed shrouded with acrylic sheet to avoid accidental touch. All connections to individual circuits from the bus bar shall be with solid connections in case current exceeds 63 Amp. All bus bars and connections shall be suitably sleeved with PVC or suitably insulated in an approved manner. The bus bar temperature should not exceed 85 degree C i.e. 35 degree C temperature rise over 50 degree C ambient. The bus bar sizes should be furnished along with shop drawing for approval. 3.4.2 BUS BAR SUPPORTS AND ATTACHMENTS Supports Bus bar shall be firmly fixed on supports constructed from SMC (glass fibre reinforced thermosetting plastic). The supports shall be sufficiently robust to effectively withstand electro-mechanical stresses produced in the event of short circuit. Connections to Bus Bars The bolts and nuts used for connections to bus bars shall be of tinned forged brass or galvanized iron. Suitable precaution shall be taken against heating due to bi-metallic contact. Further for tapping off connections from bus bars, VIR/PVC insulated wire may be used up to current capacities up to 63 amps and for higher current capacities solid conductors/ strips suitably be insulated with PVC sleeves / tape as per requirement. Clearances The minimum clearances to be maintained for open and closed indoor air insulated bus bars/ electrically non-exposed and working at system voltages up to 600 volts shall be as follows: Between ……………………………………………. Minimum Clearances Phase to Earth………………………………………. 22 mm Phase to Phase ……………………………………… 32 mm Bus Bar Markings The colours and letters (or symbols) for bus bars: Main bus bar connections and auxiliary wiring etc. shall conform to relevant Indian Standard. A brief from IS 375-1963 (revised) is given below: For AC bus bars and Main connections S.No. 1. Bus Bar & Main Connection Three Phase Colour Red, Letter/ Symbol R, Y, B Yellow, Blue 2. 3. 4. Single Phase Neutral Connection Connection to earth Red White Green 143 R N G PHASE SEQUENCE AND POLARITY Bus bars and main connections, when marked shall be marked in accordance with the following table to indicate the order in which the voltage in phases reach their maximum values. System As indicated by Phase sequence Colour or letters as indicated Vectorially Three Phase Red, Yellow, Blue R, Y, B Single Phase Red, Black R, B 4 ARRANGEMENT OF BUS BAR & MAIN CONNECTIONS: Bus bars and main connections, which are substantially in one plane, shall be arranged in order given as follows: 4.1 A.C SYSTEM The order of phase connections shall be Red, Yellow and Blue. When the run of the conductors is horizontal, the red shall be on the top or on the left or farthest away as viewed from the front. When the run of the conductor is vertical, the red shall be on the left or farthest away as viewed from the front. When the system has a neutral connection in the same plane as the phase connections, the neutral shall occupy an outer position. Unless the neutral connections can be readily distinguished from the phase connections, the order shall be red, yellow, blue and black. 4.2 TERMINATIONS Incomer terminals shall be suitable for receiving cables. 4.3 MOULDED CASE CIRCUIT BREAKERS Moulded case circuit breakers shall comply with IEC 60947.2 & 13947 part 2. They shall have the voltage and current ratings of 440 Volt & 63 Amp. respectively whereas short circuit breaking capacity and rated short – time withstand current should be as indicated below. The breaking capacity performance certificates shall be available for category A to the above mentioned standards. The test shall be carried out under the breaking performance during the ultimate breaking capacity (Icu), Ics rating=100% Icu. Certificate for all the sequences (Sequence 1 mandatory) should be available.’ MCCB’s shall be of the independent manual closing air-break type, rated for an uninterrupted duty. Auxiliary facilities, including power closing and under voltage releases, shall be provided as indicated. Each MCCB shall have a facility for padlocking in the “ OFF” position. Necessary set of cast resin type CT’s together with an ammeter and selector switch as specified. Necessary inter-connections to bus bars. 144 Necessary isolating plugs and sockets for front operated switches to enable withdrawing the entire unit and replacing with another unit disconnecting the cable for maintenance operation. Each MCCB shall provide with a rotary operating mechanism. 4.4 CONTACTOR 3 Pole contactor of 32 Amp. Rating type AC-1 should conform to IEC 60947-4-1,IS 13947 Various parameters shall be as under: Insulation voltage—690 V Impulse withstand voltage (Uimp)—8 KV Shock resistance 10/5 gn Shock pick up @85—110% of control voltage Should drop @30—60% of control voltage Operating time—15 to 35 ms 4.5 CURRENT TRANSFORMERS Cast Resin current transformer shall be provided for main distribution boards carrying current in excess of 32 amps wherever shown in drawing. All phases shall be provided with current transformers of accuracy class 0.5 and suitable VA burden to operate associated metering. Current transformers shall be in accordance with IS 2705. 4.6 EARTHING All components, frame etc shall be properly earthed. GI earth bars of 25 x 5 mm shall be provided for the LT panel for the full length of the panel and connected to the framework. Provisions shall be made for connection from this earth bar to the main earthing bar on both sides of LT panel. The Streetlight Control System will be auto controlled with a solar based real time clock /Timer with the following features. Switching of continuous load consisting of HPSV Lamps. The system should have a provision for remote and local operation with a three-way selector switch. Brief detail of material requirement to be provided is as under: 4.7 PAINTING All sheet steel shall undergo a process of degreasing, pickling in acid, cold rinsing, phosphating, passivating and then sprayed with a high corrosive resistant primer. The primer shall be baked in an oven. The finishing treatment shall be by application of two coats of epoxy paint of approved colour and stoved. 5 TESTS AT MANUFACTURERS WORK All routine tests specified in IS: 8623:1977 shall be carried out and test certificates produced to the Engineer-in-charge. Typical type test certificate shall be furnished. 6 INSTALLATIONS AND COMMISIONING OF S L. PANEL 6.1 The installation work shall cover assembly of various sections of the panels, lining up, grounding the units etc. In the case of multiple panel switchboards after connecting up the bus bars etc. all joints shall be protected with necessary insulated shrouding. A 145 common earth bar as per IS specifications shall be run at the back of switch board connecting all the sections for connection to frame earth system. All protections and other small wirings for indication etc. shall be completed before calibration and commissioning checks are commended. All equipments, meters etc. shall be mounted and connected with appropriate wiring. 7 Testing and Commissioning Commissioning checks and tests shall include all wiring checks and checking up of connections. Primary/ Secondary injection tests for the relay adjustment/ setting shall be done before commissioning in addition to routine meggar test. Checks and tests shall include the following: Operation checks and lubrication of all moving parts. Interlock function checks. Continuity checks of wiring, fuses etc. as required. Insulation test: when measured with 500 V megger the insulation resistance shall not be less than 100 mega ohms. Trip test and protection gear test. 19. TECHNICAL SPECIFICATION OF 11 KV AND 33 KV PIN INSULATORS SCOPE: This specification covers 11 KV and 33 KV Porcelain Pin insulators for use on 11 KV and 33 KV overhead power lines and substations. STANDARD: Except where they conflict with specific requirement in the specification, the Pin Insulator shall comply with the Indian Standard Specification IS 731/1971 and its amendment from time to time. The insulator conforming to any other internationally accepted standard which ensures equal or better quality than the above standard would also be acceptable. Where the material is offered according to the international standards, an English version of the specifications shall be attached with the tender. ATMOSPHERIC CONDITIONS: The material offered shall be suitable for operating under the climatic conditions indicated in General Terms and Conditions of this tender specification. Tests for the purpose of this standard shall preferably be carried out under conditions of temperature and humidity as specified in IS: 196 – 1966. The thimble for 11 KV Pin Insulator should be suitable for use with Galvanized Steel Pins conforming to reference S-165 of IS 2486 (Part II) of 1974 with shank length 150mm which is provided with a small steelhead. Similarly, the thimble of 33 KV Pin Insulator should be suitable for use with 33 KV Galvanized steel pins conforming to reference I-300-N- of fig. 6 with shank length of 150 mm and with large head of ISS-2486 (Part III) of 1974. INSULATOR CHARACTERISTICS The insulator shall have the electrical and mechanical characteristics, which are given below: No Particulars 11 KV Pin Insulator 33 KV Pin Insulator 1 Highest system voltage 12 KV (rms) 36 KV (rms) 2 Wet power frequency withstand 35 KV (rms) 75 KV (rms) voltage test for one minute 3 Visible discharge voltage 9 KV (rms) 27 KV (rms) 146 4 5 Power frequency puncture Impulse withstand voltage 105 KV (rms) 75 KV (peak) 180 KV (rms) 170 KV (peak) (In the above standards, power frequency voltage is expressed as peak values divided by 2 and impulse voltage is expressed as peak value). The withstand and flashover voltage are referred to the reference atmospheric conditions. Mechanical Loads Minimum Failing Loads i. 11 KV Pin Insulator 5 KN ii 33 KV Pin Insulator 10 KN CREEPAGE DISTANCE The insulators shall have the following minimum creepage distance for a moderately polluted atmosphere: i. 11 KV Pin Insulator 230 mm ii. 33 KV Pin Insulator 580 mm TESTS The insulators shall comply with the following tests as per IS-731-1971. TYPE TESTS The following constitute the type tests: 1. Visual Examination 2. Verification of dimensions 3. Visible discharge tests 4. Impulse withstand voltage tests 5. Wet Power frequency withstand voltage test 6. Temperature cycle test 7. Mechanical failing load test 8. Puncture test 9. Porosity test Type test certificates from recognized Govt. Lab for the tests carried out on prototype of same specifications shall be enclosed with the tender. ROUTINE TESTS The following shall be carried out as routine tests: 1. Visual examination 2. Electrical routine tests 3. Mechanical routine tests ACCEPTANCE TESTS: The samples after withstood the routine tests shall be subjected to the following acceptance tests in order indicated below: 1. Verification of dimensions 2. Temperature cycle test 3. Mechanical failing load test 4. Puncture test 5. Porosity test Tolerance in insulator dimensions shall be as per the relevant Indian Standards. MARKING 147 Each insulator shall be legibly and indelibly marked to shows the following: Name and trade mark of manufacturer Month and Year of manufacture Minimum failing load in Newton Country of manufacture. Marking on porcelain shall be printed/engraved and shall be applied before firing. PACKING All insulators shall be packed in wooden crates suitable for easy but rough handling and acceptable for rail and road transport. STANDARDISATION OF DIMENSIONS OF TOP AND NECK OF 11 KV PIN INSULATORS Board is using preformed ties for binding conductor with the Pin Insulator instead of conventional method of binding by aluminium, binding wire and tape. The design of the preformed ties depends upon the dimensions of top and neck of 11 KV Pin Insulator. Contractor must provide ties for binding purpose. 45 KN DISC INSULATOR SCOPE This specification covers Porcelain Disc Insulator for use on 11 KV and 33 KV overhead power lines. STANDARD Except where they conflict with specific requirement in the specification, the Disc. Insulator shall comply with the Indian Standard Specification IS 731/1971 and its amendment from time to time. The insulator conforming to any other internationally accepted standard which ensures equal or better quality than the above standard would also be acceptable. Where the material is offered according to the international standards, an English version of the specification shall be attached with tender. GENERAL REQUIREMENTS The porcelain shall be sound, free from defects, thoroughly vitrified and smoothly glazed. Unless otherwise specified, the glaze shall be brown in colour. The glaze shall cover all the porcelain parts of the Insulator except those areas, which serve as supports during firing or are left unglazed for the purpose of assembly. The design of insulator shall be such that stresses due to expansion and contraction in any part of the insulator shall not lead to deterioration. The porcelain shall not engage directly with hard metal. Cement used in the construction of the insulator shall not cause fracture by expansion or loosening by contraction and proper care shall be taken to locate the individual parts correctly during cementing. The cement shall not give rise to chemical reaction with metal fittings and its thickness shall be as uniform as possible. TYPE OF INSULATOR The insulator shall be of type “B” according to its construction, which is defined hereunder:Type “B” An Insulator or an insulator unit in which the length of the shortest puncture path through solid insulating material is less than half the length of the shortest flashover path through air outside the insulator. INSULATOR CHARACTERISTICS The insulator shall have the electrical and mechanical characteristics which are given below:148 The test voltage of insulator shall be as under: No. Particulars 1 Highest system voltage 2 Wet power frequency/withstand voltage for one minute 3 Visible discharge voltage 4 Power frequency puncture withstand voltage 5 Impulse withstand voltage Disc Insulator 12 KV (rms) 35 KV (rms) 9 KV (rms) 105 KV (rms) 75 KV (peak) In this standard, power frequency voltage are expressed as peak values divided by 2 and impulse voltage are expressed as peak values. The withstand and flashover voltage are referred to the reference atmospheric conditions. Minimum Failing Load: 45 KN CREEPAGE DISTANCE : The insulator shall have minimum 230-mm Creepage distance for a moderately polluted atmosphere. TESTS The insulators shall comply with the following tests as per IS 731-1971. TYPE TESTS The following constitute the type tests 1. Visual examination 2. Verification of dimensions 3. Visible discharge test 4. Impulse voltage withstand test 5. Wet power frequency withstand test 6. Temperature cycle test 7. Electro-Mechanical failing load test 8. Puncture test 9. Porosity test 10. Galvanizing test The test certificates from recognized Govt. lab for the tests carried out on prototype of same specifications shall be enclosed with the tender. ROUTINE TESTS 1. Visual examination 2. Electrical Routine tests 3. Mechanical Routine tests ACCEPTANCE TESTS Acceptance of samples after having withstood the routine tests shall be subjected to the following acceptance tests in the order indicated below: 1. Verification of dimensions 2. Temperature cycle test 3. Electro Mechanical failing load test 4. Puncture test 5. Porosity test 6. Galvanizing test Tolerance in insulator dimensions shall be as per the relevant Indian Standard. MARKING Each insulator shall be legibly and indelibly marked to show the followings: Name and trade mark of manufacturer Month and year of manufacture 149 Minimum failing load in Newton Country of manufacture Marking of porcelain shall be printed / engraved and shall be applied before firing. PACKING All insulators shall be packed in wooden crates suitable for easy but rough handling and acceptable for rail and road transport. 20. TECHNICAL SPECIFICATIONS OF L.T. DISTRIBUTION BOXES The specification provides for design, manufacture, testing before dispatch, supply and delivery of distribution boxes with three pole moulded case circuit breakers for protection of distribution transformers and LT feeders. The MCCBs provided in these boxes shall conform in all respects to the relevant IS: 2516 (Pt-I&II)/1977 and REC specification No.18/1981 (revised) or its latest revision as applicable. REQUIREMENT OF MCCBs: The moulded case circuit breakers should comprise of a switching mechanism, an effective extinguishing device and a tripping unit contained in a compact moulded case cover made of high strength, heat resistance and flame retardant thermo-insulating materials. They should comprise of a spring assisted quick make/quick break type independent manual trip free mechanism rendering it easy to manually operate the MCCBs and capable of clearly indicating “TRIPPED”, “ON” AND “OFF” positions from the position of the operating handle. The contact tips should be made of a suitable alloy having high arc resistance and a long electrical and mechanical life needing no replacement. The breakers should be designed with a common trip bar to break and make all the three phase together even when fault occurs on any of the phases. The breakers should provide protection against sustained overloads and short circuits through thermalmagnetic/fully magnetic releases. These MCCBs along with terminal blocks are intended to be housed in the distribution boxes made out of sheet steel of 2mm gauge. The assembly of the MCCBs and the terminal blocks should be compact, reliable from operation point of view and safe to the operating personnel. As already mentioned earlier, the MCCBs should be fully maintenance free TECHNICAL PARTICULARS OF MCCBs: The LT MCCBs should have inverse current/time characteristics suitable for protection of 200KVA 11/0.4KV Distribution Transformers against sustained over-loads and short circuits for following operating conditions:i Rated Operating Voltage 3 Phase 415 Volts AC 50 cycles with neutral solidly grounded system ii Standard rated current ratings for MCCBs to be used with different sizes of transformers will be as follows:For 200KVA 11/0.4KV Dist. 315 Amps Transformer iii No. of Poles 3 iv Duty Un-interrupted v Maximum ambient temperature 47oC in shade vi Minimum ambient temperature 4oC in shade vii Average altitude A maximum of 1000 meter viii Maximum humidity Frequently approaches 150 saturation point TIME/CURRENT CHARACTERISTICS: The circuit breakers shall have time/current characteristics suitable for following operating conditions :Multiple of normal current rating Tripping time 1.1 times After 4 hours 1.2 times Less than 50 minutes Multiple of normal current rating 1.3 times 1.4 times 2.5 times 6 times 12 times Tripping time Less than 30 minutes Less than 10 minutes Less than 1 minute Less than 40 mili-seconds Less than 40 mili-seconds i) Time/Current characteristic of the Circuit Breaker (MCCB) shall be tested in accordance with Clause-7.7.2.3 (b) (2) of IS: 2516-(Pt-I&II) Sec.I/1977 and the test shall be made with all the three phases loaded. ii) For time/current characteristic, the reference calibration temperature of the MCCBs shall be 40oC and durance, if any; upto 50oC operating temperature in the enclosure shall not exceed 10% of the value indicated above in Clause (I) above. iii)The MCCBs shall be calibrated and adjusted in the factory itself for the desired time/current characteristic iv) The MCCB should have the following maximum resetting time under overload & short circuit conditions :Overload conditions 3 minutes Short Circuit conditions Instantaneous RATED SHORT CIRCUIT BREAKING CAPACITY: The rated short circuit breaking capacity of the MCCBs shall be as follows: Transformer rating(KVA) Rated short circuit breaking capacity of the breaker in Kilo-Amps 200 KVA A minimum of 25 Kilo-Amps The short circuit breaking capacity test as specified above shall be based on short circuit tests carried out at 0.4 Power Factor (lagging). For the purpose of these tests, the following operating sequence shall be followed: Break-3 minutes itnerval-Make-Break-3 minutes interval-Make-Break. The Distribution Box shall be provided with two nos. 75x 40mm (ISIC) mounting channels welded to the top sheet of the Box. The channel shall have 2 nos. holes (13mmx13mm) for receiving bolts. With such top mounting facility, the Box can be mounted directly under the base channels supporting the distribution transformer. The mounting holes shall be maintained at fixed distance of 225 mm irrespective of box size so that necessary provision of drilled holes can be done. The Distribution Box shall house a Triple Pole Isolator of adequate ratings at incomer and Triple pole MCCBs equal to numbers of outgoing feeder circuits on outgoing side. The ratings of MCCB as incomer and numbers and ratings of MCCBs to be provided at out going circuits are indicated hereunder:- 151 Light emission diodes shall be provided for all the outgoing phases to indicate the availability of supply and when switched off due to tripping/manual operation of MCCBs to indicate that the same is off. LED are to be provided inside the box. Enclosures: The enclosure shall be made of 14 SWG (2mm) steel sheets and shall be suitable for outdoor installation, conforming to IP-20 degree of protection as per IS: 2147/1962. The front door shall be having locking facility. The box should be provided with single door in front and having internal locking arrangement with two keys. Extra padlock arrangement shall also be provided. The latches provided inside the door, which are locked in position by the keys, should be such that the door gets locked just by closing (for opening the door, keys will then be required). The backside cover shall be screwed type and should be fixed with 4 nos. 8mm size Allen screws at four corners. One box spinner of suitable size for the screw fitted in the box should be provided inside the box with suitable clamps Neoprene rubber gasket shall be used on front door as well as back cover. Painting of Box All sheet steel surface of the box shall be thoroughly degreased and shall be followed by antacid cleaning so as to produce smooth and clean surface free from scale grease and dust. After cleaning, the surface shall be given phosphate coating followed by two coats of anti rust paint primer (i.e. red zinc chrome primer). After which, 2 coats of synthetic paint of light grey colour (no.631 as specified in Indian Standard 5 of 1961) shall be applied on internal and external, surface of the steel structure of the box with a spray gun. The box shall be baked in the oven so as to give an elegant and durable finish to the box. Leakage Proof: The box shall be vermin proof and weatherproof. The assembly, comprising of the enclosure, framework and the circuit breaker shall be provided with earthing terminals readily accessible and of adequate size two earthing studs of 12mm dia size shall be welded to the enclosure on either side as shown in the drawing and shall be provided with locking nuts and washers. All the nuts, bolts and washers should be galvanized iron. The earthing terminal shall be clearly marked. Four nos. drainpipes of ½” diameter shall be welded at the bottom of the box at Four Corners. The bottom plate shall be centrally bent to provide slope for drainage of water through the drain pipes. Ventilation louvers with wire mesh shall be provided on both the sides as per requirements. In addition to this, louvers with wire mesh of suitable sizes and numbers also required on backside cover of box. Detailed drawing showing size of openings and size of brass mesh shall be submitted by the bidder for approval prior to manufacture. Danger Board: Specifications are shown in Technical Specifications of the package. Knock-out Holes: Knockout holes for incoming and outgoing cables will be provided. The holes shall be suitable to accommodate single core aluminium conductor LT cable of appropriate size. These holes should be provided direct contact with and gets out by the metal edges. The holes should be in alignment with the terminals of incomer and outgoing MCCBs so that the cable may be directly crimped with lugs. Bending of cable inside the box for terminal connection should not be required. BUS BAR AND CABLING: iv) The incoming single core cable shall enter from backside (top) of the enclosure. All outgoing cables shall enter from the sides of the enclosures. 152 v) Electrolytic grade aluminium shall be used for bus bar and links used interconnection of incoming and outgoing MCCBs. The minimum size acceptable are as follows :vi) Bimetallic / suitable connectors are required for connecting the MCCBs terminals to Bus Bar BUS BAR DETAILS [All dimensions are in mm] Item Main Bus Feeder Bar size Bar size 200KVA Dist.Box 10x50 5x30 or 6x25 Neutral Bar Size 10x50 Remarks The sizes of main bus and feeder can suitably changed for carrying capacity upto 2.5 times of the respective MCCB. Neutral bus may be provided separately at the backside maintaining proper clearance duly isolated from body of Distribution Box through cotton impregnated hylem sheet of 10mm thick. vii) The Bus Bar/Links shall be covered with casting of through setting compound to avoid possibility of shorting due to movement of lizards’ etc. viii) All the bolts used in the bus bar joints shall be provided with check nuts in addition to spring washers. The size of nut bolts connecting the busses to other bus etc. should be such that the clearance between phase to phase or phase to neutral should not be less than prescribed limit. ix) Crimping type aluminium lugs of suitable size shall be used for all incoming and outgoing cable connection. The size of cable used for incoming and outgoing for various boxes are as follows Transformer Incoming Outgoing capacity 200 KVA 2X300, 3.5 C Sq.mm 3.5CX 150 Sq.mm (4 ckt) x) All bus bar shall be secured by DMC/SMC, (Fibreglass reinforced polystyrene) support depending upto their design and arrangements of bus bars. The support shall have anti tracking barriers between phases. xi) The minimum clearance of 25mm between phases and 20mm between phase and Neutral/Earth shall be maintained for the bus bars. xii) DMC/SMC moulded cable support shall (fixed on sides of enclosures) have holes of sizes to suit incoming and outgoing cable of recommended size. TESTS & TEST CERTIFICATE: The type test certificates from reputed national level laboratories for the distribution box complete with suitable MCCBs (as indicated in technical specification) for incoming and outgoing feeders giving the results of sample tests as per relevant BSS/ISS indicated below are required to be submitted along with the lot 153 offered for inspection before despatch for approval in support of compliance of material to the specification and quality. Make of the MCCBs to be used should be indicated in the offer. Acceptable make of MCCBs are L&T, Siemens, Crompton Greaves, and Alstom. (a) Type test for Distribution Box as per BS 214/1959. (b) All type & routine tests, except the Short Circuit Breaking Capacity Test shall be carried out on the MCCBs in accordance with IS:2516(Pt-I&II Sec.I)/1977 or its latest modification. The short circuit breaking capacity test shall be carried out. (c) Test Certificate in respect of Type Tests, from standard testing laboratory like C.P.R.I. etc. should invariably be furnished in support of the quality. GENERAL: (i) The boxes shall be strictly as per technical specification and drawings which are to be submitted by the bidder and approved by the MBSEB before taking up the manufacturing. The specifications of Distribution boxes are detailed below: Technical Specification Of LT Distribution Boxes for 200 KVA Ratings) S.No. Particulars RATINGS 200 KVA Design, Manufacture & Testing, Installation, commissioning of L.T. 1 SCOPE Distribution Boxes 2 SYSTEM AC 3 Phase 4 Wire 50 C/S 3 MATERIAL SHOULD BE SUITABLE IN THE WEATHER CONDITIONS AS BELOW: a) Temperature Range 0o to 50oC b) Relative Humidity 20% to Max. 100% c) Altitude 0 to 1000 Meters 4 SYSTEM DETAILS a) K.V.A. Suitable for use with 200 KVA X’mer b) Voltage c) Frequency Approximate full load d) 90/140 A current e) No. of Outgoing Circuit per Phase 415 V AC 50 C/S 2 Nos. 5 APPLICABLE STANDARDS - AMENDED UPTO DATE Switch Disconnector IS:13947 (Pt-III)/1993 a) (Isolator) IS: 13947 (Pt-II)/1993. The MCCBs provided in these boxes shall conform in all respects to the relevant IS: 2516 (Pt-I&II)/1977 and b) L.T. MCCBs REC specification No.18/1981 (revised) or its latest revision as applicable. c) Enclosure Box IS:2147/1962 General Requirement IS:4237/1982 & 8623 Part I/1993 d) of LT Switchgears 6 MANUFACTURING One Triple Pole Switch Disconnector of 450 A rating on Incoming / CONTRUCTIONAL side with 6 nos. single pole MCCB (nominal rating 160 Amps, O/L DETAILS Current setting (150 Amps) on outgoing side along with necessary 154 S.No. Technical Specification Of LT Distribution Boxes for 200 KVA Ratings) Particulars RATINGS 200 KVA inter-connection with bus bar & links with other components as per drawings enclosed DETAILS OF INCOMING CURCUIT WITH TRIPLE POLE SWITCH DISCONNECTOR (HANDLE SHOULD BE DETACHABLE) a) Rated Insulation Should be more than 660 volts AC b) Utilization category AC 23A Rated Impulse c) 12 withstand voltage (KV Rated Thermal current d) 450 A (Amps) Rated Operational e) 450 Amps current at 240V (Amp) Short-withstand f) 25 KA current for one second Rated Making As per relevant clause of I No.13947 (Pt-III) i.e. 10 times of the rated g) capacity at 415 VAC operational current of S.D. at 0.45 P.F Rated breaking As per relevant clause of I No.13947 (Pt-III) i.e. 8 times of the rated h) capacity 415 VAC at operational current of S.D. = 0.45 PF Mechanical Endurance i) (Operating Cycles) As per relevant Clause of IS No.13947 (Pt-III) (Nos.) Electrical Endurance j) As per relevant Clause of IS No.13947 (Pt-III) (Operating Cycles) Cross Section of terminal strips of k) switch dis connector 50x10 Sq.mm in incoming side & outgoing side (Sq.mm) Length of terminal on 80mm l) incoming side (in mm) Length of terminal on 60mm m) outgoing side (in mm) Material of the terminal strips Tinned Electrolytic Copper n) (incoming & outgoing) Length of Operating Switch Disconnector should be front operated & length should be at o) Handle and position of least 80mm handle Body Material of p) Body of the Switch Disconnector should be made of DMC compound Switch Disconnector 7 155 Technical Specification Of LT Distribution Boxes for 200 KVA Ratings) S.No. Particulars RATINGS 200 KVA The Switch Disconnector, to be used in the Distribution Box should Applicable ISS for be type tested as per IS: 13947-III)/1993 for Seq. I, II & III. The type q) type test test should have been conducted by CPRI/EREDA only. Type Test report is to be submitted. Note: Triple Pole Switch Disconnector to be used in Distribution Box, must possesses type test design as per IS 13947 – III / 1993 for Seq. I, II & III. OUTGOING CIRCUIT DETAILS SINGLE POLE MCCB SHALL BE PROVIDED AS 8 PER DETAILS GIVEN BELOW No. of circuits on a) Outgoing side per 2 Nos / Phase phase b) Nominal Current 100 Amps Current setting For 63 KVA-50/50 Amps for 100 KVA 95/95 Amps Two c) (Fixed overload) CKT/Phase d) No. of Pole Single Pole Rated Short circuit breaking capacity e) in KA as per 5 KA at 0.4 PF (LAG) IS:13947 (PartIII)/1993 The sequence of f) operation for As per Clause 8.3.4 of IS:13947(Pt-II) MCCB Utilization g) (A) category Power factor for h) 0.4 (LAG) short CKT Test i) Colour of MCCB Grey Arrangement of j) terminal strip of To be approved MCCB Projections of terminal strips of MCCB k) on: i) Bus-bar 60mm On out-going ii) 80mm (Cable side) Size of terminal l) 30 x 3 Sq.mm strips Material of the bus Continuous tinned copper strip from the point of contact m) bar strips MCCB to be used in the distribution box must be type tested for SeqDetails of Type n) I, Seq-II & Seq.III as per IS:13947 (Pt-II)/1993 done by CPRI tests for MCCB Bhopal, Bangalore or EREDA o) Type of MCCBs Thermo magnetic/Fully magnetic 156 Technical Specification Of LT Distribution Boxes for 200 KVA Ratings) S.No. Particulars RATINGS 200 KVA THE LT MCCB SHALL HAVE THE TIME CURRENT CHARACTERISTICS AS p) INDICATED BELOW: SETTING TRIPPING TIME 1.05 More than 2.5 Hrs. 0.2 More than 10 Minutes & less than 2 Hrs. 1.3 Less than 30 Minutes 1.4 Less than 10 Minutes 2.5 Less than 1 Minute 4 Not less than 2 seconds 6 Less than 5 seconds 12 Instantaneous (less than 40 Milliseconds) For the above time current characteristics the reference calibration temperature of the breaker should be 40 degree Variation, if any upto 50oC. The operating time, shall not exceed 10% of the current setting indicated above. Note: Single Pole MCCB shall possesses Type Test report of Sequence-I, II & III as per IS:13945 Pt-II. 9 DETAILS OF BUS BAR & LINKS Electrolytic tinned copper. All bus bar should be made of single strip a) Material without joint, burrs and properly drilled. b) Size of main Bus bar 30 x 3 Sq.mm c) Size inter-link 30x3 Sq.mm PVC Insulation of standard Colour code I.e. Red, Yellow, Blue for R, Insulations over the d) Y & B Phase Bus bar & links Minimum Clearance between Bus bar Box As per IS:4237 amended up-to-date e) and terminals of Switch Disconnector & MCCBs 10 ENCLOSURES i) Size (1000x1100x350mm) ii) Material CR/MS Sheet iii) Thickness 2mm Arrangement for Pad iv) Arrangement to be provided for pad lock lock Auto lock is to be provided in such & manner that the cover of the Weather Auto lock is box cannot be left open and it gets latched automatically when closed v) to be provided on front manually. Latch should be provided with master key for opening of of door the door vi) Slopping of Roof Slopping with 5 degree on back side An aluminium sheet 2 mm thick engraved with " Station vii) Front door of the Box Transformer DP – APDRP Project” 157 Technical Specification Of LT Distribution Boxes for 200 KVA Ratings) S.No. Particulars RATINGS 200 KVA Size of Bottom plate 11 3 mm dia holes in the plate perforated Thickness of Bottom i) 4 mm of non magnetic material Plate Material of the Bottom ii) Perforated non magnetic material sheet Plate Fixing Arrangement of iii) Should be detachable the Bottom Plate iv) Knock out Holes in the Bottom plate v) Additional supports of the bottom plate 3 Nos. holes with double compression brass glands suitable for the required size of cable and 2 Nos additional holes of same size with 2 mm thick MS sheet of suitable width to be provided with suitable hardware to plug the additional holes. 2mm thick perforated sheet Bottom cleat of 45x110x3mm thick sheet to be provided below the vi) Bottom Cleats of Box box on both side, so that box does not come in direct contact with ground when stored Air Circulation& vii) Both side louvers with wire mesh, vermin proof ventilation Clearance in the Box Clearance between the terminals of bus bar Creepage should be as per IS:4237 viii) switch Disconnector and MCCB Instructions to Instruction printed in Hindi to be provided as per drawing No.03(B) x) Lineman in side each box To be provided as per specifications detailed in technical Danger Board specifications. each box must have identification plate on the front x) Identification Plate cover a) MPSEB, b) Rating Box, c) Serial No., d) Name of firm and e) APDRP Work xi) Hinges To be approved Other parts such as All Nut, Bolts & Washers used in current carrying parts should be of xii) Nuts, Bolts & Washers good quality stainless steel etc. 12 EARTHING BOLTS a) Required No. Two (One on each side) b) Fixing 12 mm diameter bolts are to be fixed by welding on both the sides. c) Size 12 mm diameter One spring washer and two plain washers should be provided on the d) Others earthing bolt PAINTING & FIXING ARRANGEMENT 13 FOR BOX 158 Technical Specification Of LT Distribution Boxes for 200 KVA Ratings) S.No. Particulars RATINGS 200 KVA a) Process No. 5 Tank process b) Painting c) d) 14 With synthetic enamel paint of good quality Colour (outside) (inside) Grey White Fixing Arrangement for box The Distribution Box shall be provided with two nos. 75x 40mm (ISIC) mounting channels welded to the top sheet of the Box. The channel shall have 2 nos. holes (13mmx13mm) for receiving bolts. With such top mounting facility, the Box can be mounted directly under the base channels supporting the distribution transformer. The mounting holes shall be maintained at fixed distance of 225 mm irrespective of box size so that necessary provision of drilled holes can be done. NETURAL BUS BAR a) Size b) Fixing c) Lugs LUGS ON INCOMING AND OUTGOING TERMINALS 15 a) Size of Incoming side cable b) Size of Outgoing cable & lugs 16 CABLE HOLDING CLAMP 17 OTHER REQUIREMENTS 50 x10 sq.mm or equivalent To be approved Double hole bimetallic lugs adequate Bimetallic lugs on incoming terminals of Cables to Switch Disconnector and outgoing side from Single pole MCCB are provided suitable for the required size of 3-1/2 core cable. The bimetallic lugs should conform to IS:8337(e.g. clause 4.1.1, clause 4.1.3 and clause 4.2) 3.5 Core, 2X300 sq.mm 3.5 Core 150 sq.mm Cable holding clamp be made of 2mm thick strip with 4mm base to be provided on incoming side and outgoing side There should be free circulation of Air between Switch Disconnector bus bar & SP MCCB at back and front so that the inside temp. does not exceed beyond permissible limits A) IS:2147/1962 with latest amendments, B) IP-20 IS:8623(Pt-II)/1993 APPLICABLE STANDARDS FOR BOX 19 TEST & TEST CERTIFICATE (I) Type Test Certificate A) Temperature rise test as per IS:8623/Pt-I/93 NOTE B) High Voltage Test should be done at 3.00 KV for one minute C) Short time withstand current test on Distribution Box. For short time current test the box should be subjected to a current of 5 KA for 1 Sec. For all the Ckt. Independently, after by passing the MCCBs. Routine Test (II) Certificate 18 159 S.No. Technical Specification Of LT Distribution Boxes for 200 KVA Ratings) Particulars RATINGS 200 KVA A) Overall dimension, B) Insulation Resistance Test, C) H.V. withstand test for 3.0KV for one minute, D) Operation test on MCCB and S.D. separately Each Distribution Box should be tested for the routine test as indicated. The routine test report indicating S.No. must be submitted with the offer at the time of inspection of the material (III) ACCEPTANCE TEST ON COMPLETE BOX With the established temperature rise as above the Distribution box TIME CURENT MCCB should be tested for time current characteristic at 1.05 and 1.2 IV) CHARACTERISTIC times of over load release current setting and it should pass the TEST requirement given as per Clause-B(P) INSTRUCTION FOR SUBMISSION OF TYPE TEST 20 CERTIFICATES I) The type Test Certificate on the name of firm must be furnished along with the offer. In case firm is supplying the materials for the first time, type testing shall be in their scope of II) work. No separate type testing charges shall be paid by MPSEB for their product. 21. SCADA SPECIFICATION FOR NEW 33/11 KV, SUB-STATION S. No. PARTICULAR OF EUIPMENT SCADA PART A - SOFTWARE PORTION 1 Remote terminal unit 2 Multi Function Transducers 3 Contact multiplying relay Unit Case-1 QTY No. No. No. 1 9 132 4 Heavy Duty Relays for CB Trip/Close No. 27 5 6 7 8 Routers LDMS Printer LDMS SOFTWARE No. No. No. No. 1 1 1 1 TOTAL AMOUNT FOR PART -A SCADA PART -B- HARWARE EQUIPEMENTS 1 SCADA compatible Differential Relay (for 5 MVA X-mer) No. 1 2 SCADA Compatible Numerical Relay No. 9 3 Master Trip Relay No. 9 4 Aux relay (30 v DC 4 NO + 4 NC) No. 30 5 contractors No. 25 6 Transformer Pressure Indicator (TPI) No. 1 160 7 Winding temperature indicator (WTI) No. 1 8 Oil Temperature indicator (OTI) No. 1 9 10 Isolator Contacts Control cable No. 19 a 2 Core. 2.5 Sq.mm. (Unarmoured) Km 0.75 b 4 Core. 2.5 Sq.mm. (Unarmoured) Km 2.5 c 8 Core. 2.5 Sq.mm. (Unarmoured) Km 0.3 TOTAL AMOUNT FOR PART -B TOTAL (Part A+B) TOTAL 22. TECHNICAL SPECIFICATION FOR 11 KV EPOXY CAST DRY TYPE SINGLE PHASE PTs 11 KV Single Phase Potential Transformer shall conform to IS-3156:92 with its latest amendments if any. Since epoxy resin are liable to weathering when exposed to atmosphere, the complete unit shall be contained in a full weather proof outdoor pole mounting type steel tank with one number of 11 KV weather proof porcelain bushing on the primary side for incoming connections. Secondary terminals of the potential transformers shall be brought-out on the side of the tank to a separate terminal box. Box shall be made suitable for taking out secondary connections through PVC Cables. Entry of the cables into the box of the unit shall be through glands and check nuts to be supplied along with epoxy compound. The transformer tank shall be given three coats of rust preventing paint and finished with light gray no. 631-IS-S on all external surfaces. The tank shall be provided with lifting hooks properly welded on the side or top cover plate of the tank. The dimensions and electrical characteristics of the 11 KV bushing shall be in accordance with IS: 2099 and its subsequent amendments, if any. The minimum electrical clearance between phases and phase to earth shall be as per ISS. The top of the tank will have slope to drain the rain water and avoid collecting pockets. To prevent moisture entry in the bushing chamber, the nuts on the top of the stem would be sealed with araldite. Further, the angular space between the stem and the bushing will be filled with epoxy cast compound or with araldite to prevent ingress of moisture. The insulating materials for winding between HV and LV between interlayer of the winding for end turns shall be as per relevant ISS. However, end turns have to be provided with enforced insulation and lead connecting to the bushing shall be provided extra insulation of fibre glass sleeves. Voltage rating, PT ratio, class of accuracy, burden of 11 KV Single Phase PTs shall be engraved/painted on the body of main tank as well as on name plate. The potential transformer will be connected phase to neutral with neutral point solidly earthed. The neutral of the system is also solidly earthed. 161 The potential transformers shall be designed to limit the temperature of winding and other parts as specified in the standards, when corrected for the difference between the temp. prevailing at site and temperature specified by the standards. The temperature rise at 1.2 times rated primary voltage when applied continuously at rated frequency and at rated burden shall not exceed the limits specified above and the temperature rise at 1.5 times rated primary voltage when applied for 30 seconds starting from previous stable operating conditions at the rated frequency and rated burden shall not exceed the above temperature limits by more than 10°C. TYPE TESTS The Single Phase PT shall be type tested, as per IS-3156/1992 with latest amendment, if any from CPRI or from any Govt. Standard Test Laboratories in India or from laboratories of Inter National repute duly attested by competent testing authority. The type test comprises of following:1. Temperature Rise Test 2. Lightning Impulse Test 3. Determination of errors or other characteristics according to requirement of the appropriate designation or accuracy class. 4. HV Power frequency wet withstand voltage test. ROUTINE TEST Each 11 KV Single Phase PT shall be subject to routine tests in accordance with IS-3156 (with it latest amendment if any) at firm’s works and shall be witnessed in the presence of owner’s representatives, if so, desired by the owner. The routine test comprises of following: Verification of terminal marking and polarity test Power Frequency Dry withstand voltage test on Primary winding Induced over voltage withstand test Power Frequency Dry withstand test on Secondary winding Partial Discharge Tests in accordance with IS-11322/1985 Determination of errors or other characteristics according to requirement of the appropriate designation or accuracy class. Routine tests indicating results of all the required tests should be submitted in duplicate by the firm along with the inspection offer or with inspection report. 23. TECHNICAL SPECIFICATION FOR 33 KV CURRENT TRANSFORMER SCOPE: This specification covers design, manufacturing, testing at manufacturers works, supply and delivery of 33 KV outdoor type epoxy moulded oil immersed, current transformers for relaying and metering services in 33 KV solidly grounded system. GENERAL REQUIREMENT: The current transformers shall be of outdoor, epoxy moulded, single phase, 50 cycle, oil immersed design and suitable for operation in humid atmospheres and in the tropical direct sun-light with temperature up to 50°C. They should be suitable for use in areas subjected to heavy lightning storms. The CT should be suitable for operation under the climatic conditions, prevailing in the State of Madhya Pradesh. The CTs are required to be mounted on an out door structure in the switchyard. CTs will therefore, have suitable mounting holes at the base channel, for clamping it on the structure. This specification does not cover supply of mounting structures for the CTs. The current transformers shall have the following specification:i Nominal System Voltage 33 KV 162 ii iii iv Highest System Voltage Frequency Earthing of the System v vi vii viii ix x xi Insulation Level Short Circuit Level Minimum one second short time current rating One Minute Power Frequency withstand Voltage Minimum creepage distance Rated Secondary Current No. of cores (with the following accuracies) S.No. Particular Core-I i Purpose Relaying/ Protection ii Rated Output 30 VA iii Accuracy Class 5 P 10 Tank Sheet Thickness Transformation Ratio xii xiii 36 KV 50 Cycles Effectively grounded 170 KV 1000 MVA 18.4 KA 70 KV 900 mm 5 Amps 2 Core-II Metering 30 VA 1.0 Minimum 3 mm 200-100/5-5A and 300-150/5-5 A DESIGN: As stated, the 33 KV CTs shall be oil immersed epoxy moulded type. Thus, the CT cores after providing insulation shall be moulded in epoxy compound and thereafter shall be housed in the steel tank. Thickness of steel tank sheet shall be more than 3 mm. Complete process of manufacturing shall be clearly described in the offer by the tenderer. STANDARDS: The current transformers shall comply with the latest issue of Indian Standard 2705 (Part-I, II, III & IV) or IEC-185 with latest amendment thereof. GENERAL: The current transformers shall be outdoor single phase, epoxy moulded oil immersed type suitable for the services indicated, complete in all respect conforming to the modern practices of design and manufacturing. The core shall be of high grade, non-ageing electrical silicon laminated steel of low hysterics loss and high permeability to ensure high accuracy at both normal and over currents. Current transformers shall be sealed properly to eliminate and prevent air and moisture from entering the tank. These shall be provided with oil level gauge and shall be provided with a pressure relieving device capable of releasing abnormal internal pressures. Design and manufacturing of mounting of pressure release device and oil level gauge should clearly be described with the help of suitable drawings. The maximum temperature attained by any part of the equipment, when in service, under continuous full load conditions and exposed to direct rays of sun, shall not exceed 45°C above ambient. The primary winding, terminals, terminal connectors etc. are required to be designed considering the continuous over loading of 25%. For the 25% continuous over loading, the ratio and phase angle error shall be maintained within the specified limit applicable for normal loading conditions. Further, temperature rise for 125% loading shall be within the permissible limits specified in the relevant IS. WINDINGS: The current transformer core to be used for metering and instrumentation shall be of accuracy class specified above. The primary winding shall be designed considering current density not exceeding 1.5 Amps/sq. mm. The saturation factor of this 163 core shall be low enough not to cause any damage to measuring instruments in the event of maximum short circuit current. Current transformer cores to be used for protective relaying purposes shall be of accuracy class specified or appropriate class suitable for over current protection. The cores shall be designed for a minimum saturation factor of 10 for the highest setting. The magnetization curves for these cores shall be furnished with the tender. The rating of the secondary windings shall be 5 Ampere. The secondary terminals shall be brought out in a compartment on side of current transformer for easy access. The secondary terminals shall be provided with short circuiting arrangement. The secondary taps shall be adequately re-inforced to with-stand normal handling, without damage. INSULATION: The quantity of insulating oil for first filling in each current transformer and the complete specification of the oil shall be stated in the tender. The oil should be preferably of improved EHV grade type. The current transformers shall be single phase, multi-core, separately mounted, free standing type for outdoor installation. The insulators shall be prepared from wet process porcelain with arrangement for sealing hermetically to the metallic tank containing the core and the secondary winding. The primary terminals of current transformer shall be of non-ferrous corrosion-proof material and shall be provided with suitable terminal connectors to receive ACSR Dog conductors. Complete design of terminal connector together with aluminium alloy composition, as per the requirement of IS, shall be decided by the Board at the time of drawing approval after placement of order and the agency will have to ensure compliance of the same at no extra cost. Further, the terminal connectors are to be made by gravity diecasing process. Secondary terminals shall be brought to a suitable weather proof sheet meal terminal box for termination of multi-core armoured cable (as per IS-2147). The terminals of primary and secondary winding shall be clearly marked according to relevant standards. INSULATION WITHSTAND CHARACTERISTICS: Insulation withstands characteristics shall be as per IS 2705 and as shown in the table below :Nominal system Highest system Lightning Impulse Power Frequency voltage voltage withstand voltage withstand voltage (for 1 minute) 33 KV (rms) 36 KV (rms) 170 KV (peak) 70 KV (rms) All exposed ferrous parts shall be hot dip galvanized conforming to IS : 2633. For the secondary connections, threaded stud terminals shall be provided. Change in CT ratio will be obtained by providing tapings in the secondary windings, while the primary will have only one winding. The tenderer should note that the CTs are required only of outdoor type having porcelain shell, duly epoxy moulded type. Compound filled CTs are not required. Further, CTs with live tank design or inverted type are not acceptable. TYPE OF MOUNTING: The 33 KV CTs shall be mounted on CT bracket, provided on 33 KV circuit breaker’s structure. TERMINAL CONNECTORS: The terminal connectors suitable for ACSR Dog Conductor and for horizontal take off shall be supplied. Suitable terminal earth connectors for earthing connection shall also be supplied. The design of clamp shall be subject to our approval. 164 STUDS: The length of stud available for clamping of terminal connector shall be 80 mm. Minimum 2 nuts with a check nut and washer should be provided on upper side of stud. The minimum size of stud should be 12 mm for 200-100/5-5 Amps and 16 mm for 300-150/5-5 Amps CTs. Further, the primary studs shall be so designed as to have current carrying capacity at least 1.5 times that of the primary winding. BUSHING: The basic insulation level of the bushing shall be as specified and porcelain shall be homogeneous and free from cavities and other flaws. This shall be so designed as to have ample insulation and mechanical strength. All insulators of identical ratings shall be interchangeable. The insulators shall be type tested from any independent Govt. Lab., as per relevant standard. TESTS PARAMETERS 1. Short time Cu comply wit short time c a. Thermal Rating CTs for the b. Dynamic Ratin can withs mechanicall not be less t c. Temperature R when carry current, at exceed 45°C TESTS: The outdoor type CTs shall be subjected to the following tests as per IS-2705 of 1992 with latest amendment thereof and the test certificates should be submitted for approval to the owner. TYPE TEST: Short Time Current Tests Temperature Rise Test Lightning Impulse Test High Voltage Power Frequency wet withstand Voltage Tests Determination of errors according to the requirements of the appropriate accuracy class. Copy of the Test certificates for the above tests must be furnished along with drawings of type tested CTs duly authenticated by the type testing authority. The type Test Certificates should be from independent Govt. Laboratory. The above tests must have been conducted on the CT during the last 5 years from the date of opening of the bids and not earlier to than that. In case of any change in design/type of CT already type tested and the one offered against this specification, the owner reserves the right to demand repetition of tests, without payment of any charges by the owner. ROUTINE TESTS The following shall constitute the routine tests :165 Verification of terminal markings and polarity Power frequency dry withstand tests on primary winding Power frequency dry withstand tests on secondary windings Over-Voltage inter-turn test Determination of errors according to the requirements of the appropriate accuracy class Each current transformer shall be subjected to routine tests, as specified in Indian Standard 2705, in the presence of owner’s representative, if so desired by the owner. All test reports should be submitted and should be got approved from the owner before despatch of the equipment. tests for chemical, mechanical, galvanizing tests as per IS-280-1979, IS: 1521-1972, IS1755-1961, IS: 6745-1972 & 4826-1979 be encrusted. Test certificate towards, chemical composition (as per S>No.1 above) shall be submitted for each lot offered for inspection. The below said tests shall be conducted in presence of Board’s representative deputed for this at firm’s works & cost. Vital Physical inspection and measurement of specified dimensions. Coating test as per IS-1755-1961, IS: 2629-1966, IS: 2633-1972, IS: 4826-1969 & 1979 – IS: 6745-1972. Adhesion test as per IS: 1755-1961, IS: 2629-1966, IS: 2633-1972, IS: 4826-1969 & 1979 – IS: 6745-1972.Tensile strength and breaking load and elongation determined as per IS 1521-1972 with up to date amendments. PACKING - Packing shall be as per IS 280-1979 (Col.3.1) and each coil between 50-100 Kegs. 24. TECHNICAL SPECIFICATION FOR 11 kV & 33 kV MS CROSS-ARMS OF OVERHEAD POWER LINES 1.0 ‘V’ SHAPE M.S. CROSS ARM WITH CLAMPS 1.1 X-arms shall be made out of 100 x 50 x 6 mm and 75 x 40 x 6 mm M.S. Channel for 33KV and 75x40X6mm for 11KV. 1.2 The cross arm shall be hot dipped galvanized generally conforming to IS – 2633/72. 1.3 The X-arm should not be welded/ jointed at any place except as specified. 1.4 The clamps for the X-arm shall be of G.I. & shall be hot dipped galvanized generally conforming to IS – 2633/72. 1.5 The clamps shall be designed to fit for the specified rail & PSC poles. 2.0 Shape & Size 2.1 The cross arms shall be of MS channel. 2.2 The cross arms shall have two holes of 22 mm dia (for 11kV line) and 26 mm dia (for 33kV line) for fixing of pin insulators. The centre-to-centre distance between the holes shall be 1070 mm (for 11kV) and 1525 mm (for 33kV) and holes shall be in the middle of the top width of cross arm. 2.3 If required by the owner, holes of specified size and spacing shall also be provided for fixing of pole back clamp to suit the pole. 3.0 Marking The following information shall be marked on each cross arm: a) Manufacturer’s name or trademark. b) Year of manufacture 166 25. TECHNICAL SPECIFICATION FOR 11/33 kV NOMINAL VOLTAGE HT XLPE POWER CABLES 1. SCOPE: The specification covers design, manufacture, shop testing, packing and delivery of 11 & 33 kV, multi core, cross linked polyethylene insulated power cables. These cables shall be suitable for the 3 phase AC-50 Hz system with the nominal voltage of 11/33 kV which may reach maximum of 12/36 kV respectively. These cables shall primarily be designed for effectively earthed neutral system. 2. SERVICE CONDITIONS: Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions. 2.1 Maximum ambient temperature (deg C) 50 2.2 Maximum temperature in shade (deg C) 45 2.3 Minimum temperature in air (deg C) in shade 3.5 2.4 Relative Humidity (%) 10 to 100 2.5 Maximum annual Rainfall (mm) 1450 2.6 Maximum Wind Pressure (kg/mm2) 150 2.7 Maximum altitude above mean sea level (Meters) 1000 2.8 Isoceraunic level (days/year) 50 2.9 Seismic level (Horizontal acceleration) 0.3 g. 2.10 Moderately hot and humid tropical climate, conducive to rust and fungus growth. 3. STANDARDS: Unless otherwise specified elsewhere in this specification, the rating as well as performance and testing of the HT XLPE power cables shall conform to the latest revisions available at the time of placement of order of all the relevant standards 4. GENERAL TECHNICAL REQUIREMENTS: 4.1 6.35/11 kV , 19/33 kV earthed, multi core power cables shall normally be with stranded compacted H2/H4 grade aluminium conductor as per IS: 8130 - 1984, provided with conductor screening (of extruded semi-conducting cross link material) and shall be insulated with XLPE of natural colour. Identification of cores shall be by colour, as per provision of clause 13.1 of IS: 7098 (Part 2) - 1985. The insulation (XLPE) screening shall be provided consisting of extruded semi-conducting cross link material in combination with a metallic layer of copper tapes. Three such screened cores shall be laid up together with fillers and/or binder tapes where necessary and provided with extruded inner sheathing of heat resistant PVC conforming to type ST-2 of IS: 5831 - 1984. Maximum continuous operating temperature shall be 90 deg C under normal operation and 250 deg C under short circuit condition. Armouring shall be provided consisting of single galvanized round steel wires (In case of Single core cable armouring shall be of Non-magnetic material) conforming to IS: 3975 1988 (amended upto date) and over the armouring a tough outer sheath of PVC compound shall be extruded. The PVC compound for the outer sheath shall conform to type ST-2 of IS: 5831 - 1984 (amended upto date). The colour of the outer sheath shall be black. The cable shall be manufactured strictly conforming to IS:7098 (Part 2) - 1985 amended upto date and shall bear ISI mark. 4.2 SEQUENTIAL MARKING OF LENGTH ON CABLE 167 Non erasable Sequential Marking of length shall be provided by embossing on outer sheath of the cable for each meter length. The quality of insulation should be good and insulation should not be deteriorated when exposed to the climatic conditions. 4.2.1 DISCHARGE FREE CONSTRUCTION: Inner conductor shielding, XLPE insulation and outer core shielding shall be extruded in one operation by special process (viz. Triple Extrusion Process) to ensure that the insulation is free from contamination and voids and perfect bonding of inner and outer shielding with insulation is achieved. The bidders are requested to elaborate the manufacturing technique adopted by their manufacturers to achieve this motive. The Company will order the verification of triple extrusion process at manufacturer’s works as a pre qualification if it is technically accepting the bid During verification if it is found that the firm is not manufacturing the cable with triple extrusion process the offer shall be rejected. IV.3 CONTINUOUS A.C. CURRENT CAPACITY: Conductor sizes in sq.mm. Continuous a.c. current capacity in Amps.at maximum conductor temp. of 90 deg .c. 11 kV 33 kV When laid When laid When laid When laid direct in in air direct in in air the ground the ground 70 sq.mm 160 190 160 95 sq mm 190 230 190 120 sq mm 220 260 215 150 sq mm 245 295 240 185 sq mm 275 335 270 240 sq mm 315 395 310 300 sq mm 355 450 350 400 sq mm 400 520 395 Continuous a.c. current capacity shall be as per Table given below. IV.4 190 230 265 300 340 400 455 530 SHORT CIRCUIT CURRENT Short circuit current of 11 & 33 kV XLPE cable shall be as per Table given below. Duration of Area of Al. Short circuit Short Conductor current in kA Circuit in sec T A I=0.094 x A/sq.rt (t) 1 70 sq.mm 6.58 1 95 sq.mm 8.93 1 120 sq.mm 11.28 1 150 sq.mm 14.1 1 185 sq.mm. 17.39 168 1 1 1 1 1 240 sq.mm. 300 sq.mm. 400 sq.mm. 500 sq.mm 630 sq.mm 22.56 28.2 37.6 47 59.2 5. TESTS AND TESTING FACILITIES: 5.1 TYPE TESTS: All the type tests in accordance with IS: 7098 (Part 2) - 1985, amended upto date, shall be performed on cable samples drawn by purchaser.. Type tests are required to be carried out from the first lot of supply on a sample of any one size of cable ordered for each voltage grade. In case facilities of any of the type tests are not available at the works of the supplier, then such type test shall be carried out by the supplier at the independent laboratory at the cost of supplier. Sample for the type test will be drawn by the purchaser's representative and the type test will be witnessed by him. Supplier, however, can claim exemption from carrying out type test as above, provided such type test were already conducted for M.P.S.E.B.) in the past within five years and the test certificates thereof submitted to our C.E.(Dist) . Chief Engineer (Dist) may at his option grant waival from carrying out type tests if the test certificates are acceptable .In case of other Government recognized laboratories / Test House valid approved Government certificate shall be enclosed alongwith test. 5.2 ROUTINE TESTS: All the Routine tests as per IS:7098 (Part 2) - 1985 amended upto date shall be carried out on each and every delivery length of cable. The result should be given in test report. Partial discharge test must be carried out in a fully screened test cell. It is, therefore, absolutely essential that the manufacturer should have the appropriate type of facility to conduct this test which is routine test. The details of facility available in the manufacturer's works in this connection should be given in the bid. 5.3 ACCEPTANCE TESTS: All Acceptance tests as per IS:7098 (Part 2) - 1985 as modified upto date including the optional test as per clause no 18.4 and Flammability Test shall be carried out on sample taken from the delivery lot. 5.4 SHORT CIRCUIT TEST: The contractor shall also undertake to arrange for the short circuit test as a type test on any one size of each voltage grade i.e. on one size of 11 kV, one size of 22 kV and one size of 33 kV earthed grade shielded XLPE cables ordered at a recognized testing centre such as Central Power Research Institute at Bangalore/ Bhopal at the cost of supplier. If facilities for carrying out short circuit tests are available at the works of the supplier, and provided the certification procedure is approved by the Purchaser, testing at the supplier's works will be acceptable. Short Circuit test shall be witnessed by the purchaser's representative. 169 5.4.1 The short circuit test shall be preceded and followed by the following tests so as to ensure that the characteristics of the cable remain within the permissible limits even after it is subjected to the required short circuit rating. a) Partial Discharge Test. b) Conductor Resistance Test. c) High Voltage Test. 5.4.2 The manufactured cable will be acceptable only after such a sample test is successfully carried out at CPRI or at suppliers works and approved by the Purchaser. 5.4.3 The contractor can however claim exemption from carrying out Short Circuit test provided the S.C.Test was carried out by the supplier on same voltage grade for M.P.S.E.B.) in the past within five years and the test certificates thereof submitted to our C. E. (Dist.).Chief Engineer ( Dist.) may at his option grant waiver from carrying out Short circuit test if the test certificates are acceptable. 5.5 TESTING FACILITIES The supplier / tenderer shall clearly state as to what testing facilities are available in the works of manufacturer and whether the facilities are adequate to carry out type, routine and acceptance tests mentioned in specified IS. The facilities shall be provided by the bidder to purchaser’s representative for witnessing the tests in the manufacturer’s works. If any test cannot be carried out at manufacturer’s works reason should be clearly stated in the tender. 6 PACKING AND MARKING: 6.1 IDENTIFICATION MARKS ON CABLE: The following particulars shall be properly legible embossed on the cable sheath at the intervals of not exceeding one meter throughout the length of the cable. The cables with poor and illegible embossing shall be liable for rejection. a) Manufactures name and/or Trade name. b) Voltage grade. c) Year of manufacture. d) M.PS.E.B. e)Successive Length. f) Size of cable g) ISI mark 6.2 The cable shall be supplied in continuous standard length of 250 running meters with plus minus 5% tolerance wound on non-returnable wooden drum of good quality and non-standard lengths not less than 100 meters upto 5% of the ordered quantity shall be accepted. Alternately cable can be supplied wound on non-returnable steel drum without any extra cost to the purchaser. Packing and marking shall be as per clause No. 21 of IS:7098 (Part 2) - 1985 amended up to date. 6.3 Supplier should provide statistical data regarding cables of all sizes viz.1) Weight of one meter of finished product of cable of various sizes and ratings. 170 2) Weight of one meter of bare conductor used for cables of various sizes and ratings. 7 QUALITY ASSURANCE PLAN: A detailed list of bought out items which got into the manufacture of cables should be furnished indicating the name of the firms from whom these items are procured.. The bidder shall enclose the quality assurance plan invariably along with offer followed by him in respect of the bought out items, items manufactured by him & raw materials in process as well as final inspection, packing & marking. The Company may at its option order the verification of these plans at manufacturer's works as a pre qualification for technically accepting the bid. During verification if it is found that the firm is not meeting with the quality assurance plan submitted by the firm, the offer shall be liable for rejection. LIST OF STANDARDS (All amended upto date) SR.NO. STANDARD NO. TITLE 1. IS: 8130 – 1984 2. IS :7098 (Part 2) – 1985 IS: 5831 – 1984 IS: 3975 – 1988 Conductors for insulated electric cables and flexible cords. XLPE PVC sheathed cable for working voltages from 3.3 KV upto and including 33 kV. PVC insulation and sheath of electric cables. Mild steel wires, Formed wires and Tapes for armouring of cables. Fictitious calculation method for determination of dimensions of protective coverings of cables. 3. 4. 5. 26. IS :10462 ( Part I) –1983 STREET LIGHT POLES: - TECHNICAL SPECIFICATION OF HOT DIP GALVANISED OCTAGONAL POLES Pole Design: The octagonal poles shall be OCTAGONAL in cross section and are continuously tapered with only one longitudinal welding thereby giving an elegant & sleek look aesthetically. The welding of pole shafts shall be done by Submerged Arc Welding (SAW) process. The poles shall be provided with base flange of suitable thickness with a provision for fixing 4 foundations bolts. Design Criterion: 171 Octagonal Poles shall be designed to withstand maximum wind speed as per IS 875 part III. The top loading i.e. area and the weight of luminaries are considered to calculate the maximum deflection of the pole to meet the requirement of BS: 5649 Part VI 1982. The design life of poles shall be 20 to 25 years under standard working conditions. Material of Construction :Pole Shaft : High Tensile steel conforming to grade S 355 JO as per BSEN 10025. Base Plate : Fe 410 conforming to IS 226 / IS 2062.Pole sections: The Octagonal Poles shall be manufactured in single section upto 14 mtrs without any joint. The cutting of sheet before bending on press brake shall be by cold shearing method to avoid development of stresses in steel. Such stresses in steel result in twisting near the top of the pole. Since these poles shall be installed in areas were aesthetics is of prime importance. Hence, such cold cutting must be adhered to, Welding: Welding of poles shall be carried out conforming to approved procedures duly qualified by third party inspection agency. The welders shall also be qualified for welding the shafts. Galvanization: The octagonal poles shall be hot dip galvanized (internally & externally) as per IS 2629 / IS 2633 / IS 4759 standards or equivalent with average coating thickness of 70 microns. The galvanizing shall be done in single dipping. Double/ part dipping shall not be allowed. Top Mountings: The luminaries shall be fixed on arms of suitable size. The arms shall be manufactured from suitable MS pipes which are duly galvanized. LIGHTING FIXTURES 27. TECHNICAL SPECIFICATIONS FOR SODIUM VAPOUR LUMINAIRES General description: Road lighting luminaire suitable for use with High Pressure Sodium Vapour SON-T PLUS 250 W Lamp. Features Housing made of LM6 high pressure die-cast aluminium which does not need painting to prevent corrosion of the housing. However the luminaries shall be painted with BLUE EPOXY COLOUR for long life Colour choice may also be changed . All electrical accessories such as energy efficient, low loss, open construction copper ballast, ignitor and power factor improvement capacitor, etc are pre-wired upto the terminal block and mounted on a removable control gear module for ease of maintenance. All electrical connections of the control gear module with the rest of the luminaire are click fix, fool proof and require use of no tools. Control gear compartment opens from top The lamp compartment consists of electrochemically brightened and anodized, high purity POT reflector with a specially designed ribbed profile for high spacing to mounting height ratio.! The lamp compartment shall consists of a heat resistant toughened, flat glass (FG) which shall be sealed to the housing. Lamp replacement is by opening the top compartment. Luminaries shall be IP 66 classification of ingress protection for the lamp compartment. 172 Specially designed pole mounting arrangement facilitates bottom as well as lateral pole mounting. Flexible optics to achieve optimum light distribution to suit different road and installation parameters Lamp Compartment shall be IP 66 Gear Compartment shall be IP 54 The Luminaire should have step dimming facility for 250-150 W operation with inbuilt timer and memory & clock operation. Make:- Philips Velocity SGP 338 / Bajaj Brallo 250 W/ Schnedder AMber 250 W SON/ GE Inaulux 250 W SON. the fixture should be capable of dimming the light output of the fixture till 50% in two steps without compromising on the life of the system 28. No 1 2 3 TECHNICAL SPECIFICATIONS OF LED Criteria Luminaire configuration technical requirement Specification for LED street light fitting / Side entry type. Shall consist of separate optical and control gear compartment. Driver should be early replaceable in the field condition High pressure die cast Aluminum LM6 housing with corrosion Housing / Body of resistant polyester powder coating with manufacturer fitting emblem/logo embossed into the housing. Aesthetically designed housing with Black / Grey / Cream color Finish corrosion resistant polyester powder coating. 4 Cover / glass 5 Glare control details Luminaire should be full cutoff as per IS 1944 6 Protection – IP Optical and Control gear compartment-IP 66 7 Impact resistance 8 Optical assembly 9 10 11 Operating voltage Frequency Power factor Fixture designed ambient Temperature Operating temperature Impact resistance greater than or equal to IK 05 Structured LED array for optimized roadway photometric distribution with photometric lenses designed to optimize application efficiency and minimal glare. 140-270 volt universal electronic driver 50 Hz > 0.9 12 13 Toughened glass + 35 degree C Range 0 to +50 degree C 173 14 15 16 17 18 19 20 21 22 Working Humidity Storage Temperature Total Current Harmonic distortion Total system wattage and lumens of Fixture including Driver LED efficacy (lumen/watt) LED Luminaire efficacy 10% to 90% RH 0 to 50 degree C Total Current Harmonic Distortion should be lesser than 20 % Nominal value to be printed in the label and within +/- 10% variation from the printed value Efficacy of LED should be greater than 120 lumens / watt. 88 lumen/watt ( As per LM 79 test report by U/l Lab) Power efficiency / The efficiency shall be more than 85 % in all cases at all times LED driver during project period. efficiency Lumen maintenance L70 @ 50,000 hours at 35 degree C System Lumen 12200 Lumens Output 23 Correlated Color temperature Correlated Color Temperature shall be nominal 5700K (with variation limits of ±355K) per ANSI C78.377A CCT standard. 24 CRI The value of CRI shall be more than 70. 25 Make of LED Make of LED: CREEE /Philips Lumileds /Nechea. The LED shall be of Surface Mounted Design 26 Lens Lens should be provided for each LED on a lens plate 27 LED Drive Current Not more than 85% of the rated current carrying capacity of LED 28 Driver Specification 140-270 Volt universal electronic potted drivers with internal surge protection of 4kV. 29 30 31 32 Electrical safety as per IEC. Conformation standards of luminaire Reports / certifications Luminaire protection As per IEC safety standards IEC61000, 61547, 61347 The luminaire conform to IEC 60598 / 10322 UL/ ERTL /ERDA or any NABL accredited laboratory for LED for luminaire and driver External surge protection of 4KV (DM / CM) and protection device components should be enclosed in a housing. The fixture should be capable of dimming the light output of the fixture till 100% in two steps without compromising on the life of the system. 174 33 Test reports of luminaire 34 Installation reference 35 Serial number 36 Approved Makes (a)The luminaire should be tested as per IEC 60598 standards and following test reports should be submitted: Heat Resistance Test, Thermal Test, Ingress Protection Test, Electrical / Insulation Resistance Test, Endurance Test, Humidity Test. The luminaire should be tested for 'Drop test' as per IEC 60068-231/IS9000 Part 7 / Sec 3 standards. The luminaire should be tested for 'Vibration test' as per ANSI/IEC 68-2-6 standards. (b) Should comply to IESNA LM-79 (Approved method for the Electrical and Photometric Measurements of Solid-State Lighting Products) (c) The LED’ used should comply to LM-80 standards (IESNA: Approved Method for Measuring Lumen Maintenance of LED Light Sources and LED lumen depreciation time to L70 based on LM-80 data) (d)Copy of above test certificates should be submitted with tender. Fixture quoted should have an installation reference of minimum 1000 nos with any Govt approved authority during the last three years. Completion certificate signed from appropriate authority should be attached with the technical bid document. LED street light fitting should be supplied with serial number which should be attached to the fitting. The label should mention: Name of Manufacturer, model name and number, system lumen pack, nominal CCT, Wattage of fitting, Date of Manufacture, and other labeling details as per IS. Kesselec Schnaider Teceo / Bajaj Rudd / Philips Green line Extra / GE Evolve make only Mandatory testing equipment available with the LED Street lighting supplier: To ensure type testing of the products and to have quality control measures the bidder / manufactures should have following in-house testing facility, R&D facility recognized by government of India GLOW wire test HV Tester Adequate number of electrical meters for measurement of different electrical parameter Megger (500 Volt) Tracking test Resistance to heat Measuring gauges such as Vernier caliper, Micrometers, Dial gauges NON contact IR based digital thermometer Harmonic analyzer and THD meter Digital Weighting machine Power analyzer Surge Tester Temperature simulation facility to test various temperature parameters 175 Ingress protection test facility for dust and water jet Transportation drop test Vibration test Compression test Humidity test Electronically controlled rotating mirror Gonio Photometer Sphere for measuring CCT Thermal Endurance testing machin Field testing of Illuminance levels (Wr) The field of calculation should be bounded by the edges of the carriageway and by the transverse lines through two consecutive luminaries. For staggered installations consecutive luminaries shall be on opposite sides of the road. S is the spacing between two consecutive luminaries (m), N is the number of calculation points in the longitudinal direction with following values; For S≤30m, N=10 For S>30m, N is the smallest integer giving D≤3m The first row of calculation points is spaced at a distance of D/2 beyond the first luminaire. 176 2. Transverse direction: d=Wr/3, where; d is the spacing between points in the transverse direction (m); Wr is the width of the carriageway or relevant area (m). 3. The spacing of points from the edges of the relevant area is D/2 in the longitudinal direction, and d/2 in transverse direction, as indicated in the figure above. 4. Luminaries which are situated within five times the mounting height from the calculation point should be included in the calculation. 5. Average Illuminance: It is the arithmetic mean of the Illuminance obtained. APPROVED VENDOR LIST;- The bidder shall use Public sector manufacturers brand with ISI mark products only . In case public sector manufacturers products are not available he should seek approval of any of makes mentioned below from MPAKVN (I) LTD who shall grant approval for these makes after verification that manufacturer has relevant type test certificates from NABL accredited laboratories and has past experience of supply . S. No. 1 Name of Vendor Item Description 33/11 KV, 5 MVA Power Transformer 2 11 and 33 KV VCB 3 11KV Capacitor Bank .1) BHEL 2) Areva T & D /Crompton/ABB/Volt amp 3) MPPKVVCO approved makes like Transformers/Tesla/Capital Transformers 1) BHEL 2) Schneider Electric 3) ABB India Ltd. 1) Sreem Capacitor 2) C & S Efacec MV Ind. Pvt. Ltd. 3) Areva T & D Ind. Ltd. 4 LT Cable 5 33 & 11 KV Disc / Pin Insulators 4) BHEL 1) RR Cables 2) Finolex 3) Havell’s 4 )RPG Cables 1) BHEL 2) Rajshree 3) Insulators and Electricals 177 Star Delta 33 and 11 KV Lightening Arrestor 6 1) BHEL 2) Elpro International ltd. 3) Areva T & D Ind. Ltd 4) MPPKVVCO LTD approved vendors after approval by MPAKVN 7 11 KV D.O. Fuse/ HRC Fuse 1) BHEL 2) Areva T & D Ind. Ltd. 3) Mahalaxmi Electricals 4) RUMA 8 Hot Dip galvanized Street Light Octogonal Poles 1. Bajaj 2. Transrail 9 Street Light Fixtures 1.PHILLIPS 2.WIPRO 3.BAJAJ 8 LT Distribution Boards/ VCB relay penals 1 BHEL 2. ABB 3 Schinder 4. . MPPKVVCO LTD approved vend ors 9 33 and 11 KV CT, PT 10 AAAC/ ACSR Conductor 11 All Misc material 1. BHEL 2 ABB 3. MPPKVVCO LTD approved vendor viz after approval by MPAKVN 3. MPPKVVCO LTD approved vendor viz after approval by MPAKVN MPPKVVCO LTD approved vendor viz after approval by MPAKVN NOTE;- Before procurement of material bidder shall submit list of vendors whose material he intends to us along with following undermentioned documents for the approval by MPAKVN EIC/Consultant:1. Name of vendor with credentials like past experience in supply of equipments with type test certificates and past successful performance. 2. Pre delivery inspection at factory shall be done by MPAKVN EIC/Consultant. APPLICABLE STANDARDS LIST OF STANDARDS: following standard with up to date amendment are applicable for the material. 178 S No 1 2 3 4 5 6 7 8 9 10 Item Standard A.C. Distribution Board IS: 13947, IS 5, C IS: 13947/1993 Part I & Part-III, IS 2705, IS 8828/1996, IS 1248, IS 375 & IS: 13703/1993 Part-I & II D.C. Distribution Board IS: 13947, IS 5, C IS: 13947/1993 Part I & Part-III, IS 8828/1996, IS 1248, IS 375 & IS: 13703/1993 Part-I & II D.C. Control And IS: 2147/1962, no.631 as specified in Indian Standard 5 of Distribution Board 1961, Disconnector unit of nominal current rating of 100Amps conforming to IS: 13947/1993, MCBs shall comply following specifications as per IS 8828/1996, Service short circuit capacity shall be 6KA as per table 15 of IS: 8828 /1996, Tripping time shall be as per (clause No. 8.6.1) table 6 of IS: 8828 /1996, MCBs shall be capable of carrying out given no. of operation cycles as per clause No. 9.11 of IS: 8828 /1996, Limits of temperature rise shall be as per (clause No. 9.8) table 5 of IS: 8828/1996, Standard range of instantaneous tripping shall be as per (clause No.5.3.5) table 2 of IS: 8828 /1996, & All type & routine tests on the MCCBs in accordance with IS:2516(Pt-I&II Sec.I)/1977 11 kv and 33 kv vacuum IEC 56 or IS 13118 (1991) with latest amendment thereof, circuit breakers except wherein specified otherwise INDOOR CONTROL PANELS FOR 11 KV & 33 KV VCBs 30V 10 AMP BATTERY CHARGER SUITABLE FOR 30V 100AH LEAD ACID BATTERY 30 VOLT 100 AH LEAD ACID BATTERY IS-3842 (Part-I) 1967, IS-3842 (Part-IV) 1967, IS-3231 (1965), IS-1885 (Part-I & II) & All indicating instruments shall conform to IS-722 or BS-89 IS:3895, IS:13947 (Part II), IS:1248, IS:2147, IS:375, IS:4540, IS:6619, IS:2026, IS:4237, IS:4064, IS:6005, IS:5, IS:5921, IS:249 & IS:5578 The cells of Lead Acid Battery shall conform to the requirement of IS:1651: 1991 with latest amendments thereof, battery with hard rubber containers which shall conform to IS: 1146:1981, sulphuric acid and water used for the preparation and maintenance of electrolyte shall conform to IS 266:1977 and IS 1069: 1964 respectively, wooden separators when used shall conform to IS 652:1960 and the synthetic separators to IS 6071:1986, Cell testing Voltmeter, 3-0-3 volts scale, Industrial Grade “A” to IS:1248 & battery shall be tested after manufacture as per the requirement of IS: 1651-1991. 11 KV CAPACITOR Each of the capacitor units as well as banks shall be BANK provided with a rating plate and terminal markings as stipulated in IS: 13925:98 33 KV and 11 KV IEC 99-4/IS-3070 Part-3 – 1993 with latest amendment if GAPLESS LIGHTNING any in all respects ARRESTORS HT XLPE POWER CABLE IS 7098 Part 2 : 1985 XLPE insulated PVC sheathed cables For working voltages from 3.3 kV up to and including 33 kV IS 5831 : 1984 PVC Insulation and Sheath of electric Cables IS 8130:1984 Conductors for insulated electric cables and flexible cords. IS 613:1984 179Copper rods and bars for electrical purposes. IS 3975:1988 Mild steel wires, formed and tapes for armouring of cable. IS 10810:1984 Method of tests for cables. Annexure-F (See clause 3 of section 2 ITB) Procedure for Participation in e- tendering 1. Registration of Bidders on e-tendering System: All the PWD registered bidders are already registered on the new e- procurement portal http://www.mpeproc.gov.in. The user id will be the contractor ID provided to them from MP Online. The password for the new portal was been send to the bidder registered email ID for more details may contact M/s Tata Consultancy Services Corporate Block, 5th floor, DB city Bhopal-462011 email id: eproc_helpdesk@mpsdc.gov.in. Helpdesk phone numbers are available on website. 2. Digital Certificate: The bids submitted online should be signed electronically with a Class III Digital Certificate to establish the identity of the bidder submitting the bid online. The bidders may obtain Class III Digital Certificate issued by an approved certifying authority authorized by controller of certifying authorities, Government of India a Class III Digital Certificate is issued upon the receipt of mandatory identity proofs along with an application. Only upon the receipt of the required documents, a digital certificate can be issued. For details please visit cca.gov.in Note: 180 i. It may take upto 7 working days for issuance of Class Iii Digital Certificate; hence the bidders are advised to obtain the certificate at the earliest. Those bidders who already have valid Class Iii Digital Certificate need not obtain another Digital Certificate for the same. The bidder may obtain more information and the application from required to be submitted for the issuance of Digital Certificate from cca.gov.in ii. Bids can be submitted till bid submission end date. Bidder will require digital signature while bid submission. iii. The digital certificate issued to the authorized user of a partnership firm private limited company / public limited company and used for online biding will be considered as equivalent to a no-objection certificate / power of attorney to that user. iv. In case of Partnership firm, majority of the partners have to authorize a specific individual through authority letter signed by majority of the partners of the firm. In case of Privet Limited Company, Public Limited Company, the Managing Director has to authorize a specific individual through authority letter. Unless the certificate is revoked, it will be assumed to represent adequate authority of the specific individual to bid on behalf of the organization for online bids as per information Technology Act 2000. This authorized user will be required to obtain a digital certificate. The Digital Signature executed through the use of digital certificate of this authorized user will be binding on the firm. It shall be the responsibility of Management / Partners of the concerned firm to inform the certifying authority, if the Authorized user changes, and apply for a fresh Digital certificate for the new authorized user. 3. Set up of Bidder’s Computer System: In order for a bidder to operate on the e-tendering System, the Computer System of the bidder is required to be set up for Operating System, Internet Connectivity, Utilities, Fonts, etc. The details are available at https://www.mpeproc.gov.in 4. Key Dates: The Bidders are strictly advised to follow the time schedule (KeyDates) of the bid on their side for tasks and responsibilities to participate in the bid, as all the stages of each bid are locked before the start time and date and after the end time and date for the relevant stage of the bid as set by the department. 5. Preparation and Submission of Bids: The bidders have to prepare their bids online, encrypt their Bid Data in the Bid forms and submit Bid of all the envelopes and documents related to the Bid required to be uploaded as per the time schedule mentioned in the key dates of the notice inviting e-tendering after signing of the same by the Digital Signature of their authorized representative. 6. Purchase of Bid Document: 181 For purchasing of the bid document bidders have to pay Service Charge online ONLY which is Rs(as per Bid Date Sheet). Cost of bid document is separately mentioned in the detailed NIT. The Bid Document shall be available for purchase to concerned eligible bidder immediately after online release of the bids and upto scheduled time and date as set in the key dates. The payment for the cost of bid document shall be made online through Debit/Credit card, Net Banking or NeFTChallan through the Payment getaway provided on the portal. 7. Withdrawal, Substitution and notification of bids Bidder can withdraw and modify the bid till bid submission end date Annexure-G (See clause 4 of section 2 ITB) Joint Venture (J.V) (NOT ALLOWED) If J.V. is allowed following condition and requirements must be fulfilled1. Bids submitted by a joint venture of two or more firms as partners shall comply with the following requirements: 182 a. One of the partners shall be nominated as being Lead Partner, and this authorization shall be evidenced by submitting a power of attorney signed by legally authorize signatories of all the partners; b. The bid and, in case of a successful bid, the agreement, shall be signed so as to legally binding on all partners; c. The partners in charges shall be authorized to incur liabilities and receive instructions for and on behalf of any and all partners of the joint venture and the entire execution of the contract including payment, shall be done exclusively with the partner in charge; d. All partners of the joint venture shall be liable jointly and severally for the execution of the contract in accordance with the contract terms, and a statement to this effect shall be included in the authorization mentioned under [c] above, as well as in the bid and in the agreement [in case of a successful bid]; e. The joint venture Agreement should indicate precisely the role of all members of JV in respect of planning, design; construction equipment, key personnel, work execution, and financing of the project. All members of JV should have active participation in execution during the currency of the contract. This should not be varied/modified subsequently without prior approval of the employer; f. The joint venture agreement should be registered, so as to be legally valid and binding on all partners; and g. A copy of the joint venture agreement entered into by the partners shall be submitted with the bid. h. The figures for each of the partners of a joint venture shall be added together to determine the bidder’s compliance with the minimum qualifying criteria required for the bid all the partners collectively must meet the criteria specified in full. Failure to comply with the requirement will result in rejection of the joint venture’s bid. 2. The performance security of a joint venture shall be in the name of the partner lead partner/ joint venture. 3. Attach the power of attorney of the partners authorizing the bid signatory (ies) on behalf of the joint venture 4. Attach the Agreement among all partners of the joint venture [and which is legally binding on all partners], which shows the requirements as indicated in the instructions to bidders’. 5. Furnish details of participation proposed in the joint venture as below: DETAILS OF PARTICIPATION IN THE JOINT VENTURE Participation Details Firm ‘A’ (lead Partner) Firm ’B’ 183 Firm ’C’ Financial Name of the Banker(s) Planning Construction Equipment Key Personnel Execution of work (Give details on contribution of each) Annexure- H 184 (See clause 12 of section 2 – ITB & clause 4 of GCC) Organizational Details (To be contained in envelope-A) Sr. No 1 2 3 Particulars Details Registration number issued by centralized registration system of Govt. of M.P. or Proof of application for registration. Valid registration of bidder in appropriate class through centralized registration of govt. of MP Name of Organization /Individual/ Proprietary Firm/Partnership Firm Entity of Organization (if applicable, scanned copy of proof of application for registration to be uploaded Registration No._________Date (scanned copy of registration to be uploaded) Individual/ Proprietary Firm/Partnership Firm 4 5 6 7 8 9 10 11 12 13 14 15 16 (Registered under Partnership Act)/ Limited company (Registered under the companies Act1956)/Corporation/joint Venture Address of Communication Telephone Number with STD code Fax Number with STD code Mobile Number E-mail Address for all communications Details of Authorized Representative Name Designation Postal Address Telephone Number with STD code Fax Number with STD code Mobile Number E-mail Address Note: In case of partnership firm and limited company certified copy of partnership deed/articles of association and Memorandum of association along with registration certificate of the company shall have to been closed. Signature of Bidder with Seal Date:_________________________ 185 Annexure – I (See clause 14 of section 2 – ITB) Envelope- B, Technical Proposal Technical Proposal shall comprise the following documents: Sr. No. Particulars Details to be Submitted 1 Experience – Financial & Physical Annexure – I (Format:I-1) 2 Annual Turnover Annexure – I (Format:I-2) 3 List of technical personnel for the key positions Annexure – I (Format:I-3) 4 List of key equipments/machines for quality control labs Annexure – I (Format:I-4) 5 List of key equipment’s/machines for construction work Annexure – I (Format:I-5) Note: 1. Technical Proposal Should be uploaded duly page numbered and indexed. 2. Technical proposal uploaded otherwise will not be considered. 186 Annexure –I (Format:I-1) (See clause 14 of section 2- ITB) Financial & Physical Experience Details A. Financial Requirement: The bidder should have completed either of the below: a. Three similar works, each costing not less than the amount equal to 20% of the probable amount of contract during the last 3 financial years; or b. Two similar works, each costing not less than the amount equal to 30% of the probable amount of contract during the last 3 financial years; or c. One similar work of aggregate cost not less than the amount equal to 50% of the probable amount of contract in any one year during the last 3 financial years; To be filled in by the contractor: i. Details of successfully completed similar works shall be furnished in the following format. ii. Certificate duly signed by the employer shall also be enclosed for each completed similar work. Agreement number & year Name of work Date of Work Order Date of Completion Amount of contract Employer’s name and Address Existing commitments – (Value of ‘C’ for Bid Capacity Formula) Agreement number & year Name of work Date of Work Order Date of Completion Amount of contract Amount of balance work Employer’s name and Address B. Physical Requirement: Execution of similar items of work in any one financial year during the last 3 financial years should not be less than the minimum physical requirement fixed for the work 187 Sr. No. Particulars Actual Quantity Executed Year-1 Year-2 Year-3 Physical qualification required 1 Power transformer at least 3.15 MVA, 33/11 KV 2 33 KV LINE Note: 1. Certificate duly signed by the employer shall be enclosed for the actual quantity executed in any one year during the last 3 financial years. 2. Similar works: the similarity shall be based on the physical size, complexity, methods technology or other characteristics of main items of work. 188 Annexure – I (Format: I-2) (See clause 14 of section -2 ITB) Annual Turnover Requirement: Average annual construction turnover on the construction works not less than 50% of the probable amount of contract during the last 5 financial years; To be filled in by the contractor: Financial Year Payments received for contracts in progress or completed 1 2 3 4 5 Note: i. Annual turnover of construction should be certified by the chartered Accountant. ii. Audit balance sheet including all related notes, and income statements for the above financial years to be enclosed Bid Capacity Applicants who meet the minimum qualifying criteria in the evaluation as stated above are to be evaluated further for bid capacity as under: Bid Capacity = (1.5 A X B)-C Where A= Maximum value of electrical contracting works executed in any one year during the last five year (10% weightage per year shall be given to bring the value of work executed at present price level) B= Proposed contract period in years. C= Amount of work in hand at present. 189 Annexure – I (Format: I-3) (See clause 14 of section -2 ITB & clause 6 of GCC) List of Technical Personnel for the Key Positions 1 PROJECT ENGINEE R 1 BE 60 ELECTRICA Yr L s 20 YRS 2 SITE ENGINEE R(CIVIL) 1 DIPLOMA CIVIL 15 YRS 3 SITE 1 SUPERVIS OR ITI 4 LINE MEN ITI 6 THREE SIMILA R JOB 40 TWO yrs SIMLA R JOBS 40 TWO yrs SIMLA R JOBS 40 ONE yrs SIMILA R JOB 190 15 YRS 10 YRS Total work Experience experience Similar work Age Qualification Key Position Name of Personnel Sr. No Total work Experience Available with the Bidder Similar work experience Age Qualification Minimum requirement Key Position Sr. No Minimum Requirement Annexure – I (Format: I-4) (See clause 14 of section -2 ITB) List of Key Equipment’s/ Machines for Quality Control Labs Minimum requirement Sr. No. 1 Name of Equipment / Machinery Available with the Bidder Quantity HI-POT EQUIPMENT 33KV MEGGER 5000 VOLTS 1 OIL TEST EQUIPMENT EARTH TESTER 1 1 6 INFRA RED TEMPERATURE MEASUREMENT MULTIMETER 7 VOLTEMETER 1 8 TONG TESTER 1 9 PRIMARY INJECTION TEST UNIT SECONDARY INJECTION TEST UNIT 1 2 3 4 5 10 1 1 1 1 191 Name of Equipment / Machinery Quantity Annexure – I (Format: I-5) (See clause 14 of section -2 ITB) List of Key Equipment’s/ Machines for Construction Work Minimum requirement Sr. No. 1 Name of Equipment / Machinery Available with the Bidder Quantity HYDRA ( ON RENT/OWNERSHIP TRIPHER 1 1 5 CRIMPING TOOL 400 SQMM JCB(ON HIRE/OWNERSHIP) WINCH 6 TOOL KIT 2 7 CONCERETE MIXER (ON HIRE/OWNNERSHIP) SAFETY DEVICES LIKE HELMET, SAFETY BELT 1 2 3 4 8 1 1 1 LOT 192 Name of Equipment / Machinery Quantity Annexure – J (See clause 14 of section – 2 ITB FINANCIAL BID (To be contained in Envelope-C) Name of Work: Supply, installation, testing and commissioning of 33/11 KV External electrification work for new industrial area at Relwa Khurd district Barwani I/we hereby bid the for the execution of the above work within the time specified at the rate (in figure)__________________ (in words)____________________________ percent below / above or at per based on the Bill of Quantities and item wise rates given therein all respects and in accordance with the specifications, designs, drawings and instruction in writing in all respects in accordance with such conditions so far as applicable. I/we have visited the site of work and am/are fully aware of all the difficulties and conditions likely to affect carrying out the work. I/we have fully acquainted myself / ourselves about the conditions in regard to accessibility of site and quarries / kilns, nature and the extent of ground, working conditions including stacking of materials, installation of tools and plant conditions effecting accommodation and movement of labour etc. required for the satisfactory execution of contract .Should this bid be accepted, I/we hereby agree to abide by and fulfill all the terms and provisions of the said conditions of contract annexure hare to 193 so far as applicable, or in default thereof to forfeit and pay to the Governor of Madhya Pradesh or his successors in office the sums of money mentioned in the said conditions. Note: i. ii. iii. iv. Only one rate of percentage above or below or at par based on bill of quantities and item wise rates given therein shall be quoted. Percentage shall be quoted in figures as well as in words. If any difference in figures and words is found lower of the two shall be taken as valid and correct rate. If the bidder is not ready to accept such valid and correct rate and declines to furnish performance security and sign the agreement his earnest money deposit shall be forfeited. In case the percentage “above” or “below” is not given by a bidder, his bid shall be treated as non-responsive. All duties, taxes, and other levies payable by the bidder shall be including in the percentage quoted by the bidder. Signature of Bidder Name of Bidder The above bid is hereby accepted by me behalf of the MPAKVN(I) Ltd., Indore dated the ________ Day of ______________20_____ Signature of Officer by whom accepted Annexure – K (See clause 15 of section 2 – ITB) Material to Be Issued By the Department (NOT APPLICABLE) Sr. No. Name of Material Rate (Issue rate) 194 Unit Remarks Annexure – L (See clause 21 of section -2 ITB) Letter of Acceptance (LOA) No.______________________ Dated:_________________ To, M/s_______________________ (Name and address of the contractor) Subject: Supply, installation, testing and commissioning of 33/11 KV External electrification work for new industrial area at Relwa Khurd district Barwani 195 Dear Sir (s), Your bid for the work mentioned above has been accepted on behalf of the governor of Madhya Pradesh at your bided percentage ______ below/ above or at per the bill of quantities and item wise rates given therein. You are requested to submit within 15 (fifteen) days from the date of issue of this latter: a. The performance security/ performance guarantee of Rs. _____________ (in figures) (Rupees______________________________________) in words only). The performance security shall be in the shape of term deposit receipt / bank guarantee of any nationalized / schedule commercial bank valid up to three months after the expiry of defects liability period. b. Sign the contract agreement. Please note that the time allowed for carrying out the work as entered in the bid is ----- months including / excluding rainy season, shall be reckoned from the date of signing the contract agreement. Signing the contract agreement shall be reckoned as intimation to commencement of work and so separate letter for commencement of work is required. Therefore, after signing of the agreement, you are directed to the Engineer-in-charge for taking the possession of site and necessary instruction to start the work. Yours Faithfully Executive Engineer Annexure – M (see clause 22 of section -2 ITB) Performance Security To, ______________________(Name of Employer ______________________ ______________________(Address of Employer WHEREAS ________________________[name and address of contractor) (Hereinafter called "the Contractor") has undertaken, in pursuance of Letter of Acceptance No.__________ dated ____________ to execute _____________[name of Contract and brief description of Works] (hereinafter called "the Contract”). AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish you with a Bank Guarantee by a recognized bank for the sum 196 specified therein as security for compliance with his obligation in accordance with the Contract; AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee: NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you on behalf of the Contractor, up to a total of ___________ [amount of guarantee]* ___________ ___(in words), such sum being payable in the types and proportions of currencies in which the contract Price is payable, and we undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums within the limits of _________________[amount of guarantee] as aforesaid without your needing to prove or to show grounds or reasons for your demand for the sum specified therein. We hereby waive the necessity of your demanding the said debt from the contractor before presenting us with the demand. We further agree that no change or addition to or other modification of the terms of the Contract of the Works to be performed there under or of any of the Contract documents which may be made between you and the Contractor shall in any way release us from any liability under this guarantee, and we hereby waive notice of any such change, addition or modification. This guarantee shall be valid until 3 (three) months from the date of expiry of the Defect Liability Period. Signature, Name and Seal of the guarantor __________________________________________ Name of Bank ________________________________________________________________ Address_______________________________________________________________________ Phone No., Fax No., E-mail Address, of Signing Authority_______________________ Date____________________________________________________________________________ _______ * An amount shall be inserted by the Guarantor, representing the percentage the contract Price specified in the Contract including additional security for unbalanced Bids, if any and denominated in Indian Rupees. 197 SECTION 3 Conditions of Contract Part- I General Conditions of Contract (GCC) Table of Clauses of GCC Claus e No. Particulars Clause No. Particulars A. General 1 Definitions 21 Payments for Variations and / or Extra Quantities 22 No compensation for alteration in or restriction of work to be carried out Interpretations and Documents 2 3 Language and Law 23 No interest Payable 4 Communications 24 Recovery from contractors 5 Subcontracting 25 Tax 6 Personnel 26 Check Measurements 7 Force Majeure 27 Termination by Engineer in charge 8 Contractor's Risks 28 Payment upon Termination 9 Liability For Accidents To Person 29 Performance security 10 Contractor to Construct the work 30 Security deposit 11 Discoveries 31 Price Adjustment 32 Mobilization and Construction Machinery advance B. Time Control 33 Secured Advance 13 Programme 34 Payments Certificates 14 Extension of Time 15 Compensation for Delay 35 Completion Certificate 16 Contractor’s quoted percentage 36 Final Account 12 Dispute Resolution System E. Finishing the Contract C. Quality Control 17 Tests F. Other Conditions of Contract 37 198 Currencies 18 Correction of Defects noticed during the Defect Liability Period D. Cost Control 19 20 Variations- Change in original Specifications, Designs, Drawings etc. Extra Items 38 39 Labour Compliance with Labour Regulations Audit and Technical Examination 40 41 Death or Permanent Invalidity of Contractor 42 Jurisdiction 199 A. General 1. Definitions 1.1. Bill of Quantities: means the priced and completed Bill of Quantities forming part of the Bid. 1.2. Chief Engineer: means Chief Engineer of the zone/ basin concerned. 1.3. Completion: means completion of the work as certified by the Engineer-in-charge, in accordance with provision of agreement. 1.4. Contract: means the contract between the Employer and the contractor to execute, complete and/or maintain the work. Agreement is synonym of contract and carries the same meaning wherever used. 1.5. Contract Data: means the documents and other information which comprise of the contract. 1.6. Contractor: means a person or legal entire whose bid to carry out the work has been accepted by the Employer 1.7. Contractor’s Bid: means the completed bid document submitted by the contractor 1.8. Contract Amount: means the amount of contract worked out on the basis of accepted bid. 1.9. Completion of Work: means completion of the entire contracted work. Exhaustion of quantity of any particular item mentioned in the bid document shall not imply completion of work or any component thereof. 1.10. Day: means the calendar day. 1.11. Defect: means any part of the work not completed in accordance with the specifications included in the contract. 1.12. Department: means department of the State Government viz. Water Resources Department, Public Works Department, Public Health Engineering Department, Rural Engineering Services and any other organization which adopts this document. 1.13. Drawing: means drawings including calculation and other information provided or approved by the Engineer-in-charge. 1.14. Employer: means the party as defined in the contract data, who employs the contractor to carry out the work. The Employer may delegate any or all functions 200 to a person or body nominated by him for specified functions. The word employer / Government /Department wherever used denote Employer. 1.15. Engineer: means the person named in the contract data. 1.16. Engineer in charge: means the person named in the contract data. 1.17. Equipment: means the contractor’s machinery and vehicles brought temporarily to the site for execution of work. 1.18. Government: means Government of Madhya Pradesh. 1.19. In writing: means communicated in written form and delivered against receipt. 1.20. Material: means all supplies, including consumables, used by the contractor for incorporation in the work. 1.21. Superintending Engineer: means Superintending Engineer-in-Charge of the circle concerned 1.22. Stipulated period of completion: means the period in which the contractor is required to complete the work. The stipulated period is specified in the contract Data. 1.23. Specification: means the specification of the work included in the contract and any modification or addition made or approved by the Engineer-in-charge. 1.24. Start Date: means the date of signing of agreement for the work. 1.25. Sub-contractor: means a person or corporate body who has a contract with the contractor, duly authorized to carry out a part of the construction work under the contract. 1.26. Temporary work: means work designed, constructed, installed, and removed by the contractor that are needed for construction or installation of the work. 1.27. Tender/Bid, Tendered/Bidder: are the synonyms and carry the same meaning where ever used. 1.28. Variation: means any change in the work which is instruction or approved as variation under this contract. 1.29. Work: The expression “work” or “works” where used in these condition shall unless there be something either in the subject or context repugnant to such construction, be construed and taken to mean the work by virtue of contract, contracted to be executed, whether temporary or permanent and whether original, altered, substituted or additional. 2. INTERPRETATIONS AND DOCUMENT 2.1. Interpretations In the contract, except where the context requires otherwise: 201 a.words indicating one gender include all genders; b. words indicating the singular also include the plural and vice versa. c.Provision including the word “agree”, “agreed” or “Agreement” require the agreement to be recorded in writing; d. Written” or “ in writing” means hand-written, type-written, printed or electronically made, and resulting in a permanent record; 2.2. Document Forming Part of Contract 1. NIT with all amendment. 2. Instructions of Bidders (ITB, Bid Data sheet with all annexures) 3. Conditions of Contract: i. Part I General Conditions of contract and the contract Data with all annexures ii. Part II special Conditions of contract. 4. Specifications 5. Drawings 6. Bill of Quantities 7. Technical and Financial Bid 8. Agreement, and 9. Any other document (s), as specified. 3. Language and Law The language of the Contract and the law governing the Contract are stated in the contract data 4. Communications All certificates, notice for instruction to be given to the Contractor by Employer/Engineer shall be sent to the address or contact details given by the contractor in [Annexure H of ITB]. The address and contact details for communication with the Employer/Engineer shall be as per the details given in the contract Data. Communication between parties that are referred to in the conditions shall be in writing. The notice sent by facsimile (fax) or other electronic means (email) shall also be effective on confirmation of the transmission. The notice sent by registered post or speed post shall be effective on delivery or at the expiry of the normal delivery period as undertaken by the postal service. In case of any change in address for communication, the same shall be immediately notified to Engineer-in-charge. 5. Subcontracting Subcontracting shall be permitted for contracts of value more than amount specified in the Contract Data with following conditions. 202 a. The Contractor may subcontract up to 25 percent of the contract price with the approval of the Employer in writing, but will not assign the contact. Subcontracting shall not alter the Contractor's obligations. b. Following shall not form part of Subcontracting i. Hiring of labour through a labour contractor. ii. The purchase of Materials to be incorporated in the works. iii. Hiring of plant & machinery c. The sub-contractor will have to be registered in the appropriate category in the centralized registration system for contractors of the GOMP. 6. Personnel 6.1. The Contractor shall employ for the construction work and routine maintenance the technical personnel as provided in the Annexure I-3 of Bid Data Sheet, if applicable. If the Contractor fails to deploy required number of technical staff, recovery as specified in the Contract Data will be made from the contractor. 6.2. If the Engineer asks the Contractor to remove a person who is a member of the Contractor's staff or work force, stating the reasons, the Contractor shall ensure that the person leaves the Site within three days and has no further connection with the works in the contract. 7. Force Majeure 7.1. The term “Force Majeure” means an exceptional event or circumstance : (a) Which is beyond a party’s control, (b) Which such party could not reasonably have provided against before entering into the contract. (c) Which, having arisen, such party could not reasonably have avoided or overcome, and (d) Which is not substantially attributable to the other party Force majeure may include, but is not limited to, exceptional events or circumstance of the kind listed below, so long as conditions (a) to (d) above are satisfied: i. War, hostilities (whether war be declared or not), invasion, act of foreign enemies, ii. Rebellion, terrorism, sabotage by persons other than the contractor’s personnel, revolution, insurrection, military or usurped power, or civil war, iii. Riot, commotion, disorder, strike or lockout by persons other than the contractor’s personnel, 203 iv. Munitions of war, explosive materials, ionizing radiation or contamination by radio-activity, except as may be attributable to the contractor’s use of such munitions, explosives, radiation or radio-activity, and v. Natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity. 7.2. In the event of either party being rendered unable by force majeure to perform any duty or discharge any responsibility arising out of the contract, the relative obligation of the party affected by such force majeure shall upon notification to the other party be suspended for the period during which force majeure event lasts. The cost and loss sustained by either party shall be borne by respective parties. 7.3. For the period of extension granted to the Contractor due to Force Majeure the price adjustment clause shall apply but the penalty clause shall not apply. It is clarified that this sub clause shall not give eligibility for price adjustment to contracts which are otherwise not subject to the benefit of price adjustment clause. 7.4. The time for performance of the relative obligation suspended by the force majeure shall stand extended by the period for which such cause lasts. Should the delay caused by force majeure exceed twelve months, the parties to the contract shall be at liberty to foreclose the contract after holding mutual discussions. 8. Contractor’s Risks 8.1. All risks of loss or damage to physical property and of personal injury and death which arise during and in consequence of the performance of the Contract are the responsibility of the Contractor. 8.2. All risks and consequences arising from the inaccuracies or falseness of the documents, drawing, designs, other documents and/or information submitted by the contractor shall be the responsibility of the Contractor alone, notwithstanding the fact that the designs/ drawings or other documents have been approved by the department. 9. Liability for Accidents to Person The contractor shall be deemed to have indemnified and saved harmless the government against all action, suits, claims, demands, costs etc. arising in connection with injuries suffered by any persons employed by the contractor or his subcontractor for the works whether under the General law or under workman’s compensation Act, or any other statute in force at the time of dealing with the question of the liability of employees for the injuries suffered by employees and to have taken steps properly to ensure against any claim there under. 10. Contractor to Construct the Works 10.1 The Contractor shall construct, install and maintain the Works in accordance with the Specifications and Drawings as specified in the Contract Data. 204 10.2 In the case of any class of work for which there is no such specification as is mentioned in Contract Data, such work shall be carried out in accordance with the instructions and requirement of the Engineer-in-charge. 10.3 The contractor shall supply and take upon himself the entire responsibility of the sufficiency of the all required electrical equipments for construction, civil work , tools and implements, and generally of all means used for the fulfillment of this contract whether such means may or may not be approved or recommended by the Engineer. 11. Discoveries Anything of historical or other interest or of significant value unexpectedly discovered on the Site shall be the property of the Employer. The Contractor shall notify the Engineer of such discoveries and carry out the Engineer's instructions for dealing with them. 12. Dispute Resolution System 12.1. No dispute can be raised expect before the competent authority as defined in contract data in writing giving the full description and ground of dispute. It is clarify that merely recording protest while accepting measurement and/or payment shall not be taken as raising a dispute. 12.2. No dispute can be raised after 45 days of its first occurrence. Any dispute raised after expiry of 45 days of its first occurrence shall not be entertained and theemployer shall not be liable for claims arising out of such dispute. 12.3. The Competent Authority shall decide the matter within 45 days. 12.4. Appeal against the order of the Appellate Authority can be preferred within 30 days to the Appellate Authority as defined in the Contract Data. The Appellate Authority shall decide the dispute within 45 days. 12.5. Appeal against the order of the Appellate Authority can be preferred before Madhya Pradesh Arbitration Tribunal constituted under Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983. 12.6. The Contractor shall have to continue execution of the works with due diligence notwithstanding pendency of a dispute before any authority or forum. B. Time Control 13. Programme 13.1. Within the time stated in the Contract Data, the Contractor shall submit to the Engineer for approval a Programme showing the general methods, arrangements, order and timing for all the activities for the construction of works. 13.2. The program shall be supported with all the details regarding key personnel, equipment and machinery proposed to be deployed on the works for its 205 execution. The contractor shall submit the list of equipment and machinery being brought to site, the list of key personnel being deployed, the list of machinery/equipment being placed in field laboratory and the location of field laboratory along with the Programme. 13.3. An update of the Programme shall be a programme showing the actual progress achieved on each activity and the effect of the progress achieved on the timing of the remaining Works, including any changes to the sequence of the activities. 13.4. The Contractor shall submit to the Engineer for approval an updated programme at intervals no longer than the period stated in the Contract Data. If the Contractor does not submit an updated Programme within this period, the Engineer may withhold the amount stated in the Contract Data from the next payment certificate and continue to withhold this amount until the next payment after the date on which the overdue Programme has been submitted. 13.5. The Engineer's approval of the Programme shall not alter the Contractor’s obligations. 14. Extension of Time 14.1. If the Contractor desires an extension of time for completion of the work on the ground of his having been unavoidably hindered in its execution or on any other grounds, he shall apply, in writing, to the Engineer-in-charge, on account of which he desires such extension. Engineer-in-Charge shall forward the aforesaid application to the Competent Authority as prescribed. 14.2. The competent authority shall grant such extension at each such occasion within a period of 30 days of receipt of application from contractor and shall not wait for finality of work. Such extensions shall be granted in accordance with provisions under clause- 15 of this agreement. 14.3. In case the work is already in progress, the Contractor shall proceed with the execution of the works, including maintenance thereof, pending receipt of the decision of the competent authority as aforesaid with all due diligence. 15. Compensation for delay 15.1. The time allowed for carrying out the work, as entered in the agreement, shall be strictly observed by the Contractor. 15.2. The time allowed for execution of the contract shall commence from the date of signing of the agreement. It is clarified that the need for issue of work order is dispensed with. 15.3. In the event milestones are laid down in the Contract Data for execution of the works, the contractor shall have to ensure strict adherence to the same. 206 15.4. Failure of the Contractor to adhere to the timelines and/or milestones shall attract such liquidated damages as is laid down in the Contract Data. 15.5. In the event of delay in execution of the Works as per the timelines mentioned in the Contract Data the Engineer-in-charge shall retain from the bills of the Contractor amount equal to the liquidated damages leviable until the Contractor makes such delays good. However, the Engineer-in-charge shall accept bankable security in lieu of retaining such amount. 15.6. If the Contractor is given extension of time after liquidated damages have been paid, the Engineer in Charge shall correct any over payment of liquidated damages by the Contractor in the next payment certificate. 15.7. In the event the Contractor fails to make good the delay until completion of the stipulated contract period (including extension of time) the sum so retained shall be adjusted against the liquidated damages levied. 16. Contractor’s quoted percentage The Contractor’s quoted percentage rate referred to in the "Bid for works" will be deducted/ added from/to the net amount of the bill after deducting the cost of material supplied by the department. C. Quality Control 17. Tests 17.1. The Contractor shall be responsible for: a. Carrying out the tests prescribed in specifications, and b. For the correctness of the test results, whether preformed in his laboratory or elsewhere. 17.2. The contractor shall have to establish field laboratory within the time specified and having such equipment’s as are specified in the Contract Data. 17.3. Failure of the Contractor to establish laboratory shall attract such penalty as specified in the Contract Data. 18. Correction of Defects noticed during the defect Liability Period 18.1. The Defect Liability Period of work in the contract shall be as per the contract Data. 18.2. The Contractor shall promptly rectify all defects pointed out by the Engineer well before the end of the Defect Liability Period. The Defect Liability Period shall automatically stand extended until the defect is rectified. 18.3. If the contractor has not corrected a defect pertaining to the defect liability period to the satisfaction of the engineer, within the time specified by the Engineer, the Engineer will assess the cost of having the defect corrected, and the cost of correction of the defect shall be recovered from the 207 performance security or any amount due or that may become due to the contractor and other available securities. D. Cost Control 19. Variations - Change in original Specifications, Designs, and Drawings 19.1. The Engineer-in-charge shall have power to make any alterations, omissions or additions to or substitutions in the original specifications, drawings, designs & instructions, that may appear to him to be necessary during the progress of thework and the contractor shall carry out the work in accordance with any instructions which may be given to him in writing signed by the Engineer-in-charge, and such alterations, omission, additions or substitutions shall not invalidate the contract and any altered, additional or substituted work, which the contractor may be directed to do in the manner above specified, as part of the work, shall be carried out by the contractor on the same conditions in all respects on which he agrees to do the main work. 19.2. The time for the completion of the work shall be adjusted in the proportion that the altered, additional or substituted work bears to the original contract work and the certificate of the Engineer-in-charge shall be conclusive as to such proportion. 20. Extra Items 20.1. All such items which are not included in the priced BOQ shall be treated as extra items. 21. Payments for Variations and / or Extra Quantities 21.1. The rates for such additional (Extra quantity), altered or substituted work/extra items under this clause shall be worked out in accordance with the following provisions in their respective order:- 21.2. The contractor is bound to carry out the additional (Extra quantity), work at the same rates as are specified in the contract for the work. a. If the item is not in the priced BOQ and is included in the SOR of the department, the rate shall be arrived at by applying the quoted tender percentage on the SOR rate. b. If the rates for the altered or substituted work are not provided in applicable SOR - such rates will be derived from the rates for a similar class (type) of work as is provided in the contract (priced BOQ) for the work. c. If the rates for the altered, substituted work cannot be determined in the manner specified in the sub clause (c) above - then the rates for such composite work item shall be worked out on the basis of the concerned schedule of Rates minus/plus the percentage quoted by the contractor. 208 d. If the rates for a particular part or parts of the item is not in the Schedule of Rates and the rates for the altered, or substituted work item cannot be determined in the manner specified in sub clause (b) to (d) above, the rate for such part or parts will be determined by the competent authority as defined in the contract data on the basis of the rate analysis derived out of prevailing market rates when the work was done. e. But under no circumstances, the contractor shall suspend the work on the plea of non-acceptability of rates on items falling under sub clause (a) to € in case the contractor does not accept the rate approved by the Engineer in charge for a particular item, the contractor shall continue to carry out the item at the rates determined by the competent authority. The decision on the final rates payable shall be arrived at through the dispute settlement procedure. 22. No compensation for alterations in or restriction of work to be carried 22.1. If at any time after the commencement of the work, the Engineer-in-charge, for any reason whatsoever, not require the whole or any part of the work as specified in the bid to be carried out; the Engineer-in-charge shall give notice in writing of the fact to the Contractor and withdraw that whole or any part of the work. 22.2. The Contractor shall have no claim to any payments or compensation whatsoever, on account of any profit or advantage which he might have derived from the execution of work in full or on account of any loss incurred for idle men and machinery due to any alteration or restriction of work for whatsoever reason. 22.3. The Engineer-in-charge may supplement the work by engaging another agency to execute such portion of the work, without prejudice to his rights. 23. No Interest Payable No interest shall be payable to the Contractor on any payment due or awarded by any authority. 24. Recovery from Contractors Whenever any claim against the Contractor for the payment arises under the contract, the department may be entitled to recover such sum by: (a) Appropriating, in part or whole of the Performance Security and Additional Performance Security, if any; and/or security deposit and / or any sums payable under the contract to the contract to the contractor. (b) If the amount recovered in accordance with (a) above is not sufficient, the balance sum may be recovered from any payment due to the contractor under any other contract of the department, including the securities which become due for release. 209 (c) The department shall, further have an additional right to effect recoveries as arrears of land revenue under the M.P. land revenue code. 25. Tax 25.1. The rates quoted by the Contractor shall be deemed to be inclusive of the commercial tax and other levies, duties, cess, toll, taxes of Central and state Governments, local bodies and authorities. 25.2. The liability, if any, on account of quarry fees, royalties, octroi and any other taxes and duties in respect of materials actually consumed on public work, shall be borne by the Contractor. 25.3. Any changes in the taxes due to change in legislation or for any other reason shall not be payable to the contractor. 26. Check Measurements 26.1. The department reserves to itself the right to prescribe a scale of check measurement of work in general or specific scale for specific works or by other special orders. 26.2. Checking of measurement by superior officer shall supersede measurements by subordinate officer(s), and the former will become the basis of the payment. 26.3. Any over/excess payments detected, as a result of such check measurement or otherwise at any stage up to the date of completion of the defect liability period specified in this contract, shall be recoverable from the Contractor, as per clause 24 above. 27. Termination by Engineer in Charge 27.1. If the contractor fails to carry out any obligation under the contract, the Engineer in charge may by notice require the contractor to make good the failure and to remedy it within a specified reasonable time. 27.2. The Engineer in Charge shall be entitled to terminate the Contract if the contractor a. Abandons the Works or otherwise plainly demonstrates the intention not to continue performance of his obligations under the contract; b. The Contractor is declared as bankrupt or goes into liquidation other than for approved reconstruction or amalgamation; c. Without reasonable excuse fails to comply with the notice to correct a particular defect within a reasonable period of time; d. The Contractor does not maintain a valid instrument of financial security as prescribed; 210 e. The Contractor has delayed the completion of the Works by such duration for which the maximum amount of liquidated damages is recoverable; f. If the Contractor fails to deploy machinery and equipment or personnel or set up a field laboratory as specified in the Contract Data; g. If the contractor, in the judgment of the Engineer in charge has engaged in corrupt or fraudulent practices in competing for or in executing the contract; h. Any other fundamental breaches as specified in the Contract Data; 27.3. In any these events or circumstances, the Engineer in charge may, upon giving 14 days’ notice to the contractor, terminate the contract and expel the contractor from the site. However, in the case of sub-paragraph (b) or (g) of clause 27.2 the engineer in charge may terminate the contract immediately. 27.4. Notwithstanding the above, the Engineer-in-Charge may terminate the contract for convenience by giving notice to the Contractor. 28. Payment upon Termination 28.1. If the contract is terminated under clause 27.3, the Engineer shall issue a certificate for value of the work accepted on final measurements, less advance Payments and Penalty as indicated in the Contract Data. The amount so arrived at shall be determined by the Engineer-in-Charge and shall be final and binding on both the parties. 28.2. Payment on termination under clause 27. 4 above- If the Contract is terminated under clause 27.4 above, the Engineer shall issue a certificate for the value of the work done, the reasonable cost of removal of Equipment, repatriation of the Contractor's personnel employed solely on the Works, and the Contractor's costs of protecting and securing the Works and less advance payments received up to the date of the certificate, less other recoveries due in terms of the contract and less taxes due to be deducted at source as per applicable law. 28.3. If the total amount due to the Employer exceeds any payment due to the Contractor, the difference shall be recovered as per clause 24 above. 29. Performance Security The Contractor shall have to submit performance security and additional performance security, if any, as specified in the Bid Data Sheet at the time of signing of the contract. The contractor shall have to ensure that such performance security and additional performance security, if any, remains valid for the period as specified in the Contract Data. 30. Security Deposit211 30.1. Security Deposit shall be deducted from each running bill at the rate as specified in the Contract Data. The total amount of Security Deposit so deducted shall not exceed the percentage of Contract Price specified in the Contract Data. 30.2. The security deposit may be replaced by equivalent amount of bank guarantee or fixed deposit receipt assigned to the Employer, with validity up to 3 (three)months beyond the completion of Defect Liability Period/ extended Defect Liability Period. 30.3. The Security Deposit shall be refunded on completion of Defect Liability Period. 31. Price Adjustment 31.1. Applicability 1. Price adjustment shall be applicable only if provided for in the Contract Data. 2. The price adjustment clause shall apply only for the works executed from the date of signing of the agreement until the end of the initial intended completion date or extensions granted for reasons attributed to Employer by the Engineer. 3. The Contractor shall not be entitled to any benefit arising from the price adjustment clause for extension in the contract period for reasons attributed to the contractor. 4. In the Force Majeure event the price escalation clause shall apply. 31.2. Procedure 1. Contract price shall be adjusted for increase or decrease in rates and price of labour, materials, fuels and lubricants in accordance with following principals and procedures and as per formula given in the contract data. 2. The price adjustable shall be determined during each quarter from the formula given in the contract data. 3. Following expression and meaning are assigned to the work done during each Quarter: R= Total value of work during the quarter. It would include the amount of secured advance granted, if any, during the quarter, less the amount of secured advance recovered, if any during the quarter, less value of material issued by the department, if any, during the quarter. 4. Weightages of various components of the work shall be as per the Contract Data. 31.3. To the extent that full compensation for any rise or fall in costs to the contractor is not covered by the provisions of this or other clauses in the contract, the unit rates and prices included in the contract shall be deemed to include amounts to cover the contingency of such other rise or fall in costs. 212 31.4. The index relevant to any quarter, for which such compensation is paid, shall be the arithmetical average of the indices relevant of the calendar month. 31.5. For the purpose of clarity it is pointed out that the price adjustment may be either positive or negative, i.e. if the price adjustment is in favour of the Employer, the same shall be recovered from the sums payable to the Contractor. 32. Mobilization and Construction Machinery 32.1. Payment of advance shall be applicable if provided in the Contract Data. 32.2. If applicable, the Engineer in charge shall make interest bearing advance payment to the contractor of the amounts stated in the Contract Data, against provision by the contractor of an unconditional Bank Guarantee in a form and by a nationalized/ scheduled banks, in the name as stated in the Contract Data, in amounts equal to the advance payment. The guarantee shall remain effective until the advance payment has been repaid, but the amount of the guarantee shall be progressively reduced by the amounts repaid by the contractor. 32.3. The rate of interest chargeable shall be as per Contract Data. 32.4. The construction machinery advance, if applicable, shall be limited to 80% of the cost of construction machinery and admissible only for new construction machinery. 32.5. The advance payment shall be recovered as stated in the Contract Data by deducting proportionate amounts from payment otherwise due to the Contractor. No account shall be taken of the advance payment or its recovery in assessing valuations of work done, variations, price adjustments, compensation events, or liquidated damages. 33. Secured Advance 33.1. Payment of secured advance shall be applicable if provided in the Contract Data. 33.2. If applicable, the Engineer shall make advance payment against materials intended for but not yet incorporated in the Works and against provision by the contractor of an unconditional Bank Guarantee in a form and by a nationalized/ scheduled bank, in the name as stated in the Contract Data, in amounts equal to the advance payment. The guarantee shall remain effective until the advance payment has been adjusted, but the amount of the guarantee shall be progressively reduced by the amounts adjusted by the contractor. 33.3. The amount of secured advance and conditions to be fulfilled shall be as stipulated in the Contract Data. 213 33.4. The Secured Advance paid shall be recovered as stated in the Contract Data. 34. Payment Certificates The payment to the contractor will be as follows for construction Work: a) The Contractor shall submit to the Engineer/PMC monthly statements of the value of the work executed less the cumulative amount certified previously, supported with detailed measurement of the items of work executed. b) The Engineer/PMC shall check the Contractor’s monthly statement and certify the amount to be paid to the contractor. c) The value of work executed shall be determined, based on the Measurement approved by the Engineer/ Engineer-in-charge/PMC. d) The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed. e) The value of work executed shall also include the valuation of Variations and Compensation Events. f) All payments shall be adjusted for deductions for advance payment, security deposit, other recoveries in terms of contract and taxes at source as applicable under the law. g) The Engineer/PMC may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information. h) Payment of intermediate certificate shall be regarded as payments by way of advance against the final payment and not as payments for work actually done and completed. i) Intermediate payment shall not preclude the requiring of bad, unsound and imperfect or unskilled work to be removed and taken away and reconstructed or be considered as an admission of the due performance of the contractor any part thereof, in any respect or the occurring of any claim. j) The payment of final bill shall be governed by the provisions of clause 36 of GCC. E. Finishing the Contract 35. Completion Certificate 35.1. Completion Certificate in the prescribed format in Contract Data shall be issued by the Engineer-in-Charge after physical completion of the Work. 35.2. After final payment to the Contractor, a Final Completion Certificate in theprescribed format in the Contract Data shall be issued by the Engineer-incharge. 214 36. Final Account 36.1. The Contractor shall supply the Engineer with a detailed account of the total amount that the Contractor considers payable for works under the contract within 21 days of issue of certificate of physical completion of works. The Engineer shall issue a Defects Liability Certificate and certify any payment that is due to the Contractor within 45 days of receiving the Contractor’s account if it is correct and complete. If the account is not correct or complete, the Engineer shall issue within 45 days a schedule that states the scope of the corrections or additions that are necessary. If the Account is still unsatisfactory after it has been resubmitted, the matter shall be referred to the Competent Authority as defined in the Contract Data, who shall decide on the amount payable to the contractor after hearing the Contractor and the Engineer in Charge. 36.2. In case the account is not received within 21 days of issue of Certificate of Completion as provided in clause 32.1 above, the Engineer shall proceed to finalize the account and issue a payment certificate within 28 days. F. Other Condition of Contract 37. Currencies All payments will be made in Indian Rupees. 38. Labour 38.1. The Contractor shall, unless otherwise provided in the Contract, make his own arrangements for the engagement of all staff and labour, local or other, and for their payment, housing, feeding and transport. 38.2. The Contractor shall, if required by the Engineer, deliver to the Engineer a retune in detail, in such form and at such intervals as the Engineer may prescribe showing the staff and the numbers of the several classes of labour from time to time employed by the Contractor on the Site and such other information as the Engineer may require. 39. Compliance with Labour Regulations 39.1. During continuance of the contract, the contractor and his sub-contractors shall abide at all times by all existing labour enactments and rules made there under, regulations, notifications and bye laws of the State or Central Government or local authority and any other labour law (including rules), regulations, bye laws that may be passed or notification that may be issued under any labour law in future either by the State or the Central Government or the local authority. Salient features of some of the major labour laws that are applicable to construction industry are given in the Contract Data. The Contractor shall keep the employer indemnified in case any action is taken against the employer by the competent authority on account of contravention 215 of any of the provision of any Act or rules made their under regulations or notifications including amendments. If the Employer is caused to pay or reimburse, such amounts as may be necessary to cause or observe, or for non observance of the provisions stipulated in the notifications/byelaws/Acts/Rules/ regulations including amendments, if any, on the part of the Contractor, the Engineer/Employer shall have the right to deduct from any money due to the Contractor including his amount of performance security. The Employer/Engineer shall also have right to recover from the Contractor any sum required or estimated to be required for making good the loss or damage suffered by the Employer. The employees of the Contractor and the Sub-Contractor in no case shall be treated as the employees of the Employer at any point of time. 40. Audit and Technical Examination Government shall have the right to cause an audit and technical examination of the works and the final bill of the contract including all supporting vouchers, abstract etc. to be made after payment of the final bill and if as a result of such audit and technical examination any sum is found to have been overpaid in respect of any work done by the contractor under the contract or any work claimed by him to have been done under the contract and found not to, have been executed, the Contractor shall be liable to refund the amount of overpayment and it shall be lawful for Government to recover the same from him in the manner prescribed in clause 24 above and if it is found that the Contractor was paid less than what was due to him, under the contract in respect of any work executed by him under it, the amount of such under payment shall be duly paid by Government to the Contractor. 41. Death or Permanent Invalidity of Contractor If the Contractor is an individual or a proprietary concern, partnership concern, dies during the currency of the contract or becomes permanently incapacitated, where the surviving partners are only minors, the contract shall be closed without levying any damages/ compensation as provided for in clause 28.2 of the contract agreement. However, if the competent authority is satisfied about the competence of the survivors, then the competent authority shall enter into a fresh agreement for the remaining work strictly on the same terms and conditions under which the contract was awarded. 42. Jurisdiction This contract has been entered into the State of Madhya Pradesh and its validity, construction, interpretation and legal effect shall be subjected to the courts at the place where this agreement is entered into. No other jurisdiction shall be applicable. ******(End of GCC)****** 216 Contract Data GCC Clause Particulars Data 1.14 Employer M.P. Audyogik Kendra Vikas Nigam (Indore) Ltd. 1.15 Engineer Assistant/Junior Engineer 1.16 Engineer in Charge Executive Engineer 1.22 Stipulated Period of completion 11 months (including rainy season) 3 Language & Law of Contract English & Indian Contract Act 1872 amended 4 Address & contact details of the Contractor As per 'Annexure-H' Address & contact details of the Employer/ Engineer – phone, Fax, e-mail Executive Engineer 5 Subcontracting permitted for the Contract Value Not permitted 6 Technical Personnel to be provided by the contractor – requirement, & As per 'Annexure-I' (Format I-3) Penalty, if required Technical Personnel not employed Rs.50000/-per month Specifications As per 'Annexure - E' Drawing As per 'Annexure - N' Competent Authority for deciding dispute under Dispute Resolution System Managing Director Appellate Authority for deciding dispute under Dispute Resolution System Chairman, MPAKVN(I) Ltd., Indore Period for submission of updated construction 15 days 10 12 13 217 Free Press House , 3/54 Press Complex, AB Road, Indore Phone:- 0731-2556111 email:indoreakvn@gmail.com GCC Clause Particulars Data program Amount to be withheld for not submitting construction program in the prescribed period Rs.1,00,000/- 14 Competent Authority for granting Time Extension Managing Director 15 Milestones laid down for the contract Yes If yes, details of Milestones As per 'Annexure - O' Liquidated Damage As per 'Annexure - P' List of equipment for lab As per 'Annexure - Q' 17 Not Applicable Time to establish lab Not Applicable Penalty for not establishing field Laboratory Not Applicable 18 Defect Liability Period 36 Months after physical completion of work Note:- in accordance with clause 18.3 GGCC), the Engineer in Charge shall intimate the contractor about the cost assessed, for making good the defects, and if the contractor has not corrected defects, action for correction, of defects shall be taken by the Engineer in Charge as below: (a) deploy departmental labour and material Or (b) engage a contractor by issuing a work order at contract rate/SOR rate Or (c) sanction supplementary work in a existing agreement to a contractor for zpnal works or similar other work. Or (d) invite open tender Or (e) combination of above 21 Competent Authority for determining the rate Managing Director or 218 GCC Clause Particulars Data officer appointed by him 27 Any other condition for breach of contract None 28 Penalty Penalty Shall include : a. Security deposit as per clause 30 of General Conditions of Contract and b. Liquidated Damages imposed as per clause 15 or Performance Security (Guarantee) including Additional Performance Security (Guarantee), if any, as per clause 29 of General Conditions of Contract, whichever is higher Till issue of physical completion certificate as per clause 35.1 29 Performance guarantee (Security)shall be valid up to 30 Security Deposit to be deducted from each running bill At the rate of 5% Maximum limit of deduction of Security Deposit Up to 5% of final contract Amount. Price adjustment formula and procedure to calculate NOT APPLICABLE Price adjustment shall be applicable Price adjustment shall be applicable only in case where the amount in NIT is more than Rs. 10 (Ten) crore. This clause shall not have any bearing with the contract amount. Clause 32.1 Mobilization and Construction Machinery Advance Applicable No Mobilization and Construction Machinery Advance Payable 31 31.1.(1) 32 219 Annexure R GCC Clause 33 Particulars Data Clause 32.2 If yes, Unconditional Bank Guarantee In the format prescribed in Annexure – S Clause 32.3 If yes, Rate of interest chargeable on advances NA Clause 32.4 If yes, Type & Amount of Advance payment that can be paid NA Clause 32.5 If yes, Recovery of advance NA Clause 33.1 Secured Advance Applicable Can be paid after partial installation but before testing and commissioning Clause 33.2 if yes, Unconditional Bank Guarantee In the format prescribed in Annexure – T Clause 33.2 if yes, Amount of Secured Advance 50% value of Material as determined by the Engineer in Charge against supply and partial erection Clause 33.3 if yes, Conditions for Secured Advance a) The material are inaccordance with the specification for works: b) Such materials have been delivered to site, and are properly stored and protected against damage or deterioration to the satisfaction of the Engineer. The contractor shall store the bilk material in measurable stacks: c) The Contractor’s records of the requirement, orders, receipt and use of materials are kept in a form approved by the Engineer and such records shall be available for inspection by the Engineer; 220 GCC Clause Particulars Data Clause 33.4 if yes, Recovery for Secured Advance d) The contractor has submitted with his monthly statement the estimated value of the materials on site together with such documents as may be required by the engineer for the purpose of valuation of the materials and providing evidence of ownership and payment thereof; e) Ownership of such materials shall be deemed to vest in the employer for which the contractor has submitted an indemnity Bond in an acceptable format; and f) The quantity of materials are not exceeding monthly payments to the extent The advance shall be repaid from each succeeding monthly payments to the extent materials (for which advance was previously paid) have been incorporated into the works. 34 Payment Certificates Monthly payments shall be made after completion of erection but before testing and commissioning upto 80 % of the work done 35 Completion Certificate – after physical completion of the Work As per 'Annexure - U' Final Completion Certificate – after final payment on completion of the work As per 'Annexure - V' 221 GCC Clause Particulars Data 36 Competent Authority Managing director, MPAKVN(I) Ltd. Indore 39 Salient features of some of the major labour laws that are applicable As per Annexure – W 41 Competent Authority Managing director, MPAKVN(I) Ltd. Indore 222 Annexure-N (See clause 10 of section 3 – GCC) DRAWINGS The scope of work is as per BOQ and the drawings mentioned below but not restricted to the same and shall include all incidental work:- S.No. Description of Drawing 1 SLD for (1x5)MVA sub Station grid Page No. 221 2 Layout of 33-11 KV Sub Station Grid 222 3 Layout of HT & LT distribution system 223 4 Chain Link Mesh Fencing for 33/11 KV Sub Station 224 5 Standard Drawing for Compound Gate 225 6 Standard Drawing for Yard Metalling 226 7 33/11 KV Control Room (6mtr x 5mtr) 227 8 Detail of WBM Road at 33/11 KV Sub Station 228 9 Typical Cross Section for 18 mtr road 229 10 Typical Cross Section for 24 mtr road 230 11 Layout for Signboard 231 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 Annexure-O (See clause 15 of section 3 – GCC) Details of Milestones (1). Milestones to be achieved during the contract period (1) 1/8th of the value of entire contract work up to 1/4 th of the period allowed for completion of construction (2) 3/8th of the value of entire contract work up to 1/2 of the period allowed for completion of construction (3) 1/2nd of the value of entire contract work up to 1/4 th of the period allowed for completion of construction 239 Annexure-P (See clause 15 of section 3 – GCC) Compensation for Delay If the contractor fails to achieve the milestones, and the delay in execution of work is attributable to the contractor, the Employer shall retain an amount from the sums payable and due to the contractor as per following scale – i. Slippage up to 25% in financial target during the milestone under consideration — 2.5% of the work remained unexecuted in the related time span. ii. Slippage exceeding 25% but up to 50% in financial target during the milestone under consideration — 5% of the work remained unexecuted in the related time span. iii. Slippage exceeding 50% but up to 75% in financial target during the milestone under consideration— 7.5% of the work remained unexecuted in the related time span. iv. Slippage exceeding 75% in financial target during the milestone under consideration— 10% of the work remained unexecuted in the related time span. Note: For arriving at the dates of completion of time span related to different milestones, delays which are not attributable to the Contractor shall be considered. The slippage on any milestone is if made good in subsequent milestones or at the time of stipulated period of completion, the amount retained as above shall be refunded. In case the work is not completed within the stipulated period of completion along with all such extensions which are granted to the Contractor for either employer default 240 or Force Majeure, the compensation shall be levied on the contractor at the rate of 0.05% per day of delay limited to a maximum of 10% of contract price. The decision of MANAGING DIRECTOR, MPAKVN(I) Ltd., Indore shall be final and binding upon both the parties. Annexure-Q (See clause 17 of section 3 – GCC) List of Equipment for Quality Control Lab SAME AS MENTIONED IN TESTING EQUIPMENT LIST 241 Annexure-R (See clause 31 of section 3 – GCC) Price Adjustment (NOT APPLICABLE) The formulas for adjustment of price are as follow: R= Value of work as defined in Clause 31.2(3) of General Conditions of Contract Weightages* of component in the work Sr. No Component 1 Cement – Pc 2 Steel – Ps 3 Bitumen- Pb 4 POL - Pf Percentage of component in the work * Weightages of various components of the work shall be as determined by competent technical sanction authority. Adjustment for cement component (ii) Price adjustment for increase or decrease in the cost of Cement procured by the contractor shall be paid in accordance with the following formula: Vc = 0.85x Pc/100 x R x (C1-C0)/C0 Vc= Increase or decrease in the cost of work during the month under consideration due to changes in rates for cement. Co= The all India wholesale price index for Grey cement on the date of opening of Bids as published by the Ministry of Industrial Development, Government of India, New Delhi. (www.eaindustry.nic.in) 242 C1= The all India average wholesale price index for Grey cement for the month under consideration as published by the Ministry of Industrial Development, Government of India, New Delhi. (www.eaindustry.nic.in) Pc= Percentage of cement component of the work Note: For the application of this clause, index of Grey Cement has been chosen to represent Cement group. Adjustment for Steel component (iii) Price adjustment for increase or decrease in the cost of Steel procured by the contractor shall be paid in accordance with the following formula: Vs = 0.85x Ps/100 x R x (S1-S0)/S0 Vs= Increase or decrease in the cost of work during the month under consideration due to changes in rates for steel. So= The all India wholesale price index for Grey steel (Bars and Roads) on the date of opening of Bids as published by the Ministry of Industrial Development, Government of India, New Delhi. (www.eaindustry.nic.in) Si = The all India average wholesale price index for Grey steel (Bars and Roads) for the month under consideration as published by the Ministry of Industrial Development, Government of India, New Delhi. (www.eaindustry.nic.in) Pc= Percentage of steel component of the work Note: For the application of this clause, index of Bars and Roads has been chosen to represent steel group. Adjustment for bitumen component (iv)Price adjustment for increase or decrease in the cost of bitumen shall be paid in accordance with the following formula: Vb = 0.85x Pb/100 x R x (B1-B0)/B0 Vb= Increase or decrease in the cost of work during the month under consideration due to changes in rates for bitumen. Bo= The Official retail price of bitumen at the IOC depot at nearest centre on the data of opening of Bids. Bi = The Official retail price of bitumen at the IOC depot at nearest centre for the 15th day of the month under consideration. Pb= Percentage of bitumen component of the work Adjustment for POL (fuel and lubricant) component (v)Price adjustment for increase or decrease in the cost of POL (fuel and lubricant)shall be paid in accordance with the following formula: Vf = 0.85x Pf/100 x R x (Fi-F0)/F0 Vf= Increase or decrease in the cost of work during the month under consideration due to changes in rates for fuel and lubricants. 243 Fo= The Official retail price of High Speed Diesel at the existing consumer pumps of IOC at nearest centre on the data of opening of Bids. Fi = the Official retail price of HSD at the existing consumer pumps of IOC at nearest centre for the 15th day of the month under consideration. Pb= Percentage of fuel and lubricant component of the work. Note: For the application of this clause, the price of High Speed Diesel has been chosen to represent fuel and lubricant group. Annexure-S (See clause 32 of section 3 – GCC) Bank Guarantee Form for Mobilization and Construction Machinery (NOT APPLICABLE) To ______________________(Name of Employer) _______________________(Address of Employer) _______________________(Name of Contractor) In accordance with the provisions of the General Conditions of Contract, clause 31 ("Mobilization and Construction Machinery Advance") of the above-mentioned contract __________________[name and address of Contractor] (hereinafter called “the Contractor") shall deposit with ______________ [name of Employer] a bank guarantee to guarantee his proper and faithful performance under the said Clause of the Contract in an amount of _______________[amount of Guarantee]*_________________(in words). We, the _______________[bank of financial institution], as instructed by the Contractor, agree unconditionally and irrevocably to guarantee as primary obligator and not as surety merely, the payment to _________________[name of Employer] on his first demand without whatsoever right of obligation on our part and without his first claim to the Contractor, in the amount not exceeding ____________[amount of guarantee]* ___________________________[in words]. We further agree that no change or addition to or other modification of the terms of the Contractor or Works to be performed there under or of any of the Contract documents which may be made between __________________[name of Employer] and the contractor, shall in any way release us from any liability under this guarantee, and we hereby waive notice of any such change, addition or modification. This guarantee shall remain valid and in full effect from the date of the advance payment under the Contract until _________________ [name of Employer] receives full repayment of the same amount from the Contractor. Yours truly, Signature and seal :_______________________________________ Name of Bank/Financial Institution:______________________ 244 Address:____________________________________ Data:_____________________________________ * An amount shall be inserted by the bank or financial institution representing the amount of the advance payment, and denominated Indian Rupees. Annexure-T (See clause 33 of section 3 – GCC) Indenture for Secured Advance (NOT APPLICABLE) This indenture made the ____________________________day of 20___ Between____________(hereinafter called the contractor which expression shall where the context so admits or implies be deemed to include his executors, administrators and assigns) or the one part and the Employer of the other part. Whereas by an agreement dated__________________(hereinafter called the said agreement) the contractor has agreed. AND WHEREAS the contractor has applied to the employer that he may be allowed advance on the security of materials absolutely belonging to him and brought by him to the site of the works the subject of the said agreement for use in the construction of such of the works as he has undertaken to executive at rates fixed for the finished work (inclusive of the cost of materials and labour and other charges) AND WHEREAS the employer has agreed to advance to the contractor the sum of rupees _____________ On the security of materials the quantities and other particular of which are details in account of secured advance attached to the running account bill for the said works signed by the contractor on_______________and the employer has reserved to himself the option of making any further advance or advance on the security of other materials brought by the contractor to the site of the said works. Now THIS INDENTURE WITNESSETH that in pursuance of the said agreement and in consideration of the sum of rupees__________________on or before the execution of these present paid to the contractor by the employer (the receipt where of the contractor doth hereby acknowledge) and of such further advance (if any) as may be made to him as a for said the contractor doth hereby covenant and agree with the president and declare as follows: That the said sum of Rupees______________ so advance by the employer to 1) The contractor as aforesaid and all or any further sum of sum advance as aforesaid shall be employer by the contractor in or towards expending the execution of the said works and for no other purpose whatsoever. 2) That the materials details in the said account of secured advance which have been offered to and accepted by the employer as security are absolutely the contractor’s own propriety and free from encumbrance of any kind and the contractor will not make any application for or receive a further 245 advance on the security of materials which are not absolutely his own property and free from encumbrances of any kind and the contractor indemnified the employer against all claims to any materials in respect of which an advance has be made to him as aforesaid. 3) That the materials detailed in the said account of secured advance and all other materials on the security of which any further advance or advance may hereafter be made as aforesaid (Hereafter called the said materials) shall be used by the contractor solely in the execution of the said works in accordance with the directions of the Engineer. 4) That the contractor shall make at his own cost all necessary and adequate arrangement for the proper watch, safe custody and protection against all risks of the said materials and that until used in construction as aforesaid the said materials shall remain at the site of the said works in the contractor’s custody and on his own responsibility and shall at all times be open to inspection by the engineer or any officer authorized by him. In the event of the said materials or any part thereof being stolen, destroyed or damaged or becoming deteriorated in a greater degree than is due to reasonable use and wear thereof the contractor will forthwith replace the same with other materials of like quality or repaid and make good the same required by the Engineer. 5) That the said materials shall not be removed from the site of the said works except with the written permission of the engineer or an officer authorized by him on that behalf. 6) That the advance shall be repayable in full when or before the contract receives payment from the employer of the employer of the price payable to him for he said works under the terms and provision of the said agreement. Provided that if any intermediate payments are made to the contractor on account of work done than on the occasion of each such payment the employer will be at liberty to make a recovery from the contractor’s bill for such payment by deducting there from the value of the said materials than actually used in the construction and in respect of which recovery has not been made previously, the value for this purpose being determined in respect of each description of materials at the rates at which the amounts of the advances made under these presents were calculated. 7) That if the contractor shall at any time make any default in the performance or observance in any respect of any of the terms and provisions of the said agreement or of these presents the total amount of the advance or advances that may still be owing of the employer shall immediately on the happening of such default be repayable by the contractor to be the employer together with interest thereon at twelve percent per annum from the date or respective dates of such advance or advances to the date of repayment and with all costs, charges, damages and expenses incurred by the employer in or for the recovery thereof or the enforcement of this security or otherwise by reason of the default of the contractor and the contractor hereby covenants and agrees with the employer to reply and pay the same respectively to him accordingly. 8) That the contractor hereby charges all the said materials with the repayment to the employer of the said sum of rupees_____________________and any further sum of sum advance as aforesaid and all costs, charges, damages and expenses payable under these presents PROVIDED ALWAYS and it is hereby agreed and declared that notwithstanding anything in the said agreement and without prejudice to the power contained therein if and whenever the covenant for payment and repayment here-in-before contained shall become enforceable and the money owing shall not be paid in accordance there with the employer may at any time thereafter adopt all or any of the following courses as he may deem best: 246 a. Seize and utilize the said materials or any part thereof in the completion of the said works on behalf of the contractor in accordance with the provision in that behalf contained in the said agreement debiting the contractor with the actual cost of effecting such completion and the amount due to the contractor with the value of work done as if he had carried it out in accordance with the said agreement and at the rates thereby provided. If the balance is against the contractor, he is to pay same to the employer on demand. b. Remove and sell by public auction the seized materials or any part thereof and out of the money arising from the sale retain all the sums aforesaid repayable or payable to the employer under these presents and pay over the surplus (if any) to the contractor. c. Deduct all or any part of the moneys owing out of the security deposit or any sum due to the contractor under the said agreement. 9) That expect in the event of such default on the part of the contractor as aforesaid interest on the said advance shall not be payable. 10) That in the event of any conflict between the provisions of the these presents and the said agreement the provisions of these presents shall prevail and in the event of any dispute or difference arising over the construction or effect of these presents the settlement of which has been here-in-before expressly provided for the same shall be referred to the employer whose decision shall be final and the provision of the Indian Arbitration Act for the time being in force shall apply to any such reference. Annexure –U (See clause 35 of section 3-GCC) Physical Completion Certificate 247 Name of Works: Agreement No._______________________________________________________Date___________________ ______________ Amount of Contract Rs._________________________________________________ Name of Agency:_________________________________________________________________________ ____________________ Used MB No.____________________________________________________________________ Last measurement recorded a. Page No. & MB No.___________________________________ b. Data___________________________________________________ Certified that the above mentioned work was physically completed on___________________________(date) And taken over on _____________________(date) and that I have satisfied myself to best of my ability that the work has been done properly. Date of issue Executive Engineer Annexure –V (See clause 35 of section 3-GCC) Final Completion Certificate 248 Name of Works: Agreement No._______________________________________________________Date___________________ ______________ Amount of Contract Rs._________________________________________________ Name of Agency:_________________________________________________________________________ ____________________ Used MB No.____________________________________________________________________ Last measurement recorded a. Page No. & MB No.___________________________________ b. Data___________________________________________________ Certified that the above mentioned work was physically completed on___________________________(date) And taken over on _____________________(date) Agreement amount Rs.___________________________ Final Amount paid to contractor Rs___________________ Incumbency officers for the work I have satisfied myself to best of my ability that the work has been done properly Date of issue Executive Engineer 249 Annexure –W (See clause 39 of section 3-GCC) Salient Features of Some Major Labour Laws Applicable a. Workman Compensation Act 1923:- The Act provided for compensation in case of injury by accident arising out of and during the course of employment. b. Payment of Gratuity Act 1972: Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed the prescribed minimum years (say, five years) of services or more or on death the rate of prescribed minimum days’ (say, 15 days) wages for every completed year of service. The Act is applicable to all establishments employing the prescribed minimum number (say, 10) or more employees. c. Employee P.F. and Miscellaneous Provision Act 1952: The Act Provides for monthly contributions by the employer plus workers at the prescribed (say. 10% or 8.33%). The benefits payable under the Act are: i. Pension or family pension on retirement or death as the case may b. ii. Deposit linked insurance on the death in harness of the worker. iii. Payment of P.F. accumulation on retirement/ death etc. d. Maternity Benefit Act 1951:The Act Provides for leave and some other benefits to woman employees in case of confinement or miscarriage etc. e. Contract Labour (Regulation & Abolition) Act 1970: The Act provides for certain welfare measures to be provided by the contractor to contract labour and in case the contractor fails to provide, the same are required to be provided, by the principal employer by law. The principal employer is required to take certificate of registration and the contractor is required to take license from the designated officer. The Act is applicable to the establishments or contractor of principal employer if they employ prescribed minimum (say 20) or more contract labour. f. Minimum Wages Act 1948: The Employer is to pay not less than the minimum wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of building, roads, runways is scheduled employment. g. Payment of Wages Act 1936: It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers. h. Equal Remuneration Act 1979: The Act provides for payment of equal wages for work of equal nature to male and female workers and for not making discrimination against female employees in the matters of transfers, training and promotions etc. i. Payment of Bonus Act 1965: The Act applicable to all establishments employing prescribed minimum (say, 20) or more workman. The Act provided for payments of annual bonus within the prescribed range of percentage of wages to employees drawing up to the prescribed amount of wages, calculated in the prescribed manner. The Act does not apply to certain establishments. The newly set-up establishments are exempted for five years in certain circumstances. States may have different number of employment size. 250 j. Industrial Disputes Act 1947: The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment. k. Industrial Employment (Standing Orders) Act 1946: It is applicable to all establishment employing prescribed minimum (say, 100 or 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and gets these certified by the designated Authority. l. Trade Unions Act 1926: The Act lays down the procedure for registration of trade unions of workmen and employers. The Trade Unions registered under the Act have been given certain immunities from civil and criminal liabilities. m. Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labour is prohibited in building and construction industry. n. Inter-State Migrant Workmen’s (Regulation of Employment & Condition of Services) Act 1979: The Act is applicable to an establishment which employs prescribed minimum (say, five) or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, Medical-Aid, Travelling expenses from home upto the establishment and back etc. o. The Building and Other Construction Workers (Regulation of Employment and Conditions of Services) Act 1996 and the cess Act of 1996: All the establishments who carry on any building or other construction work and employs the prescribed minimum (say,10) or more workers are covered under this Act. All such establishment are required to pay cess at the rate not exceeding 2% of the cost of construction as may be modified by the Government. The Employer of the establishment is required to provide safety measures at the building or construction work and other welfare measure, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the work place etc. the employer to whom the Act applies has to obtain a registration certificate from the registering officer appointed by the Government. p. Factories Act 1948: The Act lays down the procedure for approval of plans before setting up a factory, health and safety provisions, welfare provisions, working hours, annual earned leave and rendering information regarding accidents or dangerous occurrences to designated authorities. It is applicable to premises employing the prescribed minimum (say, 10) persons or more with aid of power another prescribed minimum (say,20) or more persons without the aid power engaged in manufacturing process. 251 SECTION 3 Condition of Contract Part-II Special Condition of Contract [SCC] 1. The department reserves the right to change the key dates of the tender process. 2. Payment will be made on satisfactory execution of work. 3. The validity period of tenders shall be 120 days. 4. Being labour work tender and as per the section 35(1) of MP commercial tax act deduction for commercial tax shall be made from bill of the contractor @ 2.30% and as per corrigendum issued from time to time and certificate shall be issued on form 42. 5. In case of any accident entire liability shall be with the contractor and no payment/compensation shall be paid by the department. 6. The basis of item rates in form B 7. Interested tenderers may contact Executive Engineer MPAKVN (I) Ltd., Indore for obtaining details of work proposals or for inspection of works site. 8. All the terms and condition mentioned in MPPKVVCO LTD schedule of rates/ manual shall be binding on the contractor. 9. Cost of work mentioned in the tender is estimated cost and this amount and quantity of items of work mentioned in the schedule may be reduced or increased as per requirement of site. 10. The payment of final bill of the contractor shall be made after submission of no royalty due certificate issued by the District Collector 11. In case of requirement, dewatering work in road work it shall have to be done by the contractor at his own cost. 12. All material to be provided by the contractor shall be ISI marked and as per the enclosed vendor’s list. The sample of all the materials shall have to be approved from the Engineer-in-Charge /Consultant before placing orders for their supply. 13. The machineries/ equipment related to these items required at site shall be brought to the site within 30 days from the date of issue of work order or as directed by Engineer-in-charge. 252 14. The contractor shall be responsible for the performance of the contract and maintenance of the work carried out by him for a period of 2 (TWO) years which shall be counted form the date of actual completion of work as per requirement of MPAKVN(I) LTD. after handing over of the entire distribution system. 15. Department has engaged the services of a Project Management Consultant for supervision and quality control of the proposed works. The contractor shall make available to the consultant full access to the site of work, quarries and the site testing laboratory for supervision and testing. All views and opinion as given by the consultant shall be followed in full. The consultant may also independently carry out testing of materials and finished items at the cost of the contractor, which shall be binding to the contractor. In case of any difference of opinion the decision of the Engineer-in-Charge shall be final. 16. Since the work is for SEZ the provisions of SEZ Act 2005 and Indore SEZ Act 2003 (amended) are applicable for tax and duties concessions and contractor while bidding financial bid shall consider all such tax exemptions .It would be the sole responsibility of the contractor to obtain such tax exemptions on material and services from the competent authority and AKVN will only facilitate the same, however AKVN shall not be responsible or pay any extra amount in case the contractor is unable to avail such concessions. 17. After completion of work entire work is to be handed over to O&M agency of MPAKVN(I) LTD. with joint handing over report as per requirement of MPAKVN(I) LTD. 18. Central Electricity Authority (Technical Standards for construction operation and maintenance of Electrical Plants and Electrical Lines) Regulations No 2010 CEA/TETD/MP/02/2011 are binding on the selected contractor. 19. Central Electricity Authority (Safety requirements of construction operation and maintenance of Electrical Plants and Electrical Lines) Regulations 2011 no CEA/TETD/MP/R/2010 are binding on the selected contractor. 253 20. Provisions of The Electricity Act 2003 are binding on the Contractor. 21. A class electrical contractors test report and all permissions from MP Licensing board is mandatory before commencing work at site and for commissioning of the HT/LT system. 22. Coordination with MPAKVN(I) LTD. and approval of all drawings , specifications, pre dispatch inspection of material at manufacturers works by MPAKVN(I) Ltd. representative and approval of all material used in the scope of work of the contractor. All testing charges and such arrangements for inspection shall be made by contractor. 23. Interested bidders are advised to visit site before bidding as this is addition to existing system. 254 SECTION 4 BILL OF QUANTITES (BOQ) General Description of Work: Supply, installation, testing and commissioning of 33/11 KV External electrification work for new industrial area at Relwa Khurd district Barwani Probable Amount of Contract: (Rs.In Figure) Rs. 3,73,60,000/(Rs. In Words) Rupees Three Crore seventy three lakh sixty thousand only. SUMMARY OF 33/11 KV External electrification work for new industrial area at Relwa Khurd district Barwani SR . NO . 1 PAR T UNI T QT Y. RATE AMOUN T CIVIL AND LAND (SUBSTATION GRID AREA) A JOB 1 3120078 3120078 2 1x5 MVA SUBSTATION GRID B JOB 1 1255191 2 1255191 2 3 33 KV AND 11 KV LINE (WHOLE DOUBLE CIRCUIT & SINGLE CIRCUIT LINE) C JOB 1 1578676 0 1578676 0 4 COMPOSITE AND LT LINE D JOB 1 5901915 5901915 DESCRIPTION OF WORK 3736066 5 TOTAL AMOUNT (Part A+B+C+D) 255 AMOUNT in word Thirty one lakh twenty thousand seventy eight One crore twenty five lakh fifty one thousand nine hundred twelve One crore fifty seven lakh eighty six thousand seven hundred sixty Fifty nine lakh one thousand nine hundred fifteen Three crore seventy three lakh sixty thousand six hundred sixty five PART-A BOQ FOR 33/11KV EXTERNAL ELECTRIFICATION WORK FOR NEW INDUSTRIAL AREA AT RELWA KHURD DISTRICT BARWANI LAND AND CIVIL WORKS SR. NO . 1 2 UNIT QT Y Land Fencing of S/s land with barbed wire using PCC Pole of 2000mm length..Erection of pole on concreting foundation with ratio 1:3:6(pit size 450x450x500).Distance between pole to pole 2000mm. Yard fencing with chain link mesh of size (75x75x8 SWG) over RCC beam of 200mm size (as per drawing no. Misc.-5) LS Rm LS 145 0 802 0 116290 0 One lakh sixteen thousand two hundred ninety Rm 175 4811 841925 4 MS Main and wicket gate on RCC column, using ms pipe of size 50x50x2mm and 25x25x2mm including all necessary arrangement (as per drawing no. Misc.6) job. 1 66825 66825 Eight lakh forty one thousand nine hundred twenty five Sixty six thousand eight hundred twenty five 5 Yard leveling and metalling of substation area including one layer of 6mm down crushed stone 40mm below of ground level ,one layer of sand crusher dust with cement of ratio 1:2:17 above 75mm from ground level and above this layer 80mm thick layer of 63mmMetal (as per drawing no. Misc.-10) Toilet for staff and consumers of 2000x1600mm size including with septic tank and all associated work complete job. 1 529254 529254 Five lakh twenty nine thousand two hundred fifty four Nos. 1 104247 104247 7 MS sheet sign board, bay indication board & RYB Phase indication board (as per drawing no. Misc.-7) Nos. 1 15370 15370 One lakh four thousand two hundred forty seven Fifteen thousand three hundred seventy 8 Approach road with hume pipe culvert (as per drawing no. Misc. -13) Nos. 1 80190 80190 Eighty thousand one hundred ninety 9 Control room of size (5 mtr x 6mtr) and internal electrification work of control room (as per drawing no. 3) Nos. 1 735075 735075 Seven lakh thirty five thousand seventy five 10 60 Mtr. Deep 150 mm Dia Tube well including all associated work, complete Nos. 1 173745 173745 One lakh seventy three thousand seven hundred forty five 11 1000 Ltr P/F Sintex overhead tank & GI pipe fitting for water supply including providing water tap near transformer neutral earthing Nos. 1 100238 100238 One lakh two hundred thirty eight 3 6 PARTICULARS 256 RATE AMOUN T AMOUNT in word 12 13 14 15 Providing & fixing 2HP submersible pump with pipe’s, clamp , cable and all necessary fittings for 60mtr. Deep And 150mm dia. Tube well Nos. 1 106920 106920 One lakh six thousand nine hundred twenty Providing & fixing perforated cable tray 300mm width & 2mm thick fixed on 45x45x5mm MS angle grouted in C.C. 1:24 pit of size 600x600mm below 450mm from yard level and above 150mm from yard level, pit to pit distance for laying of tray 2500mm Fire fighting Arrangement and equipment fixed on MS stand of size 1100x1500 with 65x65x6mm angle including hanging arrangement for GI bucket of 16 ltr. Capacity, grouted in pit of size 400x400mm,on area of 2500x2000mm including brick masonry work(100mm thick) up to 300mm above ground level and 300mm below ground level with sand filling Construction of RCC Cable Trench with cover in yard approximate 750x650mm size with angle of 65x65x5mm at one meter distance each as decided by Engineer-in-charge of MPPKVVCL and consultant Mtr. 50 1778 88900 Eighty eight thousand nine hundred Job. 1 27399 27399 Twenty seven thousand three hundred ninety nine Mtr. 100 1337 133700 One lakh thirty three thousand seven hundred TOTAL AMOUNT PART-A 3120078 257 Thirty one lakh twenty thousand seventy eight PART-B BOQ FOR 33/11KV EXTERNAL ELECTRIFICATION WORK FOR NEW INDUSTRIAL AREA AT RELWA KHURD (M.P.) (1X5) MVA SUBSTATION GRID (PART-B) SR. NO . 1 PARTICULARS Supply, installation, testing & commissioning of 33/11 KV, 5 MVA Power Transformer with OFF LOAD TAP CHANGER of manufacture design to be approved from consultant with all necessary arrangement of clamp, connector, interconnection, earthing, operating, fixing, arrangement for neutral support on existing structure and concreting (with ratio 1:3:6) of foundation of Transformer @15cmt per foundation as decided by Engineer-in-charge of MPPKVVCL and consultant) Including (a)Approval of estimate from MPPKVVCO LTD, Comparison of the BOQ in the tender with sanctioned estimate , approval by MPAKVN (I) Ltd authority and final (b)Testing of entries installation as per IE rule 1956(amended) HI-Pot Testing and IR testing of cable/wire /conductor through MPAKVN approved agency and final approved from electrical inspector for charging(c) Handing over the system to MPPKVVCO with as built drags UNIT Nos. QUANTITY SUBS TATI SUBS ON TATI DP STRU ON STR CTUR EQU UCT E& IPM URE BUSB ENT FOR AR 5MV 33/11 ARRA A XKV NGE mer MEN T 1 0 0 258 TOTAL QTY. 1 RATE 325844 0 AMOUNT 3258440 AMOUNT in word Thirty two lakh fifty eight thousand four hundred forty 2 3 4 5 Supply, installation, testing & commissioning of 33KV VCB (for incomer) with CT having ratio 300150/5 with 0.5 class accuracy and concreting (with 1:3:6) of foundation for VCB @3.5cmt per foundation and Control & relay panel comprising of combined O/C & EFR aux relay for Bucholze transformer diff protection, annunciation and alarm system I.L.P.B with required structure & arrangement for control & relay cable etc. as per manufacturer design as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, installation, testing & commissioning of 33KV VCB with CTs having ratio 200-150/5 with 0.5 class accuracy and concreting (with 1:3:6) of foundation for VCB @3.5cmt per foundation and Control & relay panel comprising of combined O/C & EFR aux relay for Bucholze transformer diff protection, annunciation and alarm system I.L.P.B with required structure & arrangement for control & relay cable etc. capable for full requirement for parallel operation with all necessary arrangement of clamp, connector, interconnection, earthing, operating handle fixing arrangement on existing structure as decided by Engineer-incharge of MPPKVVCL and consultant Supply, installation, testing & commissioning of 11KV VCB (for transformer protection with 2 core oil immersed CTs having ratio 300-150/5 with 0.5 class accuracy) and concreting (with 1:3:6) of foundation for VCB @3.5cmt per foundation and Control & relay panel with required structure & arrangement as per manufacture design as decided by Engineer-in-charge of MPPKVVCL and consultant. Supply, installation, testing & commissioning of 11KV VCB (for feeder protection with oil immersed CTs having ratio 200/100/5) with auto re-closure and 2 nos. Control & relay panel with required structure & arrangement on R.C.C Foundation @3.50cmt as per manufacturer design as directed/decided by Engineer-incharge of MPPKVVCL and consultant. Nos. 1 0 0 1 340848 340848 Three lakh forty thousand eight hundred forty eight Nos. 1 0 0 1 334005 334005 Three lakh thirty four thousand five Nos. 1 0 0 1 216700 216700 Two lakh sixteen thousand seven hundred Nos. 3 0 0 3 274277 822831 Eight lakh twenty two thousand eight hundred thirty one 259 Supply, installation, testing & commissioning of 11/0.433 KV 100 KVA Transformer (conventional type) for Station X'mer at 33/11 KV GRID, D.T.R Metering as per specification of LT 3phase 4 wire 3x240 volts Ib=5Amps Imax x 10Amps trivectore meter class of accuracy 0.5 sec.DLMS compliant category A meters along with GSM (GPRS compatible) modems with box on pole mounting S/s of as per MPPKVVCL drawing with all necessary arrangement of clamp, connector, interconnection, earthing, operating handle fixing arrangement on existing structure as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, installation, testing & commissioning of ACDB one no. & DCDB one no. with I/c & O/g M.C.B. for 33/11 KV (1 x 5) MVA grid substation & all the connecting D.B. for meter with stand and all necessary arrangement of clamp, connector ,interconnection , earthing etc. Nos. 1 0 0 1 164069 164069 One lakh sixty four thousand sixty nine Set 1 0 0 1 24658 24658 Twenty four thousand six hundred fifty eight 8 Supply, Installation, Testing and Commissioning of H.T. Electronic Meter with TTB (Test Terminal Block) for S/s metering 3-phase 4wire 3x63.5 Volts Ib=5amps Imax=10amps, HT trivector meter class of accuracy 0.5s DLMS Compliant category A meters along with GSM (GPRS compatible) modems, as decided by Engineer-incharge of MPPKVVCL and consultant Nos. 6 0 0 6 19152 114912 One lakh fourteen thousand nine hundred twelve 9 Supply, Installation, Testing and Commissioning of 11KV Capacitor Bank 1500 KVAR with all associated equipment i.e. Cap. Unit , CT, RVT, LA, Isolator & structure (foundation of 3.50cmt) for equipment type I/c protection (auto type) as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 30 Volts 100AH Lead acid Battery with charger, required stand and all necessary arrangement of clamp, connector, interconnection, earthing as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 1 0 0 1 104566 4 1045664 Ten lakh forty five thousand six hundred sixty four Nos. 1 0 0 1 48475 48475 Forty eight thousand four hundred seventy five 6 7 10 260 11 12 13 14 15 16 Supply, Installation, Testing and Commissioning of 33KV Isolator (600A) switch without earth switch complete with all necessary arrangement of clamp, connector ,interconnection , earthing, operating handle fixing arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 11KV Isolator (800A) switch without earth switch complete with all necessary arrangement of clamp, connector ,interconnection , earthing, operating handle fixing arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 27KV Gapless type (30KA) Polymer Lightning Arrestors (L.A.) for 33/11 KV S/s complete with all necessary arrangement of clamp, connector ,interconnection , earthing as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 9KV Gapless type (10KA) Polymer Lightning Arrestors (L.A.) for 33/11 KV S/s complete with all necessary arrangement of clamp, connector ,interconnection , earthing etc. Supply, Installation, Testing and Commissioning of 33KV oil immersed 3 phase 4wire CT-PT Metering units having ratio 400/200/5 with 0.5 class accuracy with control & relay cable and all necessary arrangement of clamp, connector ,interconnection , earthing as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 3-phase 11KV CTPT Metering unit with control & relay cable and all necessary arrangement of clamp, connector ,interconnection , earthing as decided by Engineer-in-charge of MPPKVVCL and consultant Set 5 0 0 5 32998 164990 One lakh sixty four thousand nine hundred ninety Set 8 0 0 8 19580 156640 One lakh fifty six thousand six hundred forty Nos. 12 0 0 12 4210 50520 Fifty thousand five hundred twenty Nos. 12 0 0 12 1724 20688 Twenty thousand six hundred eighty eight Nos. 3 0 0 3 85376 256128 Two lakh fifty six thousand one hundred twenty eight Nos. 4 0 0 4 60116 240464 Two lakh forty thousand four hundred sixty four 261 17 18 19 20 21 22 23 24 25 Supply, Installation, Testing and Commissioning of Outdoor type 33KV/110V single phase potential transformer (PT) for all three phase used as per MPPKVVCL's specifications with all necessary arrangement of clamp, connector, interconnection, earthing, as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Outdoor type 11KV/110V single phase potential transformer (PT) as per MPPKVVCL's specifications with all necessary arrangement of clamp, connector, interconnection , earthing Supply, Installation, Testing and Commissioning of 70Sqmm single core XLPE insulated un-armoured aluminium conductor cable Supply, Installation, Testing and Commissioning of 4-core 16Sqmm PVC cable Nos. 3 0 0 3 21451 64353 Sixty four thousand three hundred fifty two Nos. 3 0 0 3 11013 33039 Thirty three thousand thirty nine Nineteen thousand two hundred Sixteen thousand four hundred Seven thousand Mtr. 0 0 300 300 64 19200 Mtr. 0 0 200 200 82 16400 Supply, Installation, Testing and Commissioning of 2-core 2.5Sqmm PVC cable SITC of control cable :(a) 2.5sqmm 8 core Un-armoured Mtr. 0 0 200 200 35 7000 Mtr. 800 0 0 800 164 131200 (b) 2.5sqmm 4 core Un-armoured Mtr. 400 0 0 400 84 33600 (c) 2.5sqmm 2 core Un-armoured Mtr. 200 0 0 200 48 9600 Supply and Installation of Tee clamps & P.G. Clamps as decided by Engineer-in-charge of MPPKVVCL and consultant Supply and Installation of Bi- metallic clamps as decided by Engineer-incharge of MPPKVVCL and consultant Nos. 100 0 0 100 588 58800 Nos. 100 0 0 100 588 58800 Supply, Installation, Testing and Commissioning of Sodium Vapour Lamp with 250 watt Lamp complete with all necessary arrangement Nos. 5 0 0 5 10010 50050 262 One lakh thirty one thousand two hundred thirty three thousand six hundred Nine thousand six hundred Fifty eight thousand eight hundred Fifty eight thousand eight hundred Fifty thousand fifty 26 27 28 Supply, Installation, Testing and Commissioning of H-Beam 152x152mm 37.1Kg/mtr 11mtr long including concreting and excavation work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.65cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineerin-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of H-Beam 152x152mm 37.1Kg/mtr 9.1mtr long including concreting and excavation work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.65cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineerin-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of H-Beam 152x152mm 37.1Kg/mtr 9 mtr long including concreting and excavation work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.65cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineerin-charge of MPPKVVCL and consultant Nos. 0 Nos. 0 Nos. 0 0 8 23 0 0 263 5 8 33373 266984 Two lakh sixty six thousand nine hundred eighty four 23 29258 672934 Six lakh seventy two thousand nine hundred thirty four 5 28213 141065 One lakh forty one thousand sixty five Supply, Installation, Testing & Commissioning of H-Beam 152x152mm, 37.1KG/meter, 8mtr long for support of Isolator operating handle(2.9mtr long/ handle for 11KV and 33KV side, total nos. of handle is 22 ) including concreting and excavation work for erection of HBeam 2.9 mtr piece (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.65cmt minimum concrete quantity per piece separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of H-Beam 152x152mm 37.1Kg/mtr 7mtr long including concreting and excavation work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.65cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement Supply, Installation, Testing and Commissioning of Rail pole 2mtr long for Transformer plinth construction Nos. 0 5 0 5 24785 123925 One lakh twenty three thousand nine hundred twenty five Nos. 0 4 0 4 33819 135276 Two lakh sixty six thousand nine hundred eighty two Nos. 0 0 2 2 8166 16332 32 Supply, Installation, Testing and Commissioning of Stay Set 20mm complete with back clamp, stay wire 7/4.0mm (8.5Kg stay wire per stay set) & buckles including excavation and concreting work for erection of stay @0.3cmt minimum concrete quantity per stay) Nos. 0 0 8 8 3331 26648 Sixteen thousand three hundred thirty two Twenty six thousand six hundred forty eight 33 Supply, Installation, Testing and Commissioning of Back Clamps (65x8mm flat) for H-Beam pole with all accessories like, nuts and bolts for a separate H-Beam pole and two coats of red oxide and aluminium paint Pair 0 13 1003 13039 29 30 31 13 0 264 Thirteen thousand thirty nine Supply, Installation, Testing and Commissioning of MS DC cross arm 100x50mm 5.2 meter long for two on each set for top cross arm, middle cross arm, lower cross arm, with Tension Patti & other necessary material ( nuts and bolts and two coat of red oxide & aluminium paint ) as decided by Engineer-in-charge of MPPKVVCL and consultant. (For both 11KV & 33KV side) Supply, Installation, Testing and Commissioning of MS D.C. cross arm 2.7 meter long for isolator structure at top of supports for 33KV and 11KV side (53.5Kg for each set) with all necessary arrangements Set 0 52 0 52 4380 227760 two lakh twenty seven thousand seven hundred sixty Set 0 2 0 2 3802 7604 Seven thousand six hundred four Supply, Installation, Testing and Commissioning of MS cross bracings of MS angle of size 50x50x6mm for 5' centre (51.67Kg for each set) as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of DC cross arm of ISMC channel 100x50mm suitable for 10' centre DP with 2 pair of clamps suitable for each beam (14 set for O/g feeder +3 set for S/s X-mer) with all nessecry arrangement (nuts and bolts and two coat of red oxide & aluminium paint) Supply, Installation, Testing and Commissioning of support for Isolator operating handle 100x50mm MS channel of 6' length (7 nos. for 33KV side and 15 nos. for 11KV side ) with all necessary arrangement (nuts and bolts and two coat of red oxide & aluminium paint ) Supply, Installation, Testing and Commissioning of 33KV (10KN) polymer Pin insulator with top clamp 75x75x6mm angle type Set 0 2 0 2 4680 9360 Nine thousand three hundred sixty Set 0 10 7287 72870 Seventy two thousand eight hundred seventy Nos. 0 13 0 13 2205 28665 Twenty eight thousand six hundred sixty five Nos. 0 12 0 12 874 10488 40 Supply, Installation, Testing and Commissioning of 11KV (5KN) Polymer Pin insulator with top clamp 65x65x6mm angle type Nos. 0 18 0 18 474 8532 41 Supply, Installation, Testing and Commissioning of 33KV (45KN) polymer Disc insulator with strain hardware suitable for Panther conductor Nos. 0 42 0 42 1283 53886 Ten thousand four hundred eighty eight Eight thousand five hundred thirty two Fifty three thousand eight hundred eighty six 34 35 36 37 38 39 0 265 10 69 1122 77418 4 4 7244 28976 1 1 15650 15650 0 1000 278 278000 1 0 1 133650 133650 1 0 1 41699 41699 Forty one thousand six hundred ninety nine 0 0 1 432037 432037 12 0 0 12 9694 116328 175 0 0 175 414 72450 Four lakh thirty two thousand thirty seven One lakh sixteen thousand three hundred twenty eight Seventy two thousand four hundred fifty 42 Supply, Installation, Testing and Commissioning of 11KV (45KN) polymer Disc insulator with strain hardware suitable for Panther conductor Nos. 0 43 Supply, Installation, Testing and Commissioning of 11KV (Polymer) AB switch with complete fittings as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 0 0 44 Supply, Installation, Testing and Commissioning of 33KV AB switch porcelain type with complete fitting as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of AAA Panther Conductor for jumper Nos. 0 0 Mtr. 0 1000 Job 0 Job 0 48 Supply, Installation, Testing and Commissioning of Pipe Earthing in S/S as per IS:3043 for transformer and DTR transformer LA, CT/PT ME, Pole structure, equipments, metal part of electrical enclose and mesh earthing as decided by Engineer-incharge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Earthing of Transformer neutral with 2 nos. 50x5mm copper strip, 3 nos. 11KV pin insulators mounted on 100x50mm MS channel support and aluminium pad clamp with 2 nos. bi-metallic strips for twin Panther conductor and AAA conductor as decided by Engineer-in-charge of MPPKVVCL and consultant SCADA SOFTWARE SITC of Remote Terminal Unit No. 1 49 SITC of Multifunction Transducer No. 50 SITC of Contact Multiplying Relay No. 45 46 47 69 0 266 Seventy seven thousand four hundred eighteen Twenty eight thousand nine hundred seventy six Fifteen thousand six hundred fifty Two lakh seventy eight thousand One lakh thirty three thousand six hundred fifty 51 SITC of Heavy Duty Relays for CB Trip/Close No. 25 0 0 25 589 14725 52 SITC of Routers No. 1 0 0 1 81919 81919 53 SITC of LDMS No. 1 0 0 1 127447 127447 54 SITC of Printer No. 1 0 0 1 31519 31519 55 SITC of LDMS Software No. 1 0 0 1 6683 6683 56 SCADA HARDWARE SITC of Compatible Differential Relay (for power transformer) No. 2 0 0 2 66825 133650 57 SITC of Compatible Numerical Relay No. 12 0 0 12 42768 513216 58 SITC of Master Trip Relay No. 12 0 0 12 6683 80196 59 SITC of Auxiliary Relay (30V DC 4N.O.+4N.C.) No. 25 0 0 25 9730 243250 60 SITC of Contactors No. 25 0 0 25 3649 91225 61 SITC of Transformer Pressure Indicator (TPI) No. 2 0 0 2 6683 13366 267 Fourteen thousand seven hundred twenty five Eighty one thousand nine hundred nineteen One lakh twenty seven thousand four hundred forty seven Thirty one thousand five hundred nineteen Six thousand six hundred eighty three One lakh thirty three thousand six hundred fifty Five lakh thirteen thousand two hundred sixteen Eighty thousand one hundred ninety six Two lakh forty three thousand two hundred fifty Ninety one thousand two hundred twenty five thirteen thousand three hundred sixty six 62 SITC of Winding Temperature Indicator No. 2 0 0 2 7351 14702 63 SITC of Oil Temperature Indicator (OTI) No. 2 0 0 2 7351 14702 64 SITC of Isolator Contacts No. 26 0 0 26 3041 79066 65 SITC of control cable :a) 2.5 Sqmm, 2-Core (Unarmoured) Mtr. 1000 0 0 1000 48 48000 b) 2.5 Sqmm, 4-Core (Unarmoured) Mtr. 3000 0 0 3000 84 252000 c) 2.5 Sqmm, 8-Core (Unarmoured) Mtr. 300 0 0 300 165 49500 66 Supply and Installation of 33KV/11KV/0.433KV Danger Board complete set with all necessary arrangement Nos. 0 0 8 8 80 640 67 Supply and Installation of Anti Climbing devices (Barbed wire 2.24mm Dia (14 SWG) (3.5Kg wire per pole) complete with all necessary arrangement Nos. 0 0 8 8 307 2456 TOTAL AMOUNT 12551912 268 Fourteen thousand seven hundred two Fourteen thousand seven hundred two Seventy nine thousand sixty six Forty eight thousand Two lakh fifty two thousand Forty nine thousand five hundred seventeen Six hundred forty Two thousand four hundred fifty six One crore twenty five lakh fifty one thousand nine hundred twelve PART-C BOQ FOR 33/11KV EXTERNAL ELECTRIFICATION WORK FOR NEW INDUSTRIAL AREA AT RELWA KHURD (M.P.) 33 KV & 11 KV LINE (WHOLE D/C & S/C) (PART-C) QUANTITY SR. NO . 1 PARTICULARS Supply, Installation, Testing and Commissioning of H-Beam 152x152mm 37.1Kg/mtr 15mtr long including excavation and concreting work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.70cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant UNIT 33KV LINE (DC) 11KV LINE (DC) 11KV LINE (DC) TP Nos. 20 0 0 269 11K V LIN E (SC) 0 33K V LIN E (SC) 0 TO TAL QT Y. RATE AMOUNT 20 44359 887180 AMOUN T in word Eight lakh eighty seven thousan d one hundred sixty 2 3 4 Supply, Installation, Testing and Commissioning of H-Beam 152x152mm 37.1Kg/mtr 13mtr long including excavation and concreting work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.70cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of H-Beam 152x152mm 37.1Kg/mtr 11mtr long and concreting and excavation work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.65cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of H-Beam 152x152mm 37.1Kg/mtr 9.1mtr long and concreting and excavation work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.65cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 121 12 12 0 19 164 39138 6418632 Sixty four lakh eighteen thousan d six hundred thirty two Nos. 10 0 0 12 2 24 36551 877224 Eight lakh seventy seven thousan d two hundred twenty four Nos. 0 0 0 3 0 3 27801 83403 Eighty three thousan d four hundred three 270 5 6 7 8 9 Supply, Installation, Testing and Commissioning of Stay Set 20mm complete with back clamp, stay wire 7/4.0mm (8.5Kg stay wire per stay set) & buckles and concreting and excavation work for erection of stay @0.3cmt minimum concrete quantity per stay) as decided by Engineer-incharge of MPPKVVCL and consultants decided by Engineerin-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Stay Set 16mm complete with back clamp, stay wire 7/3.15mm (5.5Kg stay wire per stay set) & buckles and concreting and excavation work for erection of stay @0.3cmt minimum concrete quantity per stay) Supply, Installation, Testing and Commissioning of 33KV 'V' Cross arm angle type (75x75x6mm angle) with all accessories (nuts & bolts ) which are necessary to installed 'V' Cross arm like, nuts and bolts & binding wire and tape etc for a separate H-Beam pole and two coats of red oxide and aluminium paint as decided by Engineer-incharge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 11KV 'V' Cross arm angle type (65x65x6mm angle) with all accessories which are necessary to installed 'V' Cross arm like, nuts and bolts for a separate HBeam pole and two coats of red oxide and aluminium paint as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 11KV & 33KV Back Clamps (65x8mm flat) for H-Beam pole with all accessories like, nuts and bolts for a separate H-Beam pole and two coats of red oxide and aluminium paint as decided by Engineer-incharge of MPPKVVCL and consultant Nos. 134 0 0 0 19 153 3331 509643 Five lakh nine thousan d six hundred forty three Nos. 0 12 16 12 0 40 2742 109680 One lakh nine thousan d six hundred eighty Nos. 312 0 0 0 19 331 2128 704368 Seven lakh four thousan d three hundred sixty eight Nos. 0 36 0 12 0 48 1537 73776 Seventy three thousan d seven hundred seventy six Pair 312 36 0 12 19 379 272 103088 one lakh three thousan d eighty eight 271 Supply, Installation, Testing and Commissioning of 33KV Top Clamps angle type 75x75x6mm for H-Beam pole with all accessories like, nuts and bolts for a separate H-Beam pole and two coats of red oxide and aluminium paint Supply, Installation, Testing and Commissioning of 11KV Top Clamps angle type 65x65x6mm for H-Beam pole with all accessories like, nuts and bolts for a separate H-Beam pole and two coats of red oxide and aluminium paint Supply, Installation, Testing and Commissioning of Single pole cut point fitting channel of size 100x50mm Nos. 0 0 0 0 19 19 299 5681 Five thousan d six hundred eighty one Nos. 0 0 0 12 0 12 260 3120 Three thousan d one hundred twenty Set 0 0 0 0 10 10 2545 25450 13 Supply, Installation, Testing and Commissioning of 11 KV DC Cross arm of ISMC channel of 100x50mm suitable for 5' centre DP with 2 pair of clamps suitable for H-Beam Set 0 0 24 0 0 24 5456 130944 14 Supply, Installation, Testing and Commissioning of 33 KV DC Cross arm of ISMC channel of 100x50mm suitable for 5' centre DP with 2 pair of clamps suitable for H-Beam including nuts & bolts Set 64 0 0 0 0 64 6019 385216 15 Supply, Installation, Testing and Commissioning of Horizontal cross Bracing 5' centre (45.02 kg) with set of back clamp suitable for H-Beam as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Horizontal cross Bracing 5' centre(51.67 kg) with set of back clamp suitable for H-Beam as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 0 0 8 0 0 8 4681 37448 Nos. 24 0 0 0 0 24 5536 132864 Twenty five thousan d four hundred fifty One lakh thirty thousan d nine hundred forty four Three lakh eighty five thousan d two hundred sixteen Thirty seven thousan d four hundred forty eight One lakh thirty two thousan d eight hundred sixty four 10 11 12 16 272 17 Supply, Installation, Testing and Commissioning of 33KV 'V' Guarding channel type (75x40x6mm) as decided by Engineer-in-charge of MPPKVVCL and consultant Set 6 0 0 0 0 6 3792 22752 Twenty two thousan d seven hundred fifty two 18 Supply, Installation, Testing and Commissioning of 33KV Polymer Pin insulator including nuts & bolts Nos. 720 0 0 0 57 777 603 468531 19 Supply, Installation, Testing and Commissioning of 11KV Polymer Pin insulator including nuts & bolts Nos. 0 72 0 36 0 108 420 45360 20 Supply, Installation, Testing and Commissioning of 11KV (5KN) Polymer Pin insulator with top clamp 65x65x6mm angle type complete Nos. 0 0 24 0 0 24 474 11376 Four lakh sixty eight thousan d five hundred thirty one Forty five thousan d three hundred sixty Eleven thousan d three hundred seventy six 21 Supply, Installation, Testing and Commissioning of 33KV Disc insulator (Polymer) with strain hardware fitting as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 192 0 0 0 0 192 611 117312 one lakh sevente en thousan d three hundred twelve 22 Supply, Installation, Testing and Commissioning of 11KV Disc insulator (Polymer) with strain hardware fitting as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of AAA Dog Conductor with 3% sag and binding wire ,para tape as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 0 0 48 0 0 48 321 15408 Fifteen thousan d four hundred eight Km 31.84 0 0 0 4.9 36.7 4 71497 2626800 Supply, Installation, Testing and Commissioning of AAA Raccoon Conductor with 3% sag and binding wire ,para tape as decided by Engineer-in-charge of MPPKVVCL and consultant Km 0 3.8 0 2.53 0 6.33 55880 353720 Twenty six lakh twenty six thousan d eight hundred Three lakh Fifty three thousan d seven hundred twenty 23 24 273 SITC of 33KV 300sqmm 3-core underground XLPE HT cable including binding wire and para tape as decided by Engineer-incharge of MPPKVVCL SITC of Cable jointing kit (heat shrinkable) with lugs for 33KV grade as decided by Engineer-incharge of MPPKVVCL Mtr 400 0 0 0 0 400 2090 836000 Set 8 0 0 0 0 8 34268 274144 Supply, Installation, Testing and Commissioning of Jointing sleeves suitable for 80 Sqmm Aluminium conductor equivalent to AAAC with all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant SITC of 33KV AB cable 200sqmm for jumper as decided by Engineer-in-charge of MPPKVVCL Nos. 70 6 0 5 8 89 187 16643 Mtr 20 0 0 0 0 20 1493 29860 29 SITC of GI pipe 150mm dia Bgrade along DP as decided by Engineer-in-charge of MPPKVVCL Mtr 80 0 0 0 0 80 1537 122960 30 SITC of RCC Hume pipe 300mm inner dia 30mm thick for underground cabling as decided by Engineer-in-charge of MPPKVVCL Mtr 200 0 0 0 0 200 1069 213800 31 SITC of Cable chamber with cement cover for inspection and cable pulling of size 750x750x1000mm Nos. 3 0 0 0 0 3 3341 10023 32 SITC of Bi-metallic Clamp as decided by Engineer-in-charge of MPPKVVCL Nos. 24 0 0 0 0 24 588 14112 33 Supply, Installation, Testing and Commissioning of Earthing Coil (coil of 115 turns of 50mm dia and 2.5mtr lead of 4.0mm G.I. wire) as decided by Engineer-incharge of MPPKVVCL and Nos. 131 12 12 12 19 186 173 32162 25 26 27 28 274 Eight lakh thirty six thousan d Two lakh seventy four thousan d one hundred forty four Sixteen thousan d six hundred forty three Twenty nine thousan d eight hundred sixty One lakh twenty two thousan d nine hundred sixty Two lakh thirteen thousan d eight hundred Ten thousan d twenty three Fourtee n thousan d one hundred twelve Thirty two thousan d one hundred sixty two consultant 34 Supply and Installation of 33KV/11KV/0.433KV Danger Board complete set with all necessary arrangement Nos. 125 12 4 12 19 172 79 13588 35 Supply and Installation of GI wire 6 SWG (8mtr/kg) Kg 100 0 0 0 0 100 76 7600 36 Supply and Installation of GI wire 8 SWG (9.8mtr/kg) Kg 80 0 0 0 0 80 84 6720 37 Supply and Installation of Anti Climbing devices (Barbed wire 2.24mm Dia (14 SWG) (3.5Kg wire per pole) complete with all necessary arrangement Nos. 141 12 12 12 19 196 307 60172 TOTAL AMOUNT 15786760 275 Thirteen thousan d five hundred eighty eight Seven thousan d six hundred Six thousan d seven hundred twenty Sixty thousan d one hundred seventy two One crore fifty seven lakh eighty six thousan d seven hundre d sixty PART-D BOQ FOR 33/11KV EXTERNAL ELECTRIFICATION WORK FOR NEW INDUSTRIAL AREA AT RELWA KHURD (M.P.) COMPOSITE 11 KV AND LT LINE (PART-D) TOTA L QTY. QUANTITY SR. NO . 1 2 3 4 5 PARTICULARS Supply, Installation, Testing and Commissioning of 11/0.433KV 200KVA Transformer (conventional type) as decided by Engineerin-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of LT Distribution Box suitable for 200KVA Transformer with Isolator on Incoming with HRC fuse as decided by Engineer-incharge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Static Energy Meter (3-phase 4-wire with CT and Modem) as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 150Sqmm single core XLPE insulated un armoured aluminium conductor cable as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 70Sqmm single core XLPE insulated un-armoured aluminium conductor cable RATE AMOUN T AMOUNT (in word) Nine lakh twenty three thousand eight hundred fifty five Ninety thousand six hundred fifteen 11KV DP STRUC -TURE W/O X-MER COMPOSITE LINE LT LINE Nos. 200 KVA 11/ 0.433 KV O/D S/S 5 0 0 0 5 184771 923855 Nos. 5 0 0 0 5 18123 90615 Nos. 5 0 0 0 5 3208 16040 Sixteen thousand forty Mtr. 200 0 0 0 200 126 25200 Twenty five thousand two hundred Mtr. 400 0 0 0 400 64 25600 twenty five thousand six hundred UNIT 276 Km 0 0 2.25 0 2.25 495467 1114765 Km 0 0 0 1.2 1.2 34025 40830 Km 0 0 0 1.2 1.2 26646 31975 SITC of Spring loaded CP multi connection Bus-bar in insulated box for fixing on pole suitable for AB XLPE cable as decided by Engineer-in-charge of MPPKVVCL and consultant a) Single phase 1 in 6 out Nos. 0 0 20 0 20 1203 24060 b) Three phase 1 in 3 out Nos. 0 0 20 0 20 1671 33420 10 Supply and Installation of AB cable hanging clamps/tension clamps (Galvanized) as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 0 0 40 0 40 708 28320 11 Supply and Installation of Suspension clamps with attachment as decided by Engineer-in-charge of MPPKVVCL and consultant Supply and Installation of Tension clamps (dead end clamp) with attachment as decided by Engineer-in-charge of MPPKVVCL and consultant Supply and Installation of Clamp for neutral as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 0 0 40 0 40 481 19240 Nos. 0 0 40 0 40 601 24040 Nos. 0 0 40 0 40 33 1320 Supply and Installation of Piercing connector type-I for single phase/ three phase as decided by Engineer-in-charge Nos. 0 0 120 0 120 100 12000 6 7 8 9 12 13 14 Supply, Installation, Testing and Commissioning of AB cable XLPE cable of size 3x150 +1x35 +1x95 Sqmm (insulated neutral) as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 35Sqmm PVC arm cable as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 25Sqmm PVC arm cable as decided by Engineer-in-charge of MPPKVVCL and consultant 277 Eleven lakh fourteen thousand seven hundred sixty five Forty thousand eight hundred thirty Thirty one thousand nine hundred seventy five Twenty four thousand sixty thirty three thousand four hundred twenty Twenty eight thousand three hundred twenty Nineteen thousand two hundred forty Twenty four thousand forty One thousand three hundred twenty Twelve thousand of MPPKVVCL and consultant 15 Supply and Installation of Jhook for laying of AB cable as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 0 0 40 0 40 107 4280 16 Supply, Installation, Testing and Commissioning of High Mast Fitting 16mtr complete as per design and specifications as decided by Engineer-incharge of A.K.V.N and consultant Supply, Installation, Testing and Commissioning of Sodium Vapor Lamp with 250 watt Lamp complete with all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 140Watt LED luminaries with IP-66 degree of protection as per detailed specifications on decorative brackets all necessary required material (including copper cable from pole to light fitting etc) as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of HBeam 152x152mm 37.1Kg/mtr 11mtr long including excavation and concreting work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.65cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Job 0 0 2 0 2 160380 320760 Nos. 0 0 45 0 45 13786 620370 Six lakh twenty thousand three hundred seventy Nos. 0 0 5 0 5 49451 247255 Two lakh forty seven thousand two hundred fifty five Nos. 10 10 0 0 20 36413 728260 Seven lakh twenty eight thousand two hundred sixty 17 18 19 278 Four thousand two hundred eighty Three lakh twenty thousand seven hundred sixty 20 21 22 23 24 Supply, Installation, Testing and Commissioning of 175x85mm 19.6 Kg/ Mtr, 9.3 Mtr long RSJ support including excavation and concreting work for erection of H-Beam pole (including digging and muffing) with base padding of 1:3:6 concrete mix and back filling with boulder and concrete mix (@0.30cmt minimum concrete quantity per pole separately) with two coats of red oxide and aluminium paint & all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Stay Set 20mm complete with back clamp, stay wire 7/3.15mm (5.5Kg stay wire per stay set) & buckles including excavation and concreting work for erection of stay @0.3cmt minimum concrete quantity per stay) as decided by Engineerin-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Stay Set 16mm complete with back clamp, stay wire 7/3.15mm (5.5Kg stay wire per stay set) & buckles including excavation and concreting work for erection of stay @0.3cmt minimum concrete quantity per stay) as decided by Engineerin-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Distribution Box mounting channel of size 75x40x6mm including all necessary arrangement ( nuts & bolts) Nos. 0 0 40 20 60 14615 876900 Eight lakh seventy six thousand nine Nos. 20 10 0 0 30 3331 99930 Ninety nine thousand nine hundred thirty Nos. 0 0 0 10 10 2589 25890 Twenty five thousand eight hundred ninety Nos. 10 10 0 0 20 507 10140 Ten thousand one hundred forty Supply, Installation, Testing and Commissioning of DC cross arm of size 100x50x6mm 8' centre with 2pair of clamps (for LA, AB switch, Pin and DO fuse) suitable for H-Beam including all necessary arrangement ( nuts & bolts ) as decided by Engineer-in-charge of Set 15 15 0 0 30 4856 145680 One lakh forty five thousand six hundred eighty 279 MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Transformer mounting DC cross arm of size 100x50x6mm with complete arrangement (belting angle of size 50x50x6mm with 2-cross fixing channel, clamping angle of size (50x50x6mm) nuts and bolts suitable for H-Beam as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 11KV (5KN) Polymer Pin insulator with top clamp 65x65x6mm angle type complete Set 5 5 0 0 10 10839 108390 One lakh eight thousand three hundred ninety Nos. 15 15 0 0 30 474 14220 Fourteen thousand two hundred twenty 27 Supply, Installation, Testing and Commissioning of 11KV Disc insulator (Polymer) with strain hardware fitting Nos. 15 15 0 0 30 321 9630 Nine thousand six hundred thirty 28 Supply, Installation, Testing and Commissioning of 11KV Lightning Arrestor as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 11KV (Polymer) AB switch with complete fittings as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of 11KV (Polymer) DO fuse unit as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of LT 5pin Bracket as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Shackle Insulator 90x75mm as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 15 15 0 0 30 495 14850 Nos. 5 5 0 0 10 7244 72440 Nos. 5 5 0 0 10 1818 18180 Nos. 0 0 0 30 30 2301 69030 Fourteen thousand eight hundred fifty Seventy two thousand four hundred Forty Eighteen thousand one hundred eighty Sixty nine thousand Thirty Nos. 0 0 0 120 120 12 1440 25 26 29 30 31 32 280 One thousand Four hundred forty Supply, Installation, Testing and Commissioning of Shackle hardware 90x75mm as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Earth Knob as decided by Engineerin-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of AAA Rabbit Conductor for jumper Nos. 0 0 0 30 30 56 1680 Nos. 0 0 0 30 30 48 1440 Mtr. 200 200 0 0 400 38 15200 Supply, Installation, Testing and Commissioning of Earthing Coil (coil of 115 turns of 50mm dia and 2.5mtr lead of 4.0mm G.I. wire) as decided by Engineer-in-charge of MPPKVVCL and consultant Supply, Installation, Testing and Commissioning of Earthing set (DTR earthing) set of three pits including all necessary arrangement ( nuts & bolts ) as decided by Engineerin-charge of MPPKVVCL and consultant Supply and Installation of GI wire for Guarding as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 0 10 0 20 30 174 5220 Nos. 5 5 0 0 10 6423 64230 Sixty four thousand two hundred thirty Kg 0 0 0 30 30 76 2280 39 Supply and Installation of HT tape for covering LT bushing Mtr. 150 0 0 0 150 40 6000 Two thousand two hundred eighty Six thousand 40 Supply and Installation of 33KV/11KV/0.433KV Danger Board complete set with all necessary arrangement Nos. 5 5 0 0 10 80 800 Eight hundred 41 Supply and Installation of Anti Climbing devices (Barbed wire 2.24mm Dia (14 SWG) (3.5Kg wire per pole) complete with all necessary arrangement as decided by Engineer-in-charge of MPPKVVCL and consultant Nos. 10 10 0 0 20 307 6140 Six thousand one hundred forty 33 34 35 36 37 38 TOTAL AMOUNT 5901915 281 One thousand six hundred eighty One thousand Four hundred forty Fifteen thousand Two hundred Five thousand Two hundred twenty Fifty nine lakh one thousand nine hundred fifteen Total Amount of Part (A+B+C+D) (Rs. in words) Rupees Three crore seventy three lakh sixty thousand six hundred sixty five Executive Engineer SECTION 5 AGREEMENT FORM This agreement, made on the ______________________________ day of _______________ between ___________________ (name and address of employer) (hereinafter called “the Employer) and ____________________________ (name and address of contractor) hereinafter called “the contractor” of the other part. Whereas the Employer is desirous that the Contractor execute __________________________ (name and identification number of contractor for the execution and completion of such works and the remedying of any defects therein, at a cost of Rs.______________ NOW THIS AGREEMENT WITNESSED as follows: 1. In this Agreement, words and expression shall have the same meanings as per respectively assigned to them in the conditions of contract hereinafter referred to and they shall be deemed to form and be read and construed as part of this agreement. 2. In consideration of the payments to be made by the Employer to the Contractor as hereinafter mentioned, the contractor hereby covenants with the Employer to execute and complete the works and remedy any defects therein in conformity in all aspects with the provisions of the contract. 3. The employer hereby covenants to pay the Contractor in consideration of the execution and completion of the works and remedying the defects wherein Contract Price or such other 282 sum as may become payable under the previous of the contract at the times and in the manner prescribed by the Contract. 4. The following documents shall be deemed to form and be ready and construed as part of this Agreement viz. i. Letter of Acceptance ii. Contractor’s Bid iii. Condition of Contract : General and Special iv. Contract Data v. Bid Data vi. Drawings vii. Bill of Quantities and viii. Any other documents listed in the Contract Data as forming part of the Contract. In witnessed whereof the parties here to have caused this Agreement to be executed the day and year first before written. The Common Seal of _______________________________________________ was hereunto affixed in the presence of: Signed, Sealed and Delivered by the said __________________________________ _____________________________________________ in the presence of: Binding Signature of Employee______________________________ Binding Signature of Contractor______________________________ 283
© Copyright 2024