www.ierjournal.org International Engineering Research Journal (IERJ) Volume 1 Issue 3 Page 89-93, 2015, ISSN 2395-1621 Energy Generation Solution Using Steam Turbine ISSN 2395-1621 Mayuresh V. Savargaonkar #1, Pratik S. Sakpal #2, Atharva D. Sathe #3, Prof. Aniruddh Bulbule #4 1 mayursavargaonkar@gmail.com 2 sakpalpratik1993@gmail.com 3 atharvasathe1@gmail.com 4 aniruddhbulbule@gmail.com University Of Pune (UG), Department of Mechanical Engineering, P.V.P.I.T. #1234 #5 Assistant Professor, Department of Mechanical Engineering, P.V.P.I.T, Pune, Maharashtra, India. ABSTRACT ARTICLE INFO The increase in the demand for electricity in commercial areas is going up by the day. The recent few years have shown a lot of growth in the commercial –express feeder consumers. Consequently, the need for energy is going up. Thus to satiate the demand, the utility company needs to produce more electricity, hence increasing the economics. To cope up with the rising cost and escalating demand of electricity we have come up with an indigenous solution. This solution aims at fulfilling electricity demand of the stated consumers by domestically generating electricity. Along with satisfying the demand for electricity of the consumer, a solution for exporting excessively generated electricity to the power grid has also been developed. The power thus generated is at a lower cost as compared to the commercial utility company tariff. This is accomplished with the use of micro steam turbine, its accessories and boiler. Conclusively providing a self-sufficient and profit path to the stated consumer . Article History Received : 5th April, 2015 Received in revised form : 6th April, 2015 Accepted : 12th April, 2015 Published online : 13th April 2015 Keywords— commercial-express feeder, economics, indigenous solution, micro steam turbine, self-sufficient. I. INTRODUCTION We plan on providing a solution that is economically and technically viable, which will help make the system self-sufficient and export the surplus electrical energy developed. The system when and if developed further will be a first of its kind that provides HVAC and Electrical energy alternatively. The above figure shows a concise idea of the actual setup of the system that will be implemented The turbine and the chiller unit (if required) are connected in parallel configuration. A butterfly valve is connected to the boiler output line for controlling the flow. The boiler is completely automated state of the art unit. The steam turbine also adheres to this capability making the system a remote operated one, reducing human labour [8].. II. LITERATURE SURVEY & THEORY Fig 1 © 2015, IERJ All Rights Reserved a Selecting the right steam turbine and the power generation cycle need some basic parameters such as output power and speed of the turbine [1]. In an Extraction Steam Turbine, steam for the thermal load is obtained by extraction from one or more intermediate stages at the appropriate pressure and temperature. The remaining steam is exhausted to the pressure of the condenser, which can be as low as 0.05 bar with a corresponding condensing temperature of about 33°C [7]. In order to assure optimal electricity production and the best conditions of efficiency and security, a thermal power plant (TPP) is brought to choose an effective and robust choice of facilities [4]. Page 1 www.ierjournal.org International Engineering Research Journal (IERJ) Volume 1 Issue 3 Page 89-93, 2015, ISSN 2395-1621 The project as a whole is divided in three major parts namely- Boiler, Turbine and Electricity Tariff. A. Boiler (Thermax CB 20) Here, the „Thermax Combloc-20‟ is considered as a definitive boiler for steam generation. Combloc, the steam boiler offers customers who are forced to choose between a particular boiler design and a solid fuel option, a way out. This versatile fully packaged boiler launched by Thermax Heating SBU combines the fuel flexibility of a hybrid boiler and the inherent ruggedness and compactness of an integral furnace boiler. Combloc provides customers various options for fuel combustion - imported coal, Indian coal, pet coke, wood chips, rice husk, pellets, wood logs, dry biomass, etc. Without making expensive and time consuming boiler modifications industries can switch between these fuels, depending on their cost and availability. Combloc's compact design helps clients avoid the hassles of site civil work, longer installation time and higher investments. In a small foot print, the boiler offers one of the highest thermal efficiencies. This boiler is available in the range of 1.5 to 6 TPH. Technical Specifications: Boiler type - Horizontal Multi-tubular Shell Type Smoke Tube with Water Wall Furnace. Max steam output - 2000 kg/hr Design Pressure - 10.54/17.5 kg/sq. cm Temperature - 185/208 °C Dryness - 98% Steam / Fuel ratio- 4.55 Efficiency- 85.5% (for wood) Fuel type- wood chips ( 7 to 20 mm) Fuel moisture content- 15% to 25% Ash content - ≤ 8% Net Calorific Value of „Wood Chips‟ - 2950 kcal/kg B. Micro Steam Turbine (CTMI- PS902C) The steam turbine considered is manufactured by „Chola Turbo Machinery International Pvt ltd‟. The condensing turbines take high pressure steam, expand it in turbine nozzles and blades, and exhaust it to a condenser at lower than atmospheric pressure. It is principally used when power must be generated with minimum steam consumption [3]. The condensing turbine may also have bleed points (uncontrolled extractions) to satisfy steam demands at medium intermediate pressures. SALIENT FEATURES OF PS 902C Condensing Single Stage Steam Turbine Woodward TG-13 oil relay governor Positive over speed trip Antifriction ball bearings throttle valve Ball thrust with minimum 48,000 L10 rating Horizontally split case with metal to metal joint for ease of maintenance Multiple carbon ring gland seals with stainless steel spacers Foot mounted support system © 2015, IERJ All Rights Reserved Large bearing housing with constant level oilers and integral cooling water jackets Wheel with stainless steel blades Large efficient monel nozzles Balanced, cage guided throttle valve Stainless steel turbine shaft Simplicity of design assures reliability and low maintenance Positive seating tight shutoff valve Stainless steel strainer Sentinel warning valve Optional exhaust location Technical Specifications: Maximum Inlet Gauge Pressure (PSI/Bar)- 640/45 Maximum Inlet Temperature (°F/°C)- 840/450 Maximum Exhaust Gauge Pressure (PSI/Bar)150/10 Speed Range (RPM)- 1000-5000 Overall Efficiency - 59.29% Bearing Type- Ball and/or sleeve Wheel Pitch Diameter (IN/mm)- 17.7450 Approx. Maximum Rating (HP/KW)- 405/300 Approx. Shipping Weight (LB/kg)- 1100/500 API 611 compliant C. Tariff The utility company for providing electricity to the consumers is MSEDCL. The following category is considered for further calculations. HT II (A): EXPRESS FEEDERS Applicability Applicable for use of electricity / power supply at High Tension on Express Feeders in all non-residential, nonindustrial premises and/or commercial premises for commercial consumption meant for operating various appliances used for purposes such as lighting, heating, cooling, cooking, washing/cleaning, entertainment/leisure, pumping in following (but not limited to) places [9]: Non-Residential, Commercial and Business premises, including Shopping Malls / Show Rooms Film Studios, Cinemas and Theatres including Multiplexes, Hospitality, Leisure, Meeting / Town Halls and Places of Recreation & Public Entertainment Marriage Halls, Hotels / Restaurants, Guest Houses, Internet / Cyber Cafes, Mobile Towers, Microwave Towers, Satellite Antennas used for telecommunication activity, Telephone Booths, Fax / Xerox Shops Automobile, Any Other Type of Workshops, Petrol Pumps & Service Stations including Garages, Tyre Re-treading / Vulcanizing units Sports Club, Health Club, Gymnasium, Swimming Pool Page 2 www.ierjournal.org International Engineering Research Journal (IERJ) Volume 1 Issue 3 Page 89-93, 2015, ISSN 2395-1621 TABLE I COMMERCIAL EXPRESS FEEDERS TARIFF CHART Time Slot Tariff (Rs./ KWh) A-Zone 22000600 Hrs B-Zone 06000900 12001800 Hrs C-Zone 09001200 Hrs D-Zone 18002200 Hrs . 12.82 Discounte d/penalise d tariff (Rs/KWh ) 10.32 Demand Cost (Rs/KVA/mont h) 9 4658 1030 4.52 10 4347 974 4.46 To calculate the actual electrical consumption of the boiler room it is necessary to carry out a brief survey of equipment‟s used in the room .The following components are considered as major electricity consuming equipment‟s in the boiler. 190 TABLE III BOILER COMPONENT RATINGS 12.82 12.82 190 Sr. No 1 12.82 13.62 190 12.82 13.92 190 2 3 4 5 6 7 8 9 10 III. ACTUAL WORK A. Field Study Initially, the boiler was under observation and periodic readings were taken and noted down. The study of boiler performance was carried out for a period of five months. The observation(s) included monitoring electrical energy consumption at full load for varying atmospheric conditions. It also comprised of steam to fuel ratio monitoring and steam flow at various conditions. The average per day operation is 8 hrs (0900hrs to 1700hrs). The given readings are fortnightly averages. The readings are tabulated as below, TABLE III PERIODIC BOILER READINGS Sr. no 1 2 3 4 5 6 7 8 Boiler Observations Steam Fuel Consumption Consumptio (kg/day) n (kg/day) (FOR JULY ‟14) 8547 1882 8193 1817 (FOR AUGUST) 7320 1637 7998 1797 (FOR SEPTEMBER) 7176 1584 6717 1348 (FOR OCTOBER) 6563 1464 6317 1406 (FOR DECEMBER) © 2015, IERJ All Rights Reserved Steam/fue l ratio 4.54 4.51 4.47 4.45 4.53 4.98 4.48 4.49 11 12 13 14 15 Boiler Components Ratings Component Wattage Voltage/Current Name (kw) (volt/amp) Feed water pump 15 415/27 x2 F.D. fan 2.2 415/2.16 I.D. fan 18.5 415/33 Heat recov. Unit 0.37 415/1.3 RAV TMC filter 0.37 415/1.36 Fuel feeder x2 1.1 220/4.76 Grate hyd. Power 3.7 415/7 pck Grate air cooling 2.8 415/0.85 fan Moving floor hyd. 18.5 415/33 Power pack Moving floor air 2.8 415/0.85 cooling fan Submerged ash 2.2 240/8.66 conveyor Fuel conveyor 1.5 415/3.5 Bucket elevator 1.5 415/3.5 Bag filter motor 0.37 415/1.05 x2 RAV spark 0.37 415/1.3 arrestor Using the above data and observing the energy consumption of the boiler unit the electrical energy consumption of the boiler was pin pointed at an average of 190kw for 8 hours at full load, using the energy meter. Here, the concept full load corresponds to boiler output of 2000kg/hr at a pressure of 17.5bar. B. Survey a) Details City Pride Multiplex (Kothrud, Pune.) is a four screen movie theatre with a restaurant and stores. The purpose of this survey is to get an overview of the power consumption and study electrical tariff of this building. Air conditioning system is a major power consumer in this building. The average footfalls of the multiplex per week are considered to be 38,000 persons/week. The HVAC system currently in operation has a capacity of 9000 CFM (AHU capacity). The chillers installed are of capacity 95 TR (Standby) and 110 TR respectively. The complex includes 8 shops and 7 stalls. b) Tariff skeleton TABLE IV DISTRIBUTION OF POWER CONSUMPTION Page 3 www.ierjournal.org TOD International Engineering Research Journal (IERJ) Volume 1 Issue 3 Page 89-93, 2015, ISSN 2395-1621 Consu mption (KWh) 20740 Deman d (KVA) Rate (Rs./ KWh) Cost (Rs.) A-Zone 82.5 10.30 213622 2200-0600 Hrs B-Zone 60105 110.6 12.82 770546.1 0600-0900 1200-1800 Hrs C-Zone 22122 111 13.62 301301.6 0900-1200 4 Hrs D-Zone 35769 87 13.92 497904.4 1800-2200 8 Hrs The above table is considered on the basis of mean power consumption of three months, based on proof given by MSEDCL (Utility Company) and values in Table I c) Calculations for survey [5] The Total cost for 4-zones = 22,70,606.2/(Including Service tax (7%), Electricity duty (17%) and Demand Charge for 200 KVA at the rate of 190 Rs/KVA/Month) Considering a gross subsidy of 26.7% Total amount = 16,64,354 Rs/Month Average Unit Consumption For 3 months ≈ 138268 KWh Average Unit Cost = 1664354/138268 = 12.03 Rs/Unit IV. CALCULATIONS Considering the above details related to the survey and the tariff calculations [2], [6], [3] the following power generation solution is obtained. a. Boiler Running Cost 1. For cost of fuel Average unit cost = 12.03 Rs/KWh Fuel cost = 4.2Rs/kg S/f ratio = 4.54 (Ref. „Table II‟) fuel consumption = 16000/4.54 = 3524.22 kg/8hrs = 440.52 kg/hr fuel cost = 440.52*4.2 ≈1850.220 Rs/hr 2. For cost of electricity Consumption = 190kw/8hrs Unit Costs = 23.75*12.03 = 285.71Rs/hr Demand and unit cost ≈ 300 Rs/hr 3. Fuel cost + Cost of electricity = 1850.22+300 = 2150.22 Rs/hr b. Surplus Power Generation © 2015, IERJ All Rights Reserved The power generation is 180kw from the system. Subsequent calculations are done to find out the surplus generation using tariff in “Table I”. Break Even Points for power generation „D-Zone‟ B.E.P = 2150.22 / 13.92 = 154.46 Kw/hr Surplus for „D-Zone‟ = 180 - 154.46 = 25.54 Kw/hr „C-Zone‟ B.E.P = 2150.22 / 13.62 = 157.87 Kw/hr Surplus for „C-Zone‟ = 180 - 157.87 = 22.13 Kw/hr „B-Zone‟ B.E.P = 2150.22 / 12.82 = 167.72 Kw/hr Surplus for „B-Zone‟ = 180 - 167.72 = 12.28 Kw/hr „A-Zone‟ B.E.P = 2150.22 / 10.32 = 208.35 Kw/hr Surplus for „A-Zone‟ = 180 - 208.35 = (-28.35) Kw/hr As the calculations show, profitable solution is only viable in zones ‘D’, ‘C’, ‘B’. Hence we consider them V. RECOVERY AND PROFITABILITY aPayback Period‟ is defined as the length of time required for an investment to recover its initial outlay in terms of profits or savings. Now, from above calculations we observe that there is a surplus electrical power generation in the three specified zones, from the system. i. „D-Zone‟ is of four hours viz. 1800hrs to 2200hrs respectively. Excess power generated =102.16kw/4hrs Cost Recovered ≈1229Rs/4hrs ii. „C-Zone‟ is of three hours viz. 0900hrs to 1200hrs respectively. Excess power generated =66.39kw/3hrs Cost Recovered ≈799Rs/3hrs iii. „B-Zone‟ is of nine hours viz. 0600hrs to 0900hrs and 1200hrs to 1800hrs respectively. Excess power generated =110.52kw/9hrs Cost Recovered ≈1330Rs/9hrs Hence, the total recovery after running in above three zones i.e. 16hrs per day ≈ 3358 Rs/day Net total recovery for 1 year (30*12 days) = 3358*30*12 ≈ 12,08,880Rs/annum VI. EQUATIONS [6] Average Unit Cost (Rs) = (total amount/ Total consumption) Fuel consumption (kg/hr) = {total steam generated in 8 hrs/(s/f ratio)} Demand and unit costs (Rs/hr) = (demand per hour * rate per unit) Fuel cost (kg/Rs) = (fuel consumption * rate per kg of fuel) Zone wise generation (KWh) = (total running cost per hr / unit rate per zone) Breakeven point of power generation (KWh) = (power generated per hr - demand per hr) Page 4 www.ierjournal.org International Engineering Research Journal (IERJ) Volume 1 Issue 3 Page 89-93, 2015, ISSN 2395-1621 Surplus power =180-(Power required for B.E.P) Cost recovered ={surplus power* cost per kwh(12.03)} VII. CONCLUSION After analysing the calculations and observations we are able to deduce for a fact that the solution obtained is commercially viable and can be put to effect. As the rates of electricity are going up in the newest revision, the solution becomes more attractive. The costs of electricity considered in this paper are current and not the revised ones. This situation of rising rates of electricity can be used as a profitable business idea by selling the excess to the grid or any potential consumer. As there is no standardization in the manufacturing of steam turbines, the turbine can further be developed to harness the full potential of the system. Acknowledgement The Authors of this paper are thankful to „Thermax India Pvt. Ltd, Pune‟ and „Chola Turbo Machinery Pvt. Ltd‟. REFRENCES [1 ] Michael A. Cerce, Vinod P. Patel, “Selecting Steam Turbine for Pump Drives” [2] ASME “Theoretical Steam Rate Tables”, 1969, New York. [3] S. M Yahya, “Turbines, Compressors and Fans”. „Chapter 1, 2, 4‟. [4] M.N Lakhoua, “Casual analysis and calculation of steam turbine power plant”, IJPS vol.7 (39), pp5493-5497. [5] MSEDCL, MERC, “Case 121 of 2014”, Tariff Proposal . [6] Steam and Combustion, “Common Boiler Formulae 2006”. [7] Bureau of Energy Efficiency, “Cogeneration Handbook, 1982”. [8] Dimeo R and Lee K.Y. “Boiler-turbine control system design using a genetic algorithm”, IEEE, 6th august 1992, volume 10, issue 4. [9] MSEDCL, “Approved tariff schedule” (With effect from) 1st august, 2012, (Annexure “A”) . © 2015, IERJ All Rights Reserved Page 5
© Copyright 2024