2015 Major Construction and Renewal Projects

LaFortune Hall
West Entry Reconstruction
Start: June 8, 2015
Completion: August 15, 2015
Flanner Hall
Exterior Envelope Maintenance
Start: May 18, 2015
Completion: August 15, 2015
Two New Residence Halls
Start: March 2015
Completion: August 2016
LaFortune Hall
Roof Repairs
Start: June 8, 2015
Completion: August 15, 2015
Main Building
Stair Railing Improvements
Start: June 1, 2015
Completion: August 1, 2015
McCourtney Hall
Start: August 2014
Completion: August 2016
Main Building
Exterior Wall Maintenance
Start: May 18, 2015
Completion: September 14, 2015
Corby Hall
Exterior Wall Maintenance
Start: May 18, 2015
Completion: October 30, 2015
Log Chapel
Exterior Maintenance
Start: May 30, 2015
Completion: August 15, 2015
Howard Hall
Selective Renovation
Start: May 18, 2015
Completion: August 1, 2015
East Quad Geothermal
Well Field & Landscaping
Start: Fall 2015
Completion: August 2016
Fitzpatrick South
Basement Waterproofing
Start: May 18, 2015
Completion: August 15, 2015
Morris Inn Kitchen Expansion
Start: March 15, 2015
Completion: August 15, 2015
Campus Crossroads Project
Start: November 24, 2014
Completion: August 2017
Jenkins Hall & Nanovic Hall
Start: June 2015
Completion: June 2017
Track & Field Stadium
Start: December 1, 2015
Completion: December 1, 2016
Numerous Building Roof
Maintenance and Replacement
Start: May 18, 2015
Completion: August 15, 2015
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Hammes Mowbray Hall
Welsh Family Hall
Duncan Hall
Dillon Hall
Cavanaugh Hall
Breen-Phillips Hall
Ryan Hall
Keough Hall
Alumni Hall
Zahm Hall
O’Neill Hall
McGlinn Hall
Cushing Hall
Fitzpatrick Hall
Sculpture Park Zone
Guglielmino Athletics Complex /
Loftus Sports Center
Soil Replacement & Stockpile
Start: December 2014
Completion: June 2016
May 1, 2015
2015 Major Construction and Renewal Projects