Operation and Maintenance Schedule

Operation and Maintenance
Schedule
Overview of O&M projects and new
installations
1 January – 31 December 2017
Sag 15/18069
Introduction
According to the Rules for Gas Transport version 16.0, section 10.1 c, Energinet.dk shall provide
information on scheduled repair and maintenance activities in relation to the gas transmission system.
This document describes all scheduled activities from 1 January - 31 December 2017. Shippers who
will be affected by activities with an effect on Energinet.dk’s transport capacity will be contacted
directly.
For further information please contact:
Helle Øgaard (HOG@energinet.dk) på tlf. 23 33 89 40.
Henrik Bay (hby@energinet.dk) på tlf. 30 92 30 62
Updated: 2. january 2017
Version 1
Sag 15/18069
Color code:
Ll. Torup Gas storage
Stenlille Gasstorage
Transmission systemet
Egtved Compressor station
Nybro Gastreatment plant
2017
Periode
Start
Week Date
1
1
5
6-20
10
10
02-jan
02-jan
01-feb
06-feb
07-mar
07-mar
End
Activities
Consequences
Compressor Station: Service on help
equipment
No consequences
M/R stationer: Exterior tank
inspection
number: 61
No consequences
Frøslev - Egtved I: Tie-in at Bevtoft.
Reduced pressure
RTU replacement on MR & LV
stations stations
No signal from the communication
from station to KCG in the
replacement period for each station
(typically 1-2 hours). There will be
technicians at the station during this
time
M/R Middelfart: Inspection of inner
surface of tanks on filter and
preheater
Supply of cold gas for approx. 8 hours.
M/R Billesbølle: Inspection of inner
surface of tanks on filter and
preheater
Supply of cold gas for approx. 8 hours.
M/R Koelbjerg: Inspection of inner
surface of tanks on preheater
No consequences. The grid can be
supplied from M/R Højby
Compressorstation conversion of
Main Terminal Box 3
Compressorstation - IS 3 checking
the condition of Noreva valve
Compressor 3 is not available for 14
days
IS 3 will not be available during this
period
Flow velocity between 1.5 to 2 m / s
from Egtved against Nyborg v / pigging
with "MFL"
Date
22-dec
22-dec
28-feb
15-maj
04-aug
04-aug
10
07-mar
04-aug
13
27-mar
07-apr
13
29-mar
29-mar
14
03-apr
07-apr
Lillebælt S: Data Logger inspection
Sag 15/18069
14
03-apr
01-sep
14
03-apr
01-sep
14
03-apr
01-sep
14-15
15
03-apr
09-apr
12-apr
17-jun
18
01-maj
02-okt
18
01-maj
02-okt
18-22
01-maj
02-jun
19
08-maj
19-maj
20
16-maj
20-maj
22
30-maj
03-jun
24
12-jun
10-nov
25
20-jun
20-okt
25
21-jun
21-okt
25
21-jun
21-okt
25
23-jun
23-okt
32
08-aug
08-nov
33
17-aug
17-nov
33
18-aug
18-nov
33
14-aug
18-aug
Sag 15/18069
M/R Ullerslev: Inspection of inner
surface of tanks on filter and
preheater
M/R Dragør: Inspection of inner
surface of tanks on filter and
preheater
M/R Dragør Border: Inspection of
inner surface of tanks on filter and
preheater
Condenser E2203 renovering
M/R Måløv "1": Pipe work
Supply of cold gas for approx. 8 hours.
Supply of cold gas for approx. 8 hours.
Supply of cold gas for approx. 8 hours.
Reduced H2S treatment
(225.000Nm3/h)
No consequences
M/R Sorø:Inspection of inner surface
Supply of cold gas for approx. 8 hours.
of tanks on filter and preheater
M/R Lynge: Inspection of inner
surface of tanks on filter and
preheater
Process train 1 - container inspection
Compressorstation conversion of
Main Terminal Box 1
Supply of cold gas for approx. 8 hours.
50% treatment capacity
(225.000Nm3/h)
Compressor 1 is not available for 14
days
M/R Sorø: Change of boiler
No consequences. The grid can be
supplied from other M/R stations and
can be closed down in the summertime.
M/R Li. Selskær: Change of boiler
Supply of cold gas for approx. 4 hours.
Monday and Tuesday.
M/R Brande: Inspection of inner
surface of tanks on filter and
preheater
M/R Nyborg: Inspection of inner
surface of tanks on filter and
preheater
Supply of cold gas for approx. 8 hours.
Supply of cold gas for approx. 8 hours.
M/R Torslunde: Inspection of inner
surface of tanks on filter and
preheater
No consequences. The grid can be
supplied from other M/R stations and
can be closed down in the summertime.
M Skærbækværket: Inspection of
inner surface of tanks on filter
No consequences
M/R Vallensbæk: Inspection of inner
No consequences. The grid can be
surface of tanks on filter and
supplied from other M/R stations and
preheater
can be closed down in the summertime.
M/R Brøndby: Inspection of inner
surface of tanks on filter and
preheater
M/R Ringsted: Inspection of inner
surface of tanks on filter and
preheater
M/R Slagelse: Inspection of inner
surface of tanks on filter and
preheater
Supply of cold gas for approx. 8 hours.
Supply of cold gas for approx. 8 hours.
Supply of cold gas for approx. 8 hours.
Supply of cold gas for approx. 4 hours
Monday and Tuesday
Nybro total ESD testing (Tyra and
Syd Arne terminal)
34
35
28-aug
01-sep
35
28-aug
01-sep
35
28-aug
01-sep
36
04-sep
29-sep
M/R Brande: Change of boiler and
possible NewTech
Supply of cold gas for approx. 4 hours
Monday and Tuesday
Compressor 1,2,3,4 will periodically be
Compressor Station - Boroscopic
unavailable - Coordinated with KCG for
inspection of compressor 1,2,3,4
smooth running
Compressor station - MAN Motor
Compressor 1,2,3,4 will periodically be
Winding High Voltage Test of
unavailable - Coordinated with KCG for
kompressor 1,2,3,4
smooth running
Compressor train 1,2,3,4 will
periodically be unavailable Compressor station - MAN Level 2
Coordinated with KCG for smooth
Service of kompressor train 1,2,3,4
running so that two compressors always
available
M/R Karlslunde: Inspection of inner
surface preheater
39
26-sep
22-dec
39
28-sep
28-dec
40
02-okt
31-dec
44
30-okt
45
06-nov
45
06-nov
Sag 15/18069
Flow Stop 6 hours start-up time 2 hours
M/R Køge: Inspection of inner
surface of tanks on filter and
preheater
M/R Højby: Inspection of inner
surface of tanks on preheater
No consequences. The grid can be
supplied from other M/R stations and
can be closed down in the summertime.
Supply of cold gas for approx. 8 hours.
No consequences. The grid can be
supplied from other M/R stations
Flow velocity between 1.5 to 2 m / s
Li. Torup - Ålborg: Intelligent pigging,
from Li. Torup to Ålborg v/pigging med
(MFL og calliper)
03-nov
"MFL"
Flow velocity between 1.5 to 2 m / s
Taulov - Skærbækværket: Intelligent
from Taulov to Skærbækværket
pigging, (MFL og calliper)
10-nov
v/pigging med "MFL"
Flow velocity between 1.5 to 2 m / s
Torslunde - Lynge: Intelligent pigging,
from fra Torslunde to Lynge v/pigging
(MFL og calliper)
10-nov
med "MFL"