CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering SOLUTION OF HOMEWORK 3 Question 1 (25%) A 4m x 4m footing will be constructed on a site underlain by the given soil profile. Both the Standard Penetration Test and Cone Penetration Test results are available for the site. According to the CPT results, the average cone tip resistances for the first and second sand layers are 4 MPa and 5 MPa, respectively. The SPT is repeated at several depths, the depths and the SPT-N numbers are given in the table below. The unit weight of the sand is 20 kN/m3 and no ground water is observed at the site. Test depth from the surface 3 5 7 10 SPT-N60 6 7 12 15 a) Calculate the settlement of the footing using Burland and Burbidge (1985) Method. Ignore all of the correction factors. Use the average SPT-N value for the depth of interest. The SPT-N values given in the table are N60 (without overburden correction). b) Calculate the settlement of the footing 1 year after the construction using Schmertmann’s Method. Show all calculations necessary to fill out the table and use the results from the table for the rest of your calculations. Layer No Iz Es (Unit=………) Δz (Unit=………) Iz xΔz / Es 1 2 c) What would be the settlement value you use for design? Please explain your reason. 1 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering Solution 1 a) . 1.71 . 6 210 ∗ 4 12 15 4 1.71 0.068 10 . ∗ 0.068 37.68 . 7 10 ≅ 3.8 b) Layer 1 4000 2 5000 Note that; for square footing; 0 0.1 B/2 0.5 2B 0.0 where; B : width of footing 2.0 S C : 1 C C C I z E C C q 1 0.5 q 0.2 log 0.1 3 ∗ 20 1 0.5 0.86 210 1 1 0.2 log 1.2 0.1 2 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering Layer No 1 Depth (m) 3.0-5.0 (m) 2.0 2 5.0-11.0 6.0 4000 Es (kPa) 8000 0.3 7.5 ∗ 10 5000 10000 0.25 1.5 ∗ 10 Iz 22.5 ∗ 10 S C C q I z E 0.86 ∗ 1.2 ∗ 210 ∗ 22.5 ∗ 10 0.0487m ≅ 4.9cm c) OPTION 1: As the designer of this foundation, to be on the safe side (and to be prepared for the worst case scenario), consider the highest settlement value calculated in part (a) using SPT and part (b) using CPT data. = 49 mm OPTION 2: In order to give equal value to both methods, average of the immediate settlement values calculated in part (a) using SPT and part (b) using CPT data will be considered = 43 mm Note that allowable settlement for raft foundations in sand is 65 mm, and for single foundations in sand 40 mm" 3 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering Question 2 (15%) For the cantilever pile wall presented in the figure given below, estimate the depth of penetration, d, after penalizing the passive resistance by a factor of safety 1.5 Solution 2 SAND K tan 45 K P z z z tan 1 K 1 0.25 γz 0m → P 5m → P 9m → P ∅ 2 20 20 5 ∗ 18 q K 45 37 2 0.25 4.02 2c K 20 0.25 5kPa 5 ∗ 18 0.25 4 ∗ 19 27.5kPa 10 0.25 36.5kPa 4 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering CLAY ∅ P z z 9 γz 20 9m → P dm → P 20 z γz 0m → P dm → P q K 5 ∗ 18 5 ∗ 18 P z K 0→K 18d 1 2c K 4 ∗ 19 1 4 ∗ 19 q K 2 ∗ 90 18d 1 2c 2 ∗ 90 2 ∗ 90 6kPa 2 ∗ 90 6 18dkPa K 180kPa 180 18dkPa Apply FS=1.5 to passive resistance z z 0m → P dm → P 180 1.5 180 18d 1.5 120kPa 120 12dkPa 5 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering Force (kN/m) Force (kN/m) H1 H1 H2 H2 H3 H3 H4 5*5=25 (27.5-5)*5/2=56.25 27.5*4 (36.5-27.5)*4/2=18 6*d 18d*d/2=9d2 (4)*10*(4)/2=80 Passive 120*d 12d*d/2=6d2 H5 H5 M 0→d Moment arm to Moment (kN.m/m) point A 6.5+d 162.5+25d 5.67+d 318.9375+56.25d 2+d 220+110d 1.33+d 23.94+18d d/2 3d2 d/3 3d3 (4/3+d) 106.67+80d d/2 d/3 60d2 2d3 8m Question 3 (10%) Section of an anchored sheet-pile wall is shown in in the figure below. a) Using a factor of safety of 2.5 against the passive resistance, calculate the required depth of penetration d for the sheet-pile. b) Assuming the depth of penetration is d=6 m, calculate the required horizontal force, H, at point A. Do not change the given penetration depth in your calculations. 6 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering c) Assume the required horizontal force at point A is 120 kN/m. If that lateral support is to be provided by anchors placed at every 3 m intervals and inclined 20o from the horizontal, calculate the axial force T in each anchor. Solution 3 a) K tan 45 K ∅ 2 1 K tan 1 0.26 45 36 2 0.26 3.85 γz q K 2c K 0kPa z 0m → P 8 ∗ 19 0.26 39.5kPa z 8m → P 8 ∗ 19 10d 0.26 39.5 2.6dkPa z 8 dm → P γz q K P 0kPa z 0m → P 10 d 3.85 38.5dkPa z dm → P 8 8 d 2d 39.5 ∗ ∗ 6 39.5 ∗ d ∗ 6 2.6 ∗ d ∗ d/2 ∗ M 2 3 2 3 d 2d 6 38.5 ∗ d ∗ 2 3 0 2.5 d 6.7m P 6 "Since water pressures on both sides of the wall are equal, their moments are not considered" 7 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering a) M 39.5 ∗ 8 8 6 ∗ 6 39.5 ∗ 6 ∗ 2.6 ∗ 6 ∗ 6/2 ∗ 6/3 2 3 2 38.5 ∗ 6 ∗ 6/2 6/3 H ∗ 12 0 2.5 H 135kN "A factor of safety of 2.5 will be applied to passive pressure" b) 120 ∗ 3 cos 20 383kN Question 4 (25%) There are two videos in this question, the links of which are given below: Video 1:http://www.youtube.com/playlist?p=PLB468342B03660375 Video 2: https://www.facebook.com/507784339262303/videos/970703199637079/?type=1&theater The first video was taken from a residence construction in Ankara. In this project, a deep excavation was necessary, where the lateral stability of soil was ensured using piles. In the link, there are total of 14 video pieces uploaded on YouTube website, which were recorded during the construction stages of one of these piles. In the second video link, pile construction simulation is given (You can also watch them on the Video Wall of CE department.) Please answer the following questions to test your knowledge about piles. (In Video 1, as you watch them, the questions will appear on the screen). 1. In video 1, what kind of pile (driven or cast-in-situ), do you think, was constructed on the site? Answer the same question for Video 2. 2. For Video 1, describe the first stage of pile construction using your own words? 3. Why do you think these plastic parts are attached to the steel bars? A similar component is also shown somewhere in Video2, what are those components called in Video 2? 4. Why do you think installation of a case is necessary for constructing the pile? 5. What is the difference between Video 1 and Video 2 in terms of installing temporary casing? What is the limit for inclination of casing (therefore the pile) in Video 2? 6. As you hear in Video 1, there are two steel reinforcements with lengths 12 m and 11 m, the vertical overlap distance of these reinforcements is 1.5 m. What would be the length of longitudinal steel bars that will stay outside the pile? 7. In Video 1, the workers are trying to keep the steel bars on the air. Why do you think they do that? 8 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering 8. In Video 1, where do you think water flooding out of the pile casing come from? In Video, at what time of total of 4:55 minutes this happens? Since the idea of this question is to take you to the construction site and show you the details of constructing a pile, you are expected to answer any 6 out of these 8 questions. Only one sentence is OK for properly answering a question. Solution 4 1. Cast in-situ pile is constructed. 2. The longitudinal and spiral reinforcements are bonded according to prescribed alignment/spacing/diameter. 3. The spacers are installed to maintain the spacing between the casing/edge of the pile and the longitudinal reinforcements. – In the second video, these are called U-bars. 4. Case installation is necessary, mostly for cohesion-less soils to prevent cave-in problem (i.e., loose soil particles drops into the borehole), in other words stabilization of the borehole during the pile construction up to pouring concrete. 5. In Video 1, the pile casing in installed through rotating the casing into the soil using the pile machine. In Video 2 however, it is directly installed into soil. No details are given. The limits of inclination angle is 1/100. 6. 12 + 11 – 1.5 = 21.5 m is the total length of the combined steel bar. The length of the borehole/pile is 21 m (from the video sound records). In addition, the steel bars are installed on air to be able to fill concrete at the bottom of the pile. Therefore, at least 0.5 m is supposed to be stay outside of the bore hole. 7. There may be several reasons: (1) to prevent some dirty/ particles stuck on the tendons which may seriously lead to corrosion and decrease the capacity of the reinforcement, (2) to satisfy perfect bonding between the reinforcement and concrete. (iii) to prevent steel bars entering into the ground. 8. Water comes from the original ground water table which fills the hole after excavating the borehole. In Video 2, this happens in between 3:47 – 3:50. 9 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering Question 5 (25%) N-J-N Engineering Inc. consulting company hires you for their project in Bangkok, Thailand. The company provides you the following video. Watch the video at the link below: https://www.youtube.com/watch?v=PP8tLAwv1kE a) At a time when the pile driving machine was broken, the workers, joyfully, drove the pile into ground. Assume that each Thai men weighs 75 kg and jumps from 3 cm drop height. Using a Thailand-modified ENR pile driving formula, calculate the allowable load capacity of the pile (kN). Qallowable = 3 · Wr · H / (s+0.5·c) .... where c is a constant 25 mm, and s is the “average set”, assume 10 mm/drop. b) Assume that the soft Bangkok clay typically has a constant undrained shear strength of 20 kPa. Assume that the pile is a 30-cm diameter, hollow, concrete pile with inner diameter of 20 cm with a length of 5 m. The soil will be plugged inside the hollow area and will move together with the pile, therefore the pile can be considered as a closeended pile. Calculate the ultimate pile capacity, Qult, using the static formulas. c) A narrow excavation with a 5-m-width, in front of these piles will be made in saturated Bangkok clay with undrained shear strength of 20 kPa, and a unit weight of 18 kN/m3. There is no hard-layer underneath, it is all soft Bangkok clay. Calculate the factor of safety against base stability. 10 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering Solution 5 a) There are 6 Thai men and each weighs 75 kg, total weight of “drop hammer”, Wr= 6×75 = 450 kg = 4414 N. Drop height is 0.03 m. Qallowable = 3 × 4414 × 0.03 / (0.01 + 0.5 × 0.025) = 17656 N = 18 kN b) Undrained shear strength of Bangkok clay = cu = 20 kPa. Pile diameter D = 0.03 m, and pile length L = 5 m Qult = Skin friction + Tip resistance = Unit skin friction × clyndrical surface area of the pile + unit tip resistance × tip area of the pile. Qult = (α× cu × π × D × L) + (9 × cu × π × D2/4) Qult = (1.0× 20 × π × 0.3 × 5) + (9 × 20 × π × 0.32/4) = 107 kN For cu = 20 kPa α = 1.0 according to the graph on page 215 of CE366 Lecture Notes. c) If there is no hard layer underneath the excavation, the width of the failure zone should be taken as B1 = 0.707 B, where B is the width of the excavation. B1 = 0.707 × 5 = 3.5 m Check the depth of tension cracks: σha = 0, σha = σv · KA – 2 · c · √KA = 0 Since ϕ = 0, KA = 1.0 The depth of tension crack, z is: z = 2 · c / γ = 2 · 20 / 18 = 2.2 m 11 CE 366 Foundation Engineering Solution of Homework 3 Middle East Technical University Department of Civil Engineering Force (kN/m) Moment arm about point b (m) B1/2 = 3.5 / 2 = 1.75 B1 = 3.5 Moment about point b (kN.m/m) -551.25 385 Weight = γ· H · B1 = 18 · 5 · 3.5 = 315 S1 = (2 · π · B1/4) · cu = (2 · π · 3.5 / 4) · 20 = 110 S2 = (H - z) · cu = (5 - 2.2) · 20 = 56 B1 = 3.5 196 Passive resistance* 245 B1/2 = 3.5 / 2 = 1.75 = (2 · cu ) · B1 = (2 · 20) · 3.5 = 140 * when calculating the passive resistance, the triangular part of the passive lateral earth pressure distribution is ignored (σhp = σv · KP + 2 · c · √KP = γ· z + 2 · cu ). This is, in a way, similar to applying a reduction (FS) to passive resistance. 385 196 245 551.25 1.498 12
© Copyright 2024