How to demonstrate Additionality? Presented by: Veronique Bovee June 1st, 2005

How to demonstrate Additionality?
Presented by: Veronique Bovee
June 1st, 2005
Additionality
KP/MA: “The emission reductions of the
project must be additional to any that would
occur in absence of the project”
What does this mean?
Does it refer to emissions reductions or the
project?
Demonstrate intent to reduce GHG emissions
How to demonstrate this?
Baseline Scenario
Emissions:
tCO 2/MWh
Business as Usual scenario
Project Scenario
Emission reductions
2012
Guidance from EB
a.
A flow-chart or series of questions that lead to a narrowing of potential
baseline options; and/or
b.
A qualitative or quantitative assessment of different potential options
and an indication of why the non-project option is more likely; and/or
c.
A qualitative or quantitative assessment of one or more barriers facing
the proposed project activity; and/or
d.
An indication that the project type is not common practice in the
proposed area of implementation, and not required by the host country
legislation/regulations.
Concept of the Consolidated Tool for Demonstration of
Additionality
Step 0 – Preliminary screening of projects
started after 1-1-2000 and prior to 31-12-2005
PASS
Step 1 – Identification of Alternatives
PASS
Step 2:
Step 3:
– Investment Analysis
– Barrier Analysis
PASS
Step 4 – Common Practice
analyse similar
activities and compare
PASS
Step 5 – Impact of CERs of project
on barriers Step 2/3
Project is
Additional
First step of Additionality
Step 0 – Preliminary screening of projects
started after 1-1-2000 and prior to 31-12-2005
Only relevant for projects that want to start generating CERs before project is
registered with the CDM EB
Only relevant for projects with starting date between 1 January 2000 and date at
which first CDM project was registered with the EB
If start of construction of CDM project after 18, November 2004 go directly to step 1
Need to provide evidence that CDM was considered in decision making
from the start. How?
Host country has been contacted for approval
PIN or PDD submitted
Minutes of meetings in which CDM is discussed
Offering Memoranda or Cash flow analysis showing CDM value
Example Step 0
Biomass project submitted PIN and PDD in 2003 and started
operations in September 2004
Can indicate that CDM was taken into account from project
eligibility stage
Can claim CERs from September 2004 if the project is registered
with the CDM EB before December 2005
Question
Can I develop a landfill gas project that
captures gas and started to generate
electricity in March 2004 as a CDM project,
now I found out that there is a value for CERs?
Can I develop a project that started operations
in March 2005 as a CDM project?
Second step of Additionality
Step 1 – Identification of Alternatives
Define plausible alternatives to the project activity, including:
proposed project without CDM
Continuation of current situation
Alternative to the project that deliver the same output
The alternatives should be realistic and available to the project
developer or similar project developers.
Check whether alternatives are in compliance with existing legally
binding regulations
Example Step 1
If developer of landfill gas to energy project, define
alternatives for both capturing of the gas as well as
production of electricity (own use of sold to grid?).
Alternatives for similar project developers being landfill
managers include not capturing the gas, capturing the
gas and flare, incineration.
Alternatives for producing electricity include production
of gas fired or coal fired by IPPs.
Check against regulations
in Malaysia capturing of
gas is not required and the alternative of uncontrolled
release of methane from a landfill is thus in
compliance with the national regulations
Impact Policy and Regulations on Additionality
Decision Executive Board
Distinct between Policies and Regulations that give comparative advantages
and mandatory regulations by local or national authorities
Policy and regulations that give comparative advantages to less carbon
intensive technologies implemented since November 2001, do NOT have to
be taken into account in the baseline.
Same for regulations that give comparative advantages for more carbon
intensive technologies, implemented since 1997.
Incentives for more carbon intensive technologies introduced before the
adoption of the Protocol have to be taken into account
However, not clear on how to consider mandatory regulations when
demonstrating additionality
Question
What would be the realistic alternatives if I
would develop a biomass cogeneration
project?
The Malaysian government is providing
subsidies for energy efficiency measures. Can
my project still be eligible under the CDM if I
apply such energy efficiency measures?
Step 2 – Investment analysis
Step 2 – Investment Analysis
Indicate the proposed project is economically or financially less
attractive than alternatives
Do this analysis without accounting for the revenues of CERs
Can do this using IRR, cost benefit ratio or unit cost of service
Select the indicator and calculate and compare the financial
indicators with other identified alternatives
Carry out sensitivity analysis
Present all assumptions and analyses used in a transparent way
Example Step 2
For a landfill gas flaring project, it can easily be
demonstrated that there will be no revenues without
the CDM
For a biomass electricity project that is connected to
the grid, the project can be compared with coal fired or
gas fired power plants using their IRR or costs per
KWh of electricity produced.
Make assumptions on investments costs, O&M costs,
lifetime of the equipment etc. for the identified
alternatives.
For IRR it is also possible to use government bond
rates and add % for specific risks
Step 3 – Barrier analysis
Step 3 – Barrier Analysis
Identify technical, investment, institutional or other barriers
Provide evidence of the existence of the barrier
Indicate that the identified barrier is not a barrier for alternatives
identified
Mainly used in stead of Step 2. Does not have to be used in
addition of Step 2, but can be
Example Step 3
Barrier of a new technology for POME biogas
projects – difficult to find investors
For energy efficiency measures it could be
indicated that it is difficult to get board
approval to introduce the measures
Step 4 – Common Practice Analysis
Step 4 – Common Practice Analysis
Analyse similar projects already implemented in region/country
A project is considered similar if
it is in the same country or region
Of a similar scale
In a comparable regulatory framework and investment
climate
Demonstrate why and how your project is different from these
projects and why the barriers identified for your project are not
applicable to the identified similar projects
Example Step 4
Assume a hydropower project. The project needs to be
compared against other already operational
hydropower projects
My project may need CDM because other hydro are
developed by TNB and I am an IPP. Or because all
hydro is of 25 MW and your project is 5 MW.
I can indicate that it is more difficult for my IPP to
develop the project than for others, since I am a small
local project developer without any international
investor in place.
Question
In Malaysia, there is already a landfill gas to
electricity project operational without use of
the CDM. Can I develop my landfill gas to
electricity project using CDM?
What if more than 5 of such projects are
already operational?
Final Step of the Additionality Tool
Step 5 – Impact of CDM
Explain how the CDM benefits will alleviate economic hurdles and
other barriers
Examples of benefits given:
- Revenues of the sales of CERs
- Can attract new players who will not be exposed to same risk anymore
- May result in acceptance of lower IRR for this project type
- Reduces exchange risk
NOTE: There are simplified requirements
for small scale projects.
Any more questions?